Page 1
1
BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION
GANDHINAGAR
Petition No. 1302 of 2013
In the matter of:
In the matter of petition under GERC (Terms and Conditions of Intra-State
Open Access) Regulations, 2011 for determination of Additional Surcharge
payable by Open Access consumers availing power under open access.
Petitioner : Gujarat Urja Vikas Nigam Limited
Represented by : Learned Advocate Shri M.G. Ramchandran,
alongwith S/Shri K.P. Jangid and V.T. Patel.
Co- Petitioner No. 1 : Madhya Gujarat Vij Company Limited
Represented by : Ms. M.M. Marathe and Shri Umesh Parikh.
Co- Petitioner No. 2 : Uttar Gujarat Vij Company Limited
Represented by : Shri Kamal Sindhi.
Co- Petitioner No. 3 : Paschim Gujarat Vij Company Limited
Represented by : Shri J. J. Gandhi.
Co- Petitioner No. 4 : Dakshin Gujarat Vij Company Limited
Represented by : Shri B.V. Shah.
Versus
Respondent No. 1 : M.D. Inducto Cast Private Limited
Represented By : Nobody was present.
Page 2
2
Respondent No. 2 : Garg Casteels Private Limited
Represented By : Nobody was present.
Respondent No. 3 : RSK Industries Private Limited
Represented By : Nobody was present.
Respondent No. 4 : Sintex Industries Private Limited
Represented By : Nobody was present.
Respondent No. 5 : Hans Industries Private Limited
Represented By : Nobody was present.
Respondent No. 6 : Arvind Limited
Represented By : Shri Hemen Joshi.
Respondent No. 7 : Shree Durga Syntex Private Limited
Represented By : Nobody was present.
Respondent No. 8 : JK Paper Limited
Represented By : Nobody was present.
Respondent No. 9 : Pioneer Syntex Private Limited
Represented By : Nobody was present.
Respondent No. 10 : Mohit Industries Private Limited
Represented By : Shri Hiren Bhatt.
Respondent No. 11 : Laxcon Steels Limited
Represented By : Nobody was present.
Respondent No. 12 : Federation of Kutch Industries Associations
Page 3
3
Represented By : Advocate N. D. Chhaya.
Respondent No. 13 : Reliance Industries Limited
Represented By : Learned Advocates S/Shri R.S. Sanjanwala and Shri
Gaurav Thakore along with Jayant Roktar.
Respondent No. 14 : UltraTech Cement
Represented By : Shri K.K. Sukhadia.
Respondent No. 15 : Umiya Ceramics Private Limited
Represented By : Nobody was present.
Respondent No. 16 : Sentosa Granito Private Limited
Represented By : Nobody was present.
Respondent No. 17 : Birla Century
Represented By : Nobody was present.
Respondent No. 18 : Federation of Gujarat Industries
Represented By : Shri R. N. Purohit.
Respondent No. 19 : Senso Granito Private Limited
Represented By : Nobody was present.
Respondent No. 20 : Sorento Granito Private Limited
Represented By : Nobody was present.
Respondent No. 21 : Simpolo Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 22 : Sims Ceramics Private Limited
Page 4
4
Represented By : Nobody was present.
Respondent No. 23 : Real Granito Private Limited
Represented By : Nobody was present.
Respondent No. 24 : Ramoji Granite Limited
Represented By : Nobody was present.
Respondent No. 25 : New Pearl Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 26 : Jet Granito Private Limited
Represented By : Nobody was present.
Respondent No. 27 : Ajanta Manufacturing Limited
Represented By : Nobody was present.
Respondent No. 28 : Mega Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 29 : Antique Mabronite Private Limited
Represented By : Nobody was present.
Respondent No. 30 : Sunshine Tiles Company Private Limited
Represented By : Nobody was present.
Respondent No. 31 : Sunora Tiles Private Limited
Represented By : Nobody was present.
Respondent No. 32 : Tirthak Paper Mill Private Limited
Represented By : Nobody was present.
Page 5
5
Respondent No. 33 : Simola Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 34 : Platina Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 35 : Milano Papers Private Limited
Represented By : Nobody was present.
Respondent No. 36 : Famous Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 37 : Vita Granito Private Limited
Represented By : Nobody was present.
Respondent No. 38 : Vadilal Industries Limited
Represented By : Nobody was present.
Respondent No. 39 : Confederation of Indian Industries
Represented By : Nobody was present.
Respondent No. 40 : Simolex Ceramics Private Limited
Represented By : Nobody was present.
Respondent No. 41 : Comet Granito Private Limited
Represented By : Nobody was present.
Respondent No. 42 : Coral Granito Private Limited
Represented By : Nobody was present.
Respondent No. 43 : Lorenzo Vitrified Tiles Private Limited
Page 6
6
Represented By : Nobody was present.
Respondent No. 44 : Elica Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 45 : Max Granito Pvt. Ltd.
Represented By : Nobody was present.
Respondent No. 46 : Varmora Granito Private Limited
Represented By : Nobody was present.
Respondent No. 47 : Silk Touch Vitrified Private Limited
Represented By : Nobody was present.
Respondent No. 48 : Gujarat Granito Manufacturer’s Association
Represented By : Nobody was present.
Respondent No. 49 : Mono Steel India Limited
Represented By : Nobody was present.
Respondent No. 50 : United Phosphorus Limited, Vapi.
Represented By : Nobody was present.
Respondent No. 51 : Transpek-Silox Industries Limited
Represented By : Nobody was present.
Respondent No. 52 : United Phosphorus Ltd., Ankleshwar
Represented By : Nobody was present.
Respondent No. 53 : Nilkanth Concast Private Limited
Represented By : Nobody was present.
Page 7
7
Respondent No. 54 : Essar Steel India Limited
Represented By : Advocate Sahil Shah.
Respondent No. 55 : Ambuja Intermediates Limited
Represented By : Shri D. S.Doshi.
Respondent No. 56 : AIA Engineering Limited
Represented By : Learned Advocate Shri Gaurav Mathur.
Respondent No. 57 : Videocon Industries Limited
Represented By : Nobody was present.
Respondent No. 58 : Regent Granito (India) Limited
Represented By : Nobody was present.
Respondent No. 59 : Deepak Nitrite Limited
Represented By : Nobody was present.
Respondent No. 60 : Mafatlal Industries Limited
Represented By : Nobody was present.
Respondent No. 61 : Gujarat Sidhee Cement Limited
Represented By : Learned Advocate Shri Gaurav Mathur
Respondent No. 62 : L & T Special Steel and Heavy Forgings
Represented By : Nobody was present.
Respondent No. 63 : Spectrum Dyes and Chemicals Private Limited
Represented By : Nobody was present.
Respondent No. 64 : Rajashree Polyfil
Page 8
8
Represented By : Nobody was present.
Respondent No. 65 : Shah Alloys Limited
Represented By : Learned Advocate Shri Gaurav Mathur.
Respondent No. 66 : Gondal Chambers of Commerce and Industry
Represented By : Nobody was present.
Respondent No. 67 : Gujarat Fluorochemicals Limited
Represented By : Shri Pradeep Dhir.
Respondent No. 68 : Devika Fibres Private Limited
Represented By : Nobody was present.
Respondent No. 69 : Fag Bearings India Limited
Represented By : Nobody was present.
Respondent No. 70 : Shree Alkali and Chemicals
Represented By : Nobody was present.
Respondent No. 71 : Gujarat Polyfilms Private Limited
Represented By : Nobody was present.
Respondent No. 72 : S. Kumars Nationwide Limited
Represented By : Nobody was present.
Respondent No. 73 : Air Liquid India Holding Private Limited
Represented By : Nobody was present.
Respondent No. 74 : Mafatlal Denims Limited
Represented By : Nobody was present.
Page 9
9
Respondent No. 75 : Gujarat Chambers of Commerce and Industry
Represented By : Shri D. S. Doshi.
Respondent No. 76 : Raymond Limited
Represented By : Nobody was present.
Respondent No. 77 : Navin Fluorine International Limited
Represented By : Shri L.K. Pisolkar.
Respondent No. 78 : Pratibha Fabrics Limited
Represented By : Nobody was present.
Respondent No. 79 : Steel Cast Limited
Represented By : Nobody was present.
Respondent No. 80 : Open Access Users Association
Represented By : Nobody was present.
Respondent No. 81 : Saint Gobain Glass India Limited
Represented By : Nobody was present.
Respondent No. 82 : Nirma Limited
Represented By : Learned Advocate Shri Gaurav Mathur.
Respondent No. 83 : Welspun Private Limited
Represented By : Learned Advocate Shri Gaurav Mathur.
Respondent No. 84 : Shree Ram Oxy-Gas Private Limited
Represented By : Nobody was present.
Respondent No. 85 : Plastene India Limited
Page 10
10
Represented By : Nobody was present.
Respondent No. 86 : Essar Electric Power Development Corporation
Limited
Represented By : Shri Bhavesh Kundalia.
Respondent No. 87 : Chiripal Poly Films Limited
Represented By : Nobody was present.
Respondent No. 88 : SICGIL Industrial Gases Limited
Represented By : Nobody was present.
Respondent No. 89 : Ankur Scientific Energy Technology Private Limited
Represented By : Nobody was present.
Respondent No. 90 : Knowledge Infrastructure Systems Private Limited
Represented By : Nobody was present.
Respondent No. 91 : SAL Steel Limited.
Represented by : Learned Advocate Shri Gaurav Mathur.
CORAM:
Shri Pravinbhai Patel, Chairman
Dr. M.K. Iyer, Member (Finance)
Date: 12/03/2014
ORDER
1. The present petition has been filed by the petitioner seeking the
following reliefs:
Page 11
11
a. Hold that the obligation of the state distribution licensees in terms
of power purchase agreements has been and continues to be
stranded and there is an unavoidable obligation and incidence to
bear fixed costs consequent to such agreements.
b. Determine the additional surcharge of Rs 1.35 payable by new
open access consumers on quantum of power purchase through
open access using the network of distribution licensee.
c. Make applicable the additional surcharge on power purchased by
open access consumers under open access.
d. Maintain the cross subsidy surcharge at current levels in order to
ensure viability and sustainability in operations of DISCOMs.
e. Consider the information submitted by GUVNL for determining
the amount of additional surcharge.
