-
MAGNETOM
Register 8 EnglishPrint No.: M2-050.031.01.09.02 Doc. Gen. Date:
04/99Replaces: M2-050.031.01.08.02
Siemens AG 1998The reproduction, transmission oruse of this
document or its contentsis not permitted without expresswritten
authority. Offenders will beliable for damages. All
rights,including rights created by patentgrant or registration of a
utilitymodel _or_ design,_are_ reserved.
VisionVision plus
MR
Planning & Installation
Installing the System
-
MAGNETOM Register 8 M2-050.031.01 Page 2 of 4 Siemens AGPlanning
& Installation Rev. 09 04/99 TD SD 23 Medical Engineering
0 - 2 Installing the System
This page intentionally left blank.
-
Contents 0 - 31 _______General
_______________________________________________________ 1 - 1
Read this first . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 1 - 1Safety Note . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 - 2Magnet
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . 1 - 4
Transport dimensions . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 1 - 4Floor Loading . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . 1 - 5Magnet
environment. . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . 1 - 5Availability of LHe when the magnet is shipped
cold . . . . . . . . . . . . . . . . . . 1 - 5Issuing orders and
transport procedures . . . . . . . . . . . . . . . . . . . . . . .
. 1 - 6
Transport routes . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . 1 - 6Issuing the order . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . 1 - 6
Inspecting the magnet shock indicators . . . . . . . . . . . . .
. . . . . . . . . . . . 1 - 7Checking the shock indicators . . . .
. . . . . . . . . . . . . . . . . . . . . . . . 1 - 8
Damage during system transport . . . . . . . . . . . . . . . . .
. . . . . . . . . . . 1 - 8Important notes for the operation of the
magnet . . . . . . . . . . . . . . . . . . . . 1 - 9Component
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . 1 - 10
System components . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . 1 - 10Explanation of the abbreviations used. . .
. . . . . . . . . . . . . . . . . . . . 1 - 11
2 _______Installation of the
RF-room_______________________________________ 2 - 1
Read this first . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 2 - 1Safety . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 -
1General Notes . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . 2 - 2
3 _______Unloading and positioning the
magnet_____________________________ 3 - 1
Additional information . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . 3 - 1Moving the magnet into the room
(through the front) . . . . . . . . . . . . . . . . 3 - 1Moving the
magnet into the room (through the back) . . . . . . . . . . . . . .
. . 3 - 2Checklist . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . 3 - 3
Safety instructions . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 3 - 4Installation Prerequisites . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 4
Transport Requirements . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 3 - 4Completion of the MR suite . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . 3 - 5Tools . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3 - 5
Tools required . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . 3 - 6Unloading . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . 3 - 6
Unloading of a crated magnet . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 3 - 6Unloading a magnet without crate . . . . .
. . . . . . . . . . . . . . . . . . . . 3 - 11Positioning the
rollers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. 3 - 13Moving the magnet into the RF-room . . . . . . . . . . . .
. . . . . . . . . . . 3 - 14
PageSiemens AG Register 8 M2-050.031.01 Page 3 of 6
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
0 - 4 ContentsPositioning the magnet . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . .3 - 15Positioning the magnet
within the markings . . . . . . . . . . . . . . . . . . . .3 -
15Levelling the magnet . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . .3 - 16Adding the aluminium shim plates . . . . .
. . . . . . . . . . . . . . . . . . . .3 - 18Setting the center
height of the magnet . . . . . . . . . . . . . . . . . . . . . .3 -
19
Checking the galvanic separation of the magnet . . . . . . . . .
. . . . . . . . . . .3 - 19Removing the shipping brackets . . . . .
. . . . . . . . . . . . . . . . . . . . . . .3 - 20
At the gradient coil . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . .3 - 20Between magnet and gradient coil . . . .
. . . . . . . . . . . . . . . . . . . . .3 - 21
Sea Ship Kit Removal Instructions . . . . . . . . . . . . . . .
. . . . . . . . . . . .3 - 22Introduction . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . .3 - 22Procedure. . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.3 - 23
Air Ship Kit Removal instructions. . . . . . . . . . . . . . . .
. . . . . . . . . . . .3 - 24Instruction. . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . .3 - 24Procedure. . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
.3 - 25
Determining the temperature . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . .3 - 26General . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . .3 - 26Position of
the carbon temperature sensors . . . . . . . . . . . . . . . . . .
. .3 - 26Flowchart for magnet installation . . . . . . . . . . . .
. . . . . . . . . . . . . .3 - 27Measuring the cryogenic linear
temperature sensors . . . . . . . . . . . . . . .3 - 28
Connecting the quench tube . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . .3 - 30
4 ______ Component installation in the RF-room
____________________________4 - 1
Read this first . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . 4 - 1Example of room layout . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . 4 - 2Remote
control for Magnet Stop . . . . . . . . . . . . . . . . . . . . . .
. . . . . . 4 - 3Installing the table guide support . . . . . . . .
. . . . . . . . . . . . . . . . . . . . 4 - 4
Connecting the ground cables for the AS 25 coil . . . . . . . .
. . . . . . . . . . 4 - 6Installing the magnet covers . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . 4 - 6
Installing the adaption plate for the cable duct of the patient
table . . . . . . . . . 4 - 7Installing the front and back panel .
. . . . . . . . . . . . . . . . . . . . . . . . 4 - 8
Magnet side panels. . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . .4 - 13Side panels . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . .4 - 13DCU
adjustments . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . .4 - 14
Lighting in the patient tunnel . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . .4 - 15Video camera. . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . .4 -
16Installation of the filter plate . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . .4 - 17Installing the RFCC. . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . .4 -
18Installation of patient table . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . .4 - 19
Preparing the patient table . . . . . . . . . . . . . . . . . .
. . . . . . . . . . .4 - 19Opening of the patient table . . . . . .
. . . . . . . . . . . . . . . . . . . . . .4 - 20Removing the
transport brackets . . . . . . . . . . . . . . . . . . . . . . . .
. .4 - 21Installing the cable duct and the patient table . . . . .
. . . . . . . . . . . . . .4 - 22
Intercom . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . .4 - 24
PageMAGNETOM Register 8 M2-050.031.01 Page 4 of 6 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Contents 0 - 55 _______Computer Room
_______________________________________________ 5 - 1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . 5 - 1Read this first . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . 5 - 1Flowchart
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . 5 - 1Prerequisites. . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . 5 - 2Tools . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 -
2Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 5 - 2
Areas prone to earthquakes . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . 5 - 3Bolting the MR cabinets to the floor .
. . . . . . . . . . . . . . . . . . . . . . . . 5 - 3Bolting the
magnet to the floor . . . . . . . . . . . . . . . . . . . . . . . .
. . . . 5 - 4Unloaoding and setting up the three-in-one cabinet . .
. . . . . . . . . . . . . . 5 - 4Unloading and setting up the ACCU
and RFPA cabinet. . . . . . . . . . . . . . . 5 - 6
Installation of ACCU (Air Compressor Chiller Unit) . . . . . . .
. . . . . . . . . . . . 5 - 7General Description/Subsystems . . . .
. . . . . . . . . . . . . . . . . . . . . . 5 - 7Connecting the
on-site water supply. . . . . . . . . . . . . . . . . . . . . . . .
. 5 - 8Connecting the hoses . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . 5 - 10Checking the synthetic hoses for leaks
. . . . . . . . . . . . . . . . . . . . . . 5 - 11
Connecting the cold head with the refrigerator . . . . . . . . .
. . . . . . . . . . . 5 - 12General / Overview . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . 5 - 12Connecting the
semirigid pressure lines via the filter plate . . . . . . . . . . .
. 5 - 13Attaching the half-shells to the filter plate . . . . . . .
. . . . . . . . . . . . . . 5 - 15Connecting the cold head power
cable via the filter plate . . . . . . . . . . . . . 5 -
17Connecting the water hoses for the gradient coil . . . . . . . .
. . . . . . . . . 5 - 18Connecting the ramping cables to the filter
plate . . . . . . . . . . . . . . . . . 5 - 23Connecting the
monitoring cables to the filter plate . . . . . . . . . . . . . . .
. 5 - 24Connecting the gradient cable plate . . . . . . . . . . . .
