1 Pismo Beach Medical Building Pismo Beach Medical Building Pismo Beach, California 1 Proposed Site Located adjacent to numerous existing structures below and on hilltop behind 2
1
Pismo Beach Medical BuildingPismo Beach Medical BuildingPismo Beach, California
1
Proposed Site Located adjacent to numerous existing structures below and on hilltop
behind
2
2
Proposed Site Located in Previous Marshland Area
3
USGS Program Was Utilized to Establish Seismic Design Category of Site
4
3
Site Once Occupied by a Marsh
Site Subject to jLiquefaction
OPTIONS:1. Stone Columns to 35 ft, to continue 15 ft beyond perimeter
5
p
2. Driven Concrete or Steel Piles to 50 ft
3. 8” Diameter Helical Pile
Further Review of Cone Penetration Test (CPT) S di b (CPT) Soundings by Project Geotechnical
Engineers Determine that Stone Columns Should Extend to 45 ft
Li i P i l to Limit Potential Settlement to 2 in or less.
6
4
Foundation Issues to Address
7
Boring Logs Indicate Poorly Compacted Clayey Sand, Moist to Saturated in Upper 40 ft
8
5
Competent Bearing Material Classified Material Classified as Dense, Clayey Sand Found at a Depth Below 42 ft.
Boring Terminated at 50 ftat 50 ft
9
8” Helical Pile Considered Pending Review of Sieve Analysis
10
6
Theoretical Ultimate Theoretical Ultimate Axial Geotechnical Pile Capacities Were Determined Based Upon Boring Logs Provided
11
Estimated Total Installation Torque – Excluding Soil-Pipe Resistance Was Determined for
Installation Equipment Requirements
12
7
Total Theoretical Pile Capacity Determined Using Both Helical Bearing Capacity and Pipe
Friction
13
Pile Load Test Was Performed to Verify Theoretical Pile Capacity
14
8
Results of Load Test Indicated That A Ultimate Capacity of 175 KIP Could Be Utilized For Final
Design
15
Structural Foundation Plans were Finalized Based Upon Results of Field Load Test
16
9
8” Helical Piles Embeded 8” Minimum into Pile Cap Connected by (4) #5 Dowels Embeded 48”
into Helical Pile at All Columns
17
8” Pile Embeded 8” into Pile Cap Connected with (4) #9 Dowels Embeded 60” Minimum into
Helical Pile and 27” Minimum into Grade Beam
18
10
8” Piles Were Delivered to Site Based Upon Revised Criteria Determined from Field Load Test
19
One Additional Helical Plate was Added to Pile to Assist in Drawing Pile Down to Proper Depth Thru Extremely Soft Upper Soils
8” Helical Piles Were Installed Utilizing a 25K Pengo Head gMounted to a John Deere 120C Excavator
Soil Was Determined As Noncorrosive so Ungalvanized Piles gWere Utilized To Minimize Cost
20
11
Internal Mandral Tool Utilized to Install the Male/Female Square Ended Piles
21
Square Male/Female Connections on .188 Wall Thickness Pipe Allowed for High Installation Torques to be Utilized
Installation Logs Installation Logs were Maintained on All Piles Installed Reflecting Installation Torque in 1ft Increments and Final Pile Depthp
22
12
DP1 Utilized to Monitor Differential Hydraulic Pressure
23
Hydraulic Pressure Required to Install Test Pile Was Utilized on All Production Piles
Concrete Batch Plant P id d D i Provided a Design Mix to Eliminate the Necessity to Place the Grout With a Tremie
Further Minimizing Overall Pile CostsOverall Pile Costs
24
13
A Freefall Grout Design Was Provided To Eliminate the Necessity of Tremie
Installation
25
Rebar Was Installed Into Grouted Pile
U lUtilizing Centralizers
Engineer Increased Rebar Size as They were Bundled in
Units of 4
26
14
Pile Grout Was Vibrated Lightly Once Steel had Been Installed
27
Piles were Installed at Intersections of All Grade Beams and Center of All Columns
Project Completed Utilizing 64 - 8” Diameter Helical Displacement Piles
28
15
Pismo Medical Center Synopsis
• Subject Site Deemed as Potentially Liquefiable during a seismic event• Pile Options Included Rock Piles, Driven Piles, or Helical Piles• Helical Piles were Chosen as Less expensive and Easier to Construct
During the Winter Months• Pile Load Tests Verified Theoretical Pile Capacities and Compression
and Tension• 67 8” Diameter Helical Piles were installed at the site• Deepest Pile at 53 feet with average pile depth of 48 feet across site• Average Pile Installation Time was 43 minutes per pile• All Piles were installed to 25 000 foot/pounds utilizing a Pengo 2 speed
29
All Piles were installed to 25,000 foot/pounds utilizing a Pengo 2 speed head and DP1 Pressure Monitor mounted on a John Deere 120C 15 Ton Excavator
• Piles were installed during rainy season with minimal disturbance to site or loss of production
• Piles were Grouted Utilizing a Freefall Mix Design
Design/Construction Team
• Geotechnical Engineer – GeoSolution, Inc.• Structural Engineer – Allshouse Engineering Inc• Structural Engineer – Allshouse Engineering, Inc• Helical Pier Manufacturer – MacLean Dixie HFS• Helical Pier Distributor – Advanced Support
Technology, Inc.• Helical Pier Installation Contractor- J.R. Spencer
Construction• General Contractor – Inland Pacific Builders, Inc.
30