Top Banner
PERT AND CPM PROJECT MANAGEMENT ARCHITECTURE SITI YAUMILIA SALSA
34

PERT AND CPM PROJECT MANAGEMENT

Apr 13, 2017

Download

Engineering

salsa moyara
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PERT AND CPM PROJECT MANAGEMENT

PERT AND CPM

PROJECT MANAGEMENT

ARCHITECTURE

SITI YAUMILIA SALSA

Page 2: PERT AND CPM PROJECT MANAGEMENT

Project

Combination of interrelated activities

Executed in logical sequence

Accomplishment of a desired objective

Page 3: PERT AND CPM PROJECT MANAGEMENT

Project Management

• Management is generally perceived as concerned with planning, organizing, and control of an ongoing process or activity.

• Project Management is concerned with control of an activity for a relatively short period of time after which management effort ends.

• Primary elements of Project Management to be discussed:

Project Team

Project Planning

Project Control

Page 4: PERT AND CPM PROJECT MANAGEMENT

Network analysis is the general name given to certain specific techniques which can

be used for the planning, management and control of projects.

Methods used for network planning are:

CPM

PERT

Managing a project with network planning methods involves four steps:

1. Describing the Project.

2. Diagramming the Network.

3. Estimating time of completion.

4. Monitoring Project Progress.

Network Planning

Page 5: PERT AND CPM PROJECT MANAGEMENT

HISTORY OF PERT/CPM

Developed by the US Navy for the planning and control of the Polaris missile program

The emphasis was on completing the program in the shortest possible time.

PERTDeveloped by Du Pont to solve project scheduling problems

The emphasis was on the trade-off between the cost of the project and its overall completion time

CPM

Page 6: PERT AND CPM PROJECT MANAGEMENT

CPM - Critical Path Method

Drafting the design of Programme or Project

Evaluation of drafted Programme or Project

Review of evaluated Programme or Project

Page 7: PERT AND CPM PROJECT MANAGEMENT

PERT -Project Evaluation & Review Techniques

To analyze and represent the tasks involved in completing a given project

Accommodates the variation in event completion time

Event-oriented technique rather than start- and completion-oriented

Commonly used in conjunction with the critical path method

Page 8: PERT AND CPM PROJECT MANAGEMENT

Basic Terms In Network Analysis

Activity

Event

Constraints

Network Diagram

Critical Path

Page 9: PERT AND CPM PROJECT MANAGEMENT

Steps in PERT/CPM

4. CONTROLLING

3. ALLOCATION OF RESOURCES

2. SCHEDULING

1. PLANNING

Page 10: PERT AND CPM PROJECT MANAGEMENT

PERT/CPM

Project managers reply on PERT/CPM to help them answer questions such as:• What is the total time to complete the project?

• What are the scheduled start and finish dates for each specific activity?

• Which activities are critical and must be completed exactly as scheduled to keep the project on schedule?

• How long can noncritical activities be delayed before they cause an increase in the project completion time?

Page 11: PERT AND CPM PROJECT MANAGEMENT

Both PERT and CPM

• Graphically display the precedence relationships & sequence of

activities

• Estimate the project’s duration

• Identify critical activities that cannot be delayed without delaying the

project

• Estimate the amount of slack associated with non-critical activities

Page 12: PERT AND CPM PROJECT MANAGEMENT

Framework for PERT and CPM

• Define the Project. The Project should have only a single start activity and a single finish activity.

• Develop the relationships among the activities.

• Draw the "Network" connecting all the activities.

• Assign time and/or cost estimates to each activity

• Compute the critical path.

• Use the Network to help plan, schedule, monitor and control the project.

Page 13: PERT AND CPM PROJECT MANAGEMENT

PERT Diagrams

• Activity-on-node diagrams:• Maybe more than one single start and end node

• Nodes represent activities

• Arrows indicate precedence

• Activity-on-arrow diagrams:• One single start and one single end node

• An arrow represents a task, while a node is the completion of a task

• Arrows represent activities

• Nodes indicate beginning/end of activities

13

Page 14: PERT AND CPM PROJECT MANAGEMENT

Dummy Activities

• Sometimes it is necessary to insert dummy activities (duration zero) in order to maintain the clarity of the diagram and the precedence relationships between activities.

