ABA 2510 COST PLANNING & CONTROL LECTURE 5: PLANNING & SCHEDULING TECHNIQUES 1
Sep 27, 2015
ABA 2510
COST PLANNING &
CONTROL
LECTURE 5:
PLANNING & SCHEDULING TECHNIQUES
1
Introduction
A schedule is the conversion of WBS into an
operating time table, in the form of network of
activity & event relationships that graphically
portrays the sequential relations btn tasks in a
project
Serves as a basis for monitoring & control project activity
A key input in establishing the monitoring & control system
2
Benefits of scheduling
Provides a consistent framework for planning,
monitoring & control
Illustrates the interdependency of all tasks,
work packages & elements
Denotes the times when resources must be
available
Determines project completion date
Identifies so called critical activities..
3
Benefits of scheduling cont
Identifies activities with float/slack
Identifies dates which tasks must be
started
Identifies which tasks may be run in
parallel
It relieves some interpersonal conflict by
clearly showing task dependencies
4
Types of Planning & Scheduling tech
Gantt or bar charts
Milestone charts
Line of balance
Program Evaluation and Review Technique
(PERT)
Arrow Diagram Method (ADM) or
Critical Path Method (CPM)
Graphical Evaluation and Review
Technique (GERT)
5
Gantt Chart
Developed around 1917 by Henry L.
Gantt a pioneer in scientific management
Involves the use of bar charts with:
specified start time
completion time and
duration.
Does not show the dependency
relationship among the activities and the
logical flow of the project.
6
Gantt Chart cont
Advantages of Gantt charts includes:
Easily understood
Easy to construct
Do not require frequent updating
They provide a picture of the current state of a project
Powerful devices for communicating to senior mgt
7
Gantt Chart cont
8
Gantt Chart Example
9
Network techniques
10
Network Techniques
Activity on Arrow
CPM PERT
Activity on Nodes
PNA (PDM)
GERT
Network Fundamentals
Activity is an identifiable, quantifiable, discrete
lowest level element of work, which must be
performed during the course of the project. Each
activity consumes time for their completion.
Example of activities include;
Excavation, Fixing steel, building a wall, constructing a
roof ,curing concrete etc
11
Network Fundamentals cont
12
Network Fundamentals cont
The activities are represented by arrows pointing
in the forward direction
The tail of the arrow depicts the commencement of an
activity and the arrow head its termination
The length of the arrow is not drawn to scale
Arrows are neither curved nor drawn in reverse
direction
13
Event
14
It is the state that marks the completion of a
preceding activity & the beginning of a
succeeding one.
It has no duration
Symbolically shown by a circle or ellipse
The events are labeled numerically to identify
them & describe the connecting activities
Event cont
15
The first event of a project is called the start event,
and the last, end event
Preceding event- an event at which an activity starts
Succeeding event-the event which terminates an
activity
Key event the event of significance i.e building
ready for occupation, its occurance is termed as a
milestone
Event cont
16
Dangling event-The loose events before the addition
of dummies.
Bust & Sink points
17
IN fig A, event 26 must take place before event 7,18&
31.In Fig. B event 7,18 & 31 must take place prior to
26.
Sink /Merge
18
Dummy activity
It is a superimposed activity, which does not
represent any specific operation or process. it has
Zero duration & consumes no resources. Its
purpose is twofold:
To provide a logical link to maintain the correct
relationship of activities
To simplify the description of concurrent activities in
terms of event numbers
19
Dummy activity cont
20
F follows C and E starts after completion of C
& D. Activity H provides the logical link
Event timings & Associated terms
21
a) Earliest event time(EET)- it is the earliest time an
event can take place, assuming that all the events
prior to it also occur at their earliest time
The EET is set at Zero, while the EET of subsequent
events is calculated by adding the activity duration into it
in the process known as forward pass.
If there is more than one activity terminating into the
event, consider the largest value
Event timings & Associated terms
22
b) Latest Event Time (LET)- it is the latest time by
which an event can occur, if the project is to be
completed within the specified time.
Unless otherwise specified, the LET of the end event
EET. The remaining events are calculated by subtraction
in the reverse direction in the process known as
backward pass.
If there is more than one activity diverging from an
event, consider the lowest value
Event timings & Associated terms
23
c) Slack- the difference between the LET & EET of an
event
d) Critical events- the events having Zero slack, they
must take place at a stipulated time without fail.
Any change in their occurrence would affect the
project completion time.
Activity timings & Connected terms
24
a) Earliest start time(EST)- the earliest time an activity
can be started, assuming that all the activities prior
to it have taken place as early as possible. The EST
of an activity EET of the preceding event
b) Latest start time(LST)the latest time an activity can
start consistent with the completion of the
project in the stipulated time. Determined by
subtracting preceding event
Activity timings & Connected terms
25
c) Earliest finish time(EFT)- the earliest time by which
an activity can be completed, assuming that all the
activities prior to it begin at their ESTs
d) Latest finish time(LFT) the latest time by which an
activity must be completed to ensure the
completion of the project within the stipulated
time. LFT=LET
Activity timings & Connected terms
26
e) Float/activity slack - the difference between the
latest start time(LST) & the earliest start
time(EST) of an activity
f) Critical activities - the activities including dummy
ones having Zero float
g) Network Critical Path the path of critical
activities (including dummy activities) which links
the start & end events
Duration Estimation Methods
27
a) One-time estimate
b) Three-time PERT estimate
c) Non-linear distribution
One-time estimate
28
a) Estimation is based on one or more of the
following;
i. Planning data
ii. Past experience on execution of similar project
iii. Average time assessed by experts
Three-times PERT estimate
29
When the exact duration of an activity like R &D,
is not certain, duration is computed using;
Where;
Te =Expected completion time
To=Optimistic time, assuming that everything goes extremely well
Tp = pessimistic time, assuming that everything goes wrong
Pm = most likely time, assuming normal conditions
Example
30
Questions?
31