. . . . . . . . . . . . 5 - 25
Control and Supervision . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . 5 - 25Room thermostat . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . 5 - 26
6 _______Control room
__________________________________________________ 6 - 1
Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . 6 - 1MR-console . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . 6 - 2
Key caps to be replaced . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . 6 - 4Alarm box . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . 6 - 5
PageSiemens AG Register 8 M2-050.031.01 Page 5 of 6
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
0 - 6 Contents7 ______ Component cabling
_____________________________________________7 - 1
Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . 7 - 1Additional information . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . 7 - 1
Circuit diagrams . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 7 - 1Bending radius for cables . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . 7 - 1Type numbers . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 -
2
Ready, set, go . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . 7 - 3We recommend the following cable
installation to avoid spikes . . . . . . . . . . . . 7 - 3
Cabling in the computer room . . . . . . . . . . . . . . . . . .
. . . . . . . . . 7 - 3Cabling in the magnet room . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 7 - 3Cabling in the control
room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 -
3
Line voltage connection . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . 7 - 4Line voltage cable . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . 7 - 4Protective
conductor cables . . . . . . . . . . . . . . . . . . . . . . . . .
. . . 7 - 6
Detailed views of component connections . . . . . . . . . . . .
. . . . . . . . . . . 7 - 8Gradient cables . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . 7 - 8Overview of
connectors on top of the PCA cabinet. . . . . . . . . . . . . . . .
.7 - 11Overview of connectors on top of the CCA cabinet. . . . . .
. . . . . . . . . . .7 - 12Overview of the connectors on top of the
RFPA cabinet . . . . . . . . . . . . . .7 - 13Overview of the table
connectors . . . . . . . . . . . . . . . . . . . . . . . . . .7 -
14Overview of the RFAS connectors . . . . . . . . . . . . . . . . .
. . . . . . . .7 - 15Preasurized air connections between Resonator
and RFAS . . . . . . . . . . . .7 - 16Overview of the RFCC
connectors . . . . . . . . . . . . . . . . . . . . . . . . .7 -
17Top view of ACCU . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . .7 - 18
Cable routing . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . .7 - 19Cable numbers . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . .7 - 19
Installing the shim filter assembly . . . . . . . . . . . . . .
. . . . . . . . . . . . .7 - 20Protective Conductor Test . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . .7 - 21Installing
the magnet covers . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . .7 - 21Examples of cable installations. . . . . . . . . . .
. . . . . . . . . . . . . . . . . .7 - 22
Computer room . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . .7 - 22Magnet room . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . .7 - 24
8 ______ Changes to previous version
_____________________________________8 - 1
PageMAGNETOM Register 8 M2-050.031.01 Page 6 of 6 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
1 - 1
MAGNETOMning & Installation
General 1Siemens AG Register 8 M2-050.031.01 Page 1 of 12Medical
Engineering Rev. 09 04/99 TD SD 23 Plan
Read this first 1The separate installation guide provided
previously with the system documentation has been elimi-nated.
Register 8 of the Planning Guide is the reference guide for the MR
installation. The individual installation steps are described in
detail in the respective chapters of this manual.Information
regarding site-planning is contained in the Planning Guide.The
flowchart below provides you with an overview of the complete
installation.
Fig. 1 Installation flowchart
Install2
Preliminary stepschapter 1 (this chapter)
MagnetOR35refer to chapter 3
Rem.systemcomp.refer to chapter 4
Control roomrefer to chapter 6
Computer roomrefer to chapter 5
CablingMagnetcovers
refer to chapter 7
Start-up (register 1 of Start-up manual)
InstallationStart
RF-roomrefer to chapter 2
-
1 - 2 GeneralSafety Note 1The superconducting magnet described
in this document is designed for use with whole body Magnetic
Resonance Imaging (MRI) systems. The magnet is designed for
stationary use.
Wear the following protective clothing:
safety shoes face mask gloves (cryogenics) leather gloves
(RF-room)
Always
wear protective clothing (leather gloves, safety shoes, hard
hats) inspect all equipment and tools for defects prior to use
ensure that tools and auxiliary materials are in satisfactory
condition and conform to manufacturers
specifications (comply with legal regulations) use only the
transport devices specified inform temporary personnel assigned to
Siemens employees of the potential hazards and of the
safety measures to be taken when handling heavy loads secure the
transport device and load before moving the load report defects to
supervisors immediately
Superconducting magnets are highly sensitive pieces of medical
equipment. Use utmost caution during transport and delivery to
avoid hazardous condi-tions to the equipment as well as the
personnel. Only specially trained per-sonnel may install/service
the magnet. Review the safety instructions before working on the
magnet.
Adhere to the safety information in Register 2 of this manual
when performing the work described in this chapter.
CAUTION
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 2 of 12 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
General 1 - 3Never
stand under heavy loads use defective or damaged equipment allow
personnel to stay close to a moving load exceed the load capacity
of devices route or stretch ropes, chains and straps over sharp
edges knot rope or chains twist rope block emergency exits
Refer to Register 2 of this manual for a detailed description of
the various safety recommendations for electrical or mechanical
activities.
NOTICESiemens AG Register 8 M2-050.031.01 Page 3 of 12
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
1 - 4 GeneralMagnet Overview 1
Transport dimensions 1 Maximum height (current probe inserted)
2508 mm Minimum height 2411 mm Width 2150 mm Length 2264 mm Magnet
weight (with gradient coil and cryogens) 8000 kg Gradient coil
weight 1500 kg
Fig. 2
You have to add the diamensions of the transport tools which
will be used.
For detailed smallest possible transport dimensions refer to
register 5, chap-ter 1 of this manual.
M-or35
NOTICE
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 12 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
General 1 - 5Floor Loading 1Request assistance from a civil or
constructional engineer. This applies for: Installation on ground
level with a solid base Installation on one of the other floors or
a suspended floor Installation on a sectionally constructed floor
such as timber or pre-cast concrete slabs
Magnet environment 1
Availability of LHe when the magnet is shipped cold 1
Ferromagnetic objects in close proximity to the magnet
adverselyaffect the field homogeneity of the magnet.
Just like the Impact magnet, the OR 35 magnet is usually shipped
cold. No time will be lost to precooling the magnet. Instead it can
be filled with helium immediately after it has been moved into the
building. For that purpose you should have at least 450 liters of
liquid helium on-site.
Refer to chapter 3 in this register for checking the temperature
and/or the liq-uid helium level of the magnet.
In case the magnet is shipped warm, refer to chapter 3 in
Register 1 of the Start-up manual.
NOTICE
NOTICE
NOTICE
NOTICESiemens AG Register 8 M2-050.031.01 Page 5 of 12
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
1 - 6 GeneralIssuing orders and transport procedures 1 All
transport activities, including delivery into the RF room, should
be performed by a licensed carrier
only. Transport of the magnet or any other heavy components by
SIEMENS employees is prohibited.
Transport routes 1 Before issuing orders to the carrier, the
project manager and the architect/construction engineer must
determine the weight capacity of the floor along the transport
route and in the temporary storage areas. The
architect/construction engineer must certify in writing that the
route can withstand the expected load.
It is the responsibility of the carrier to obtain information
concerning the various transport routes before the actual
transport. Copies of the transport plans and certification must be
provided by the carrier upon receipt of the order.
Issuing the order 1 The order for transport by a licensed
carrier must be issued in writing. In addition to general
information (e.g., a list of parts, etc.), the order must
contain the following data and documen-tation:
Copies of plans for the transport route/temporary storage areas.
Copy of the certification regarding the weight capacity of the
floor. Final destination of transport.
(It is recommended that the carrier obtain information
concerning the transport route before the actual transport).
Weight of components to be transported (refer to Register 1 of
this folder). Dimensions of components to be transported (refer to
Register 1 of this folder). Use of transport devices. MAGNETOM
Register 8 M2-050.031.01 Page 6 of 12 Siemens AGPlanning &
Installation Rev. 09 04/99 TD SD 23 Medical Engineering
-
General 1 - 7Inspecting the magnet shock indicators 1The shock
indicators are located at the back of the magnet (right side,
middle section) as seen from the patient table. One is configured
for 2 g, the other one is for 6 g.
Inspect the shock recorders immediately on the truck when the
magnet arrives at the installation site (refer to the figure on the
next page).
Check the condition of the shock indicators again after final
positioning of the magnet in the magnet room.
Fig. 3
Report the shock indicator status to OMT, Oxford, using the form
and enve-lope enclosed with the shipment.
Shock_3
NOTICESiemens AG Register 8 M2-050.031.01 Page 7 of 12
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
1 - 8 GeneralChecking the shock indicators 1
Damage during system transport 1Inform the carrier immediately
if you detect damage to the packing or the product.After you have
informed the carrier, send a FAX to the Oxford Shipping Department
and to TD MR in Erlangen. Indicate the nature or extent of damage
in the fax. If at all possible, includephotographs of the damaged
items.
