Page 1: Planning Ahead - NDEP

REVISED TOTAL COLIFORM

RULE

Planning Ahead

Page 2: Planning Ahead - NDEP

Effective April 1, 2016

Revised Total Coliform Rule

Sampling Changes

Specific Sample Siting Plans

Number of samples required following TC+

Treatment Technique

Assessments, Level 1 and 2

Seasonal Systems

Seasonal Start-up Certification

2

Page 3: Planning Ahead - NDEP

Revised Total Coliform Rule

Specific Sampling Locations

Routine

Where

Repeat

Routine Site

Within 5 Upstream

Within 5 Downstream

3

Page 4: Planning Ahead - NDEP

Jemmy Jo’s Country Grub

4

Page 5: Planning Ahead - NDEP

Small Non-Community

Jemmy Jo’s Country Grub

1 routine sample per quarter

Taken at kitchen sink (only 1 sink?)

3 Repeat samples per coliform detect

Sample taken at SAME sink as above

Sample taken at restroom sink

Sample taken at janitor closet

3 Follow-up samples the following month

5

Page 6: Planning Ahead - NDEP

Source Water Sample

Groundwater Rule

Well (how many)

Spring

Consecutive Connection

Surface Water Rule

ZERO

6

Page 7: Planning Ahead - NDEP

Jemmy Jo’s Barnstorming Center

7

Well

Storage,

Pumps

Mgr’s

Office

Hostel

Bldg #1

Con

ven

ien

ce S

tore

Hostel

Bldg #3

Gas

Bay

Hostel

Bldg #2

RV

Park

Page 8: Planning Ahead - NDEP

Large Non-Community

Jemmy Jo’s Barnstorming Center

Large hostel, 100/night

RV Park, 50/night

C-Store, Gas Station, 1200/month

2 routine samples per month

8

RV Park Site 10

Hostel 3 Kitchen

Page 9: Planning Ahead - NDEP

Large Non-Community

Jemmy Jo’s Barnstorming Center

Large hostel, 100/night

RV Park, 50/night

C-Store, Gas Station, 1200/month

2 routine samples per month

3 Repeat samples per coliform detect

9

Sample At RV Site 10

Sample At RV Site 1

Sample At C-Store

Sample Site Hostel 3 Kitchen

Sample Site Hostel 2 Kitchen

Sample Site C-Store

Page 10: Planning Ahead - NDEP

Jemmy Jo’s Barnstorming Center

10

Well

Storage,

Pumps

Mgr’s

Office

Hostel

Bldg #1

Con

ven

ien

ce S

tore

Hostel

Bldg #3

Gas

Bay

Hostel

Bldg #2

RV

Park

Page 11: Planning Ahead - NDEP

Jemmy Jo’s Barnstorming Center

What about the well???

11

Page 12: Planning Ahead - NDEP

Revised Total Coliform Rule

Sample Siting Plan

Where to sample

Number of samples

Following a TC +

Where to Repeat

How often to Repeat

How NOT to Repeat

What Not to Forget

12

Page 13: Planning Ahead - NDEP

You CAN Contact Us

Phone

E-mail

Face-to-face

PWS has responsibility

13

Page 14: Planning Ahead - NDEP

Communicate

14

Page 15: Planning Ahead - NDEP

YOUR Responsibility

PWS or Certified Operator Must

1. Contact State about detect

2. Know your sample plan and protocol

3. Consider what may have caused the positive

result

4. DO NOT chlorinate

Only masks the problem

15

Page 16: Planning Ahead - NDEP

Treatment Technique

Triggers

Level 1 Assessment

Following a confirmed coliform sample

Water System Completion Required within

30 days of trigger

16

Page 17: Planning Ahead - NDEP

17

Page 18: Planning Ahead - NDEP

18

Page 19: Planning Ahead - NDEP

And If

Next month the lab calls

In FACT if the lab calls any time in the

next 11 months …

19

Page 20: Planning Ahead - NDEP

Treatment Technique

Triggers Level 1 Assessment

Following a confirmed coliform

sample

WITHIN 30 DAYS OF TRIGGER.

Return form to office with repairs

scheduled or completed.

20

Page 21: Planning Ahead - NDEP

Treatment Technique

Triggers

Level 2 Assessment

Following an E. coli

or

2nd Level 1 Assessment

within 12 mos.

Also Completed within 30 days of

trigger.

