CANADA These are representations of standard pipeline construction techniques. Trans Mountain will use the most appropriate technique for each specific location. PIPELINE CONSTRUCTION METHODS May 2017 Conventional Pipeline Construction Salvaged Topsoil Salvaged Topsoil Excavated Subsoil Trench Subsoil Side Permanent Right-of-Way Construction Footprint Boundary Construction Footprint Boundary Construction Footprint Work Side Work Lane Existing TMPL Pipeline Travel Lane Trenchless Technique for Crossing Roads and Railways
3

PIPELINE CONSTRUCTION METHODS

Oct 06, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PIPELINE CONSTRUCTION METHODS

CANADA

These are representations of standard pipeline construction techniques. Trans Mountain will use the most appropriate technique for each specific location.

PIPELINE CONSTRUCTION METHODS

May 2017

Conventional Pipeline Construction

SalvagedTopsoil

SalvagedTopsoil

ExcavatedSubsoil

Trench

Subsoil Side

Permanent Right-of-Way

ConstructionFootprintBoundary

ConstructionFootprintBoundary

Construction Footprint

Work Side

Work Lane

Existing TMPLPipeline

Travel Lane

Trenchless Technique for Crossing Roads and Railways

Page 2: PIPELINE CONSTRUCTION METHODS

Community Construction Schedule

2018

• Clearing continues

• Direct pipe installation in key areas

• Hydrovacing

• Pipeline construction: - Grading - Stringing - Welding - Trenching - Lowering in - Backfill - Cleanup

• Terminals and trenchless construction

• Hydrostatic testing

• Road boring

• Reclamation/Restoration

2019

• Pipeline construction continues

• Hydrostatic testing continues

• Leave to open

• Commissioning

• Cleanup

• Restoration

2017

• Infrastructure – laydowns

• Hydrovacing

• Construction yards

• Clearing

• Start of grading in select areas

• Site preparations for Sumas Terminal expansion and major trenchless pipeline locations

• Select river crossings and specialty construction

May 2017

Spread 6 - Fraser Valley Key Construction Activities

Committed to Safety Since 1953.

Page 3: PIPELINE CONSTRUCTION METHODS

Pipeline Construction Methods

May 2017

Direct Pipe™

• Direct Pipe is a trenchless installation technique combining the benefits of micro-tunnelling and Horizontal Directional Drill (HDD) trenchless crossing techniques

• The pipeline is attached to a boring machine pushed forward by a thruster attached to the pipe as the machine excavates

• Allows for simultaneous borehole excavation and pipe installation and can progress at a rate of 25 to 50 metres per day depending on ground conditions

• The excavated material is pumped out via the pipeline

• Can be applied to a wider range of ground condition than HDD but there are limitations on length of installation compared to HDD

Benefits of Direct Pipe:• Allows for reduced environmental foot print due to shorter pipe entry length requirements than HDD

• Permanent borehole support during construction

• Can be used for gravelly/sandy soils

Separation Plant

Pipe Thruster

Control Containers

Machine