Fig. 4 Undamaged shock indicators
Do not forget to complete the Magnet Acceptance Protocol
(included inRegister 9 of the System Manual)
Check all items against the packing list supplied with each
magnet and notify the Oxford Quality Department and TD MR in
Erlangen by FAX of any short-age or damage.
Shocki_1
The shock indicators are o.k if the balls are stillin the
holders.
NOTICE
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 8 of 12 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
General 1 - 9Important notes for the operation of the magnet
1
Fig. 5
1 It is essential that the installation/operators manual be read
and understood before commenc-ing any operation on the system.
2 Always wear protective clothing when handling cryogens and
heed all warnings and safety notices associated with cryogens and
magnetic fields.
3 Never allow recommended pressure levels to be exceeded in
cryogen dewars or vessels inside the magnet.
4 Before energizing the magnet, ensure that the ERDU is
connected to the magnet and in full working order.
5 Always ensure that the helium vessel is fully depressurized
before removing any blanking plug buffle set or fitting from the
turret.
6 Always check that the current probe is connected for the
correct magnet polarity before run-ning current into or out of the
magnet and ensure that gas is venting through the probe with
adequate flow.
7 Never leave a running magnet power supply unattended while it
is in operation. Before remov-ing the current probe, ensure the
power supply is in standby and no fault lights are illuminated.
8 Always keep a log of any operation performed and record
cryogen levels on a daily basis.
9 Never allow the helium level to fall below the recommended
minimum.
10 Always keep a stock of essential spares on-site.
ImportantNotes
The Important Notes are located on the right side ofthe magnet
as seen from the patient table (fig. 1-5 on the left).These notes
are very important for the installation engineer and operator.
Installation engineer/operatorPlease read this first.(Text is
also listed below).Siemens AG Register 8 M2-050.031.01 Page 9 of 12
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
1 - 10 GeneralComponent Overview 1
System components 1
Refer to the next page for a listing of the system
components.
Fig. 6 System overview VISION
compon_1
RFfilterplate&RFCC
ACCU RF-Power MR-ElectronicsCabinet
CCA PCA GPS
Alarmbox
MagnetOR35
Patienttable
19" 15"
MRCMAGNETOM Register 8 M2-050.031.01 Page 10 of 12 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
General 1 - 11The system consists of the following components:
Magnet 1.5 Tesla / Type OR35 ACCU Cabinet (Air Compressor Chiller
Unit), RF Power Cabinet MR Electronics Cabinet (consisting of
CCA/PCA/GPS) RF Filter Plate and RFCC, Patient Table, Alarm Box,
MRC
Explanation of the abbreviations used 1
The installation instructions contain certain abbreviations
which are explained below: CCA Control Cabinet PCA Power Cabinet
GPS Gradient Power Supply RFPA Radio Frequency Power Cabinet ACCU
Air Compressor Chiller Unit RFCC Radio Frequency Control Cabinet
RFAS Radio Frequency Amplifier System MRC MR Console MRSC MR
Satellite Console SMI Siemens Medical Imager CCU Communication
Control Unit RFSU Radio Frequency Small UnitSiemens AG Register 8
M2-050.031.01 Page 11 of 12 MAGNETOMMedical Engineering Rev. 09
04/99 TD SD 23 Planning & Installation
-
1 - 12 GeneralThis page intentionally left blank.MAGNETOM
Register 8 M2-050.031.01 Page 12 of 12 Siemens AGPlanning &
Installation Rev. 09 04/99 TD SD 23 Medical Engineering
-
2 - 1
MAGNETOMning & Installation
Installation of the RF-room 2Siemens AG Register 8 M2-050.031.01
Page 1 of 2Medical Engineering Rev. 09 04/99 TD SD 23 Plan
Read this first 2Most of the modular RF-rooms used in Germany
and Europe are manufactured by Siemens Matsush-ita GmbH & Co.
KG in Heidenheim and installed by a team of Simon Hegele employees.
In view of Sie-mens Med minimal involvement in these areas and the
separate, detailed documentation available on the subject, we are
only providing General Notes for the RF-room installation.
However, you can always contact Siemens Med, TD MR 7, in
Erlangen, if you have questions regard-ing the installation of the
RF-room. The telephone numbers to call are ..-9131-84-3791 or
6201.
Safety 2The following should be worn during the installation of
the RF-room: Protective gloves (made from leather) Safety shoes
Safety helmet Safety glasses
When using other RF-rooms (e.g. copper or aluminium-clad
RF-rooms, etc.) outside of Germany or Europe, manufacturers
specifications and installation instructions should be used.
Refer also to Register 2 of this manual.
NOTICE
NOTICE
-
2 - 2 Installation of the RF-roomGeneral Notes 2 The RF-room and
floor have to be completed before the magnet arrives at the site.
Ensure that the
opening in the RF-room wall allows for easy transportation of
the magnet into the room. The floor has to be level (including the
grouting, etc.) It is recommended to start the installation of the
first side panel at the corner located opposite the RF-
room door. The contact surfaces of the RF-gaskets (used with
particular designs) should be free of grease. The nuts should be
tightened with the torque specified by the manufacturer. The
RF-integrity of the RF-room must be measured (attenuation 90 dB).
The door contacts cannot be damaged. The protocols must be filled
out and filed with the other protocols (register 9 of the system
manual).
The spectroscopy retrofit requires a second filter plate which
includes the RF wave guides for the gradient cables.Depending on
the location of the second filter plate, the gradient cables may
not be long enough. For this reason install the second filter plate
in a way, which allows you to reuse the gradient cables.
Dont forget the RF-gaskets while installing the filter plate for
the copper-clad or steel-clad RF-room.
NOTICE
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 2 of 2 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
3 - 1
MAGNETOMning & Installation
Unloading and positioning the magnet 3Siemens AG Register 8
M2-050.031.01 Page 1 of 30Medical Engineering Rev. 09 04/99 TD SD
23 Plan
Additional information 3
Moving the magnet into the room (through the front) 3 If there
is very little room between the sides of the magnet and the wall,
move in the rear magnet
covers before positioning the magnet on its location.
Depending on the space available and the layout of the
facilities, the cabinets may have to be moved into the computer
room before transporting the patient table, magnet cover, and
magnet into the MR suite.Refer to the examples on the next two
pages for further details.The order of bringing in the system
components depends on the location of the opening for magnet
transport plus the space available for magnet posi-tioning.
Fig. 1 Handling of the rear magnet covers when the installation
is from the front
NOTICE
Raump_1
Installing the magnet through the front
Final position of the rear magnet coverframe
It is not possible to install the rear coversbecause there is
not enough spacebetween the magnet and the RF wall!
-
3 - 2 Unloading and positioning the magnetMoving the magnet into
the room (through the back) 3 Move in the patient table and the
front magnet cover before positioning the magnet on its
location.
Fig. 2 Handling of the front magnet covers and the patient table
when the installation is from the back
Raump_2
Installing the magnet through the back
Front magnetcover frame
Patie
nt ta
bleMAGNETOM Register 8 M2-050.031.01 Page 2 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 3Checklist 3 This
checklist ranges from the preliminary steps to moving/installing
the magnet
Fig. 3 Checklist for the magnet installation
Required L-Heliumon site or ordered
Rooms completed
checkl
RF-room installed
Waterinstallation forACCU prepared
Final location ofmagnet marked
Magnet moved inACCU positioned
Finalized transportroute
Roped off unloadingzone
Coldhead connected
Licensed carrierinformed/crane
Yes No
ACCU
MagnetSiemens AG Register 8 M2-050.031.01 Page 3 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 4 Unloading and positioning the magnetSafety instructions 3
Always wear safety shoes and protective clothing Never stand under
heavy loads Rope off the unloading zone (take into consideration
detours or other traffic regulations) Use only tools which are in
good working condition
Installation Prerequisites 3
Transport Requirements 3 Ensure that the magnet room is ready
and the RF-shielding is installed. Ensure that the opening to the
RF-room is large enough (refer to the Planning Guide). Verify
dimensions of the RF-room opening (height, width; refer to the
Planning Guide). Provide temporary storage for the magnet with
sufficient floor load capacity
(refer to the Planning Guide). Ensure sufficient space for
magnet installation (refer to the Planning Guide). Take into
account obstructions due to dropped ceilings, support beams, and
columns. Determine the final magnet location in the RF-room (refer
to the Planning Guide). Verify that the water for the ACCU has been
routed to the final location of the ACCU. In this way you
will be able to quickly connect the compressor. This is an
important advantage when the magnet has been shipped cold, and the
cold head has to be connected immediately to reduce the boil-off
rate.
Rope off the unloading zone to prevent injury to onlookers.
