PETAL-II Preliminary Eurocontrol Test of Air/ground data Link, Phase II Operational Validation & Early Implementation Rob Mead Rob Mead PETAL-II Trials Manager PETAL-II Trials Manager Eurocontrol, DIS/ATD Eurocontrol, DIS/ATD
Mar 30, 2015
PETAL-II Preliminary Eurocontrol Test of Air/ground data Link, Phase II
Operational Validation &Early Implementation
PETAL-II Preliminary Eurocontrol Test of Air/ground data Link, Phase II
Operational Validation &Early Implementation
Rob MeadRob Mead
PETAL-II Trials ManagerPETAL-II Trials Manager
Eurocontrol, DIS/ATDEurocontrol, DIS/ATD
TopicsTopics
Trials ContextTrials Context
PETAL-IIPETAL-II Current operations and statusCurrent operations and status
AAL / ARINC ATN Extension AAL / ARINC ATN Extension
Preliminary ResultsPreliminary Results
PETAL “Operations first, then technology.”
PETAL “Operations first, then technology.”
GOAL: requirements validation & captureGOAL: requirements validation & capture Are we headed in the right direction?Are we headed in the right direction?
So, we implement:So, we implement: ODIAC operational concept, services, ODIAC operational concept, services,
procedures, & abnormal modesprocedures, & abnormal modes international standards where ever possibleinternational standards where ever possible withwith airlines, industry, service providers airlines, industry, service providers withwithoutout backing a technology (triple stack) backing a technology (triple stack) withwith the ops floor and cockpit skeptics the ops floor and cockpit skeptics
PETAL-II Operational PackagePETAL-II Operational Package OperationalOperational trials, in situ, trials, in situ, with userswith users Clearly defined procedures and airspaceClearly defined procedures and airspace Pilot and controller always in commandPilot and controller always in command Voice readback before clearance executionVoice readback before clearance execution Fully silent for all other communicationsFully silent for all other communications Limited CPDLC message set (32 up, 12 down)Limited CPDLC message set (32 up, 12 down)
Routine R/T (transfer, level, route, heading, Routine R/T (transfer, level, route, heading, crossing conditions, vertical rate, speed, + few)crossing conditions, vertical rate, speed, + few)
A A littlelittle ADS and CM / AFN (log-on) ADS and CM / AFN (log-on) ATN (and FANS-1/A) compliant events.ATN (and FANS-1/A) compliant events. Multiple a/g datalink-equipped aircraftMultiple a/g datalink-equipped aircraft
PETAL-II Front-End
Processors
NEANGroundStations
Mode-S
ARINCVDL-2 stations
PETAL-II Players, End-EndPETAL-II Players, End-End
ParisMaastricht
NEAN ATN SITAFANS-1/A
SAS, Lufthansa AAL ANZ, UAL, DLH, COA, etc. Simulation
ICAO CNS/ATM Op data and behavior
Downlink Parameters
Reims FAA
PETAL-II Review (current ops)PETAL-II Review (current ops) NEAN Live Operations: Apr ‘98 NEAN Live Operations: Apr ‘98
600+ flights June - Oct '98600+ flights June - Oct '98 400+ April - June '99400+ April - June '99
FANS-1/A live operations: Feb ‘99FANS-1/A live operations: Feb ‘99 24-29 August: 23 of 36 total flights24-29 August: 23 of 36 total flights Key addition to resultsKey addition to results
Connection-orientedConnection-oriented Automated cockpitAutomated cockpit New cockpit culturesNew cockpit cultures
Over 1200 flights have used CPDLC in 9 monthsOver 1200 flights have used CPDLC in 9 months Multi-stack operations in placeMulti-stack operations in place All day, all sectors (14+)All day, all sectors (14+)
Maastricht SectorsMaastricht Sectors ABOVE HAMBURG AND SOLLING = HIGH EAST
ABOVE COASTAL = COASTAL HIGH
ABOVE DELTA = DELTA HIGH
Maastricht Controller HMIMaastricht Controller HMI
NEAN Airborne HMINEAN Airborne HMI
NEAN Communications LogNEAN Communications Log
B777 Flight DeckB777 Flight Deck
Airborne HMIAirborne HMI
NEAN CDTINEAN CDTI FANS-1FANS-1
B747-400 MCDUB747-400 MCDU B777 Flat PanelsB777 Flat Panels
FANS-A DCDU?FANS-A DCDU? ATN MCDUATN MCDU
High Level ResultsHigh Level Results Original objectives met at end ‘98Original objectives met at end ‘98 Tremendous amount of validation materialTremendous amount of validation material Total rewrite of one key service (transfer)Total rewrite of one key service (transfer) Numerous defects identified (e.g. timers)Numerous defects identified (e.g. timers) Requirements gaps identified, e.g.:Requirements gaps identified, e.g.:
log-onlog-on message pairsmessage pairs concatenated message rulesconcatenated message rules
ClearlyClearly added momentum to implementation added momentum to implementation
Ground ArchitectureGround ArchitectureController
HMIController
HMIController
HMIController
HMI
Flight Data Processing System- Flight plan / address association- ATN SARPS version 2.3 (ICAO doc 9705), CPDLC, ADS, CM- All datalink service logic (e.g. connection set-up / transfer, timers, etc.)
