Plan SAGE X3 Upgrade

Abubakr Asif, BEng, MBA

[email protected]

www.pannimanagement.com

Page 2: Plan sage x3 upgrade

Page 2

Upgrade Phases

Page 3: Plan sage x3 upgrade

Page 3

Project Planning & Preparation Phase

The Project Planning & Preparation phase includes such tasks as

ensuring the hardware and product are available for the new installation,

defining the project plan, holding the kick-off meeting, and defining the

timeline and schedules.

Page 4: Plan sage x3 upgrade

Page 4

Project Planning & Preparation Phase

Key Project Plan activities:

Upgrade Implementation Spreadsheet (time lines and

specific activities)

Upgrade Configuration & Cutover Checklist

Upgrade Customization List (customization list has to

be provided by customer)

Project Kick off meeting

Page 5: Plan sage x3 upgrade

Page 5

Installation and First Pass

Key Steps in Installation and First Pass:

Pre-migration Tasks and new version installation

Technical & Functional Steps – First Pass

Customization and Product Add-ons

Customer Training and Setup

Testing

Milestone 1 – Configuration and Testing Phase Sign-off

Page 6: Plan sage x3 upgrade

Page 6

Installation and First Pass

Pre-migration and new version installation (Vx, x being

the version being installed

Pre-migration

Task

Vx

(Installation

Create

MIGVx

folder

A critical task under Pre-migrations steps is the

extraction of production data in preparation for the

first pass. During this step in the phase, the

Customer site is down where no new data can be

entered until the extraction is complete.

Page 7: Plan sage x3 upgrade

Page 7

Installation and First Pass

Technical and Functional Steps:

Includes both Technical and Functional Steps that are

completed by the consultant throughout the First Pass

process.

Many of the tasks are technical in nature and are part of the

installation of the program, ensuring patches are updated,

and modifying the existing data in the current version in

preparation for upgrading.

Specific Financial, Distribution, and Manufacturing steps

must be completed within the program for a successful

upgrade.

Page 8: Plan sage x3 upgrade

Page 8

Installation and First Pass

Customizations and Product Add ons:

Includes tasks associated with upgrading any customizations

to the software as any custom reports, workflows, or

requestors that need to be part of the upgrade.

Customizations are listed and tracked using the Upgrade

Customization List.

The installation, configuration, and migration of 3rd party

applications must be addressed as part of this phase. This is

completed in conjunction with the Installation and First Pass

phase, and must be completed before the Dry Run phase.

Page 9: Plan sage x3 upgrade

Page 9

Installation and First Pass

Customer Training and Setup:

The Training and Setup phase contains tasks associated with providing the

customer with training on the changes between their current version and the new

version along with specific setup requirements that must be completed in the new

version after the installation is completed.

If the customer has purchased any new add-ons as part of the upgrade, training

for those add-ons will also take place at this time.

Page 10: Plan sage x3 upgrade

Page 10

Installation and First Pass

Testing Test scripts are prepared for testing customizations, and upgraded

data.

The Unit Testing phase is specific to testing customizations as well

as any custom reports.

It is important that these customizations be tested to ensure they

are functioning correctly and displaying the correct information.

Key User Test the data upgraded to the new version as part of the

First Pass. This includes ensuring access is granted to the

appropriate users and the TEST folder as well as developing

specific scripts for testing critical areas.

The first milestone is reached on Configuration and Testing

Phase Sign-off.

Page 11: Plan sage x3 upgrade

Page 11

Dry Run Phase

The Dry Run Phase includes end user customer training, pre and

post-cutover tasks, specific activities such as creating the Vx Dry

Run folder, and testing on the newly created Dry Run folder.

The Dry Run Activities includes the creation of the Vx Dry Run

folder, the import of production data, folder validation and error

correction, copying of data to a DRYRUNVx folder, and the

completion of post-cutover tasks.

Prior to the sign-off of the Dry Run phase, a readiness assessment

will be completed to ensure all steps or the Dry Run phase have

been completed, issues have been discussed and resolutions

found, and testing is completed.

Page 12: Plan sage x3 upgrade

Page 12

GO Live and Post Go live phase

The Go Live Preparation Activities task includes a preparation

meeting, completing pre-cutover tasks, and a final extraction of

production data and upgrade.

Page 13: Plan sage x3 upgrade

Page 13

GO Live and Post Go live phase

Vx Prod. folder

and validation

Copy Data

from Dry Run

Folder to

Prod

Post Cutover

Tasks

Update user

folder and

deactivate old

version

Technical and Functional carried out for the Dry Run phase will be executed during the

Go Live phase as well.

Once all of the Go Live Activities tasks are completed, the customer is ready to use

Sage ERP X3 Vx as their new production environment.

The Go Live Activities task includes the creation of the Vx Production folder, the import of

production data, folder validation and error correction, copying of data setup from DRYRUNVx

folder to Production folder, and the completion of post-cutover tasks.

Page 14: Plan sage x3 upgrade

Page 14

Time Estimates

Below are typical time lines for a upgrade project

This time may increase depending on the complexity of the customizations in the old version,

number of third party integrations, and new add-ons

Project Task Days

Project Management 5 Days

Setup/Configuration 4 Days

Installation and Ist Pass 3 Days

Customer Difference Training 3 Days

Unit Test 5 Days

Dry Run Phase 3 Days

Go Live Cutover 3 Days

Production Support 5 Days

Total 31 Days