2. The facts mentioned in the petition are briefly as under:
2.1. The petitioner is a government company incorporated under the
Companies Act, 1956, and performs the function of Bulk power
purchase and sale on behalf of the distribution licensees, Uttar Gujarat
Vij Company Limited (UGVCL), Madhya Gujarat Vij Company Limited
(MGVCL), Dakshin Gujarat Vij Company Limited (DGVCL) and Paschim
Gujarat Vij Company Limited (PGVCL) which are the co-petitioners to
the present petition.
2.2. The Intra State ABT in the state of Gujarat was implemented on
5.4.2010 and SLDC / Discoms are granting approvals / consent to open
access consumers for purchase and sale of power through open access
Page 12
12
as per Open Access Regulations. Accordingly, open access consumers
are now buying considerable quantum of power under open access and
on the other hand State DISCOMs have tied up considerable quantum of
power considering the overall growth of the state. This results into
stranded generation capacity and under recovery of fixed cost. The
present Petition is filed by the Petitioner before Hon’ble Commission
under GERC (Terms and Conditions of Intra-State Open Access)
Regulations 2011, hereinafter referred to as Intra State Open Access
Regulations for determination of additional surcharge payable by open
access consumers availing power under open access.
2.3. Further, Section 42 (4) of the Electricity Act, 2003, Section 8.5 of the
Tariff Policy, and Regulation 25 of the GERC (Terms and Conditions of
Intra-State Open Access) Regulations, 2011 provide Additional
Surcharge to meet the fixed cost of distribution licensee arising out of its
obligation to supply if it is conclusively demonstrated that the obligation
of a licensee, in terms of existing power purchase commitments, has
been and continues to be stranded, or there is an unavoidable obligation
and incidence to bear fixed costs consequent to such a contract.
2.4. Further, the petitioners have tied up the considerable quantum of
power procurement from various sources. The Installed capacity of the
power procurement from conventional sources works out to 18270 MW
as on 31.03.2013.
2.5. Further, the state has made significant capacity addition from
renewable sources to utilize natural resources available with the state.
At present total 3873 MW capacity is available from renewable sources
Page 13
13
2.6. Thus, total installed capacity of the state from all sources (Conventional
and Non Conventional) works out to 22143 MW (18270 MW from
Conventional and 3873 MW from Non Conventional sources) as on
31.03.2013.
2.7. The peak demand for electricity in the state for FY 2011-12 was 11209
MW and for FY 2012-13 (as on date of application) was 12348 MW.
Thus, the generation capacity tied up by state is adequate to mitigate
demand for electricity.
2.8. Further, to meet the future demand of the State, State Utilities have tied
up adequate power from various sources including Competitive bidding
under Case I. By the end of 12th Five Year Plan i.e. by 2016-17 the
capacity to the tune of 7632 MW is expected to be commissioned
2.9. On commissioning of the above capacity, the installed capacity of State
from conventional sources will be 25902 MW which will be required to
serve the peak demand of 19670 MW estimated as per 17th Electric
Power Survey report (EPS) published by Central Electricity Authority
for the long term power purchase planning purpose.
2.10. Clause 3 of Regulation 25 the Intra-State Open Access Regulations
notified by the Commission provides that the distribution licensee shall
submit to the Commission on six monthly basis, a detailed calculation
statement of fixed cost which the licensee is incurring towards his
obligation to supply and the Commission shall scrutinize the statement
Page 14
14
of calculation of fixed cost submitted by the distribution licensee and
obtain objections, if any, and determine the amount of additional
surcharge applicable to new open access customers.
2.11. Relevant details of amounts incurred towards obligations to pay
capacity charges under power purchase agreements, cost of
transmission payable to transmission licensees, other costs of
distribution business apart from power purchase costs for the year
2011-12 are as under:
Table A
Particulars Units
(Mus)
Amt.
(Rs Cr)
Fixed Cost of Power Purchase 6056
Variable Cost of Power Purchase 16104
Total Power Purchase 65827 22159
Less: Short term sale of power 5815 2181
Power Purchase for DISCOM
Consumers 60012 19978
Table B
Particulars
Net Fixed Cost (Rs Crs) (6056 Cr X 60012/65827) 5521
Net Variable Cost (Rs Crs) 14457
Total Cost (Rs Crs) 19978
Unit for DISCOMs consumers (Mus) 60012
Page 15
15
Table – C
Particulars 2011-12
Total Fixed Cost of Power Purchase to
Generators (Rs Cr) (Table B)
A 5521
Add: Cost of Transmission (Rs Cr) B 1940
Add: Costs of Distribution business
excluding power purchase (Rs Cr)
C 2243
Total Fixed Cost (Rs Cr) (A+B+C) D 9704
The Total fixed cost for power purchase from the generators plus cost of
transmission and cost of distribution business excluding power
purchase works out to Rs 9704 Crs for 2011-12. The energy sold to the
consumers by the distribution licensees during financial year for FY
2011-12 was 49096 MUs. Additionally, the open access customers
purchased 1491 MUs of power under Open Access. If the open access
customers would have drawn this quantum of electricity from the
distribution licensees instead of through open access, the distribution
licensees would have supplied 50587 MUs. However, the same reduced
to 49096 MUs as the open access customers purchased and consumed
1491 MUs under Open Access. Thus, the fixed cost per unit of total
consumption of the consumers (including electricity drawn from the
licensees as well as through open access) works out to Rs. 1.92 per unit
as shown below:
Page 16
16
Table - D
Particulars 2011-12
Total power sold by Discoms to end
consumers (Mus)
A 49096
Consumption under OA (Mus) B 1491
Total Units (Mus) (A+B) C 50587
Total Fixed Cost (Rs Cr) (Table C) D 9704
Fixed Cost Per unit sold to consumers plus
OA consumption (Rs / Unit) (D/C×10)
F 1.92
The details of under recovery of fixed charges, amount recovered by
Discoms towards wheeling charges and demand charges are as under:
Table - E
Particulars
2011-12
Amt.
(Rs.Crs)
Unit
(MUs)
Rs / Unit
Gross Under recovery of Fixed
Cost Due to OA Consumption 286 1491 1.92
Less: Wheeling Charges recovered 16 1491 0.11
Less: Recovery of Demand
Charges from OA Consumers 69 1491 0.46
Total Under recovery 201 1.35
There was gross under recovery of fixed cost of Rs 286 Crs for 2011-12
due to consumption of power by OA consumers under open access. Net
under recovery of fixed cost by Discoms due to OA consumption after
adjustment of demand charges and wheeling charges works out to Rs
1.35 per unit for the 2011-12.
2.12. In the above calculation Cross subsidy Surcharge of Rs 0.39/unit has not
been considered as it is towards the Cross subsidization to subsidized
Page 17
17
category of consumers like Agriculture and BPL and this cross
subsidization is mainly through higher energy charges. As per Section 25
of Open Access Regulations, additional surcharge is payable by open
access consumers in addition to cross subsidy surcharge.
3. The matter was first heard on 4.5.2013. During the hearing the
Commission directed the petitioner to issue public notice inviting
comments/objection from stakeholders within 30 days of such notice
and also to upload the copy of the petition on the website of the
petitioner as the prayers sought by the petitioners shall impact a wide
range of entities situated in different parts of the State in different
distribution licensees’ area.
3.1. The petitioner on 17.05.2013, issued a public notice, as per the directives
given in the oral order of the Commission dated 10.05.2013 inviting
comments/objection from stakeholders, in newspapers, viz. Gujarat
Samachar, Sandesh and Indian Express, within 30 days from the date of
public notice.
3.2. In response to the aforesaid public notice, the Office of the Commission
received comments/objections from 91 stakeholders whose names are
shown as the respondents.
Considering the objections/comments of various stakeholders, the gist
of their suggestions is as follows:
GUVNL is a company in the State carrying out the function of Bulk
Power Purchase and Bulk Sale of power and has no locus standi to
file the present petition.
Page 18
18
The data/calculations given are for the period of FY 2011-12 i.e. of
full year and not precedent six months, hence, need to be rejected on
this ground also.
The total installed/contracted capacity in the State has been
projected as 22143 MW consisting of 18270 MW of conventional and
3873 MW of Non-conventional as on 13.03.2013. As against the peak
demand reached in the year 2012-13 has been indicated as 12348
MW. Thus, only 55.8 % of the total capacity was utilized when the
State observed the peak demand.
The power purchased through open access for the year 2011-12 is
stated as only 1491 MUs which is less than 3% of the total
consumption of 50587 MUs by the consumers.
As per the data submitted in the petition, by Year 2016-17, the State
would have installed capacity of 25902 MW from conventional
sources and if we add the capacity of non-conventional sources, the
total availability may be above 30,000 MW against the recorded
maximum demand of 12348 MW. Thus, with an average growth of
power demand of 8 % the available capacity will far exceed the
demand and hence, the surplus capacity.
While allowing the power purchase cost in the ARR, the Commission
has rightly considered the overall tariff of the generating sources
including the fixed cost and variable cost. Hence, the computation of
additional surcharge indicated by the petitioner is misleading.
Detailed Study of the MYT data of Discoms clearly shows that in case
of HT/EHT consumers, the average tariff being recovered is more
than the average cost to serve.
Page 19
19
Inspite of several directives of the Commission, the Gujarat
Distribution licensee have not yet furnished consumer category wise
and voltage level wise cost to serve data.
The agricultural subsidy accounts for a major liability to utilities and
cost to serve for agricultural section is artificially kept lower to
reduce the subsidy obligation of the Government.