P2FEP
NFEP- Aircraft address/state- ASE emulation CM, CPDLC, ADS- Data conversion
FaFEP- Aircraft address/state- ASE emulation CM, CPDLC, ADS- Data conversion
ALLA- Aircraft address/state- Data conversion
ProATN - ASEs: CM, CPDLC, ADS - ATN Router
FANS-1/A Gateway
NEANServer
IDD 4.0BER
IDD 4.0PER
PETAL-IIe: AAL InitiativePETAL-IIe: AAL Initiative US and European airspaceUS and European airspace Core set of common messagesCore set of common messages Interoperable, documented functional Interoperable, documented functional
differencesdifferences Interoperable, documented procedural Interoperable, documented procedural
differencesdifferences
ATS / Airline deadlock brokenATS / Airline deadlock broken Harmonisation for airlines and ATSHarmonisation for airlines and ATS
PETAL-II Review (ATN)
Jan ‘99: PETAL-II End-End Spec’s frozenJan ‘99: PETAL-II End-End Spec’s frozen
Spring '00: First flights Spring '00: First flights cancan take place take place BAC1-11 trials ATN and Services, and satcomBAC1-11 trials ATN and Services, and satcom
May ‘01: AA, Maas, & Reims red label flightsMay ‘01: AA, Maas, & Reims red label flights 4 B767-300ER (European operations)4 B767-300ER (European operations)
Jun ‘02: First flights at Miami (FAA Build 1)Jun ‘02: First flights at Miami (FAA Build 1) Jun ‘03: US Key Site Build 1A (national 2004)Jun ‘03: US Key Site Build 1A (national 2004)
Maastricht & Reims SectorsMaastricht & Reims Sectors
UY
URFL340
FL245
XN
UNFL340
FL245
Global Timelines
1997 1998 1999199619951994 2000 2001 20042002 2003 2007 ….20062005
Base-1
PETAL
Op Concept
Op Requirements
LINK
Sim
PETAL-II extension
PETAL-II
Base-2
Sim
B-1
B-1A
B-2
FAA Implementation Program
CPC
ADS
AIDC
PIT
Preliminary ResultsPreliminary Results
Questionnaires and InterviewsControllers and Flight Crews
Problem & System Improvement ReportsControllers and Flight CrewsProject OfficeDesign Authorities
Statistics, e.g.Transmission and dialogue timesMessage useFDP system states, e.g. log-on, connect, transferall analysed for comm performance & debug
Data SourcesOperator and Designer Experience and Logs
Data SourcesOperator and Designer Experience and Logs
Integration Teams are EssentialIntegration Teams are Essential
Develop End-to-End SpecificationsDevelop End-to-End Specifications FAA Builds 1 and 1A (key site, Miami ARTCC)FAA Builds 1 and 1A (key site, Miami ARTCC) Maastricht and French UACsMaastricht and French UACs End-end procedures, automation, messagesEnd-end procedures, automation, messages interoperable use of SARPS, now to DO/EDinteroperable use of SARPS, now to DO/ED
Plan and coordinate initial fielding & certPlan and coordinate initial fielding & cert (air, ground, comm) (air, ground, comm)
Monitor and manage initial operationsMonitor and manage initial operations Formalise issues via RTCA/Eurocae, ICAOFormalise issues via RTCA/Eurocae, ICAO
Mixed EquipageMixed Equipage Simultaneous datalink aircraft / sectorSimultaneous datalink aircraft / sector
Up to 30 aircraft (all types) in sector at one timeUp to 30 aircraft (all types) in sector at one time Flight time / sector: 5 - 30 minutesFlight time / sector: 5 - 30 minutes Max number datalink aircraft (June '99): 3Max number datalink aircraft (June '99): 3 Overlap time: 1 - 16 minutesOverlap time: 1 - 16 minutes Datalink use: heavy to not at allDatalink use: heavy to not at all
Mixed equipage Mixed equipage preliminarypreliminary results results Equipage ratio: 1-3 datalink / 5-30 totalEquipage ratio: 1-3 datalink / 5-30 total Controllers unaware of NEAN or FANS-1/AControllers unaware of NEAN or FANS-1/A Not considered a serious problem Not considered a serious problem butbut Will limit benefitsWill limit benefits Minimum one flight per control session requiredMinimum one flight per control session required
Response Times and CPDLC UseResponse Times and CPDLC Use PETALPETAL-I-I dialogue & delivery times confirmed. dialogue & delivery times confirmed.