• In activity-on-arrow PERT diagrams, each activity must be uniquely identifiable by its start and end nodes.

• However, sometimes multiple tasks have the same predecessors and successors.

14

Page 15: PERT AND CPM PROJECT MANAGEMENT

DUMMY ACTIVITY

Dummy Activity is used in two situations:

1) When two or more activities start and end at the same nodes

1 3

2

2) When two or more activities share the same precedence activity but not all the precedence are shared.

1 53

6

7

2 4

Page 16: PERT AND CPM PROJECT MANAGEMENT

Determining the Critical Path

• Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute:• Earliest Start Time (ES) = the maximum of the earliest finish times of all activities

immediately preceding activity i. (This is 0 for an activity with no predecessors.). This is the earliest time an activity can begin without violation of immediate predecessor requirements.

• Earliest Finish Time (EF) = (Earliest Start Time) + (Time to complete activity i. This represent the earliest time at which an activity can end.

The project completion time is the maximum of the Earliest Finish Times at the Finish node.

Page 17: PERT AND CPM PROJECT MANAGEMENT

Determining the Critical Path

• Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, (i,j), compute:

• Latest Finish Time (LF) = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.). This is the latest time an activity can end without delaying the entire project.

• Latest Start Time (LS) = (Latest Finish Time) - (Time to complete activity (i,j)). This is the latest time an activity can begin without delaying the entire project.

Page 18: PERT AND CPM PROJECT MANAGEMENT

Determining the Critical Path

• Step 3: Calculate the slack time for each activity by:

Slack = (Latest Start) - (Earliest Start), or

= (Latest Finish) - (Earliest Finish).

A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times.

Page 19: PERT AND CPM PROJECT MANAGEMENT

A Simple Project

Activity ImmediatePredecessor

ExpectedTime

A - 5

B - 6

C A 4

D A, B 2

Page 20: PERT AND CPM PROJECT MANAGEMENT

Precedence Diagram

Page 21: PERT AND CPM PROJECT MANAGEMENT

ES Earliest Starting (time)

EF Earliest Finishing

LS Latest Starting

LF Latest Finishing

Slack Difference Time

Page 22: PERT AND CPM PROJECT MANAGEMENT
Page 23: PERT AND CPM PROJECT MANAGEMENT

• Activity time estimates usually can not be made with certainty.

• PERT used for probabilistic activity times.

• In PERT, three time estimates are used: most likely time (m), the optimistic

time (a) , and the pessimistic time (b).

• These provide an estimate of the mean and variance of a beta distribution:

• mean (expected time):

• variance:

6b 4m a t

2

6a - b

v

Probabilistic Activity Times

Page 24: PERT AND CPM PROJECT MANAGEMENT
Page 25: PERT AND CPM PROJECT MANAGEMENT

Difference Between PERT & CPM

Probabilistic Model

Non-repetitive Jobs like planning & scheduling of programmes

Results calculated on basis of Events

Related with activities of uncertain time

Deterministic Model

Repetitive Jobs like residential construction

Results calculated on basis of activities

Related with activities of Well Known time

PERT CPM

Page 26: PERT AND CPM PROJECT MANAGEMENT

Advantages of PERT/CPM

Reduction in cost

• Elimination of Risk in Complex activity

Flexibility

• Optimisation of Resources

Reduction of Uncertainties

Page 27: PERT AND CPM PROJECT MANAGEMENT

Disadvantages of PERT/CPM

Network charts tend to be large

Lack of a timeframe on most PERT/CPM charts makes it harder to show status

When PERT/CPM charts become unwieldy, they are no longer used to manage the project

Planning & Implementation required skillful personnel

Page 28: PERT AND CPM PROJECT MANAGEMENT

PERT TABLENO. ACTIVITY

KOEFISIEN Days LaborsToptimis

(a)Tmostlikely

(m)Tpesimis

(b)Texpected

(Te)Variance

(v)