Avoid blocking emergency or other vital access routes to the
hospital. Stay within traffic regulations. If necessary, get in
touch with the hospital administration. Only a licensed carrier
should transport the magnet to the site and into the magnet
room.
To ensure maximum safety for the personnel and the system, the
chains, straps, or other lifting devices, as well as the hydraulic
lifts and the steel roll-ers must be in good working condition.
Read through this chapter carefully. It lists all the
items/steps that should have been completed or prepared before the
magnet arrives at the site.
The distance of the truck to the unloading zone determines the
size and capacity of the crane.
CAUTION
NOTICE
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 5Completion of the MR
suite 3 The rooms have been completed. This means that the RF-room
has been installed including
the opening for moving in the magnet. In addition, the room
should have sufficient light and the floor should be level and
clean for easy transportation of the system.
The four corners of the magnet have been drawn on the floor of
the RF-room (refer to Fig. 3-28 on page 22 of this register).
The floor from the unloading zone to the final location of the
magnet in the examination room has been covered with steel plates
(min. 5 mm thick).
The tools and auxiliary tools must be on-site (steel rollers,
hydraulic lifts, etc.) For detailed information refer to chapter 1
of this register (transport requirements). Review the checklist one
more time (page 4 of this chapter).
Tools 3
Fig. 4 Transport rollers for moving heavy loads
Manruverable in every direction Four sets of steel rollers with
a weight capacity of3 tons each.
The four sets of the steel rollers should be fully maneuverable
in every direction. Siemens AG Register 8 M2-050.031.01 Page 5 of
30 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning
& Installation
-
3 - 6 Unloading and positioning the magnetTools required 3 Four
hydraulic lifts Sufficient number of steel plates (5mm thick for
covering the floor). Several crowbars for positioning and moving
the magnet. Standard tool set 4 insulation plates (included in the
magnet shipment) Aluminium shim plates for levelling out the magnet
(included in the magnet shipment) Water level Yardstick Fluke meter
Protective ground meter Special tools for magnet installation Water
hose level 4 shackles (load capacity 3000 kg each) 4 chains/ropes
(each approximately 4m in length, load capacity 3000 kg each)
Unloading 3
Unloading of a crated magnet 3
Ensure that the measurement devices and tools are in good
working condi-tion.
Fig. 5 Magnet shipped in overseas container
NOTICE
For deliveries outside Europe, the magnet is shippedin an
overseas container. MAGNETOM Register 8 M2-050.031.01 Page 6 of 30
Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23
Medical Engineering
-
Unloading and positioning the magnet 3 - 7Fig. 6 Marks
indicating the openings for lifting the magnet
Fig. 7 Opening for the chains
Fig. 8 Feeding the chains through the opening using a bar
There are two openings in the floor of the container. Use only
these openings in combination with the lift-ing device (rope or
chain).
Feed the chains through these openings.
Use the bar for this purpose. Siemens AG Register 8
M2-050.031.01 Page 7 of 30 MAGNETOMMedical Engineering Rev. 09
04/99 TD SD 23 Planning & Installation
-
3 - 8 Unloading and positioning the magnetFig. 9 Overseas
container lifted by the crane
Fig. 10 Lifting the container from the truck
Fig. 11 Removing the screws on each side
The chains can be extended as required.
The tension of the chains must be distributed uniformly for
lifting the container.
The overseas container should be lifted carefully from the
truck.
Location of screwss Remove the screws which connect the
upper
section with the lower section of the container. Each side has 4
screws. MAGNETOM Register 8 M2-050.031.01 Page 8 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 9Fig. 12 Attaching the
ring nut
Fig. 13 Running the chain through the lifting eye
Fig. 14 Removing the upper section of the container
Attach a ring nut to each side of the container.
Each corner has a hole for the ring nut. The hole is located at
a height of approximately 2 m.
Attach a lifting eye to each of the 4 ring nuts and run the
chain through the lifting eye.
Remove the upper section of the container. Siemens AG Register 8
M2-050.031.01 Page 9 of 30 MAGNETOMMedical Engineering Rev. 09
04/99 TD SD 23 Planning & Installation
-
3 - 10 Unloading and positioning the magnetProceed with the
transportation of the magnet into the building as described on the
next pages.
The magnet is attached to the four corners of the container
floor.Remove the four nuts before you lift the magnet from the
container. The same four holes can be used to bolt the magnet to
the floor in areas prone to earthquakes.
Fig. 15 Attachment points of the chains
Attach the chains to the magnet as described under Domestic
transport with-out crate (page 12 and up).
Lift up the magnet carefully out of the lower container and
position it on the four transport rollers.
NOTICE
Mag_1
Attach the lifting eyes with the chains atthis points only!
NOTICE
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 10 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 11Unloading a magnet
without crate 3 Use four ropes or chains with a capacity of at
least 3000 kg per rope/chain (length of rope/
chain is approx. 4 m).
Fig. 16
Fig. 17 Attaching the lifting eyes
Remove the remaining crates carefully from the truck.
When opening the crates, do not damage any system
components.
30mm
Lifting eye
Diameter25 mm
Attach the four lifting eyes to the magnet.
The bolts should have a diameter of 25 mm. The inside diameter
of the lifting eye at the magnet is 29 mm. The width of the lifting
eyes must be 30 mmSiemens AG Register 8 M2-050.031.01 Page 11 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 12 Unloading and positioning the magnetFig. 18 Hooking the
shakle into the lifting eye
Fig. 19 Magnet lifted by the crane
Do not damage or tear off the connections on the turret or other
pipes at the magnet. The transport rollers should be positioned on
the steel plates by now (refer to Fig. 20 on page 13).
Proceed slowly while unloading the magnet from the truck.Never
stand under the magnet during the unloading process.
Shackle Hook the four shackles into the lifting eyes. The
opening of the shackle has to be secured by a safety slide.
To prevent the shackle from getting twisted, it should have
enough space in the lifting eye.
Raise the magnet slowly.
Before you lift the magnet from the truck, ensure once more that
the shackles and lifting eyes are fitted correctly.
NOTICE
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 12 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 13Positioning the
rollers 3
Position the four maneuverable steel rollers under the
magnet.
Lower the magnet carefully onto the rollers.
Identify the front and the back of the magnet. Position the
magnet correctly on the steel rollers so that you do not have to
turn it around in the RF-room.
Fig. 20 Configuration of the four sets of transport rollers
Verify that the magnet and the steel rollers are balanced.
The steel rollers must not shift when you move the magnet. If
they do, the magnet may be damaged when it slides off the
rollers.
NOTICE
ANORD_1
Maneuverablesteelrollers
Aluminiumbeams Magnet
NOTICE
CAUTIONSiemens AG Register 8 M2-050.031.01 Page 13 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 14 Unloading and positioning the magnetMoving the magnet
into the RF-room 3
To facilitate moving the magnet, a manual or electrical cable
winch can be used.
Fig. 21 Steering the magnet with the front rollers
Move the magnet slowly and carefully!
Fig. 22 Moving the magnet with a cable winch
Ensure that the ropes attached to the magnet do not damage the
magnet or the gradient coil.When using the cable winch, ensure that
the magnet does not pick up speed (especially when the floor runs
slightly downhill).
Steer the magnet into the desired direction with the four
rollers.
NOTICE
Mag_3
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 14 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 15Positioning the
magnet 3
Positioning the magnet within the markings 3
Position the magnet exactly above the markings on the floor
(refer to the Register 3, chapter 1-6 of this manual). It is not
necessary to draw the markings for the insulation and shim plates.
However, just before positioning the magnet, verify that insulation
and shim plates are handy.
Fig. 23 Slowing down the magnet
Adhere to the distances required for the side panels. They may
vary accord-ing to the size and layout of the room.
Fig. 24 Removing the transport rollers
Magnet transport can be slowed down by using wooden blocks.
NOTICE
Insert the four swan necks into the magnet supportbeams
Move the four hydraulic lifts underneath the swan necks.
Raise the magnet uniformly and remove the rollersSiemens AG
Register 8 M2-050.031.01 Page 15 of 30 MAGNETOMMedical Engineering
Rev. 09 04/99 TD SD 23 Planning & Installation
-
3 - 16 Unloading and positioning the magnet Lower the magnet
carefully and uniformly onto the floor.
Levelling the magnet 3
The objective is to align the magnet in the horizontal and to
set the center height of the magnet.For that purpose, you need the
following tools:
Water hose level Insulation plates Aluminium shim plates
Hydraulic lifts
Fig. 25 Markings for the magnet
Leave the hydraulic lifts at the magnet. You will need them
again.
