Top Banner
TSP TECHNICAL TRAINING Permit To Work System Permit To Work System SOUTH PARS
25
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Permit To Work presentation - original

TSP TECHNICAL TRAINING

Permit To Work SystemPermit To Work System

SOUTH PARS

Page 2: Permit To Work presentation - original

P/TM/TRG/S/PW/0012 TSP Training

SOUTH PARS

ContentsContents

1.01.0 Course PurposeCourse Purpose

2.02.0 Permit to Work ProcedurePermit to Work Procedure

3.03.0 Permit to WorkPermit to Work

4.04.0 Types of Permit to WorkTypes of Permit to Work4.14.1 Main Hot Work (Naked Flame) PermitMain Hot Work (Naked Flame) Permit

4.24.2 Main Hot Work PermitMain Hot Work Permit

4.34.3 Main Cold Work PermitMain Cold Work Permit

5.05.0 Complementary PermitsComplementary Permits

5.15.1 Entry to vessels & confinedEntry to vessels & confined spacesspaces

5.25.2 RadiographyRadiography

5.35.3 ExcavationExcavation

5.45.4 Process/Mechanical IsolationProcess/Mechanical Isolation

5.55.5 High Voltage Electrical IsolationHigh Voltage Electrical Isolation

5.65.6 High Voltage Electrical - Sanction to TestHigh Voltage Electrical - Sanction to Test

5.75.7 Low Voltage Electrical IsolationLow Voltage Electrical Isolation

5.85.8 Limitation of AccessLimitation of Access

5.95.9 DivingDiving

Page 3: Permit To Work presentation - original

P/TM/TRG/S/PW/0013 TSP Training

SOUTH PARS

Contents Contents (Continued)(Continued)

6.06.0 Permit to Work Structure and ContentPermit to Work Structure and Content6.16.1 GeneralGeneral

6.26.2 Permit StructurePermit Structure

7.07.0 Responsible PersonsResponsible Persons7.17.1 GeneralGeneral

8.08.0 ProceduresProcedures8.18.1 Administration of PermitsAdministration of Permits

8.28.2 Procedures Applicable to All PermitsProcedures Applicable to All Permits

8.38.3 Validity of Permits to WorkValidity of Permits to Work

8.48.4 Process/Mechanical IsolationsProcess/Mechanical Isolations

8.58.5 Gas TestsGas Tests

9.09.0 PTW - Step By Step ProceduresPTW - Step By Step Procedures

10.010.0 SummarySummary

Page 4: Permit To Work presentation - original

P/TM/TRG/S/PW/0014 TSP Training

SOUTH PARS

1.01.0 Course PurposeCourse Purpose

• This training course is designed to give new employees a clear understanding of the Permit To Work system as it is applied in TSP Production Operations (refer TSP Permit to Work Procedure: TPS-P-PR-PRD-MET-001TPS-P-PR-PRD-MET-001)

• It is important to note that staff training on making out and using work permits is a continuouscontinuous exercise

• Staff need to refer to this document which clearly defines the procedure and the types of permit available.Note also that a separate Procedure (PR-PRD-MET-002) covers offshore wellhead platforms

• All personnel working on site must be familiar with the procedure so everyone is aware of the risks and can make their own contribution to overall safety

Page 5: Permit To Work presentation - original

P/TM/TRG/S/PW/0015 TSP Training

SOUTH PARS

2.02.0 Permit to Work ProcedurePermit to Work Procedure

The primary purpose of this Procedure is to ensure that written permission, in the form of an approved Permit to Work, is correctly issued to allow authorised personnel to perform clearly defined tasks

It is further to ensure that nothing is done, during the performance of these tasks, to prejudice the safety of personnel or the installation

In particular, the following points must be observed:

•Correct operation of the Permit to Work (PTW) System is Correct operation of the Permit to Work (PTW) System is achievedachieved

•All necessary personnel are aware of the safety precautions to All necessary personnel are aware of the safety precautions to be takenbe taken

•The equipment, or area affected by the work is clearly definedThe equipment, or area affected by the work is clearly defined

•All departments concerned with the equipment, or area affected All departments concerned with the equipment, or area affected by the work, are aware of its status and the progress of the workby the work, are aware of its status and the progress of the work

•The correct protective clothing and other equipment specified The correct protective clothing and other equipment specified on the PTW, on the PTW, is provided and usedis provided and used

•Relevant Line Managers and Supervisors are kept aware and Relevant Line Managers and Supervisors are kept aware and fully informed fully informed of all work in progress of all work in progress

Page 6: Permit To Work presentation - original

P/TM/TRG/S/PW/0016 TSP Training

SOUTH PARS

3.03.0 The Permit to WorkThe Permit to Work

• The Onshore Permit to Work System is based around the use of Main Permits to WorkPermits to Work that cover all classes of work, whether carried out by Company employees or Contractors