Amount payable under various heads can be decided in tariff
petitions only. As per the Section 62 (4) of the Electricity Act, 2003,
ordinary tariff or part thereof cannot be revised in the Financial year.
As per Regulations, Additional Surcharge is only applicable to new
open access customers.
Open Access consumers cannot be levied on Additional Surcharge till
they remain the consumer of the licensee of his area and continue to
pay Fixed Charges by way of Contract Demand Charges.
Considerable loss is attributable to not procuring power from other
more economical sources e.g. IEX/PXIL, UI Regime etc., even when
such opportunity are available and favoring GSECL to help it to
achieve better plant load factor overlooking to the fact that such
favours are not available to other IPPs/Generators.
Additional Surcharge is a surcharge payable on the charges of
wheeling, Additional Surcharge shall be only to meet out the Fixed
Cost of Distribution licensee arising out of its obligation to supply.
The Additional Surcharge shall become applicable only if obligation
of licensee in terms of power purchase commitments has been and
continues to be stranded.
The Calculations should consider the stranded fixed cost which is due
to the direct result of open access power brought during those time
Page 20
20
blocks, where the generating capacity is available but not scheduled
solely due to such open access power.
The under recovery of Rs. 286 Crores for the year 2011-12 shown
by the petitioner is also not valid as the Commission has already
passed the MYT order and approved ARR and Annual Performance of
FY 2011-12 in which the Commission has not recognized such under
recovery.
Further, the month wise demand charges for energy drawn by open
access consumers furnished in annexure B of the petition are not
consistent. For DGVCL, in the month of September- 2011 to January,
2012 when exchange prices are low, open access consumption is
shown very low. Demand charges recovered are increasing some
time and then there is sudden drop (from Rs. 13.2 Crs in June 2011 to
Rs. 2.00 Crs in August, 2011) and so on. Demand charges recovery
cannot be fluctuating.
As per the data provided in tables A, B and C of the petition, the fixed
cost of power purchase should be Rs. 5521 Crs and not Rs. 9704 Crs.
as mentioned since the fixed cost related to network assets are to be
recovered through wheeling charges. Taking the aforesaid amount,
per unit fixed cost works out to be Rs. 0.92 and not Rs. 1.92 per unit.
According to Table A of the petition, per unit cost for total power
purchase is Rs. 3.37 per unit where as income from sale of power is
Rs. 3.75 per unit which clearly shows that for surplus capacity
GUVNL is gaining more than its purchase costs.
GUVNL should explore all the option of reducing its liability towards
capacity charges payment on surplus capacity and selling the surplus
capacity outside Gujarat.
Page 21
21
4. The matter was heard on 23.07.2013, during which learned counsel of
objectors sought copies of the PPAs entered into by the petitioner on
account of which the petitioner has claimed the stranded fixed cost. The
Commission vide oral order dated 29.07.2013 directed the petitioner to
provide copies of following categories of PPAs (i) GUVNL and GSECL (ii)
GUVNL and Central Sectors like NTPC and (iii) PPA signed based upon
competitive bidding process for the reference of the objectors. In
compliance to above, the petitioner uploaded the PPAs signed with
Central power station i.e. NTPC, with State Generating Company i.e.
GSECL, and also uploaded the PPAs signed with IPP under competitive
bidding process for reference of the objectors.
5. The matter was further heard in detail on 17.08.2013. The petitioners
and respondents made their submissions regarding the maintainability
of the petition, validity of Additional Surcharge, documents provided by
the petitioners, deficiency in the documents etc.
Based on the submissions made by the parties the Commission framed
the following issues:
“1. Is the claim of the petitioner for Additional Surcharges valid and legal
in terms of provisions of the Electricity Act, 2003?
2. What are the data/documents required for determination of the
Additional Surcharge and whether the petitioner has submitted all the
relevant data/documents?”
Page 22
22
6. After considering the submissions of the parties, the daily order dated
4.10.2013 was passed by the Commission, wherein it decided issue No.
1 in paras 9.1 to 9.5 of the said order as under:
“…
9.1 We have carefully considered the submissions made by the parties.
The preliminary objection raised by the objectors is that the
Additional Surcharge claimed by the petitioner is not legal and valid
in terms of provision of Electricity Act, 2003. While the petitioner
contended that the claim of the petitioner is legal and valid. It is,
therefore, necessary to refer the relevant provisions of the Electricity
Act, 2003 and GERC (Terms and Conditions of Intra-State Open
Access) Regulations, 2011 notified by the Commission and provisions
of National Electricity Policy notified under Section 3 of the
Electricity Act, 2003 by the Ministry of Power.
9.2. Section 42 of the Electricity Act, 2003 states about the duties of the
distribution licensees and open access, which is relevant in the
present petition is reproduced below:
“42.(1) It shall be the duty of a distribution licensee to develop and
maintain an efficient, co-ordinated and economical distribution
system in his area of supply and to supply electricity in accordance
with the provisions contained in this Act.
(2) The State Commission shall introduce open access in such
phases and subject to such conditions, (including the cross
subsidies, and other operational constraints) as may be specified
Page 23
23
within one year of the appointed date by it and in specifying the
extent of open access in successive phases and in determining the
charges for wheeling, it shall have due regard to all relevant
factors including such cross subsidies, and other operational
constraints:
Provided that such open access may be allowed before the cross
subsidies are eliminated on payment of a surcharge in addition to
the charges for wheeling as may be determined by the State
Commission :
Provided further that such surcharge shall be utilised to meet the
requirements of current level of cross subsidy within the area of
supply of the distribution licensee :
Provided also that such surcharge and cross subsidies shall be
progressively reduced and eliminated in the manner as may be
specified by the State Commission:
Provided also that such surcharge shall not be leviable in case
open access is provided to a person who has established a captive
generating plant for carrying the electricity to the destination of
his own use.”
(3) Where any person, whose premises are situated within the area
of
supply of a distribution licensee, (not being a local authority
engaged in the business of distribution of electricity before the
appointed date) requires a supply of electricity from a generating
company or any licensee other than such distribution licensee,
such person may, by notice, require the distribution licensee for
wheeling such electricity in accordance with regulations made by
the State Commission and the duties of the distribution licensee
Page 24
24
with respect to such supply shall be of a common carrier providing
non-discriminatory open access .
(4) Where the State Commission permits a consumer or class of
consumers to receive supply of electricity from a person other than
the distribution licensee of his area of supply, such consumer shall
be liable to pay an additional surcharge on the charges of
wheeling, as may be specified by the State Commission, to meet the
fixed cost of such distribution licensee arising out of his obligation
to supply.”
Sub-Section (1) of Section 42 of the Electricity Act, 2003 cast duty
upon the distribution licensee to develop and maintain an efficient,
co-ordinated and economic system in his area of supply and to
supply electricity in accordance with the provisions of the Act. Sub-
Section (2) of Section 42 enables the Commission to decide the
terms and conditions and the charges payable for availing open-
access. Sub-Section 3 of Section 42 of the Act states that for the
consumers who obtain power supply from sources other than the
Distribution Licensee in whose area such consumer is situated, the
duty of the distribution licensee is of common-carrier for allowing
non-discriminatory open access to such consumer. Sub-Section
(4) of the Section 42 of the Electricity Act states that whenever the
Commission permits a consumer or class of consumers to receive a
supply of electricity other than the distribution licensee of his area
of supply such consumer shall require to pay an additional
surcharge on charge of wheeling as specified by the Commission to
meet fixed cost of the distribution licensee arising out of its
obligation to supply. Thus, aforesaid section recognizes that the
Page 25
25
distribution licensee is entitled to receive the Additional Surcharge
on the charges of Wheeling as may be specified by the Commission.
Hence, the aforesaid provision recognize that Additional
Surcharge claim by the petitioner is legal and in accordance with
the provision of Electricity Act, 2003.
9.3. It is also necessary to refer regulation 25 of the GERC (Terms and
Conditions of Intra-State Open Access) Regulations, 2011 notified
by the Commission which reads as under:
“25. Additional Surcharge
(1) An open access customer, receiving supply of electricity from a
person other than the distribution licensee of his area of supply,
shall pay to the distribution licensee an additional surcharge on
the charges of wheeling, in addition to wheeling charges and
cross-subsidy surcharge, to meet out the fixed cost of such
distribution licensee arising out of his obligation to supply as
provided under sub-section (4) of section 42 of the Act.
(2) This additional surcharge shall become applicable only if the
obligation of the licensee in terms of power purchase commitments
has been and continues to be stranded or there is an unavoidable
obligation and incidence to bear fixed costs consequent to such a
contract. However, the fixed costs related to network assets would
be recovered through wheeling charges.
Page 26
26
(3) The distribution licensee shall submit to the Commission on six
monthly basis, a detailed calculation statement of fixed cost which
the licensee is incurring towards his obligation to supply.
The Commission shall scrutinize the statement of calculation of
fixed cost submitted by the distribution licensee and obtain
objections, if any, and determine the amount of additional
surcharge:
Provided that any additional surcharge so determined by the
Commission shall be applicable only to the new open access
customers.
(4) Additional surcharge determined on Per Unit basis shall be
payable, on monthly basis, by the open access customers based on
the actual energy drawn during the month through open access:
Provided that such additional surcharges shall not be levied in
case distribution access is provided to a person who has
established a captive generation plant for carrying the electricity
to the destination of his own use.”
Regulation 25 (1) of the above Regulations recognizes that the
distribution licensee is entitled to receive Additional Surcharge on
charges of wheeling in addition to wheeling charges. Regulation
25 (2) of the said regulation state the conditions in which the
Additional Surcharge shall become applicable. It states that
Additional Surcharge shall become applicable only if the
obligation of licensees in terms of Power Purchase Agreement
Page 27
27
continues to be stranded or there is unavoidable obligation to bear
the fixed cost consequent to contract. The aforesaid Regulation
provides the process of determination of Additional Surcharge by
the Commission. Thus, the GERC (Terms and Condition of Intra-
State Open Access) Regulations 2011 notified by the Commission,
recognizes the applicability of Additional Surcharge and provides
for determination of such surcharge by the Commission.