Mark_2
Patie
nt E
nd
Serv
ice
End
Markings for thecornerpoints ofthe magnet
Magnetsupportbeams
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 16 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 17Procedure Use the
water level hose to level A with B and C with D (in the x
direction). Raise the magnet with the hydraulic lifts and slide the
insulation plate and the aluminium shim plates
between the magnet support beam and the floor (refer to Fig. 27
as well). Lower the magnet and verify that A,B and C,D are aligned
with one another. If they are not , add more
shim plates until the markings match the water level.
Subsequently, check whether A is level with C (on the left side of
the magnet) and B is level with D (on
the right side of the magnet). Align the magnet referring to the
markings on the flor in the z direction(as described in Fig.
25).
Finally, check the alignment of all four points, A,B,C, and D,
to one another. The markings must be on the same level according to
the water hose level. Acceptable tolerance is 3 mm.
Fig. 26 Leveling the magnet with a waterhose level
Verify that the magnet rests squarely on the floor.
Centrpu1
PatientEnd
leveling hose
X
Z
Y A
B
C
D
CAUTIONSiemens AG Register 8 M2-050.031.01 Page 17 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 18 Unloading and positioning the magnetAdding the aluminium
shim plates 3 Slide the insulation plates and the aluminium shim
plates underneath the magnet support beam
(the number and the thickness of the aluminium shim plates
depend on how much the magnet alignment deviates from the values of
the water hose level).
For each corner of the magnet you are provided with the
following amount of plates: 5 x 1mm aluminium shim plates 1 x 3mm
aluminium shim plates 1 x 5mm insulation plateThe size of the
plates is 300mm x 200mm.
Fig. 27
51
23 Shimpl_1
Magnet support beam
Shimplates
Insulation plateMAGNETOM Register 8 M2-050.031.01 Page 18 of 30
Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23
Medical Engineering
-
Unloading and positioning the magnet 3 - 19Setting the center
height of the magnet 3 Measure the center height of the magnet.
It should be 1100 mm (max. 1105 mm, min. 1095 mm). Either add or
take away the same number of aluminium plates at each corner of the
magnet until the
center height of the magnet is 1100 mm.
When the magnet is aligned correctly, remove the hydraulic
lifts. Store the remaining aluminium shim plates in a safe
place.
The procedure for positioning the magnet is now completed.
Checking the galvanic separation of the magnet 3 Ensure that the
magnet is galvanically separated from the RF-room.
Fig. 28 Measuring the center height of 1100 mm
Check once more the horizontal alignment of the magnet, the
distance to the walls on either side, as well as the center
height.
The magnet must rest squarely on the floor!
The magnet must be galvanically separated from the RF-room.
Centrpu3Patient
End
1100
+/-5
m
m
NOTICE
CAUTION
CAUTIONSiemens AG Register 8 M2-050.031.01 Page 19 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 20 Unloading and positioning the magnetRemoving the shipping
brackets 3
At the gradient coil 3
To ensure safe transport, the gradient coil is secured on each
side by two brackets and four screws.
Each end of the magnet support beams includes a hole for bolting
the magnet to the floor in areas prone to earthquakes.
Fig. 29 Position of the brackets
NOTICE
Brackets Remove the two brackets in front and in back of
the magnet.MAGNETOM Register 8 M2-050.031.01 Page 20 of 30
Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23
Medical Engineering
-
Unloading and positioning the magnet 3 - 21Between magnet and
gradient coil 3
Fig. 30 Location of the screws at the upper coil suspension
Fig. 31 Location of the screws at the lower coil suspension
Screw
Lock nut
Apply Loctite 221 to the upper screws (two each in front and
back) and back up the screws to the endstop.
Secure the screw with the lock nut.
Screw
Lock nut
Apply Loctite 221 to the lower screws (two each in front and
back) and back up the screws to the endstop.
Secure the screw with the lock nut.Siemens AG Register 8
M2-050.031.01 Page 21 of 30 MAGNETOMMedical Engineering Rev. 09
04/99 TD SD 23 Planning & Installation
-
3 - 22 Unloading and positioning the magnetSea Ship Kit Removal
Instructions 3
Introduction 3If the magnet system has been sea freighted with
liquid helium contained in the helium vessels, the venting system
will be equipped with a relief valve and bursting disk, regulating
the pressure in the sys-tem to 2 bar absolute (see figure
below.)The magnet system can be left safely venting through the
relief valve, until depressurizing is required. When
depressurization is required, carefully follow the procedure
described below.
Fig. 32 Sea ship kit
Ensure that the system includes the DCL Baffle and 1/3 psi
pressure gauge before you perform this procedure.
SEASHIP1
Blank
30 psia relief valve
Helium syphonventline
Quench valve with integral10 psi bursting disc
Pressure gauge
AutofillHelium syphon Depressurisation
valve (shown closed)
2 Bar bursting disc
1/3 PSI non return valve
Shut off valve(shown on anelbow for clarity)
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 22 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 23Procedure 3
Check that the shut-off valve at the quench valve is in the
closed position (handle is at right angles to the valve axis.)
Remove the VW25KF blank from the end of the shut-off valve and
connect the valve to the site venting.
Ensure that the pipes used are supported and not left to hang on
the connections alone. If the site venting is not installed, run
the pipes to atmosphere outside the MR suite.
To minimize the amount of helium lost, open the shut-off valve
slowly to approximately 15 degrees from the closed position and
monitor the pressure gauge.
Helium gas should now be heard escaping. The vent line will cool
in a few minutes until it becomes very cold.
When the pressure indicated on the gauge has dropped to 5 psi,
the valve opening should be gradually increased until fully
open.
Open the depressurization valve.
Allow the system to depressurize until the vent line has thawed,
indicating the system is now at atmospheric pressure.
Remove the bursting disk assembly from the end of the quench
valve and connect the site venting to the quench valve.
Remove the 30 psia valve assembly and replace it with the
stopper rod (baffle assembly) which is packed in the accessories
case.
Replace the 2 bar pressure gauge with the 1/3 psi gauge which is
packed in the accessories case.
This procedure should be performed only by trained personnel,
wearing pro-tective clothing.
Helium gas should not be allowed to vent into the MR suite or
any other closed room.
Do not come in contact with cold components. Do not smoke or use
open flames.
The following operations should be performed quickly to prevent
air from entering the system.
NOTICE
NOTICE
NOTICE
NOTICESiemens AG Register 8 M2-050.031.01 Page 23 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 24 Unloading and positioning the magnet Remove the shut-off
valve from the quench valve and blank the outlet with an NW25KF
blank and check the depressurization valve. The system will now
pressurize to its normal operating pressure, 1/3 psi (approx. 20
mbar).
Pack the removed parts and return them to the Oxford Service
Department for reuse.
Adress:
Oxford Magnet Technology Ltd.Wharf Road, EynshamWitney, Oxon OX8
1BP, EnglandTelephone: 0044 (1865) 880 880Fax: 0044 (1865) 880
872
Air Ship Kit Removal instructions 3
Instruction 3If the magnet system has been air freighted with
liquid helium contained in the helium vessel, the vent-ing system
will be fitted with relief valve which ensure that the pressure
within the helium vessel is kept above atmospheric pressure.The
magnet system can be left safely venting through the relief valves
until depressurisation is required.
Fig. 33 Air ship kit
AIRSHIP2.AI
Blank
13 psig relief valveHelium syphonventile
Quench valve with integral10 psi bursting disc
Blank 16 psia reliefvalve
Pressure gauge
SmartHelium Syphon
Depressurisationvalve (shown closed)
Blank A
F
D
B
E
C
depressurisationlineMAGNETOM Register 8 M2-050.031.01 Page 24 of
30 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD 23
Medical Engineering
-
Unloading and positioning the magnet 3 - 25Procedure 3
Remove the blanking plug (A) from the end of the
depressurisation line. There may be a small release of gas, but
there should not be a continuous flow. If there is, cap off the
tube and call the Oxford Service Department, since there may be a
fault with the quench valve. Do not proceed further since this
might allow air to enter the system.
Assuming there is no flow refit blank (A) and remove the large
blanking flange (B) from the end of the quench valve and connect
the site venting to the quench valve.
Open the depressurisation valve (C).
Allow the system to depressurise until the depressurisation line
has thawed, indicating that the system is now at atmospheric
pressure.
Remove the 13 psig valve (F) assembly and and replace it with
the current lead baffle assembly which is packed in the accessories
case.
Remove the 16 psia valve (D) from the 1/3 psig valve (E), remove
blank (A) from the Tee, connect the Tee to the 1/3 psig valve and
close the depressurisation valve (C). The system will now
pressurise to its normal operating pressure, 1/3 psi.