• Certain specific defined tasks also require Complementary PermitsComplementary Permits in addition to the main Permits to Work

• Furthermore, certain routine tasksroutine tasks, which do not create any potential hazard to personnel, equipment, or the site, will notnot require a Permit to Work. Such tasks are listed by the Process and Shift Superintendents/Supervisors for the areas under their control. These listed tasks must be covered by detailed Procedures to ensure safe performance and must have written approval from the Operations Assistant, Phases 2 & 3

Page 7: Permit To Work presentation - original

P/TM/TRG/S/PW/0017 TSP Training

SOUTH PARS

4.04.0 Types of Permit to WorkTypes of Permit to Work

There are three, Main Permits to Work: three, Main Permits to Work:• Main Hot Work (Naked Flame) Permit • Main Hot Work Permit• Main Cold Work Permit

4.14.1 Main Hot Work (Naked Flame) PermitMain Hot Work (Naked Flame) Permit

A main Hot Work (Naked Flame) Permit is required for any work involving equipment iving rise to a definite source of ignition, including, but not limited to, use of equipment for oxy-acetylene burning, gas welding, electric-arc welding, propane torch heating and burning, grinding or use of a hot-air gun

This permit is identical to Main Hot Work Permit but clearly stamped ‘Naked Flame’

Page 8: Permit To Work presentation - original

P/TM/TRG/S/PW/0018 TSP Training

SOUTH PARS

4.24.2 Main Hot Work PermitMain Hot Work Permit

A main Hot Work Permit is required for any work involving, or giving rise to, a potential source of ignition, including, but not limited to, grit blasting and work on non-intrinsically safe equipment. A Hot Work Permit is also required for electrical work, unless the equipment is fully isolated

The Area Authorities and safety Authorities may refuse or postpone Main Hot Work Permits, particularly the Main Hot Work (Naked Flame) Permits, if they consider that the prevailing conditions are not suitable for several simultaneous hot work activities

Page 9: Permit To Work presentation - original

P/TM/TRG/S/PW/0019 TSP Training

SOUTH PARS

4.34.3 Main Cold Work PermitMain Cold Work Permit

A main Cold Work Permit is required for all work that is not covered by the Main Hot Work Permits and Main Hot Work (Naked Flame) Permits described previously

5.05.0 Complementary PermitsComplementary Permits

In addition to the three Main Work PermitsMain Work Permits there are Nine,Nine, Complementary Permits,Complementary Permits, that may be issued together with any of the Main Permits

(These are listed on the next slide)

Page 10: Permit To Work presentation - original

P/TM/TRG/S/PW/00110 TSP Training

SOUTH PARS

Complementary PermitsComplementary Permits

• Entry to Vessels and Confined Spaces• Radiography• Excavation• Process/Mechanical Isolation• High Voltage Electrical Isolation• High Voltage - Sanction to Test• Low Voltage Electrical Isolation• Limitation of Access• Diving

These nine complementary permits will now be discussed individually

Page 11: Permit To Work presentation - original

P/TM/TRG/S/PW/00111 TSP Training

SOUTH PARS

5.15.1 Entry to Vessels or confined SpacesEntry to Vessels or confined Spaces

• This complementary Permit is required before any person is allowed to enter an enclosed space for any purpose.

• An Enclosed Space is considered to be any area, (including tanks, vessels, pipes, sumps, or pits), in which there could be an accumulation of any flammable or toxic materials and where gas, vapor, liquid or solid residues may accumulate, or in which oxygen deficiency may occur and which could prove harmful to personnel entering without a suitable respiratory protection device

Page 12: Permit To Work presentation - original

P/TM/TRG/S/PW/00112 TSP Training

SOUTH PARS

5.25.2 RadiographyRadiographyThis complimentary Permit is required for any work entailing the use of radioactive sources

5.35.3 ExcavationExcavationThis Complementary Permit is required for any excavation work in areas under TSP control

5.45.4 Process/Mechanical IsolationProcess/Mechanical IsolationThis Complementary Permit is required to withdraw equipment from service by physical isolation

5.55.5 High Voltage Electrical IsolationHigh Voltage Electrical IsolationThis Complementary Permit is required for all work on electrical systems or equipment where the voltage exceeds the following limits:

Page 13: Permit To Work presentation - original

P/TM/TRG/S/PW/00113 TSP Training

SOUTH PARS

5.55.5 High Voltage Electrical IsolationHigh Voltage Electrical IsolationThis Complementary Permit is required for all work on electrical systems or equipment where the voltage exceeds the following limits:

• 1000 volts AC or 1500 volts DC between conductors• 600 volts AC or 900 v0lts DC between conductors and earth

5.65.6 High Voltage - Sanction to TestHigh Voltage - Sanction to TestThis Complementary Permit is required to test the high voltage electrical systems or equipment defined in 5.5 above

Page 14: Permit To Work presentation - original

P/TM/TRG/S/PW/00114 TSP Training

SOUTH PARS

5.75.7 Low Voltage Electrical IsolationLow Voltage Electrical Isolation

This Complementary Permit is required for all work on electrical systems or equipment where the voltage is lower than as defined in 5.5 above

5.85.8 Limitation of AccessLimitation of Access

This Complementary Permit is requiredto work in any area close to live electrical systems or equipment. A Limitation of Access Permit is not required where the work to be performed is already covered by any of the other Main Permits to Work

5.95.9 DivingDiving

This Complementary Permit is required to work on any underwater equipment

Page 15: Permit To Work presentation - original

P/TM/TRG/S/PW/00115 TSP Training

SOUTH PARS

6.06.0 Permit to Work Structure and ContentPermit to Work Structure and Content6.16.1 GeneralGeneral

All the Permits to Work are four-part, uniquely numbered, forms with a top White Copy, Green, Pink and Blue copies. Each of the four pages has a large shadow-style numeral: 1,2,3 or 4, corresponding to the page number

Permit to Work forms all have a two-letter prefix identifier as shown in the table:

Permit Type Identifier

Main Hot Work (Naked Flame) Permit MF

Main Hot Work Permit MH

Main Cold Work Permit MC

Complimentary (Entry to Vessels & Confined Spaces) CE

Complimentary (Radiography) CR

Complimentary (Excavation) CX

Complimentary (Process/Mechanical Isolation) CP

Complimentary Permit (High Voltage Electrical Isolation) CH

Complimentary Permit (High Voltage Electrical - Sanction to Test) CS

Complimentary Permit (Low Voltage Electrical Isolation) CL

Complimentary Permit (Limitation of Access) CA

Complimentary Permit (Diving) CD

Page 16: Permit To Work presentation - original

P/TM/TRG/S/PW/00116 TSP Training

SOUTH PARS

6.2 6.2 Permit StructurePermit Structure

Although clearly there are many individual differences between the Although clearly there are many individual differences between the various Permits to Work, there is a common overall structure to enable various Permits to Work, there is a common overall structure to enable the process to move smoothly. The four basic steps, from start to finish, the process to move smoothly. The four basic steps, from start to finish, may be simplified and summarised as follows:may be simplified and summarised as follows:

INITIATION/PREPARATION OF PERMIT TO INITIATION/PREPARATION OF PERMIT TO WORKWORK

LIST OF EXTERNAL REQUIREMENTS SUCH LIST OF EXTERNAL REQUIREMENTS SUCH AS : SAFETY EQUIPMENT, STATUS OF AS : SAFETY EQUIPMENT, STATUS OF PLANT, NEED FOR COMPLEMENTSRY PLANT, NEED FOR COMPLEMENTSRY

PERMITS ETC;PERMITS ETC;

PERMIT AUTHORISATION,ISSUE & PERMIT AUTHORISATION,ISSUE & ACCEPTANCE FOR WORK TO STARTACCEPTANCE FOR WORK TO START

PERMIT CANCELLATION ON COMPLETION OF PERMIT CANCELLATION ON COMPLETION OF WORKWORK

Page 17: Permit To Work presentation - original

P/TM/TRG/S/PW/00117 TSP Training

SOUTH PARS

7.07.0 Responsible PersonsResponsible Persons

7.17.1 GeneralGeneral• All site personnel, without exception, have an individual

responsibility to ensure that the Permit to Work system operates correctly and efficiently. The named positions in column 1 of the following Table have further specific and clearly defined responsibilities

• Not all of the named positions are TSP Job Titles, but are Functional Titles for the purpose of this training course. Each of the positions and their associated responsibilities are described individually later in the course

• The table overleaf is arranged to show the correspondence between the TSP Functional Titles, the duties associated with those functions and the Functional Titles as defined in HSE standard 601

Page 18: Permit To Work presentation - original

P/TM/TRG/S/PW/00118 TSP Training

Table 2: TSP PTW Procedure/HSE STD Correspondence Table 2: TSP PTW Procedure/HSE STD Correspondence tabletable

SOUTH PARS

ProductionPTW Procedure

DefinitionDuties HSE Standard Definition

Operations AssistantPhases 2 & 3

Overall Responsibility,Appoints other PTWsignatories

Site Manager

Task SupervisorInitiates Permits to Work.Defines Scope of Work

Work AuthorityWork Operator

Area Authority

Approves work go-ahead.Defines plant status forwork. Arranges anyrequired isolations