9.4. Further, clause 5.8.3 of the National Electricity Policy notified by
the Ministry of Power, Govt. of India, reads as under:
“5.8.3 Under sub-section (2) of Section 42 of the Act, a surcharge is
to be levied by the respective State Commissions on consumers
switching to alternate supplies under open access. This is to
compensate the host distribution licensee serving such consumers
who are permitted open access under section 42(2), for loss of the
cross-subsidy element built into the tariff of such consumers. An
additional surcharge may also be levied under sub-section (4) of
Section 42 for meeting the fixed cost of the distribution licensee
arising out of his obligation to supply in cases where consumers
are allowed open access. The amount of surcharge and additional
surcharge levied from consumers who are permitted open access
should not become so onerous that it eliminates competition that
is intended to be fostered in generation and supply of power
directly to consumers through the provision of Open Access under
Section 42(2) of the Act. Further it is essential that the Surcharge
be reduced progressively in step with the reduction of cross-
subsidies as foreseen in Section 42(2) of the Electricity Act 2003.”
Page 28
28
The aforesaid policy also recognizes leviability of the Additional
Surcharge on the Consumers who are permitted open access.
9.5. Learned Advocate Shri R. K Jain, who appeared on behalf of 36
objectors, fairly admitted that Additional Surcharge is leviable as
per the provisions of the Electricity Act, 2003, National Electricity
Policy and GERC (Terms and Conditions of Intra-State Open
Access) Regulations, 2011 framed under it by the Commission.
Considering all the above provisions, we decide that the claim of
the petitioner for Additional Surcharge is legal and valid.
…”
7. As the issue No. 1 was decided by the Commission in its daily order
dated 4.10.2013, the Commission held the hearing for issue No. 2 as
stated in para 5 above. The issue No. 2 is pertaining to what are the
data/documents required for determination of the Additional Surcharge and
whether the petitioner has submitted all the relevant data/documents or not.
7.1. The Commission heard the parties on above issue on 16.11.2013 and
21.12.2013. On 21.12.2013, some of the objectors contended that they
have filed review petitions against daily order dated 4.10.2013, which
need to be heard and decided first. The Commission observed that the
review petitions filed by some of the respondents are kept for hearing
on separate day hence the same will be heard by the Commission on the
date of hearing. These review petitions No. 1381, 1382, 1383, 1384, and
1385 of 2013 were heard by the Commission on 8.01.2014 and
dismissed vide order dated 5.03.2014.
Page 29
29
7.2. M/s. Essar Steel India Limited, respondent No 54, herein, in response to
the public notice, had filed their submissions/objections against the levy
of Additional Surcharge claimed by the petitioners. Thereafter, M/s.
Essar Steel India Limited filed Miscellaneous Application No. 1 of 2013
in Petition No. 1302 of 2013, contending that the such Additional
Surcharge shall not be applicable to them as they have been granted the
status of a Regional Entity and its control centre has been shifted to
WRLDC, Mumbai vide order dated 8.6.2013 in Case No. 245/MP/2012
passed by the Central Electricity Regulatory Commission. During the
hearing on 21.12.2013, M/s. Essar Steel India Limited submitted that
they want to withdraw its submission in the present petition and also
the Misc. Application No.1 of 2013. They further submitted that they
have filed a separate petition No. 1362 of 2013 regarding applicability of
additional surcharge in their case. We, therefore, allow them to
withdraw their submission in the present case and also the Misc.
Application No. 1 of 2013.
7.3. On 21.12.2013, the Commission proceeded with hearing the parties on
issue No. 2 listed above along with methodology for determination of
the Additional Surcharge.
8. Submissions were made by various stakeholders including Reliance
Industries Limited, AIA Engineering Limited, Gujarat Chambers of
Commerce and Industry, Arvind Limited, Shri R K Jain’s (on behalf of 36
Objectors), Federation of Gujarat Industries and Others. Issues raised by
them , in brief, are as under :
I. The GUVNL has added contacted capacity in excess of its
requirement and hence burdening the consumers with large
Page 30
30
stranded capacity and additional fixed costs. Moreover, the
Commission had, in ARR for FY 2013-14, approved 9484 MUs as
the units to be traded by GUVNL. Against this, the actual traded
units have been only 2494 MUs, which has also resulted in
stranded capacity.
II. The petitioner has not furnished data regarding backing down due
to transmission constraints as well as generation backing down
due to orders of WRLDC. Hence, based on the above it is amply
clear that GUVNL has added disproportionate capacity, which is
more than the requirement and hence burdening the consumers
with large stranded capacity and additional fixed cost.
III. The Open Access consumption i.e. 3247 MUs, against the available
generation of 54800 MUs is only 6%. Against it the stranded
capacity of generation is 20642 MUs which is 37 % of the available
generation of 54800 MUs for FY 2013-14 (for six months). This
establishes that the capacity would have remained stranded even
if there were no open access at all.
IV. It is also observed that deficit in traded units i.e. 2494 MUs by
GUVNL compared to approved units by GERC is of 4742 MUs
during six months of FY 2013-14. This deficit in traded units is one
of the reasons for stranded generation capacity. Hence, these units
also need to be considered while computing the fixed cost per
unit.
V. There needs to be conclusive evidence that such generating
capacities has been and will continue to be stranded solely due to
such open access consumers.
VI. Under such circumstances, when open access consumers have to
pay transmission charges and wheeling charges as approved by
Page 31
31
the Commission, including Fixed Cost of Transmission and
Distribution for computing Additional Surcharge is not justified at
all. Open Access consumers are also compensating for
transmission and wheeling losses as approved by the Commission.
VII. As the open access consumers are compensating for losses
separately, per unit additional surcharge may be computed
considering the fixed cost per unit of power purchase payable to
Generating Company and not the Fixed Cost per unit of Energy
Supplied by Distribution Company.
VIII. The open access consumers are paying for transmission and
distribution assets fixed cost by way of Transmission charges and
wheeling charges and the transmission and distribution losses are
also applicable to them. In addition the Cross Subsidy Surcharge is
being paid by the Open access consumers to take care of cross
subsidy burden. The demand charges being paid by the open
access customers are being used to off-set the fixed charges
towards power purchase.
IX. The petitioner has submitted that the fixed costs could have been
reduced had the open access consumers availed the power from
discom which they otherwise purchased under open access.
Therefore, there is need to define the process of computation of
Additional Surcharge.
X. The open access consumers need to be categorized as the Open
Access consumers with CPP and the Open Access consumers
without CPP. Open Access consumers with CPPs normally
generate power for self consumption without drawing power from
discom. Due to economic reasons CPP generation is backed down
and power is availed through open access. CPP user is already
Page 32
32
burdened with the fixed cost of his own stranded CPP generation
capacity. Hence, further burdening the OA consumers with CPP by
levying Additional Surcharge is not justifiable.
XI. The RIL has also raised the issues pertaining to various situations
such as (I) A consumer was using own generation for
consumption and discom had not planned the capacity for the
consumer. If such consumer opts for OA from other supplier, will
it be considered new Consumer? (ii) The consumer was availing
Open Access before Additional Surcharge was made applicable,
will it be considered a New Open Access consumer, if he filed for
Open Access again after Additional Surcharge is levied? (iii) A new
industry is being planned and it ties power under Open Access
from the start, will it cause stranded capacity of discom and
covered under additional surcharge?
XII. Thus the definition of New open access consumer needs to be
clarified by the Commission and its applicability.
XIII. In open access, all commercial settlements are done in 15 minutes
time blocks. All four discoms are separate legal entities.
Application of scheduling/UI charges etc. is company wise and not
for the entire GUVNL. It may happen that one discom is
overdrawing in particular time block and at the same time another
one is not. As a whole there may or may not be over drawal in
particular time block. However, UI account will be settled discom
wise. As such, to analyze the status of stranded power it is
necessary that the petitioner submits data each discom wise and
that too in 15 minute time block only. Then only real analysis can
be done. Present data does not serve any purpose in open access
case.
Page 33
33
XIV. From Annexure-1 of data provided by the petitioner, no one can
ascertain the amount of MUs backed down conclusively due to
power purchase through open access. Similarly, data of demand
charges given in Annexure 6 is not reliable. Fluctuation shown
there-in in Demand Charges recovery is never possible.
XV. Demand Charges recovery data is required in two parts- One for
OA with Contract Demand and second for OA beyond or without
Contract Demand. It is pertinent to mention that consumer with
OA within Contract Demand is paying some amount against
Demand Charges, whereas another is not paying Demand Charges
at all and as such, additional surcharge, if at all applicable, should
be derived separately for both categories.
XVI. Insufficiency of data is therefore fatal to the present petition. The
objector relied upon the order dated 22.05.2011 of Punjab State
Electricity Regulatory Commission in petition No. 55 of 2011 and
submitted that the petitioner should submit the data regarding
backing down of generation capacity due to various reasons. The
total amount of Stranded Power Procurement cost is required to
be worked out on daily basis to be apportioned amongst the open
access customers importing power during the period when
additional surcharge is leviable.
XVII. The consumer availing OA within Contract Demand is paying
some amount against Demand Charges whereas consumer
availing open access beyond Contract Demand or without Contract
Demand is not paying anything against Contract Demand. As such
there should be separate additional surcharge;
(i) For power purchased through open access within Contract
Demand and
Page 34
34
(ii) For power purchased through open access beyond contract
demand/without contract demand.
XVIII. GUVNL while proposing formula for determination of additional
surcharge, has considered fixed cost of (i) power purchase, (ii)
transmission cost and (iii) distribution cost excluding power
purchase.