Max dialogue time, 10s = 55%Max dialogue time, 10s = 55% Observed performance acceptable = 84%Observed performance acceptable = 84% Actual averages = about 30sActual averages = about 30s
CPDLC good for strategic commCPDLC good for strategic comm CPDLC CPDLC notnot good for tactical acft separation good for tactical acft separation
regardless of transmission speedregardless of transmission speed tactical = use, not message typetactical = use, not message type
CPDLC good for climb, cruise, descendCPDLC good for climb, cruise, descend
(climb-out & approach???) (climb-out & approach???)
FANS-1/A ObservationsFANS-1/A Observations ARINC 424 vs. ground nav databasesARINC 424 vs. ground nav databases
CPDLC connection for close departuresCPDLC connection for close departures If automated event, may occur at poor timeIf automated event, may occur at poor time Aircrew HMI should consider not alerting Aircrew HMI should consider not alerting
"connect" at same level as clearance"connect" at same level as clearance Resume Own Nav without a "to"Resume Own Nav without a "to" Concatenation and Conditional Clearances Concatenation and Conditional Clearances
require additional restrictionsrequire additional restrictions
All applicable to ATNAll applicable to ATN
ATN Interoperability IssuesATN Interoperability Issues You You havehave message pairs. Standardise them! message pairs. Standardise them! Log-onLog-on
What's a "positive log-on"?What's a "positive log-on"? Mandatory (optional) log-on dataMandatory (optional) log-on data Static ground CM addresses / airborne data basesStatic ground CM addresses / airborne data bases Which aircraft address used by the ground?Which aircraft address used by the ground?
Logical Response (LACK)Logical Response (LACK) How does aircraft know whether to use them?How does aircraft know whether to use them? How do you resolve the cockpit differences?How do you resolve the cockpit differences?
Who connects CPDLC, air or ground?Who connects CPDLC, air or ground? New airspaces > different needs (e.g. timers)New airspaces > different needs (e.g. timers)
Operational ResultsReported Usefulness (controllers)
Operational ResultsReported Usefulness (controllers)
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Time Clearance
Speed Clearance
Vertical Rate Clearance
Heading Clearance
ATC Mic Check
Route Request
Route Clearance
Flight Level Request
Flight Level Clearance
Transfer of Voice
No Comment
Not Useful
Useful
Message SetsMessage Sets Cut the message set, at least for initial opsCut the message set, at least for initial ops
Eases HMI and training (300+ messages??)Eases HMI and training (300+ messages??) Too many options (e.g. meter data types)Too many options (e.g. meter data types) Some don’t fit ops (e.g. deviate N/S/E/W)Some don’t fit ops (e.g. deviate N/S/E/W) No guidance on how to handle "bad" optionsNo guidance on how to handle "bad" options
Trick is to find a common core, andTrick is to find a common core, and Define interop handling for data types involvedDefine interop handling for data types involved Design HMIs to have these "on top"Design HMIs to have these "on top" Implement those firstImplement those first International set now being standardisedInternational set now being standardised
Builds and BaselinesBuilds and Baselines
0
10
20
30
40
50
60
70
80
90
100
Build 1A PETAL-II PETAL-IIe Build 2
Uplink
Downlink
Baseline 2
0
10
20
30
40
50
60
70
80
90
100
Build 1A PETAL-II PETAL-IIe Build 2
0
10
20
30
40
50
60
70
80
90
100
Build 1A PETAL-II PETAL-IIe Build 2
PETAL-II Datalink CapabilityLive operations, all 12 sectors, all day (539 CPDLC flights, 6/98 - 9/98)
Cap
abili
ty
1997 19981996 1999
NEANOperations
ATN 1.1 compliant - FDPS - Operations
Pre-Op environment
FANS-1/AOperations
ATN 1.1 compliant - FDPS - Operations
FANS-1/A Front-End
Pre-Op environment
FANS-1/AATN
2001 . . . . . .
NEAN
ATNOperations
ATN 2.3+ compliant - FDPS - Operations
Operational upgrades
FAA interoperable
Final step to certified / op approved environment
2000
Link 2000+
What Is This All Accomplishing?What Is This All Accomplishing? Bringing requirements into touch with realityBringing requirements into touch with reality Bringing standards into contact with designersBringing standards into contact with designers Uncovering expensive interoperability issues Uncovering expensive interoperability issues
beforebefore initial operations initial operations Bridging the Transatlantic divideBridging the Transatlantic divide
for procedures and systemsfor procedures and systems for operationsfor operations
Breaking the "you go first" deadlockBreaking the "you go first" deadlock Bringing together comm providers, airlines, Bringing together comm providers, airlines,
ATS, and suppliers to build a single systemATS, and suppliers to build a single system
ConclusionConclusion We have broken the "I will if you will" We have broken the "I will if you will"
deadlockdeadlock
Monthly report or newsletter distro?Monthly report or newsletter distro?
Individual or organizational inputIndividual or organizational input?? [email protected]@eurocontrol.be www.eurocontrol.be/projects/eatchip/petal2/