BRACBRACPMO WESTPMO WEST
Petroleum Program UpdatePetroleum Program Update
Wilson DoctorWilson DoctorNavy Project ManagerNavy Project Manager
March 13, 2008March 13, 2008RAB MeetingRAB Meeting
Former NAS Moffett FieldFormer NAS Moffett FieldFormer NAS Moffett Field
Additional Building 29 PipelinesAdditional Building 29 PipelinesAdditional Building 29 Pipelines
• Background– 3-inch pipeline and 8-inch pipeline
• 4,880 ft and 3,640 ft– Installed in 1930s and 1940s– Inactive since 1960s
• Sampled soil every 50 feet
• Fieldwork completed in November 2007
• Preparing draft report
BRACBRACPMO WESTPMO WEST
8
Additional Building 29 PipelinesAdditional Building 29 PipelinesAdditional Building 29 Pipelines
BRACBRACPMO WESTPMO WEST
9
Building 55 SumpBuilding 55 SumpBuilding 55 Sump
• Sump installed during the Building 55 pipeline investigation in 2005
• 10-foot deep PVC pipe
• Removed sump and collected soil samples February 2008
• Four quarters of groundwater monitoring
• Prepare draft report
BRACBRACPMO WESTPMO WEST
10
Building 55 SumpBuilding 55 SumpBuilding 55 Sump
BRACBRACPMO WESTPMO WEST
11
Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background
• Fuel station
• Site covers about 1 acre
• Two 5,000-gal USTs (Tanks 19 & 20)– Removed in 1986– Contained gasoline and diesel
BRACBRACPMO WESTPMO WEST
12
Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background
BRACBRACPMO WESTPMO WEST
13
Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background
• Previous Investigations:
– Initial soil and groundwater (GW) assessment began 1987
– Periodic GW monitoring mid-1990s
– Site assessment activities 2003
BRACBRACPMO WESTPMO WEST
14
Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background
• Previous investigations (continued):
– Chemical oxidation January 2005
– Quarterly groundwater monitoring 2005 to 2006• levels decreased initially• levels returned
• Previous investigation findings:– No free product observed at the site– Stable contaminant plume
BRACBRACPMO WESTPMO WEST
15
Site 14 SouthSite 14 SouthSite 14 South
Current investigation:
• Final Work Plan February 2008– Additional site characterization– Install seven additional groundwater monitoring wells– Four quarters groundwater sampling
• New wells and nine existing wells– Evaluate data– Potential tank testing