XIX. (A). As per Section 61 of the Electricity Act, 2003, while
determining tariff the Commission is guided by National Tariff
Policy (NTP). Moreover, while determining the Additional
Surcharge it is necessary to refer Section 61 of the Electricity Act,
2003, Clause 8.5.4 of Tariff Policy and Regulation 25 of the GERC
(Terms and Conditions of Intra-State Open Access) Regulations,
2011. From the above it is clear that
a. Fixed cost related to stranded power purchase commitment
only is to be considered to derive additional surcharge,
b. The fixed cost related to network assets would be recovered
through wheeling charges and
c. The distribution licensee shall submit to the Commission on six
monthly basis, a detailed calculation statement of fixed cost,
d. Additional surcharge so derived is applicable only to the new
open access customers.
The fixed cost of power purchase commitments only can be
considered as stranded power purchase cost and other fixed cost
like transmission cost/other distribution cost etc cannot be
considered for levy of additional surcharge.
To conclusively derive stranded power purchase cost, analysis of
each time block of 15 minute is must to ascertain that there is no
Page 35
35
over drawl/no load shedding/ power surrendered is not more
than power purchased by open access customers through Open
Access (except CPP wheeling/from renewable) in each 15 minute
time block considered for derivation of stranded power purchase
cost. Fixed cost of stranded power so derived to be considered as
base.
If the petitioner is not in a position to submit the required data,
overall fixed cost of completed power purchase of GUVNL may be
considered as the basis.
(B). From above base value of fixed power purchase cost, the
following items/values need to be subtracted
1. Per unit demand charges recovered from open access
consumers (to be considered zero for quantum of open access
beyond Contract demand or without Contract demand)
2. Cross subsidy Surcharge.
3. To meet consumers’ demand, some reserve (spinning, non-
spinning etc.) is required in power purchase, therefore some
percentage of fixed cost of overall power purchase is also to be
reduced.
4. Gain due to
a. Inadvertent flow,
b. Wheeling charges recovered,
c. Difference of amount recovered from sale of power and
variable cost of the power
d. Gain due to avoided power purchase cost in 11 KV. Actual
line losses of HT Industrial/express feeders are @ 2.5 %
whereas applicable losses are 10%. Difference of this one
needed to be deducted.
Page 36
36
e. Any other deduction as deemed fit to the Commission.
The Amount derived above should be transformed to per
unit cost for Open Access consumption and then to be
deducted from per unit cost of stranded power purchased.
Thus, Additional Surcharge should be = XIX (A)-XIX (B)
(Here, A is Fixed Cost of Power Purchase derived as per
narration in XI (A) above and B is per unit amount derived
as per XIX (B) above.)
XX. While first provision to Section 42 (2) speaks of payment of a
surcharge in addition to the charges for wheeling as determined
by the State Commission, Section 42 (4) talks of paying an
additional surcharge on the charges of wheeling, as may be
specified by the State Commission. Therefore, it is very clear
under the Act that while ‘Open Access Surcharge’ is in addition to
the ‘Wheeling Charges’, the Additional Surcharge is a surcharge on
the Charges of wheeling or in other language Additional surcharge
will be worked out on the Charges of wheeling and that too if it is
established beyond doubt that there was stranding of the PPAs
and the quantum of power wheeled was effected thereof.
Moreover, the extent to which such stranding of the PPAs was on
account of the open access consumers.
XXI. While the Surcharge used in Section 42 (2) of the Act is nothing
else than the Cross subsidy Surcharge computed by the
Commission while considering the Annual Revenue Requirement
of the Distribution Licensee, it should not be mixed/confused with
the Additional Surcharge. Hon’ble APTEL, in its recent judgment
passed in Appeal No. 231 of 2012 filed by M/s. Jindal Stainless
Page 37
37
Limited, hisar Vs. Dakshin Haryana Bijli Vitran Nigam Limited
dated 14.11.2013, had rejected the plea of the respondent that the
term surcharge as mentioned in the Regulation 3 of the Supply
Code was not the Cross Subsidy Surcharge. The term surcharge as
appearing in Regulations 3 of the Haryana Supply Code is the
same as appearing in Regulation 2 (19) of the Supply Code.
XXII. The Commission determines the Wheeling Charges and Cross
Subsidy Surcharge as a part of the Tariff Order for each power
utilities on annual basis. The Commission determines the
Wheeling Charges by dividing the Distribution Cost of four
Discoms with the energy input at 11 kV. The impact of stranding
of the PPAs is only on the quantum of the ‘Energy Input’ at 11 kV
and would get reduced (by a small percentage) which will affect
the value of ‘Wheeling Charges’ in the same ratio. In this
computation, the cost of power due to stranding of power
procurement cost of generating stations for energy purchase does
not find any place. It is only the reduction in net quantum of
available energy which is, in turn, affects the ‘Wheeling Charges’.
XXIII. The impact of stranded Power Procurement Cost, if any, has to be
accounted for towards the ‘Fuel Supply Adjustment’ and not in the
‘Wheeling Charges’. Therefore, the Additional Surcharge, which is
on the Charges of Wheeling, is not affected by the changes in cost
of power, which may be due to stranding of power procurement
cost.
XXIV. Moreover, a Surcharge on any normal charges cannot be greater
than the principle charges and it could be a small fraction of
percentage of the principle charges only. Hence, the Additional
Surcharge even if levied by the Commission could be a small
Page 38
38
percentage of the approved wheeling charges only rather than the
computation submitted by the petitioners.
XXV. Fixed Cost obligation of following generators should be excluded:
a. The machine/units which have completed their
standard/useful life of 25 years and above whose full fixed
costs have been recovered.
b. For IPPs machines/units, particularly gas/liquid fuel based
plants where initial period of PPA viz. 15 years is already over,
c. The generation capacity considered for use during
annual/capital overhauling/outages as also the spinning
reserves since it is for the benefit of all consumers and cannot
be considered as stranded capacity due to open access
consumers.
XXVI. Renewable power wheeled to consumers using open access is well
thought and deliberated process duly provided under the
Electricity Act, 2003 as well as the Regulations framed by the
Commission to provide incentives to such generation and
therefore such consumers should not be punished/burdened with
additional surcharge.
XXVII. Section 43 (1) of the Electricity Act, 2003 mandates that supply
should be provided within one month from application. The
petitioners should provide figures of pending application for new
connections/extension in load which were more than one month
old on the day of the petition, since had these application been
cleared, the total stranded capacity figure might be substantially
lower.
Page 39
39
9. In response to the objections raised by the objectors/respondents on
issue No. 2 regarding adequacy of the data and the
methodology/formula for determination of Additional Surcharge,
Learned Advocate Shri M. G. Ramachandran, on behalf of the petitioners,
submitted that the methodology for calculation/determination of
additional surcharge suggested by the petitioner is valid and legal as per
the provisions of the Electricity Act, 2003 read with Regulations framed
under it by the Commission. The essence of Section 42 (4) of the
Electricity Act, 2003 is to compensate the distribution licensee to meet
the fixed cost of the distribution licensees arising out of its obligation to
supply. The stranded power purchase cost of the distribution licensees
is to be determined as per the obligation of the licensees under sections
42 and 43 of the Electricity Act, 2003 to contract such quantum of
power purchase as would be required to meet not only the quantum of
power purchase for which agreements have already been entered into
with the consumers but also any increase the contract demand at any
point of time as well as the obligation to provide the electricity
connection that may be required by any person in the State. It is not
correct on the part of the objector to say that the distribution licensee
can contract only such quantum of power as is necessary for meeting
the demand of the existing consumer up to the existing contract demand
or demand under the existing agreement with the consumers.
9.1. In addition to the above, the licensee is required to arrange power
purchase in manner that the quantum of power is sufficient to (i) meet
the peak demand in a day, (ii) meet the peak demand in any particular
season i.e. taking into account the seasonal variation; and (iii) to meet
the increasing demand of new consumers.
Page 40
40
9.2. Thus the total quantum of power purchase duly approved by the
Commission for procurement by the distribution licensee, particularly
on long-term or medium-term basis ought to be considered. The Long-
term power purchase agreement involve payment of capacity charges,
even if, the power is not scheduled on account of any reason including
reduction in the load during non-peak hours, seasonal variations.
9.3. The next issue to be considered is, the quantum of stranded power. This
would depend upon the capacity charges paid to the generator for non
utilization of power. Though, under the merit order the capacity
utilization is generally on the basis of the lowest variable cost, the
capacity charges has to be paid for the total capacity declared as
available. However, the methodology of considering the stranded
capacity based on merit order principle i.e. ascertaining particular
generating stations remained stranded to the extent of open access
quantum (lowest variable cost) is not uniform and absolute. There are
occasion, where the thermal power station is required to operate on a
technical minimum, transmission constraints etc and therefore there is
limitation to operate the power system in strict adherence to the merit
order. Accordingly, a particular generating station may be operated fully
or at technical minimum level though not falling under the merit order.
9.4. The fixed cost of the entire capacity tied up to meet the demand of the
consumers need to be shared by all the consumers on equitable manner
instead of identifying fixed cost of particular generating station to the
extent of open access quantum on the basis of any assumption. The
Page 41
41
concept of spinning reserve etc should equally apply to Open Access
customers also for the reason mentioned above. All of these are
considered by the Commission while approving the quantum of power
purchase and the petitioners are referring to the said quantum while
determining the cost of stranded power.
9.5. The payment of Cross Subsidy Surcharge (CSS) has nothing to do with
the determination of Additional Surcharge. The CSS is related to tariff
design and not the quantum of power purchase and more particularly
not to the stranded power purchase cost. The wheeling charges are not
counted at all while determining Additional Surcharge under provision
of Section 42 (4) of the Act.
9.6. The loss level adjustment for the power purchase quantum is as per the
Commission’s ruling permitted under the tariff orders. Hence, the
formula suggested by the objectors is not inconsistent with the concept
of Additional Surcharge.
The petitioner has also referred and relied upon the order dated
23.12.2013 passed by the Delhi Electricity Regulatory Commission
determining the Additional Surcharge.
10. We have carefully considered the submissions made by the parties on
issue No.2 regarding data required for determination of the Additional
Surcharge and methodology for determination for determination of the
Additional Surcharge.