Pack the remove parts and return them to the Oxford Service
Department for re-use.(Address for the return parts on page 24)
Proceed with care during the depressurization procedure
described on this page.
This procedure should only be carried out by trained personnel,
wearing pro-tective clothing.Ensure DCL Baffle is on hand prior to
carrying out this procedure.
Helium gas should not be allowed to vent into the imaging suite
or any closed room.
Do not touch the cold parts. Smoking and naked lights are
forbidden.
The following operation should be done quickly to prevent air
entering the system.
CAUTION
NOTICE
NOTICE
NOTICE
NOTICESiemens AG Register 8 M2-050.031.01 Page 25 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 26 Unloading and positioning the magnetDetermining the
temperature 3
General 3The magnet is usually shipped cold. However, the magnet
may warm when it is shipped to certain countries or when it is in
transport or storage for an extended period of time.For that
reason, the temperature of the helium vessel should be determined
as quickly as possible after the magnet arrives at the customer
site. The temperature of the helium vessel is measured via the
three carbon temperature sensors in the helium vessel.If the magnet
is still cold, that is, the vessel contains liquid helium, the
temperature can be maintained if you refill the magnet immediately
with liquid helium. You will not only save time, you will also save
a great deal of money.However, should the magnet have warmed, you
have to pump down the vacuum and fill it with helium again.Refer to
the next page for instructions on how to measure the temperature as
well as on how to deter-mine the threshold between a warm and a
cold magnet.
Position of the carbon temperature sensors 3
Fig. 34
Sensor
R-Top
R-Middle
R-Bottom
Heliumvessel
The helium vessel contains three carbon temperature sensors.
MAGNETOM Register 8 M2-050.031.01 Page 26 of 30 Siemens AGPlanning
& Installation Rev. 09 04/99 TD SD 23 Medical Engineering
-
Unloading and positioning the magnet 3 - 27Flowchart for magnet
installation 3The course of the magnet installation is illustrated
in the flowchart shown below.The diagram on the next page helps you
in determining whether the magnet is warm or cold.
Fig. 35 Flowchart for determing the temperature
Flolw_2
Determining the magnet temperature by measuring viathe
carbonsensors or the helium service levelmeter
and by comparing these values with the values from theOMT
factory acceptance protocol
Quench tube installation(or tempory exhaust to theoutside)LHe
refilling up to100% (98%)
Magnet cold =Temperature is between
helium and nitrogentemperature
Refilling liquid heliumrefer to register 8,
chapter 1"Preventive Maintanance"
Magnet warm =Temperature is between
nitrogen and roomtemperature
Precooling and filling ofthe magnet OR 35refer to Start up
manualregister 1"System Start-up"
Continue with start upMagnet / ACCUon the next pages Siemens AG
Register 8 M2-050.031.01 Page 27 of 30 MAGNETOMMedical Engineering
Rev. 09 04/99 TD SD 23 Planning & Installation
-
3 - 28 Unloading and positioning the magnetMeasuring the
cryogenic linear temperature sensors 3 Use a digital voltmeter and
measure the resistance (in ohm) of every CTLS at plug C on the
magnet
service turret.
Fig. 36 Location of plug C
A
B
Ca
b
c
d
eCommon
R-Bottom
R-Top
R-Middle
C-plug
Plug C MAGNETOM Register 8 M2-050.031.01 Page 28 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Unloading and positioning the magnet 3 - 29 Enter the actual
values measured at the sensors into the tabl.
Enter the values from the Oxford Magnet Acceptance Protokol into
Table 1 (for room-,nitrogen-,and helium temperature).
Compare the actual values with the resistance values from the
OMT Magnet Acceptance Protocol.
If the temperature ranges between a room temperature of 293 K
and a nitrogen temperature of 77 K, precool and fill the magnet as
described in chapter 15 of Register 1 in the Start-up Manual.
If the temperature ranges between 77 K (liquid nitrogen) and 4.2
K (liquid helium), refill the cry-ostat with LHE only as described
in chapter 1 of register 8 in the System Manual.
Fig. 37 Pin configuration of plug C
Points Room temp. (293K) Nitrogen temp. (77K) Helium temp.
(4.2K)A - E (top)
B - E (middle)
C - E (bottom)
If C-E (bottom) is 77 K, refill the cryostat immediately to
prevent additional warming of the magnet.
C_plug_2
a
b
c
d
eCommon
R-Bottom
R-Top
R-Middle
Fig. 37 shows the pin configuration of plug C.
A - E (top)
B - E (middle)
C - E (bottom)
CAUTIONSiemens AG Register 8 M2-050.031.01 Page 29 of 30
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
3 - 30 Unloading and positioning the magnetConnecting the quench
tube 3
For more detailed information refer to chapter 6 in Register 4
of this manual.
Prior to refilling liquid helium, install the quench tube or an
equivalent so that escaping gas can be exhausted to the
outside.
Fig. 38
Verify that the magnet is galvanically separated from the quench
tube.
CAUTION
adaption flangeThe quench tube comes supplied with a Teflon
seal. The flange for connecting the quench tube has to be
configured on-site.
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 30 of 30 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
4 - 1
MAGNETOMning & Installation
Component installation in the RF-room 4Siemens AG Register 8
M2-050.031.01 Page 1 of 24Medical Engineering Rev. 09 04/99 TD SD
23 Plan
Read this first 4 The chart provides you with an overview of the
components to be installed in the RF-room.
Fig. 1 System components inside the examination room
The RF-shielding of the RF-room must not be damaged when
installing the magnet stop or the cable ducts.
hfroom
RF-room
Filterplate RFCC
Intercom
Remote control for magnet stop
Magnet covers
Videocamera, microphone
Patient table
Tunnel lighting
Cablingrefer to chapter 7
NOTICE
-
4 - 2 Component installation in the RF-roomExample of room
layout 4For other room layouts, please refer to Register 3 of this
manual
Fig. 2 The example is showing the installation of the
filterplate and the RFCC
raumplan
ACCURFCCFilterplate
RFASRFPA
PCA
CCA
GPSMAGNETOM Register 8 M2-050.031.01 Page 2 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 3Remote control for
Magnet Stop 4
Install the remote control for the Magnet Stop at an easily
accessable location in the examination room (see Fig. 3)
Do not locate the Magnet Stop in the vicinity of the dewars.Use
non magnetic srews only.
Fig. 3
Fig. 4 Magnet stop button open
CAUTION
magstop
80
80
120
200
1600
~~
Emergencyshut-downbutton
Cable inletMagnet stop
Use non magnetic screwsSiemens AG Register 8 M2-050.031.01 Page
3 of 24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning
& Installation
-
4 - 4 Component installation in the RF-roomInstalling the table
guide support 4The table guide is aligned via four adjustable bolts
to the table guide supports.The following drawing is valid for the
front and rear support of the table guide.
Mount the front and back support to the magnet flange using the
allen screws M10x16.Use the allen screws M10x50 and lock nuts to
stabilize the supports in the vertical direction (refer to Fig. 6
on the next page). Do not forget the washers.
Fig. 5
Do not forget to connect the grounding cable from the AS 25 coil
to the magnet (page 6, Fig.7)
support1
frontview
M10x16locknut
M10x50 allen screws and locknuts
adjustment bolts
M10X20 allen screwand brass washer
front support
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 4 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 5 Attach the
adjustment bolts to the table guide. Do not forget the lock nuts.
Attach the table guide with the four adjustment bolts to the table
supports. Since you need the funnel to set the vertical distance of
the table guide, this procedure will be
described later on pages 10-14 (Installing the front and back
panel) in this chapter.
Fig. 6 Support for the table slideway
Front
locknut
Adjustment screw
Screw M10x16
Front support
support2
Magnet flange
90 degreesSiemens AG Register 8 M2-050.031.01 Page 5 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 6 Component installation in the RF-roomConnecting the ground
cables for the AS 25 coil 4The two grounding cables are locatet at
the rear side of the magnet nearby the tuning boxes.
Installing the magnet covers 4The magnet covers consist of one
front panel, one back panel, as well as three right and three left
side panels. The following panel components are already integrated
and adjusted in the factory: Front panel:
Light localizer, the DCU with touchscreen, and the coil
connector at the right side. Back panel:
Patient air, light box for tunnel lighting.
Fig. 7 Connecting the ground cables
The two bolts which are holding the front-funnel to the
front-panel are locked with nuts. These nuts have to be removed.
They are just for transportation!
The front panel is top heavy. Ensure that it does not tip over
when you remove it from the pallet.
