BRAC BRAC PMO WEST PMO WEST Petroleum Program Update Petroleum Program Update Wilson Doctor Wilson Doctor Navy Project Manager Navy Project Manager March 13, 2008 March 13, 2008 RAB Meeting RAB Meeting Former NAS Moffett Field Former NAS Moffett Field Former NAS Moffett Field
18

Petroleum Program Update

May 17, 2015

Download

Technology

Steve Williams

Navy presentation to the Moffett Field Restoration Advisory Board on March 13, 2008, regarding the petroleum sites, including those near Hangar One and between Hangars Two and Three.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

Petroleum Program UpdatePetroleum Program Update

Wilson DoctorWilson DoctorNavy Project ManagerNavy Project Manager

March 13, 2008March 13, 2008RAB MeetingRAB Meeting

Former NAS Moffett FieldFormer NAS Moffett FieldFormer NAS Moffett Field

Page 2: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

2

Presentation OverviewPresentation OverviewPresentation Overview

• Background

• Petroleum projects– Buildings 29 & 55 pipelines– Additional Building 29 pipelines– Building 55 sump– Site 14 South

Page 3: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

3

BackgroundBackgroundBackground

• 76 petroleum sites - closed to date

• 54 petroleum sites - in progress

Page 4: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

4

Building 29 & 55 PipelinesBuilding 29 & 55 PipelinesBuilding 29 & 55 Pipelines

• Two inactive pipelines not previously investigated

• Building 29 pipelines– Aviation gasoline– Near Hangar 1– Inactive since 1950s– 900 ft, 2-inch and 3-inch diameter, metal

• Building 55 pipeline– Boiler fuel– Near Hangars 2 & 3– Inactive since at least 1994– 1400 ft, 3-inch diameter, metal

Page 5: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

5

Building 29 & 55 PipelinesBuilding 29 & 55 PipelinesBuilding 29 & 55 Pipelines

• Collected soil samples along pipelines every 20 feet

• Fieldwork completed

• Draft report

Page 6: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

6

Building 29 & 55 PipelinesBuilding 29 & 55 PipelinesBuilding 29 & 55 Pipelines

Page 7: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

7

Additional Building 29 PipelinesAdditional Building 29 PipelinesAdditional Building 29 Pipelines

• Background– 3-inch pipeline and 8-inch pipeline

• 4,880 ft and 3,640 ft– Installed in 1930s and 1940s– Inactive since 1960s

• Sampled soil every 50 feet

• Fieldwork completed in November 2007

• Preparing draft report

Page 8: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

8

Additional Building 29 PipelinesAdditional Building 29 PipelinesAdditional Building 29 Pipelines

Page 9: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

9

Building 55 SumpBuilding 55 SumpBuilding 55 Sump

• Sump installed during the Building 55 pipeline investigation in 2005

• 10-foot deep PVC pipe

• Removed sump and collected soil samples February 2008

• Four quarters of groundwater monitoring

• Prepare draft report

Page 10: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

10

Building 55 SumpBuilding 55 SumpBuilding 55 Sump

Page 11: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

11

Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background

• Fuel station

• Site covers about 1 acre

• Two 5,000-gal USTs (Tanks 19 & 20)– Removed in 1986– Contained gasoline and diesel

Page 12: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

12

Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background

Page 13: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

13

Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background

• Previous Investigations:

– Initial soil and groundwater (GW) assessment began 1987

– Periodic GW monitoring mid-1990s

– Site assessment activities 2003

Page 14: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

14

Site 14 South BackgroundSite 14 South BackgroundSite 14 South Background

• Previous investigations (continued):

– Chemical oxidation January 2005

– Quarterly groundwater monitoring 2005 to 2006• levels decreased initially• levels returned

• Previous investigation findings:– No free product observed at the site– Stable contaminant plume

Page 15: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

15

Site 14 SouthSite 14 SouthSite 14 South

Current investigation:

• Final Work Plan February 2008– Additional site characterization– Install seven additional groundwater monitoring wells– Four quarters groundwater sampling

• New wells and nine existing wells– Evaluate data– Potential tank testing

Page 16: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

16

Site 14 South Site 14 South Site 14 South

Page 17: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

17

SummarySummarySummary

• Moffett petroleum program ongoing

• 76 petroleum sites - closed to date

• 54 petroleum sites - in progress

Page 18: Petroleum Program Update

BRACBRACPMO WESTPMO WEST

18

Questions?Questions?Questions?