Page 42
42
10.1. The respondents contended that the petitioner has not provided the
necessary data/documents in support of the calculation of Additional
Surcharge demanded by the respondents. It is further submitted that
the objector Reliance Industries Limited (RIL) contended that it has
filed an application on 12.07.2013 demanding certain documents from
the petitioner. Thereafter, it has also filed an application seeking
direction from the Commission to direct the respondent to provide the
documents. The objector has also contended that the documents sought
by them are not provided by the petitioner. In contrast to above, the
petitioner submitted that he had provided all relevant
documents/evidences to respondents demanded by them like the
details of various PPAs signed by the petitioner with NTPC, IPPs and
State Generating Companies etc. as per the directives of the
Commission. With regard to the issue for the documents demanded by
the objectors is concerned, we have already dealt with the issue in para
9.6 to 9.17 and para 10 of the order dated 4.10.2013. Therefore, the
contention of the objectors that the documents are not provided by the
petitioner is not valid and acceptable and the same is rejected.
10.2. The respondents also submitted that as directed by the Commission, the
petitioner should have suggested the methodology/formula for
calculation of additional surcharge, so that the respondents could have
responded on it.
10.3. The petitioner submitted that it has proposed the
methodology/calculation to determine the Additional Surcharge in the
petition which is required to be levied on Open Access consumers as
Page 43
43
Stranded Power Purchase cost of distribution licensees. The petitioner
has also specified how to evaluate stranded power purchase cost of
distribution licensee in its petition.
10.4. We note that the petitioner has in the present petition prayed for
determination of Additional Surcharge. The petitioner has also
submitted the proposed methodology regarding determination of the
Additional Surcharge in the petition. The petitioner has also provided
the data of power procurement by the distribution licensee from
various sources which includes NTPC, State Generating Company, UMPP
projects, power procurement through Competitive Bidding Process ,
IPPs, etc. The petitioner has also provided the details of transmission
cost and distribution cost incurred by the distribution licensee. The
Commission had directed the petitioner in its order dated 4.10.2013 to
provide the methodology and formula if any to determine Additional
Surcharge by the Commission. However, the petitioner reiterated the
facts stated in the petition and submitted that the methodology
proposed in the petition may be adopted.
10.5. As the proposed methodology/ calculation/formula for determination
of Additional Surcharge is optional to the petitioner and validity of the
same be decided by the Commission and as the petitioner desire to
continue the proposed formula on which the objector/stakeholder have
given their objections/comments, we are of view that when the
petitioner himself desires to continue proposed methodology/
calculation for determination of Additional Surcharge, we decide that
there is no further need to direct to the petitioner in this matter and the
Page 44
44
Commission shall decide the appropriate formula for determination of
the Additional Surcharge.
10.6. The respondents have also raised the issue and contended that the
Additional Surcharge shall be leviable only if the power purchase
commitment of Discoms continue to be stranded or there is an
unavoidable incidence to bear fixed cost consequent to such a contract.
It was also submitted that the petitioners have contracted capacity in
excess of the contract demand of the consumers and the capacity would
have remained stranded even if there would have no open access at all.
Moreover, there is deficit in traded unit as compared to that approved
by Commission. This deficit in traded units is one of the reasons for
stranded generation capacity.
10.7. There is a need of conclusive evidence that the generation capacity has
been and will continue to be stranded solely due to Open Access
consumers. The claim of the GUVNL that the fixed cost due to stranded
capacity of generation is on account of Open Access consumers is
erroneous.
10.8. The contention of the respondents about the stranded capacity is not
acceptable on following reasons:
1. The stranded power purchase cost of discom are required to
be decided on the basis of the obligation of licensee under
section 42 read with 43 of the Electricity Act, 2003.
2. The distribution licensee is obligated to meet the demand of
its consumers upto the total contracted demand of all
consumers. Moreover, the distribution licensee is duty bound
Page 45
45
to provide connections to any new applicant within stipulated
period. To meet this obligation, the distribution has to source
adequate capacity of generation to meet the demand of its
consumers at any time through Power Purchase Agreement.
3. The distribution licensee is therefore duty bound to execute
the contract for purchase of power in a such quantum that
they are able to supply to the consumers under various
conditions, including outages of the generating units and
transmission constrains.
4. Moreover, while procuring the power it is required to ensure
that the power procurement quantum is sufficient to meet
peak demand in a particular season considering seasonal load
variation and also increase in demand of new consumers.
Thus ,the quantum of procurement of power varies based on
the various factors., which is decided by the Commission from
time to time.
10.9. The contention of the Respondents that the distribution licensee
has not procured the power in planned manner is incorrect
because discom cannot plan procurement of the power on the
basis that the certain demand has been reduced on account of
consumers opting for open access. The discom shall require to
supply electricity at all times to all the persons who have load
requirement in the State. The Discoms cannot ignore the contract
demand of the existing consumers and anticipated increase in
demand of consumers with consideration of Load forecast by it.
Moreover, the quantum of long-term power procurement is
decided by the Commission on the basis of projected demand and
Page 46
46
of the basis of accepted norms of availability. As such, the licensees
enter into any PPA, only after approval of quantum by the
Commission. The Commission while approving the quantum of
power verifies the load demand stated in the EPS published by the
CEA and also the past data for demand growth observed in the
licensee area and also considers the load forecast anticipated by
the licensees with consideration of economical aspects of the
State/Nation. Therefore, the distribution licensees are procuring
the power on Long-Term/Medium-Term basis only with prior
approval of the Commission while in case of an emergency they
opt for procurement of power under Short Term Open Access,
without approval of the Commission to fulfill its obligation of USO.
10.10. In case of power procurement by the discoms on the basis of long-
term power purchase agreement, the licensees are required to pay
the capacity charges even if power is not scheduled on account of
any reason including reduction in load during non-peak hours,
peak hours, seasonal variance in demand due to various reasons
such as there is rainfall or if the summer is on peak or in case of
delay in rainy season increase of Agricultural load. Therefore, it is
incorrect to say that Discoms have tied up power more than
requirement.
10.11. The distribution licensees are obligated to pay the capacity charge,
even if the full available capacity is not scheduled due to load
variation or any other reason including procurement of power by
the consumer through open access.
Page 47
47
10.12. The respondents have contended that the distribution licensees of
the State having different sources and different power
procurement costs, therefore while deciding the stranded capacity
and Additional Surcharge, the stranded capacity of power
procurement of each distribution licensee is required to be
considered by the Commission and to determine additional
surcharge separately for each distribution licensee. On this issue,
we observe that in the State of Gujarat, the GUVNL has been
authorized by the Government to purchase bulk power on behalf
of all the four distribution licensees. This enables a co-ordinated
power planning and results in economy in power purchase due to
different load patterns of different Discoms. Hence, the quantum of
stranded capacity and determination of additional surcharge has
also to be the common basis.
10.13. The capacity tied up with the generating stations is to meet the
demand of consumers of the State and needs to be paid fixed cost
of entire capacity by the discoms. Therefore, the fixed cost charges
need to be shared by all the consumers on equitable manner
instead of identifying fixed cost of particular generating stations to
the extent of open access quantum on the basis of any assumption.
10.14. The distribution licensee are required to keep spinning reserve to
meet the demand of the consumers which include open access
consumers also so that on demand by the consumers, the
Page 48
48
distribution licensee is able to supply the power at any point of
time.
10.15. The respondents have also contended that once the Cross Subsidy
Surcharge is paid by the open access customers, levy of additional
surcharge is not valid. As far as levy of Additional Surcharge is
concerned, it is legal and valid as decided by the Commission in its
order dated 4.10.2013. We also clarify that the Cross Subsidy is a
part of tariff design and it is applicable amongst the different
categories of the consumers. Whereas the additional surcharge is
the charges which are levied on the Open access consumers due to
stranded capacity of power procurement cost of the distribution
licensee, which is required to be paid by the Discoms to the
generators.
10.16. The respondents have referred the provisions of Electricity Act,
2003 and GERC (Terms and Conditions of Intra-State Open Access)
Regulations, 2011, and submitted that the Additional Surcharge
payable is required to be determined on the charges of wheeling in
addition to wheeling charges and cross subsidy surcharge to meet
the fixed cost of distribution licensee arising out of it obligation to
supply as provided under sub-section 4 of Section 42 of the Act. It
is therefore necessary to refer the definition of Wheeling. The
“wheeling” is defined in the Electricity Act, 2003, as under:
(76) "wheeling" means the operation whereby the distribution
system and associated facilities of a transmission licensee or
distribution licensee, as the case may be, are used by another person
Page 49
49
for the conveyance of electricity on payment of charges to be
determined under section 62;
Thus, the wheeling charges are charges payable by the person for
utilization of distribution system, associated facilities of a
transmission licensee or distribution licensee for conveyance of
electricity. Thus, the wheeling charges are with regard to
utilization of the transmission and/or distribution licensees assets
by the person for utilization of the assets for conveyance of
electricity. The additional surcharge on the other hand is payable
to meet the fixed cost of distribution licensee arising out of its
obligation to supply as provided under Section 42 (4) of the
Electricity Act, 2003. The above provision provides that the
Additional Surcharge is in addition to wheeling charges. Section 42
(4) stipulates recovery of Fixed Cost by the distribution licensee
arising out of obligation to supply the electricity to the consumers.
The fixed costs incurred by the distribution licensee consist of
followings:
I. Fixed Cost payable to the generating companies for the
capacity booked by the distribution licensee to meet the
obligation to supply the electricity to the consumers,
II. Cost payable to the Transmission licensee for conveyance of
energy from the generating stations to the input point of the
distribution licensees, and
III. The cost payable for utilization of distribution licensee assets
from the input point or receipt of electricity from transmission
licensee to place of consumption of electricity at consumer
place.
