Planning and Development Committee Public Infrastructure Public Improvement Districts #1, #2, and #3 October 13, 2016
29

Planning and Development Committee Public Infrastructure

Dec 18, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Planning and Development Committee Public Infrastructure

Planning and Development Committee

Public Infrastructure

Public Improvement Districts #1, #2, and #3

October 13, 2016

Page 2: Planning and Development Committee Public Infrastructure

Public Improvement Districts

Tax Increment Reinvestment Zones

Ranchview/Campion Hollows

Bridges

Parkside

2

Page 3: Planning and Development Committee Public Infrastructure

Public Improvement District (PID)

Assessment districts created by the City to fund public improvements

Benefitted properties assessed annually to repay debt used to fund infrastructure

Expires once debt is paid off (2032/2033)

Not a Home Owner’s Association

Service and Assessment Plan Update (SAP)

Updated annually (October) and adopted by City Council

Establishes annual assessments to pay current debt service and collection costs

Tax Increment Reinvestment Zone (TIF or TIRZ)

TIF Districts established to assist in paying off debt

50% of Maintenance and Operations Tax Rate dedicated toward debt service

Not an increase in taxes – simply an allocation of portion of a taxes paid to the city

3

Page 4: Planning and Development Committee Public Infrastructure

4

TIRZ #4 is approximately 37 acres

121 single-family homes ---completed by the end of 2016

Average value of lot plus improvements is $539,772 for a total buildout value of $65.3M.

Estimated average home value during planning was $400,000, or an estimated total buildout value of $48.4M.

Page 5: Planning and Development Committee Public Infrastructure

5

Page 6: Planning and Development Committee Public Infrastructure

6

Page 7: Planning and Development Committee Public Infrastructure

7

Page 8: Planning and Development Committee Public Infrastructure

8

Page 9: Planning and Development Committee Public Infrastructure

9

Total development cost, including the PID-financed portion of public infrastructure is $6.6 M.

Page 10: Planning and Development Committee Public Infrastructure

10

Authorized Improvement Estimated Cost Actual Expenditures

Water Distribution Improvements $ 474,797.00 $ 480,756.61

Sewer System Improvements $ 275,603.00 $ 338,403.37

Drainage Improvements $ 690,319.00 $ 619,346.95

Landscaping/Open Space Improvements $ 1,559,281.00 $ 1,561,493.07

Total $ 3,000,000.00 $ 3,000,000.00

Total development cost, including the PID-financed portion of public infrastructure is $6.6 M.

Page 11: Planning and Development Committee Public Infrastructure

11

TIRZ #3 is approximately 122 acres

400 single-family homes with average value of lot plus improvements is $479,000 for a total buildout value of $192M

Original estimated home values of $450k to $490k

Infrastructure completed in 2017

Total build-out expected by the end of 2017 (334 Permits issued to date)

Page 12: Planning and Development Committee Public Infrastructure

12

Page 13: Planning and Development Committee Public Infrastructure

13

Page 14: Planning and Development Committee Public Infrastructure

14

Page 15: Planning and Development Committee Public Infrastructure

15

Page 16: Planning and Development Committee Public Infrastructure

16

Public improvements that are financed in part by the incremental taxes generated within the TIRZ.

Page 17: Planning and Development Committee Public Infrastructure

17

Total development cost, including the PID financed portion of public infrastructure is $26.8M.

Authorized Improvement Estimated Cost Actual Expenditures

Water Distribution Improvements $ 498,122.00 $ 555,137.37

Sewer System Improvements $ 897,939.00 $ 495,833.16

Street Improvements $ 3,717,745.00 $ 54,299.33

Drainage Improvements $ 1,118,114.00 $ 455,371.83

Public Landscaping and Hardscaping $ 2,049,762.00 $ 6,721,040.31

Total $ 8,281,682.00 $ 8,281,682.00

Page 18: Planning and Development Committee Public Infrastructure

18

• 3 Bridges were completed at a cost of $2.4M.

• Lake Rialto was improved by removing in excess of 100,000 CY of silt from the lake bottom behind the dam, creating natural water depths up to 12 feet.

• Passarelle Trails is approximately 1 mile of completed pedestrian trails along the Lake Rialto waterway.

• Completed Sulis Square Park, with a children’s spray park, playground equipment and a covered community gathering area.

• Completed Apollon Hill Park, a large open space gathering area. Community movie nights have been a popular feature.

