Planning Tools and Techniques Module

Jun 21, 2015

Download

Business

hunjoo14

Planning Tools and
Techniques Module
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-1

Page 2: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-2

Page 3: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-3

Assessing the Environment

• Environmental scanning - the screening of large amounts of information to anticipate and interpret changes in the environment.

• Competitor intelligence - an environmental scanning activity by which organizations gather information about competitors.

Page 4: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-4

Forecasting Techniques

• Forecasts - predictions of outcomes.• Quantitative forecasting - forecasting that

applies a set of mathematical rules to a series of past data to predict outcomes.

• Qualitative forecasting - forecasting that uses the judgment and opinions of knowledgeable individuals to predict outcomes.

Page 5: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-5

Exhibit PM-1: Forecasting Techniques

Page 6: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-6

Exhibit PM-1: Forecasting Techniques (cont.)

Page 7: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-7

Benchmarking

• Benchmarking - the search for the best practices among competitors or non-competitors that lead to their superior performance.

Page 8: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-8

Exhibit PM-2: Steps in Benchmarking

Page 9: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-9

Allocating Resources

• Resources - the assets of the organization including financial, physical, human, intangible, and structural/cultural.

• Budget - a numerical plan for allocating resources to specific activities.

Page 10: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-10

Exhibit PM-3: Types of Budgets

Page 11: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-11

Exhibit PM-4: How to Improve Budgeting

Page 12: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-12

Scheduling

• Scheduling - detailing what activities have to be done, the order in which they are to be completed, who is to do each, and when they are to be completed.

• Gantt chart - a scheduling chart developed by Henry Gantt that shows actual and planned output over a period of time.

Page 13: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-13

Exhibit PM-5: A Gantt Chart

Page 14: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-14

Scheduling (cont.)

• Load chart - a modified Gantt chart that schedules capacity by entire departments or specific resources.

Page 15: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-15

Exhibit PM-6: A Load Chart

Page 16: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-16

Scheduling (cont.)

• PERT network - a flowchart diagram showing the sequence of activities needed to complete a project and the time or cost associated with each.

• Events - end points that represent the completion of major activities in a PERT network.

• Activities - the time or resources needed to progress from one event to another in a PERT network.

Page 17: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-17

Scheduling (cont.)

• Slack time - the amount of time an individual activity can be delayed without delaying the whole project.

• Critical path - the longest sequence of activities in a PERT network.

Page 18: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-18

Exhibit PM-7: Steps in Developing a PERT Network

Page 19: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-19

Exhibit PM-7: Steps in Developing a PERT Network (cont.)

Page 20: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-20

Exhibit PM-8: Events and Activities inConstructing an Office Building

Page 21: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-21

Exhibit PM-9: PERT Network forConstructing an Office Building

Page 22: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-22

Breakeven Analysis

• Breakeven analysis - a technique for identifying the point at which total revenue is just sufficient to cover total costs.

Page 23: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-23

Exhibit PM-10: Breakeven Analysis

Page 24: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-24

Linear Programming

• Linear programming - a mathematical technique that solves resource allocation problems.

Page 25: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-25

Exhibit PM-11: Production Data forCinnamon-Scented Products

Page 26: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-26

Exhibit PM-12: Graphical Solution to a Linear Programming Problem

Page 27: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-27

Project Planning

• Project - a one-time-only set of activities that has a definite beginning and ending point in time.

• Project management - the task of getting a project’s activities done on time, within budget, and according to specifications.

• Scenario - a consistent view of what the future is likely to be.

Page 28: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-28

Exhibit PM-13: Project Planning Process

Page 29: Planning Tools and Techniques Module

Management, Eleventh Edition by Stephen P. Robbins & Mary Coulter ©2012 Pearson Education, Inc. publishing as Prentice Hall 9A-29

Terms to Know

• Environmental scanning• Competitor intelligence• Forecasts• Quantitative forecasting• Qualitative forecasting• Benchmarking• Resources• Budget• Scheduling• Gantt chart

• Load chart• PERT network• Events• Slack time• Critical path• Breakeven analysis• Linear programming• Project• Project management• Scenario