Page 50
50
The wheeling charge calculated under Section 62 of the Electricity
Act, 2003 is with regard to the cost payable for utilization of
distribution licensee assets. Therefore, the Fixed Cost required to be
recovered by distribution licensees to meet its obligation to supply
the electricity is with respect to Fixed Cost payable by the
distribution licensee to generating companies for capacity booked by
it and transmission licensee cost which payable for conveyance of
energy.
10.17. In the Regulation 42 (4), the word Additional Surcharge on charges
of wheeling means that the Additional Surcharge shall be over and
above the charges of Wheeling. As such the distribution licensees are
entitled to recover the additional surcharge (in addition to the
Wheeling Charge) to meet its fixed cost commitments on capacity
that remains stranded due to some of its consumers opting to
purchase power from third party sources through open access.
10.18. Based on the above observations, we decide that the Additional
Surcharge is required to be evaluated with consideration of stranded
capacity of the generating stations for which the distribution licensee
is required to pay capacity charges and the transmission charges
payable for conveyance of energy from generating station to
distribution licensee network and fixed cost of stranded capacity of
distribution network assets.
10.19. The objectors have also contended that the Additional Surcharge
determined shall be applicable to the New Open Access customers
Page 51
51
only. Based on the above submissions, the objectors have submitted
that the Additional Surcharge be applicable to only those consumers
who apply for open access for the first time and not by those who
were already availing open access. In this connection, we observe
that the open access is granted to any consumer for a fixed period of
time. At the end of such period, the consumer has an option to apply
afresh for open access, where the duration and quantum of open
access may be different than the previous case. As such, there is no
concept of existing open access customers. Each application for open
access is dealt by the nodal agency independent of the fact that
whether the applicant was earlier availing open access or not.
As such, we decide that the word new open access customers
specified in the Regulations 25 (3) of the said Regulations relates to
all the consumers who apply for open access commencing during the
period for which the additional surcharge is determined by the
Commission.
10.20. The objectors have also objected regarding calculations of the
stranded capacity of the distribution licensee and they have also
submitted that the stranded capacity be evaluated with
consideration of following;
1. Block wise back down of generation due to open access
consumers.
2. Block wise power purchase in megawatt by open access
consumers.
Page 52
52
3. Gain due to less power purchase (higher variable cost avoided
as per merit order)
4. Fixed cost of less power purchase stated at point 3 above.
5. Wheeling charges recovered from open access consumers.
6. Per unit demand charges recovered from each open access
consumers along with its contract demand.
7. Transmission charges paid per unit by open access
consumers.
8. Per unit gain due to Open Access consumers for reason stated
as :
(i) Applicable wheeling losses for 11 kV are 10%
whereas actual loss of HT express/industrial feeder
is about 2.5%.
(ii) Per unit cross subsidy surcharge received on actual
drawn energy (for which set-off given).
(iii) Gain due to inadvertent flow.
10.21. The petitioner in contrast submitted that the stranded capacity is
required to be calculated with consideration of following aspects:
1. Power procurement of the distribution licensee
2. Backing down of the generating units due to purchase of power
by the open access customers from the market lead to lower
requirement of demand and scheduled of energy,
3. Sell of surplus energy to third party.
4. Backing down of generating stations due to force outage,
reserved shut down etc.
Page 53
53
5. There is no congestion in the transmission network due to
which backing down be carried out.
10.22. Regarding adequacy or otherwise of the data furnished by the
petitioner for determination of additional surcharge, we have taken
note of the submissions made by the parties and dealt with the
matter in subsequent paras of this order.
10.23. Some of the respondent contended that the additional surcharge is
not applicable in the cases of consumers availing open access to
wheel power from their own captive power plants and/or from the
renewable sources. Here, it may be clarified that the additional
surcharge is payable to meet the fixed charges of capacity stranded
due to the open access customers. In case, a consumer is meeting his
full demand from his captive generation, there is no question of any
stranded power purchase cost due to such consumer. As such, the
additional surcharge will not be leviable on such open access
customers who wheel power from their own captive generation
plant and/or renewable energy sources.
10.24. On the other hand, there may be cases, where the consumers are
meeting their demand partially from the distribution licensee and
partially from its own CPP or the renewable sources. In such cases, if
the consumer avails open access to purchase power from any third
party, the additional surcharge shall be levied to the extent of power
purchased from third party.
Page 54
54
10.25. Based on the submissions made by the petitioners and the objectors,
the issues that emerged for decision of the Commission are as under:
(1) Maintainability of the Petitions, legality and validity of levy of
additional surcharge.
(2) Categories of consumers on which the additional surcharge is
leviable.
(3) Data required for determination of additional surcharge.
(4) Methodology for determination of additional surcharge.
So far as the first issue is concerned, we have already dealt with it in
our daily order dated 4/10/2013, wherein we have held that
additional surcharge is leviable on the open access consumers as per
the provisions of the Electricity Act, 2003, National Electricity Policy
and GERC (Terms and Conditions of Intra-State Open Access)
Regulations 2011. Some of the objectors had filed review petitions on
this daily order. These review petitions have been disposed of by the
Commission vide its order dated 5/3/14 wherein we have decided
that these petitions were devoid on merit and the same were
dismissed. As such, this issue attained finality and the Commission has
upheld the legality and validity of levy of additional surcharge.
10.26. Regarding the second issue, some of the objectors have contended that
they are connected with EHV network of the transmission licensee
and hence not liable to pay the additional surcharge. This issue was
also dealt by the Commission in its order dated 5/3/2014 on the
Page 55
55
review petitions referred above. The decision of the Commission on
this issue recorded in the said order is reproduced below:
“8.9. The contention of the petitioners that they are connected to the 66
kV transmission line of GETCO and hence are not liable to pay the
additional surcharge is not correct. As pointed out in para 8.8 above, the
consumer who is supplied with electricity for its own use by a licensee
can be at any level of voltage which is operated either by distribution
licensee or transmission licensee. The fact that a consumer is connected
to the transmission network does not alter his relationship with the
distribution licensee as the licensee is obligated to supply his demand
and the bills for electricity consumed by such consumers are raised by
the distribution licensee and not the transmission licensee. As provided
under section 42 (4), the additional surcharge is to be levied to meet the
fixed cost of such distribution licensee arising out of its obligation to
supply. So long as the supplier-consumer relationship exists between the
licensee and the consumer, the licensee has to meet his obligation to
supply power to such consumer on demand and the section 42 (4) of the
Act provides for levy of additional surcharge to meet the fixed cost of
licensee arising out of his obligation to supply. Further, the contention of
the petitioner that he is not liable to pay additional surcharge since he is
not connected to the distribution network and not paying any wheeling
charges is not correct. The intention of section 42(4) is to levy the
additional surcharge over and above the charges of wheeling and not as
a fraction of the wheeling charges. As such the additional surcharge is to
reflect the fixed cost of the distribution licensee arising out of his
obligation to supply. Hence, the contention of the petitioner on this
ground is not acceptable and rejected.”
Page 56
56
10.27. Some of the objectors have also contended that since they are drawing
power from their captive generators and from renewable sources,
they are not liable to pay the additional surcharge. As observed in
paras 10.23 and 10.24 above, we decide that the consumers drawing
power through open access from their own captive generators and/or
from renewable generators are not liable to pay additional surcharge
for power drawn from these sources. In other words, consumers of
the distribution licensee who avail open access to procure
conventional power from a third party other than their respective
distribution licensees are liable to pay the additional surcharge.
10.28. Regarding data requirement for determination of additional
surcharge, petitioners have furnished certain data pertaining to FY
2012-13 in the petition. The objectors have contested that this data is
not sufficient to determine the additional surcharge. Moreover, the
regulations provide for determination of additional surcharge based
on the six monthly data.
Further, we observe that the additional surcharge is to be levied to
meet the fixed cost of the distribution licensee arising out of its
obligation to supply power. As such the distribution licensee has to
contract sufficient power to meet the aggregate demands of its
consumers and to provide for unforeseen outages of the generators.
However, even in normal scenario, full availability of such contracted
capacity may not be required by the licensee. As such the total
quantum of backing-down cannot be considered for determination of
additional surcharge. The relevant figure would be the capacity
Page 57
57
stranded due to the consumer who opt to purchase power from third
parties through open access instead of drawing their full requirement
form the licensee. As such, it is important to ascertain the surplus
power available with the licensee viz-a-viz power procured by the
consumers from third parties. Further, we are in the middle of second
half of FY. 2013-14, it is per pertinent to consider data for the first half
of FY 2013-14 and the additional surcharge calculated on the basis of
this data shall be leviable for the next six monthly period i.e. 1st April
2014 to 30th September 2014. For this purpose, we decided to collect
hourly data of availability, schedule and open access transactions from
the SLDC. The list of data obtained from SLDC and the petitioners for
the period from April 2013 to September 2013 is as under:
(i) Total contracted capacity in MW.
(ii) Hourly availability declared by the generator in MW.
(iii) Hourly schedules given by the petitioner in MW.
(iv) Hourly schedules of Open Access transactions by the Open
Access consumers in MW.
(v) Total fixed charges paid by the petitioner.
(vi) Total transmission charges paid by the petitioner.
(vii) Total energy scheduled by the petitioner in MUs.
(viii) Total energy consumed by the Open Access consumers from
their respective licensees in MUs.
(ix) Total energy scheduled by Open Access consumers for third
parties.
(x) Total demand charges paid by the HT/EHT consumers and total
sale of energy to the HT/EHT consumers.
Page 58
58
(xi) Total demand charges paid by the Open Access consumers
having contracted demand with the licensees.
