PLINACRO PLINACRO CROATIAN GAS TRANSMISSION CROATIAN GAS TRANSMISSION SYSTEM OPERATOR SYSTEM OPERATOR Mladen Čavić, B. Sc. Director of Transmission Division
Dec 16, 2015
PLINACROPLINACRO
CROATIAN GAS TRANSMISSION CROATIAN GAS TRANSMISSION SYSTEM OPERATORSYSTEM OPERATOR
Mladen Čavić, B. Sc.Director of Transmission Division
22
Liberalization
Security of supply
Unbundling infrastructure system operators
Regulatory Agency
Energy Reforms
33
Legislative Framework – TPA, Tariff system
Energy subject – TSO = legally unbundled
Technical and technological preconditions- construction of infrastructure
Gas TransmissionGas Transmission
44
Gas Market – harmonization with EU directives
Legal FrameworkLegal Framework
Transmission of natural gas is defined as energy activity
Transmission of gas is a public service The price of gas transmission service is regulated and
set in accordance with the tariff system The licence (issued by HERA) is required for the gas
transmission activity
55
PPlinacrolinacro Ltd Ltd
Croatian Gas Transmittion Company
Defined as Croatian TSO (Gas Transmission System Operator) by Gas Market Act - next 30 years
Plinacro established by unbundling of gas transmission activity from INA Plc
100% state-owned company In charge of natural gas transmission; maintenance,
managing and supervision of the entire gas transmission system and its development and construction
66
ZAGREB
50 bar do 2002
50 bar > 2002
75 bar
63 bar
Key:
KARLOVAC
Technical data - 2002
1,641 km of pipelines
137 MRSs
DC/SCADA
2.95 Bcm of gas transported
max. capacity 560.000 m³/h
Plan of Development and Modernization of the Gas Transmission System in the Republic of Croatia
first investment cycle 2002 – 2006
second investment cycle 2007 - 2011
UGS OKOLI
77
LUČKO
KUTINA
KARLOVAC
ZAGREB
S. BROD
PULA
BELIŠĆE
OSIJEK
BELI MANASTIR
50 bar do 2002
50 bar > 2002
75 bar
63 bar
Key:
Technical data - 2007
2,085 km of pipelines
19 entry point
151 exit point
DC - new SCADA, CS system
3.1 Bcm of gas transported
max. capacity 860.000 m³/h
I. Investment phase 2002-2006
Planned: 210 million € 520 km of pipelines 17 exit points new SCADA + DC headquarters
• Development of the gas transmission systemand gasification of the parts of the Republic of Croatia – Istra, Primorje and Gorski kotar
Kutina-Sl. BrodZagreb Istok-KutinaPula-KarlovacLučko-Ivanja RekaBelišće-OsijekBolman-Beli Manastir
Goals
• Increased reliability of pipeline system and security of gas supply
88
VODNJAN
UMAG
KUKULJANOVO
OMIŠALJ
BOSILJEVO
SPLIT
PLOČE
ZABOK
LUČKO
SLOBODNICA
D. MIHOLJAC
DRAVASZERDAHELY
ROGATEC
B. BROD
NOVA KAPELA
POŽEGADOBROVAC
OMANOVAC
SV. IVAN ŽABNO
BJELOVAR
KUTINA
GOSPIĆ
ZADAR
JOSIPDOL
KARLOVAC
BENKOVAC
KNIN
ZAGREB
S. BROD
PULA
BELIŠĆE
OSIJEK
BELI MANASTIR
50 bar do 2002
50 bar > 2002
75 bar
63 bar
Key:
Technical data - 2011
3,081 km of pipelines
19 entry point
178 exit point
2 interconnections (import routes)
4.5 Bcm of gas to be transported
max. capacity 1.200.000 m³/h
II. Investment phase 2007-2011
Planned:Planned:• 996 km of pipelines• 24 MRS• 443 mil. €Goals:
•Increased reliability of pipeline system and security of gas supply•Development of the gas transmission system and gasification of the parts of the Republic of Croatia – Lika and Dalmatia•Opening of new import supply route
Dravaszerdahely-D. Miholjac
Kutina-Dobrovac
Kukuljanovo-Urinj-Omišalj
Slobodnica-Bosanski Brod
Split-PločeRogatec-ZabokZabok-Lučko
Vodnjan-Umag
Sl. Brod-D. Miholjac
99
VODNJAN
UMAG
KUKULJANOVO
OMIŠALJ
BOSILJEVO
SPLIT
PLOČE
ZABOK
LUČKO
SLOBODNICA
D. MIHOLJAC
DRAVASZERDAHELY
ROGATEC
B. BROD
NOVA KAPELA
POŽEGADOBROVAC
OMANOVAC
SV. IVAN ŽABNO
BJELOVAR
KUTINA
GOSPIĆ
ZADAR
JOSIPDOL
KARLOVAC
BENKOVAC
KNIN
ZAGREB
S. BROD
PULA
BELIŠĆE
OSIJEK
BELI MANASTIR
Connections with neighboring countries transmission systems
Slovenia
Bosnia and
Hercegovina
Hungary
Italy
Montenegro
InterconnectionsInterconnections
Serbia
Italy
BiH
Hungary
Slovenia
Serbia
Montenegro