A PREPARATION, MINING AND LAND 32 6,10,16 8,5/6,4 6 10 16 10,33333333 2,777777778

B FOUNDATION AND CONCRETE CONSTRUCTION 240 40,60,80 8,6,4 40 60 80 60 44,44444444

C COUPLE AND PLASTERING CONSTRUCTION 12 2,4,6 6,4,3 2 4 6 4 0,444444444

D FLOOR AND WALL INSTALLATION 12 1,1,4 4,4,1 4 10 12 9,333333333 1,777777778

E ROOF CONSTRUCTION 42 6,7,11 7,6,4 11 14 21 14,66666667 2,777777778

F CEILING INSTALLATION 4 1,1,4 4,4,1 1 1 4 1,5 0,25

G INSTALLATION KUSEN, DOOR AND WINDOW 15 2,3,5 8,5,3 2 3 5 3,166666667 0,25

H EQUIPMENT INSTALLATION DOOR AND WINDOW 6 1,2,3 6,3,2 1 2 3 2 0,111111111

I INSTALLATION OF SANITARY 24 3,4,6 8,6,4 3 4 6 4,166666667 0,25

J1 SEPTIC TANK 10 4,5,10 3,2,1 4 5 10 5,666666667 1

J2 PLUMBING 7 3,4,7 3,2,1 3 4 7 4,333333333 0,444444444

K1 PLN INSTALLATION 1 1,1,2 2,1,1 1 1 2 1,166666667 0,027777778

K2 CABLE 3 1,2,3 3,2,1 1 2 3 2 0,111111111

K3 FINISHING 1 1.2.3 2,1,1 1 1 2 1,166666667 0,027777778

L PAINTING 7 1,1,3 1,1,3 3 4 7 4,333333333 0,444444444

M FINISHING 8 3,4,8 3,2,1 3 4 8 4,5 0,694444444

Page 29: PERT AND CPM PROJECT MANAGEMENT

PERT DIAGRAM

A B C

K1

E F

J2J1

G

I

D

L H

K2

I K3 M

NO. ACTIVITY Texpected (Te)

A PREPARATION, MINING AND LAND 10,33

B FOUNDATION AND CONCRETE CONSTRUCTION 60

C COUPLE AND PLASTERING CONSTRUCTION 4

D FLOOR AND WALL INSTALLATION 9,33

E ROOF CONSTRUCTION 14,67

F CEILING INSTALLATION 1,5

G INSTALLATION KUSEN, DOOR AND WINDOW 3,17

H EQUIPMENT INSTALLATION DOOR AND WINDOW 2

I INSTALLATION OF SANITARY 4,17

J1 SEPTIC TANK 5,67

J2 PLUMBING 4,34

K1 PLN INSTALLATION 1,17

K2 CABLE 2

K3 FINISHING 1,17

L PAINTING 4,34

M FINISHING 4,5

Page 30: PERT AND CPM PROJECT MANAGEMENT

0M

4,50

117,4

112,9

112,9

117,4

Page 31: PERT AND CPM PROJECT MANAGEMENT

S ^ = 54,25

S=7,365459931328117

Z=(120-115,5)/ 7,365Z= 0,61Z= 74,8 %

NO. ACTIVITYVariance (v)

CRITICAL PATH

A PREPARATION, MINING AND LAND 2,777777778 YA

B FOUNDATION AND CONCRETE CONSTRUCTION 44,44444444 YA

C COUPLE AND PLASTERING CONSTRUCTION 0,444444444 YA

D FLOOR AND WALL INSTALLATION 1,777777778 YA

E ROOF CONSTRUCTION 2,777777778 YA

F CEILING INSTALLATION 0,25 YA

G INSTALLATION KUSEN, DOOR AND WINDOW 0,25 YA

H EQUIPMENT INSTALLATION DOOR AND WINDOW 0,111111111 YA

I INSTALLATION OF SANITARY 0,25 YA

J1 SEPTIC TANK NO

J2 PLUMBING NO

K1 PLN INSTALLATION NO

K2 CABLE NO

K3 FINISHING 0,027777778 YA

L PAINTING 0,444444444 YA

M FINISHING 0,694444444 YA

S^2 54,25

Page 32: PERT AND CPM PROJECT MANAGEMENT
Page 33: PERT AND CPM PROJECT MANAGEMENT
Page 34: PERT AND CPM PROJECT MANAGEMENT

THANK YOU