Determination of Additional Surcharge
10.29. Now, we deal with the issue regarding determination of Additional
Surcharge. It is therefore necessary to refer the relevant provisions
provided in the National Electricity Policy, Tariff Policy and Regulations
25 of the GERC (Terms and Conditions of Intra-State Open Access)
Regulations ,2011 which reads as under:
Clause 5.8.3 of the National Electricity Policy reads as under
“5.8.3 Under sub-section (2) of Section 42 of the Act, a surcharge is to be
levied by the respective State Commissions on consumers switching to
alternate supplies under open access. This is to compensate the host
distribution licensee serving such consumers who are permitted open
access under section 42(2), for loss of the cross-subsidy element built into
the tariff of such consumers. An additional surcharge may also be
levied under sub-section (4) of Section 42 for meeting the fixed cost
of the distribution licensee arising out of his obligation to supply in
cases where consumers are allowed open access. The amount of
surcharge and additional surcharge levied from consumers who are
permitted open access should not become so onerous that it eliminates
competition that is intended to be fostered in generation and supply of
power directly to consumers through the provision of Open Access under
Section 42(2) of the Act. Further it is essential that the Surcharge be
reduced progressively in step with the reduction of cross-subsidies as
foreseen in Section 42(2) of the Electricity Act 2003.”
Page 59
59
Clause 8.5.4 of the Tariff Policy reads as under:
“8.5.4 The additional surcharge for obligation to supply as per section
42(4) of the Act should become applicable only if it is conclusively
demonstrated that the obligation of a licensee, in terms of existing power
purchase commitments, has been and continues to be stranded, or there
is an unavoidable obligation and incidence to bear fixed costs
consequent to such a contract. The fixed costs related to network assets
would be recovered through wheeling charges.”
Gujarat Electricity Regulatory Commission (Terms and Conditions of
Intra-State Open Access) Regulations, 2011 provides that-
“25 (3) The distribution licensee shall submit to the Commission on six
monthly basis, a detailed calculation statement of fixed cost which
the licensee is incurring towards his obligation to supply.
The Commission shall scrutinize the statement of calculation of fixed cost
submitted by the distribution licensee and obtain objections, if any, and
determine the amount of additional surcharge:
Provided that any additional surcharge so determined by the Commission
shall be applicable only to the new open access customers.
(4) Additional surcharge determined on Per Unit basis shall be
payable, on monthly basis, by the open access customers based on the
actual energy drawn during the month through open access:
Provided that such additional surcharges shall not be levied in case
distribution access is provided to a person who has established a captive
generation plant for carrying the electricity to the destination of his own
use.”
Page 60
60
The above provisions provide that the Additional Surcharge is leviable
under Section 42 (4) of the Electricity Act, 2003 for meeting the fixed
cost of the distribution licensee arising out of its obligation to supply to
the consumers when allowed for open access. While determining the
Additional Surcharge, it is necessary to evaluate the stranded cost of the
distribution licensee.
10.30. While deriving the stranded cost it must be kept in mind that the fixed
cost arrived at for the stranded capacity shall be purely attributable to
the Open Access Consumers and the distribution licensee, which has the
universal service obligation, is appropriately compensated for allowing
such open access. The formula for arriving at the stranded cost on
account of the Open Access Consumers as well as the compensation to
the distribution licensee for its universal service obligation is kept at
Annexure-I.
The Regulation 25 (3) of the GERC (Terms and Conditions of Intra-State
Open Access) Regulations 2011 provides that on the basis of six months
data the calculation of obligation of licensee to supply be evaluated with
consideration of stranded power procurement of the licensees. In view
of the above, the six-monthly details for the period from April 2013 to
September 2013 as submitted by the GUVNL, is analyzed and Additional
Surcharge on per unit basis is determined as given below-
(i) In order to derive the stranded capacity due to Open Access
Consumers, the Commission has considered the hourly data of
surplus capacity (available capacity – scheduled capacity) vis-à-
Page 61
61
vis scheduled capacity of OA consumers. The lower of the surplus
capacity as shown above and capacity scheduled by OA
consumers is considered as stranded capacity for the hour. The
average stranded capacity due to OA consumers for the six
months period (April 2013 to September 2013) works out as 739
MW.
(ii) Petitioner has submitted that they have paid Rs. 4,663 crore as
fixed charges in accordance with the arrangement with various
generators against the average availability of 12,477 MW capacity
for the six month period from April 2013 to September 2013.
Thus, the average fixed charges paid by the petitioner works out
as 0.37 crore per MW capacity. (i.e. 4663 Crores/12477 MW)
(iii) Accordingly the fixed charges for stranded capacity of 739 MW
works out as Rs. 276.18 crore (739 x 0.37).
In order to compensate the distribution licensee for transmission
and wheeling charges, which otherwise they have incurred, for
allowing energy drawn by open access consumers shall be
deducted from the demand charges paid by the Open Access
Consumers to the distribution licensee, which otherwise was due
to the distribution licensee.
The OA consumers have also paid the demand charges to the
Distribution Licensee as a regular consumer and also drawn
energy from the Distribution Licensee. Hence, it is required to give
adjustment of demand charges paid by the open access consumers
in the stranded costs after deducting the transmission and
Page 62
62
wheeling charges related to energy drawn by Open access
consumers from the Distribution Licensees, as mentioned above.
(iv) The Open Access consumers have paid Rs. 211.54 crores as
demand charges to the Distribution licensee and drawn 1288 MU
from the licensee as retail consumers.
(v) The actual transmission charges paid by the GUVNL for the six
month period is Rs. 1531.40 crore and scheduled energy for that
period is 34,158.21 MUs. Hence, the actual transmission cost
works out as Rs. 0.45 per kWh.
(vi) The Distribution wheeling charges as approved by the
Commission for the FY 2013-14 is Rs. 0.12 per kWh.
(vii) Thus, the total T & D cost comes to Rs. 0.57 per kWh. (Rs.
0.45/unit + Rs. 0.12/unit)
(viii) Thus, the Open Access consumers have to compensate Rs. 73.20
Crores (i.e. 1288 MUs x 0.57 Rs./Unit) to the distribution licensees
towards transmission and distribution charges.
(ix) Thus, the demand charges to be deducted from the stranded
capacity charge works out to be Rs. 138.34 Crores. (i.e. 211.54-
73.20 Crs.)
Based on the above, the Additional Surcharge is determined as under:
Page 63
63
(x) Hence, the net stranded charges of Rs. 137.85 crores, (i.e. Rs.
276.18 – 138.34 crores) is to be considered for determination of
additional surcharge.
The OA scheduled energy during the period is 3247.51 MU and hence
the additional surcharge per unit works out as Rs. 0.42 per kWh.
Hence, the Commission determined the additional surcharge at Rs. 0.42
per kWh.
Detailed computation worksheet attached as Annexure-I.
11. In view of above observations, we decide that the present petition
succeeds. The petitioner is eligible to recover the additional surcharge
as per the provisions of the Electricity Act, 2003, National Electricity
Policy, Tariff Policy and GERC (Terms and Conditions of Intra-State
Open Access) Regulations, 2011. The Additional Surcharge determined
based on the data for period April, 2013 to September, 2013 of the
petitioner works out to Rs. 0.42 per kWh. The additional surcharge of Rs
0.42 per kWh shall be applicable to the consumers of the co-petitioner,
viz. MGVCL, UGVCL, PGVCL and DGVCL, who avail power through open
access from any source other than their respective DISCOMs and for the
open access transaction commencing from 1st April, 2014 to 30th
September, 2014. The Additional Surcharge shall be levied on the
quantum of electricity scheduled by such consumers.
12. We, further, decide that the rates of additional surcharge for the
subsequent periods shall be determined by the Commission on the
similar methodology on the basis of data to be furnished by the
Page 64
64
petitioners. For this purpose, the petitioners are directed to furnish data
as listed in para 10.28 above, for each 6 monthly period of October to
March and April to September within 30 days of completion of the 6
months period. The additional surcharge shall be determined by the
Commission on the above data for the subsequent 6 months period, i.e.
the additional surcharge determined on the basis of data for April to
September of a particular year shall be applicable for April to
September period of next year and so on.
13. In view of the submissions made by M/s. Essar Steel India Limited, as
mentioned in para 7.2 above, they are allowed to withdraw their
submission in the present case.
14. We order accordingly.
15. With this order, the present petition stands disposed of.
Sd/- Sd/-
[Dr. M. K. IYER] [SHRI PRAVINBHAI PATEL]
MEMBER (Finance) Chairman
Place: Gandhinagar.
Date: 12/03/2014.
Page 65
65
Annexure I of Order dated 12.3.2014 in Petition No. 1302 of 2013:
Determination of Additional Surcharge
For the period from April '13 to September'13
Sr. No Description Value Unit
1 Contracted Capacity 18,852 MW
2 Maximum Availability 15,168 MW
3 Minimum Availability 10,339 MW
4 Average Availability 12,477 MW
5 Maximum Scheduled 10,622 MW
6 Minimum Scheduled 4,551 MW
7 Average Scheduled 7,777 MW
8 Capacity not availed (Max) 9,550 MW
9 Capacity not availed (Min) 891 MW
10 Capacity not availed (Avg.) 4,700 MW
11 OA Allowed (Max) 939 MW
12 OA Allowed (Min) 496 MW
13 OA Allowed (Avg.) 739 MW
14 Capacity stranded due to OA 739 MW
15 Total Fixed Charge (PPA) 4,663 Rs. Crore
16 Fixed charges per MW available 0.37 Rs. Crore
17 Fixed charges of stranded capacity 276.18 Rs. Crore
18 Transmission Charges paid 1,531.40 Rs. Crore
19 Energy Scheduled 34,158.21 MU
20 Transmission Charges per kWh 0.45 Rs./kWh
21 Distribution Charges (As approved in Tariff Order) 0.12 Rs./kWh
22 Total T & D Charges per kWh 0.57 Rs./kWh
23 Energy Consumed by OA Consumer from Discoms 1,288.00 MU
24 T & D charges payable to Discoms by OA consumers 73.20 Rs. Crore
25 Demand Charges Recovered by Discoms from OA 211.54 Rs. Crore
26 Demand Charges to be adjusted 138.34 Rs. Crore
27 Net stranded charges recoverable 137.85 Rs. Crore
28 OA scheduled energy 3,247.51 MU
29 Additional surcharge 0.42 Rs./kWh