• Developer continues to work with DCURD on the State Water Permit for Lake Rialto. Approval is expected by the end of 2016.

Page 19: Planning and Development Committee Public Infrastructure

19

TIRZ #5 is approximately 233 acres

888 single-family homes priced at $350,000 to $900,000 Originally estimated 869 lots at $450K to $700K

Estimated assessed value upon completion of $460M+ Original estimated @ $360M

Parkside East -154 homes Parkside East - 2017/2018

Parkside West -131 homes Parkside West - 2019/2020

Page 20: Planning and Development Committee Public Infrastructure

20

Page 21: Planning and Development Committee Public Infrastructure

21

Page 22: Planning and Development Committee Public Infrastructure

22

Page 23: Planning and Development Committee Public Infrastructure

23

Page 24: Planning and Development Committee Public Infrastructure

24

Page 25: Planning and Development Committee Public Infrastructure

25

Page 26: Planning and Development Committee Public Infrastructure

26

Total development cost, including the PID financed portion of public infrastructure is $97.8M.

Authorized Improvement Estimated Cost Actual Expenditures

Water Distribution Improvements $ 2,040,579.00 $ 1,778,907.75

Sewer System Improvements $ 1,328,872.00 $ 1,423,936.44

Street Improvements $ 4,821,659.00 $ 8,253,157.02

Drainage Improvements $ 864,899.00 $ 1,424,813.16

Open Space, Park & Recreation Facilities $ 11,443,991.00 $ 5,125,494.13

Total $ 20,500,000.00 $ 18,006,308.50

Page 27: Planning and Development Committee Public Infrastructure

• 3560 LF of 4E6 underground duct bank electrical installed to relocate overhead power along Belt Line Road and Cabell Road east of Belt Line

• 6100 LF of conduit and pull box system installed along Cabell Drive west of Belt Line and along Esters to underground overhead power and telecom (which provided power for the DART LRT in the area)

• Cabell Road east of Belt Line realigned and reconstructed

• Two additional lanes of Cabell Drive west of Belt Line from Arches Avenue to Esters completed

• 2.1 miles of the 3.3 miles of public trails completed in open space areas

• Pedestrian underpass boardwalk under Belt Line Road completed

• Approximately 30 acres of open space and park improvements have been completed, including Parkside Commons, the reclamation of 23.5 acres of floodplain land in Parkside East – including a dog park, storm water retention area (provides mitigation of regional storm water issues related to DFW Airport), turfed and irrigated play areas and a fountain to enhance water quality in the detention area

• Developer had to mitigate prior illegal dumping of poor material and concrete materials within the Phase 1 site.

27

Page 28: Planning and Development Committee Public Infrastructure

28

• Infrastructure for Phases 1A, 1B, 2A and 3 have been completed.

• Infrastructure for Phase 2C is underway and Phase 2B will commence by the end of 2016. All lot infrastructure work will be complete during 2017.

• Cabell Drive expansion is approximately 35% complete. Hines has been waiting on ONCOR to remove the remaining 18 overhead poles along Esters and Cabell that impede ROW construction.

• Construction of the Cabell Drive Culvert Bridge is scheduled to commence in November, 2016 after receipt of FEMA comments related to the channel improvements. Comments are due by the end of October, 2016. Hines has worked extensively with Garry Fennell and Dan Vedral on completing the design plans and submittals.

• The Cabell Culvert Bridge will have to be constructed in two phases in order to maintain two-way traffic on Cabell Drive from Belt Line Road to Esters Boulevard. The plan is to complete the westbound lanes of Cabell Drive by the end of the 1Q, 2017. The complete roadway, including Esters Boulevard expansion, will be completed by Summer, 2017.

28

Page 29: Planning and Development Committee Public Infrastructure

29

Total development cost of all three PID’s, including the PID financed portion of public infrastructure is $131.2M.

Authorized Improvement Estimated Cost Total Expenditures

to Date

Water Distribution Improvements $ 3,013,498.00 $ 2,814,801.73

Sewer System Improvements $ 2,502,414.00 $ 2,258,172.97

Street Improvements $ 8,539,404.00 $ 8,307,456.35

Drainage Improvements $ 2,673,332.00 $ 2,499,531.94

Public Landscaping, Open Space, Park & Recreation Facilities $ 15,053,034.00 $ 13,408,027.51

Total $ 31,781,682.00 $ 29,287,990.50

Combined Summary – Bridges/Ranchview/Parkside