Phase 1 Project Status: Design • Continued development of alternative station design concepts for stations in the vicinity of USC and Expo Park • Received 85% design from FFP for Work Package A2, Corridor Improvements 23 rd Street to Vermont Avenue • Received 60% design from FFP for Work Package D4, OCS/Traction Power • Received 60% design from FFP for Work Package D5, Train Control and Communication Equipment Supply System Wide • Completed 85% Design Review Work Package A3, Trench Construction 1
Phase 1 Project Status:. Design Continued development of alternative station design concepts for stations in the vicinity of USC and Expo Park Received 85% design from FFP for Work Package A2, Corridor Improvements 23 rd Street to Vermont Avenue - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Phase 1 Project Status:Design
• Continued development of alternative station design concepts for stations in the vicinity of USC and Expo Park
• Received 85% design from FFP for Work Package A2, Corridor Improvements 23rd Street to Vermont Avenue
• Received 60% design from FFP for Work Package D4, OCS/Traction Power
• Received 60% design from FFP for Work Package D5, Train Control and Communication Equipment Supply System Wide
• Completed 85% Design Review Work Package A3, Trench Construction
1
Phase 1 Project Status:Construction
• Continued sidewalk modifications on West side of Flower Street between 23rd and Washington
• Continued procurement of the 61” water line for Work Package A4, 61” Water Line Relocation
• Continued potholing for utilities in Segments A and B • FFP continues submitting construction submittals for trench
construction
• Completed exploratory drilling at Flower/Exposition grade separation to support final trench design
• Continued negotiating construction costs for Work Package A3, Trench Construction
• Hosted the West End Project Status Update Community Meeting
• Briefed Councilman Park’s Staff on TPSS #3
• Briefed Caltrans Staff on TPSS #11
• Project Status Briefings for Council District #9
6
Phase 1 Planned Activities:Design
• Submit Approved for Construction on Work Package A3, Trench Construction
• Submit 85% design on 2 Work Packages:• Work Package B1, Utility Improvements Vermont to Harcourt• Work Package B2, Corridor Improvements Vermont to Harcourt
• Submit 60% design for 3 Work Packages:• Work Package C1, Utilities Improvements Harcourt to Venice
• Continue negotiation on construction costs for Work Package A3, Trench Construction
• Begin Construction Cost Estimate on 85% Work Packages:• B1. Utilities Vermont Av to Harcourt Av• B2, Corridor Improvements Vermont Av to Harcourt Av
7
Phase 1 Planned Activities:Construction
• Complete storm drain line relocation between Adams and 23rd street in Flower Street
• Continue sewer line relocation between Adams and Washington on the East side of Flower Street
• Complete demolition and reconstruction of curb and sidewalk on West side of Flower Street
• Start installing street lighting system along West side of Flower Street between 23rd and Washington
• Start Utility relocation to support trench construction
8
Phase 1 Planned Activities: Government/Community Relations • Continue meeting with administrators, parents and teachers at
schools sites along alignment to provide construction schedule and safety information tips
• Meet with various stakeholders in Segment A to discuss utility relocation work schedule, timeline and coordination items
• Host Project Status Update Meeting for Segment A
Real Estate
• Continue real estate acquisition and lease termination activities
Third Party Agreements
• Negotiate Master Cooperative Agreements with Culver City, LA County and Time Warner 9
Phase 1 Project Status:Construction Progress
10Utility work on Flower near 23rd
Phase 1 Project Status:Construction Progress
11Looking Southwest on Flower St.
Project Major MilestonesMar 2007 Apr 2007
Authority Actions
May 2007 Jun 2007 Jul 2007
Design Build Contract
Community Outreach
Aug 2007
Legend:Urban Design Committee Meeting
Downtown Project Status Update
Meeting
West End Project Status
Update Meeting
12
Negotiate Construction Packages A3 (Trench) & CCTV
Approve Construction Pkg. A3 (Trench) & CCTV
Negotiate Construction Package B1 Utilities Vermont - Harcourt
Mid-Corridor Project Status
Update Meeting
Approve Construction Package B1 Utilities Vermont to Harcourt
Negotiate Construction Package A2 Corr Impmnts 23rd -Vermont
Approve Construction Package A2 Corr Impmnts 23rd -Vermont
Approve Construction Package B2 Corr Imp Vermont to Harcourt
Negotiate Construction Package B2 Corr Imp Vermont to Harcourt
Approve LNTP Procure TPSS Prefab Bldg Package D3
Negotiate Construction Package C1 Utilities Harcourt to Venice
Mid-Corridor Project Status
Update Meeting
West End Project Status Update Meeting
April 2007
• Met with Union Local 300 Field Representatives to discuss progress in hiring new and existing union members from the Expo corridor. Will meet with the Union on a monthly basis.
• Continued to use PVJOBS workers to distribute construction notices and public meeting announcements throughout the corridor.
• Distributed Expo Jobs Program information throughout the Expo Corridor to libraries, community organizations, senior centers and retail establishments
• Continued to update database of individuals interested
Summary of Jobs Program Activities:
13
AA/EIS/Conceptual Engineering
• Organized and summarized approximately 3,000 communications (letters, scoping cards, emails, etc.) regarding project scoping. Distributed comments among disciplines for review and action as required.
• Prepared draft Scoping Report for internal review
• Conducted Agency Scoping meeting
• Continued data collection on various environmental issues, e.g., biological resources, historic resources, etc.
• Continued Phase 1 Grade Crossing Policy analysis development for LRT alternatives
• Continued monitoring of Metro Ridership model and coordinated with FTA
Phase 2 Project Status:
14
AA/EIS/Conceptual Engineering (cont.)
• Began alternatives development including initial plan and profiles, alternative station locations and initial trip times
• Continued development of baseline mapping
• Began identification of potential TPSS and ancillary facilities sites in support of environmental review
• Developed and submitted priority traffic count list for LADOT action
• Held initial meetings with Santa Monica and Los Angeles regarding bikepath plans
Phase 2 Project Status:
15
Government/Community Relations
• Received over 2,700 separate submittals of scoping comments
• Compiled scoping comments and summarized them in a draft Scoping Report
• Further developed the Public Outreach Plan
• Continued to monitor the Phase 2 Project hotline
Phase 2 Project Status :
16
Alternative Analysis/EIS/Conceptual Engineering
• Continue development of BRT, TSM and build alternatives
• Continue development of Metro Grade Crossing Policy study of grade crossings with LADOT traffic data
• Continue collection of background information for environmental studies
• Continue concept engineering of challenge areas such as west end terminal, I 405/Sepulveda, Venice / Sepulveda alignment
• Monitor progress on Metro development of Ridership model
Phase 2 Planned Activities:
17
Government/Community Relations
• Finalize Scoping Report and publish it on the Expo website
• Complete Public Participation Plan
• Conduct tours of the alternative alignments for elected official staff
• Conduct staff briefing for local, state and federal elected official representatives