Phoenix Convention Center • Phoenix, Arizona
Data Center Energy Management StrategiesEdwards AFB Data Center Consolidation ESPB
Building Performance
Data Center Energy Management Strategies
Les MartinUnited States Air Force– ESPC/UESC Program Manager
Energy Exchange: Federal Sustainability for the Next Decade2
Edwards AFBData Center Consolidation ESPC
First AF Data Center Consolidation ESPC
IT driven effortReduce the energy use and footprint of 14 data centers
Upgrade/consolidate telephone switch facility
Energy Exchange: Federal Sustainability for the Next Decade3
• Ongoing endeavor since Jan 2012• Ground breaking opportunity, AF pilot• Combination of:– Energy conservation mandates– Data center consolidation mandates
Energy Exchange: Federal Sustainability for the Next Decade4
• ESPCs…– …are contracting vehicles that leverage 3rd party funds– …to identify and implement energy saving measures (ECMs)– …for a term of up to 25-years– …are financed through energy and O&M cost savings– …annual payments cannot exceed what the agency would
have paid without an ESPC
• Energy Service Company (ESCO) finances, designs, implements, operates, maintains and owns infrastructure improvements
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade5
• Acquisition Team:– HQ Space Command-Lead Command– AFCEC ESPC PMO– HQ AFMC– AF Life Cycle Mgmt Center (Data Consolidation)– Edwards AFB Engineering– Edwards AFB Communications
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade6
• Notice of Opportunity Sent to 16 ESCOs– Identified project opportunity
• 14 Data Centers, 26,066 SF and 568
– Identified Service Levels, Tech rqmts and O&M rqmts – Identified evaluation factors
• Interested ESCOs submitted Expression of Interest and attended Site Visit
• ESCOs submitted “Sample” Preliminary Assessments (PA)– PA establishes the merits, technical feasibility, level of
projected savings and economics
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade
• Schneider Electric selected to complete Investment Grade Audit (IGA)
• IGA underway• ESCO’s proposed Energy Conservations
Measures (ECMs) must meet the rqmts below:– Must be economical– Must meet provided Service Level Agreements– O&M savings should not be the driver
7
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade8
• Who knows what the ESCO will find/propose– Right sizing data centers– Retire/consolidate servers– Data center power conservation and HVAC
reduction– Lighting upgrades– Liquid cooling– Thin/zero client reduction– Base network power saving initiatives (optic
switching)– Virtualization
Energy Exchange: Federal Sustainability for the Next Decade
• ESCO will submit proposal with tech/price components– Baseline current energy consumption– Inventory/analyze systems, hardware and
applications– Strong M&V Plan– Proposal reviewed at 30/60/90% phases
• First of its kind in DoD, significant visibility• Successful negotiations/award may have AF wide
implications if repeatable
9
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade
Questions?
10
Edwards AFBData Center Consolidation ESPC
Energy Exchange: Federal Sustainability for the Next Decade11
Energy Exchange: Federal Sustainability for the Next Decade12