Connection point forthe grounding cable
Attach the two grounding cables together with thetable guide
support to the rear magnet flange.
NOTICE
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 6 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 7View of the front
panel
Installing the adaption plate for the cable duct of the patient
table 4 Attach the distance plate to the front panel frame using
screws M16X30 as shown in Fig.9.
Fig. 8 Attaching the front panel to the magnet
Fig. 9 Adaption plate for the patient table duct
frontv_1
Bracket
Levelling feet Levelling feetPlate for patient table
Bracket
Bracket
tischfla
bolts
bolts
M12
frontpanel
M16x30
distance plate
levelling feet
magnet
frontpanel frameSiemens AG Register 8 M2-050.031.01 Page 7 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 8 Component installation in the RF-roomInstalling the front
and back panel 4
Insert the twelve bolts M16 into the holes (detail "X") at the
patient and service end of the magnet. Tighten the bolts with lock
nuts. Attach a second nut and a washer onto the bolt. Attach the
front panel onto the support bolts and fix it with washers and
nuts.
Use nut A and B (Fig. 10, detail "X") to set the distance .
Fig. 10 Installing the front and rear panel
Front
Not used at the back and the frontbolts
lock nuts
bracket
back viev
X X
XRear
XX
A
B
Detail "X"
magnet_3MAGNETOM Register 8 M2-050.031.01 Page 8 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 9 Adjust the distance
of 245 mm +/-5mm between the outside surface of the front panel and
the front flange of the magnet refer to Fig.11.
Click the front funnel into the holders of the front panel.
Adjust the front panel. Use for the adjustment the levelling feet
and the nuts shown in Fig. 8 and Fig. 9
The adjustment has to be done with the front funnel installed!
The front panel with the front funnel must be in align with the
guide rails of the gradient coil (Fig.13).
Attach the rear panel onto the support bolts. Mount the front
and rear panel with the guide rails together (Fig. 12).Check
wheather the guide rails
are levelled horizontal. Mount the two cross bars to the points
A and B . Refer to Fig. 12
Fig. 11 Measuring the distance between cover and magnet
Fig. 12 Magnet with front and back panel and guide rails
flange Measure the distance between the outside surface of the
front panel to the magnet flange.
front
guide rails
A B
cover_1Siemens AG Register 8 M2-050.031.01 Page 9 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 10 Component installation in the RF-room If the guide rails
are not levelled horizontal readjust the front or/and the rear
panel in the height.
Ensure that the guide rails (Fig.12) are levelled out
horizontal.This is important for the adjustment of the side cover
panels.
Check the adjustment of the front funnel the rear funnel and the
table guide during readjustment of the panels.
Fig. 13 Adjustment of the front panel
Affix the Laser Warning Labels on the front panel (refer to
Register 2,chapter 1, page 7).
NOTICE
CAUTION
Front panel
coveradj
Guide rails
Funnel
Guide rails
FunnelPosition of the funnelmust be centered withthe guide
rails
approx.3mm
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 10 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 11 Place the table
guide (with the adjustment bolts already installed) onto the front
and reartable support. Use the M10X20mm allen screws with the large
brass washers to fix the table guide to the supports. Align the
table guide as shown in Fig.14 .
In the vertical, the upper platform of the table guide has to be
completely flush with the triangular surface of the funnel. In the
x-direction, the table guide has to be positioned symmetrically to
the gradient coil (guide rails). In the z-direction, the front of
the table guide has to lie against the front panel.
Adjust the back panel. The guide rails define the upper distance
from the front panel to the back panel. The exact
position of the back panel is determined by the back funnel.
Ensure that the funnel is symmet-ric with the gradient coil in the
x-direction.
Fig. 14 Adjustment for the tableguide
Levelling feet Levelling feet
Front panel
Plate for patient table duct
Funnel
Guide rail
Funnel
Guide rail
guideadj
Table guideup
down
Position of funnelmust be centered withthe guide railsSiemens AG
Register 8 M2-050.031.01 Page 11 of 24 MAGNETOMMedical Engineering
Rev. 09 04/99 TD SD 23 Planning & Installation
-
4 - 12 Component installation in the RF-roomDon t forget to
attach the connector ( Wire W26, see also wiring diagrams in the
Planing Guide, Reg.10 ) of the Display-box (part number: 31 04 077)
in the opening 1 (see Fig.15) of the back funnel.
Fig. 15 Location of the connector
CAUTION
connector Attach the connector to the rear funnel befor yuo
attach the funnel to the rear cover.MAGNETOM Register 8
M2-050.031.01 Page 12 of 24 Siemens AGPlanning & Installation
Rev. 09 04/99 TD SD 23 Medical Engineering
-
Component installation in the RF-room 4 - 13Magnet side panels
4
Side panels 4 Attach the side panels on both sides and adjust
them as required.
We recommend to mount the side panels when the cabling
(described in chapter 7 of this register) has been completed.
Fig. 16 Side panels of the magnet cover
NOTICE
frontfine adjustment
sidecovSiemens AG Register 8 M2-050.031.01 Page 13 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 14 Component installation in the RF-roomDCU adjustments 4
The DCU is factory adjusted. In case additional adjustments are
required, refer to the functions
of the screws described in Fig. 17.
Fig. 17 DCU adjustmaent hardware
The mounting hardware shown in Fig.17 is the same for both sides
of the DCU.
2
3 1 4
Adjustment and mounting screws
- 1 - Mounting screws- 2 - Height adjustment- 3 - Distance to
funnel- 4 - Height adjustment including tilt angle
NOTICEMAGNETOM Register 8 M2-050.031.01 Page 14 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 15Lighting in the
patient tunnel 4The tunnel lighting consists of a light bar which
is part of the inside covering for the AS 25 coil. The light
generated in the light box by the Halogen lamp (at the back panel
of the magnet) is distributed via a large number of individual
fiber optic cables.
Handle the black corrugated hose with care during the
installation process. The hose contains the highly fragile fiber
optic cables.
Fig. 18 Light box
CAUTION
A
Connect the fiber optic cable connector at the end of the
corrugated hose to the housing of the light box.
Secure the end of the corrugated hose with the headless screw A.
Siemens AG Register 8 M2-050.031.01 Page 15 of 24 MAGNETOMMedical
Engineering Rev. 09 04/99 TD SD 23 Planning & Installation
-
4 - 16 Component installation in the RF-roomVideo camera 4The
video camera and the microphone for patient monitoring are
contained in the same housing.
Take off the back cover of the camera housing by removing the
two screws. Route the video and audio cable through the opening in
the back panel, up through the swivel arm
into the camera housing which also contains the sockets. Connect
the cables to the sockets. Attach the swivel arm to the back panel
using the four supplied screws. Attach the back cover of the camera
housing. Attach the support arm using the five supplied Allen
screws.
Handle the camera and the microphone with care. Like any other
electronic device, they are highly sensitive to shock or other
impacts.
Fig. 19 Video camera and microphone
CAUTION
Location and configuration of the video cameraand the
microphone.MAGNETOM Register 8 M2-050.031.01 Page 16 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 17Installation of the
filter plate 4To provide the service engineer with enough room, the
RF filter plate together with the RFCC should not be installed in
the immediate vicinity of the magnet. In addition, a more
cost-effective cover can be selected for the RFCC.In a modular
RF-room, the filter plate can be installed directly in the recess
provided for that purpose. In a conventional RF-room the filter
plate can be installed directly as well, as long as the RF
integrity is maintained. However, we recommend the use of a filter
frame (refer to chapter 3 Components in Reg-ister 1 and to chapter
1 'RF-shielding' in Register 4 of this manual). Install the RF
filter plate (56 screws M10).
Fig. 20 Installation of the filter plate
The RF integrity can now be measured if the transport opening of
the RF-room has been closed.
Interior ofRF-room
RF filter frameRF filter plate
filterpl
NOTICESiemens AG Register 8 M2-050.031.01 Page 17 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 18 Component installation in the RF-roomInstalling the RFCC
4 Attach the two mounting brackets for the RFCC (8 washers, lock
washers, nuts M6 each)
Lift up the RFCC, guide the support bolts through the elonguated
holes in the mounting brackets. Secure the RFCC to the brackets
using 10 washers, lock washers, and nuts M6.
Shift the RFCC in the elonguated holes until it is flush with
the RF-room wall. Tighten the nuts.
Fig. 21 Installation of the RFCC mounting brackets
The RFCC is very heavy. You either need a lifting device or
three people for the installation.
