ABA 2510 COST PLANNING & CONTROL LECTURE 5: PLANNING & SCHEDULING TECHNIQUES 1
31

Planning and Scheduling Technique

Sep 27, 2015

Download

Documents

Jackson Pires

PLANNING & SCHEDULING TECHNIQUES
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • ABA 2510

    COST PLANNING &

    CONTROL

    LECTURE 5:

    PLANNING & SCHEDULING TECHNIQUES

    1

  • Introduction

    A schedule is the conversion of WBS into an

    operating time table, in the form of network of

    activity & event relationships that graphically

    portrays the sequential relations btn tasks in a

    project

    Serves as a basis for monitoring & control project activity

    A key input in establishing the monitoring & control system

    2

  • Benefits of scheduling

    Provides a consistent framework for planning,

    monitoring & control

    Illustrates the interdependency of all tasks,

    work packages & elements

    Denotes the times when resources must be

    available

    Determines project completion date

    Identifies so called critical activities..

    3

  • Benefits of scheduling cont

    Identifies activities with float/slack

    Identifies dates which tasks must be

    started

    Identifies which tasks may be run in

    parallel

    It relieves some interpersonal conflict by

    clearly showing task dependencies

    4

  • Types of Planning & Scheduling tech

    Gantt or bar charts

    Milestone charts

    Line of balance

    Program Evaluation and Review Technique

    (PERT)

    Arrow Diagram Method (ADM) or

    Critical Path Method (CPM)

    Graphical Evaluation and Review

    Technique (GERT)

    5

  • Gantt Chart

    Developed around 1917 by Henry L.

    Gantt a pioneer in scientific management

    Involves the use of bar charts with:

    specified start time

    completion time and

    duration.

    Does not show the dependency

    relationship among the activities and the

    logical flow of the project.

    6

  • Gantt Chart cont

    Advantages of Gantt charts includes:

    Easily understood

    Easy to construct

    Do not require frequent updating

    They provide a picture of the current state of a project

    Powerful devices for communicating to senior mgt

    7

  • Gantt Chart cont

    8

  • Gantt Chart Example

    9

  • Network techniques

    10

    Network Techniques

    Activity on Arrow

    CPM PERT

    Activity on Nodes

    PNA (PDM)

    GERT

  • Network Fundamentals

    Activity is an identifiable, quantifiable, discrete

    lowest level element of work, which must be

    performed during the course of the project. Each

    activity consumes time for their completion.

    Example of activities include;

    Excavation, Fixing steel, building a wall, constructing a

    roof ,curing concrete etc

    11

  • Network Fundamentals cont

    12

  • Network Fundamentals cont

    The activities are represented by arrows pointing

    in the forward direction

    The tail of the arrow depicts the commencement of an

    activity and the arrow head its termination

    The length of the arrow is not drawn to scale

    Arrows are neither curved nor drawn in reverse

    direction

    13

  • Event

    14

    It is the state that marks the completion of a

    preceding activity & the beginning of a

    succeeding one.

    It has no duration

    Symbolically shown by a circle or ellipse

    The events are labeled numerically to identify

    them & describe the connecting activities

  • Event cont

    15

    The first event of a project is called the start event,

    and the last, end event

    Preceding event- an event at which an activity starts

    Succeeding event-the event which terminates an

    activity

    Key event the event of significance i.e building

    ready for occupation, its occurance is termed as a

    milestone

  • Event cont

    16

    Dangling event-The loose events before the addition

    of dummies.

  • Bust & Sink points

    17

    IN fig A, event 26 must take place before event 7,18&

    31.In Fig. B event 7,18 & 31 must take place prior to

    26.

  • Sink /Merge

    18

  • Dummy activity

    It is a superimposed activity, which does not

    represent any specific operation or process. it has

    Zero duration & consumes no resources. Its

    purpose is twofold:

    To provide a logical link to maintain the correct

    relationship of activities

    To simplify the description of concurrent activities in

    terms of event numbers

    19

  • Dummy activity cont

    20

    F follows C and E starts after completion of C

    & D. Activity H provides the logical link

  • Event timings & Associated terms

    21

    a) Earliest event time(EET)- it is the earliest time an

    event can take place, assuming that all the events

    prior to it also occur at their earliest time

    The EET is set at Zero, while the EET of subsequent

    events is calculated by adding the activity duration into it

    in the process known as forward pass.

    If there is more than one activity terminating into the

    event, consider the largest value

  • Event timings & Associated terms

    22

    b) Latest Event Time (LET)- it is the latest time by

    which an event can occur, if the project is to be

    completed within the specified time.

    Unless otherwise specified, the LET of the end event

    EET. The remaining events are calculated by subtraction

    in the reverse direction in the process known as

    backward pass.

    If there is more than one activity diverging from an

    event, consider the lowest value

  • Event timings & Associated terms

    23

    c) Slack- the difference between the LET & EET of an

    event

    d) Critical events- the events having Zero slack, they

    must take place at a stipulated time without fail.

    Any change in their occurrence would affect the

    project completion time.

  • Activity timings & Connected terms

    24

    a) Earliest start time(EST)- the earliest time an activity

    can be started, assuming that all the activities prior

    to it have taken place as early as possible. The EST

    of an activity EET of the preceding event

    b) Latest start time(LST)the latest time an activity can

    start consistent with the completion of the

    project in the stipulated time. Determined by

    subtracting preceding event

  • Activity timings & Connected terms

    25

    c) Earliest finish time(EFT)- the earliest time by which

    an activity can be completed, assuming that all the

    activities prior to it begin at their ESTs

    d) Latest finish time(LFT) the latest time by which an

    activity must be completed to ensure the

    completion of the project within the stipulated

    time. LFT=LET

  • Activity timings & Connected terms

    26

    e) Float/activity slack - the difference between the

    latest start time(LST) & the earliest start

    time(EST) of an activity

    f) Critical activities - the activities including dummy

    ones having Zero float

    g) Network Critical Path the path of critical

    activities (including dummy activities) which links

    the start & end events

  • Duration Estimation Methods

    27

    a) One-time estimate

    b) Three-time PERT estimate

    c) Non-linear distribution

  • One-time estimate

    28

    a) Estimation is based on one or more of the

    following;

    i. Planning data

    ii. Past experience on execution of similar project

    iii. Average time assessed by experts

  • Three-times PERT estimate

    29

    When the exact duration of an activity like R &D,

    is not certain, duration is computed using;

    Where;

    Te =Expected completion time

    To=Optimistic time, assuming that everything goes extremely well

    Tp = pessimistic time, assuming that everything goes wrong

    Pm = most likely time, assuming normal conditions

  • Example

    30