21

Page 22: Planning Ahead - NDEP

Treatment Technique

Triggers

22

Page 23: Planning Ahead - NDEP

Find and Fix

o No Violation if a total coliform No public notice required

o Sanitary Defects must be fixed within 30

days of Trigger

o Failure to assess and/or correct is a

Treatment Technique (TT) violation

Page 24: Planning Ahead - NDEP

Find and Fix

o E. Coli results in an MCL violation

o Immediately triggers a Level 2

Assessment

o Public Notice required

o Sanitary Defects must be fixed

within 30 days of Trigger

Page 25: Planning Ahead - NDEP

Remember

25

= Level 2 Assessment

(Done by a State Assessor)

30 Days to fix or develop plan

E. coli MCL

violation

2nd Level 1

12 rolling

months

Page 26: Planning Ahead - NDEP

Jemmy Jo’s Barnstorming Center

26

Well

Storage,

Pumps

Mgr’s

Office

Hostel

Bldg #1

Con

ven

ien

ce S

tore

Hostel

Bldg #3

Gas

Bay

Hostel

Bldg #2

RV

Park

Page 27: Planning Ahead - NDEP

Jemmy Jo’s

Barnstorming Center

Level 1 Assessment

Completed Checklist

No Other Issues Reported

Sampling Technique valid finding

Page 28: Planning Ahead - NDEP

Jemmy Jo’s Level 1 Sampling Sites: Unsuitable site (swivel faucet that is not disinfected

before sampling, multiple attachments, not kept clean)

Change of use at sampling tap

Failure to follow sampling protocol Failure to remove tap aerator

Inadequate flushing prior to sample grab

Improper handling of sample

Sampling of cold and hot water rather than cold water only

Failure to follow sampling plan

28

Page 29: Planning Ahead - NDEP

Distribution System:

Backflow prevention devices not tested or not

working

Line breaks or repairs

SCADA issues (ignored, set improperly, not calibrated, not verified, alarms disengaged)

Repairs completed without disinfection and follow-up sampling

Unusual flow demand placed on the system

Failure to construct or repair in accordance with approved Engineering Plans and design and construction standards

29

Page 30: Planning Ahead - NDEP

Level 2 Assessment

Agency Personnel

Team based on your system’s complexity

and type of problem

Technical Assistance Providers

Operator from another system

30

Page 31: Planning Ahead - NDEP
Page 32: Planning Ahead - NDEP

Jemmy Jo’s

Barnstorming Center

Level 2 Assessment

Found multiple small leaks

Backflow preventers untested

Chlorine residual not checked

System fix within 30 days.

Schedule of Compliance with interim

measures.

Page 33: Planning Ahead - NDEP

SEASONAL SYSTEMS 33

Page 34: Planning Ahead - NDEP

Seasonal Systems

Treatment Technique

Start-up Procedures

Complete all State-required seasonal system start-up procedures prior to serving water to the public

Submit certification form about completion of start-up procedures BEFORE water is served to the public

Page 35: Planning Ahead - NDEP

Seasonal Systems

Required April 1, 2016

Start-up Standard Operating

Procedure

Certification from State before

opening

Page 36: Planning Ahead - NDEP

Change is Coming

Required April 1, 2016

Start-up Standard Operating Procedure

36

Page 37: Planning Ahead - NDEP

REQUIRED

37

Standard Operating Procedure for YOUR system

Start-up Checklist

Clean coliform samples on 2 consecutive days

Approval from State or Agency

Page 38: Planning Ahead - NDEP

AVAILABLE

38

Standard Operating Procedure template

Start-up Checklist (or Start-up/Shut-down

Checklist)

Facility Manager standing by -- Approval from

State or Agency

Page 39: Planning Ahead - NDEP

Start-up Procedure Certified

Page 40: Planning Ahead - NDEP

What If

I don’t shut down my system

Or maybe just a piece of it

Page 41: Planning Ahead - NDEP

What If

I’m not seasonal – I operate year-round

I just close off a couple of loops of the campground during the slow season

Loss of pressure NAC445A.67265

Collect, on 2 or more consecutive days, samples of water from that part of the distribution system which indicate that the presence of any coliform bacteria complies with primary standards.

Page 42: Planning Ahead - NDEP

Public Safety

BSDW

Southern Nevada Health District

Washoe County Health District

#1 Priority is public health and safety.

42

Page 43: Planning Ahead - NDEP

How Can We Help

Call Us

Explain your situation

Ask for advice.

#1 Priority is public health and safety.

43

Page 44: Planning Ahead - NDEP

Your Turn

Questions?

44