Fig. 22 Installation of the RFCC
interior ofRF-room
mountingbracketattach mounting brackets
brackets
CAUTION
rfccin
RFCC
InteriorofRF-room
RFCCMAGNETOM Register 8 M2-050.031.01 Page 18 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 19Installation of
patient table 4
Preparing the patient table 4 Protect the tabletop against
damage by covering it with corrugated paper or packing
material.
Fig. 23 Patient table
Fig. 24 Detailed view of the patient table
liege1
connectorplates
vertical motor
table front coverscrews holding the side panel
screws
liegedet
S2transport
levelling
limit switch S4
mechanical endstop
feets
roller
gear bolt 1 of 4Siemens AG Register 8 M2-050.031.01 Page 19 of
24 MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning
& Installation
-
4 - 20 Component installation in the RF-roomOpening of the
patient table 4
Fig. 25 Table front cover removed
Fig. 26 Screws for removing the side sections
Fig. 27 Unlock and remove the table stop button
front cover removed
Remove the front cover of the table (4 Allen screws). Refer to
Fig.25.
S
Take off the side sections by removing the screws "S" shown in
Fig.26.
Be careful when you take off the side sections. You have to
unlock and remove the table STOP button before removing the side
sections.
Unlock the button by turning the lever (see arrow in Fig.27).
MAGNETOM Register 8 M2-050.031.01 Page 20 of 24 Siemens AGPlanning
& Installation Rev. 09 04/99 TD SD 23 Medical Engineering
-
Component installation in the RF-room 4 - 21Removing the
transport brackets 4
Fig. 28 Rails for bellow shaped cover
Fig. 29 Transport brackets inside the patient table
Fig. 30
S
Remove the rails which hold the bellow-shaped cover of the
patient table. on both sides.
Remove screws "S" shown in Fig.28.
The bellow-shaped cover comes off easily.
transich
transport brackets
mounting screws
Position the ratchet at the gear bolt and crank the table upward
by approx. 3 cm. Refer to Fig. 30and 31.
Remove the mounting screws of the transport brackets see
Fig.29.
Remove the transport brackets.Siemens AG Register 8
M2-050.031.01 Page 21 of 24 MAGNETOMMedical Engineering Rev. 09
04/99 TD SD 23 Planning & Installation
-
4 - 22 Component installation in the RF-roomInstalling the cable
duct and the patient table 4 Attach the cable duct to the two bolts
sitting on the mounting plate refer to Fig.32 (tighten by hand
only). Move the patien table in position behind the cable duct.
Lower the transport rollers of the patient table until the table is
sitting on the floor. Mount the cable duct and the patient table
with the delivered screws together and tighten them.
Fig. 31 Gear bolt
Fig. 32 Installation of the cable duct
View of the gear bolt for cranking up the patient tableby
hand.
Cable duct
ductmon
85mm
Front panelInstallation frame
M16
mounting plate
BoltsM12MAGNETOM Register 8 M2-050.031.01 Page 22 of 24 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Component installation in the RF-room 4 - 23 Align the patient
table with the cable duct to the magnet, table guide and front
funnel refer to Fig. 33.
To prevent potential injuries, the distance between the table
guide and the patient table cover at the head end must not exceed 5
mm (see Fig. 33)
Fig. 33 Align the patient table with the cable duct to magnet,
table guide and front funnel
The patient table will be aligned and bolted to the floor during
system start-up (Start up manual, register 1, chapter 9).
CAUTION
allign
max.5 mm distance
magnet cover
cable ductmagnet
patient table
NOTICESiemens AG Register 8 M2-050.031.01 Page 23 of 24
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
4 - 24 Component installation in the RF-roomIntercom 4The
intercom system is integrated into the CCA cabinet K2120. A
loudspeaker has to be installed inside the RF-room. A second
loudspeaker (piezo) is already installed the rear table guid
support.
The RF-shielding of the RF-room must not be damaged when
installing the loudspeaker.
Fig. 34 Loudspeeker
CAUTION
lautspr
Attach the loudspeaker bracket to the wall. Attach the
loudspeaker to the bracket.MAGNETOM Register 8 M2-050.031.01 Page
24 of 24 Siemens AGPlanning & Installation Rev. 09 04/99 TD SD
23 Medical Engineering
-
5 - 1
MAGNETOMning & Installation
Computer Room 5Siemens AG Register 8 M2-050.031.01 Page 1 of
26Medical Engineering Rev. 09 04/99 TD SD 23 Plan
General 5
Read this first 5To keep the helium boil-off to a minimum,
install the ACCU cabinet (ACCU = Air Compressor Chiller Unit) first
so that the cold head can be connected as quickly as
possible.Install the three-in-one cabinet (CCA, PCA, gradient) and
the RFPA in parallel or immediately after completion of the ACCU
cabinet. Route the cables after you finished installing the
cabinets.After the ACCU has been connected to the PCA, switch on
the refrigerator immediately (naturally only if the helium vessel
contains liquid helium).
Flowchart 5The flowchart provides you with an overview of the
components to be installed in the computer room.
Fig. 1 Installation flowchart for the computer room
equippm
Installation ofACCU to
reduce boil off
Installation ofthe othercabinets
Cabling / referto chapter 7
Start-uprefrigerator
Installation incomputer room
Magnet unloading,transport,set-up
Installation inRF-room
Set up thecabinet
Connect the waterhoses
Connect the semi-rigid lines
Connect the powercable between cold head and
refrigerator
-
5 - 2 Computer RoomPrerequisites 5
The interior of the rooms has been completed The location of the
cabinets has been drawn on the floor The chilled water hoses for
the ACCU have been installed The magnet has been aligned
Tools 5
Standard tool kit Drill, etc. Forklift for transporting the
cabinets 4 hydraulic jacks
Safety 5
Refer to Register 2 of this manual.NOTICEMAGNETOM Register 8
M2-050.031.01 Page 2 of 26 Siemens AGPlanning & Installation
Rev. 09 04/99 TD SD 23 Medical Engineering
-
Computer Room 5 - 3Areas prone to earthquakes 5
Bolting the MR cabinets to the floor 5
In areas prone to earthquakes, the cabinets have to be bolted to
the floor according to local regulations.
Fig. 2 Holes for ACCU and RFPA
Fig. 3 Holes for the electronics cabinet
CAUTION
holes450
710
Mark the holes to be drilled into the floor. Use a piece of tape
or a felt pen.
Drill the holes (17 mm in diameter) Insert the anchors Position
the cabinets Secure with nuts and washers Ensure that the cabinets
are secure. They must
not tip over when you remove one of the assemblies.
1650
710
holes_3Siemens AG Register 8 M2-050.031.01 Page 3 of 26
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
5 - 4 Computer RoomBolting the magnet to the floor 5
Unloaoding and setting up the three-in-one cabinet 5Move cabinet
unit on the transport pallet in the immediate vicinity of its final
location.Remove the screw connections between the cabinet unit and
the pallet.
Fig. 4 Position of the holes
Fig. 5 Remove transport pallet
Do not wrap the cabinet.
holemagPatient End
Service End
magnet
magnet support beams
Mark the holes. There is a hole in each of the four corner
joints of the magnet support beams.
Remove the magnet. Drill the holes, and insert the respective
anchors (parts like the screws and the anchors have to be obtained
locally).
Position the magnet again. Align the magnet vertically and
horizontally. Refer
to chapter 8 of this register for additional details. Bolt the
magnet to the floor.
1
34
2
2
3
1
1
Remove the red lifting brackets attached to the cabinet (1/Fig.
5), turn them by 180, and reattach them.
Connect the 4 hydraulic jacks so that they can be raised and
lowered in common (2/Fig. 5).
Uniformly lift the cabinet unit with the 4 hydraulic jacks
(3/Fig. 5).
Remove the transport pallet (4/Fig. 5).
CAUTIONMAGNETOM Register 8 M2-050.031.01 Page 4 of 26 Siemens
AGPlanning & Installation Rev. 09 04/99 TD SD 23 Medical
Engineering
-
Computer Room 5 - 5Fig. 6 Position the rollers
Fig. 7 Positioning of the cabinets
5
6
5
6
Position four rollers (5/Fig.6) under the first and last cabinet
section next to the cabinet interconnections.
Lower the cabinet unit onto the rollers (6/Fig.6).
7 9
8
9
8
Position the cabinet (7/Fig.7). Uniformly lift the cabinet with
the
4 hydraulic jacks (8/Fig.7). Remove the rollers
(9/Fig.7).Siemens AG Register 8 M2-050.031.01 Page 5 of 26
MAGNETOMMedical Engineering Rev. 09 04/99 TD SD 23 Planning &
Installation
-
5 - 6 Co