Installation AuthorityShift Authority

Permit Controller

Checking of PTW's beforeissue. Administers PTWProcedure. Logging/Filingof cancelled Permits

Safety AuthorityDefine Safetyrequirements. Monitorsworking practices

Safety Authority

Responsible/AuthorisedElectrical Persons

Performs electricalisolations & deisolations

DisciplineAuthorities/Operators

Gas TesterPerforms all required gastesting

Gas Tester

Maintenance MethodsSection

Issues Work Orders Work Organiser

Page 19: Permit To Work presentation - original

P/TM/TRG/S/PW/00119 TSP Training

SOUTH PARS

Note: The detail responsibilities of the ‘responsible Note: The detail responsibilities of the ‘responsible persons’ are outside the scope of this course. persons’ are outside the scope of this course. Please Please refer to procedure PR-PR-MET-001refer to procedure PR-PR-MET-001

8.08.0 ProceduresProcedures

8.18.1 Administration of PermitsAdministration of Permits

The Operations Assistant Phases 2 & 3 has the ultimate and overall responsibility for the implementation of the Permit to Work Procedure and also for limiting the number of Permits that are valid at any one time

The routine administration of the Permit to Work procedure is carried out by those persons designated by the Operations Assistant. These designated persons are responsible for:

•Issue of the Permits•Management of the work progress•Revalidation or cancellation of Permits

Page 20: Permit To Work presentation - original

P/TM/TRG/S/PW/00120 TSP Training

SOUTH PARS

8.28.2 Procedures Applicable to All PermitsProcedures Applicable to All Permits– The top (White) copy of all main Permits to Work and

any associated Supplementary Permits, are retained by the person performing the work, or in charge of the group performing the work. White copies of PTW’s must be clearly displayed, and available for inspection at all times at the work sites

– It is the responsibility of all personnel involved in the work to ensure that the conditions stated on the Permit are maintained throughout the duration of the work

Every Main Permit to Work mustEvery Main Permit to Work must:

• Clearly define the specific item of equipment to be worked onClearly define the specific item of equipment to be worked on• Show the precise location and exact nature of the work to be doneShow the precise location and exact nature of the work to be done• List the number of persons in the working teamList the number of persons in the working team

Page 21: Permit To Work presentation - original

P/TM/TRG/S/PW/00121 TSP Training

SOUTH PARS

– All Permits are automatically suspended on the raising of any Emergency Alarm. Only when the situation is back to normal may the work be resumed. The Permit must be endorsed to show the break in the work and the times of the interruption

– During any interruptions, the work sites must be patrolled by the Production Operators and Safety Authority to ensure that all personnel are aware of the change in conditions

8.38.3 Validity of Permits to WorkValidity of Permits to Work– Main Hot Work (Naked Flame) Permits and Main Hot Work

Permits are valid for a period of one shift (12 hours) only. If work is to continue beyond one shift or the end of the shift, whichever is sooner, a new Permit must be issued

– No Main Hot Work Permit can be used, or remain in use, later than seven (7) shifts after the original PTW issue

Page 22: Permit To Work presentation - original

P/TM/TRG/S/PW/00122 TSP Training

SOUTH PARS

– Main Cold Work Permits are valid for a maximum period of seven (7) consecutive days, with revalidation required at every shift change. If for any reason it is necessary to specify a shorter time limit, this is to be noted in the ‘Valid Until’ section of the PTW

– The following three Complimentary Permits are valid for a period of one shift (12 hours) only. If the work is to continue beyond 12 hours or the end of the shift, whichever is sooner, a new Permit must be issued:

° Entry to Vessels or Confined SpacesEntry to Vessels or Confined Spaces° RadiographyRadiography° DivingDiving

– Complimentary Permits (High or Low Voltage Electrical Isolations) are normally valid for the duration of the related Main Work Permit. However, when the isolation is required for a longer duration than the Main Permit (e.g. when equipment is isolated for a major repair outside the Site, or when awaiting long term spare parts delivery), the Electrical Complimentary Permits may remain valid

– Under these circumstances, the Complimentary Permit is logged as a Long Term Isolation and remains in the Permit Office even though the associated Main Permit has bee cancelled

Page 23: Permit To Work presentation - original

P/TM/TRG/S/PW/00123 TSP Training

SOUTH PARS

8.48.4 Process/Mechanical IsolationsProcess/Mechanical Isolations• Safety polypropylene straps with plastic tag plates must be used

at each of the specified mechanical locking-off points where work is done under a Complimentary Permit (Process/Mechanical Isolations

• The unique numbers of both the Main and the Complimentary Permits must be clearly written on each of the tag plates, using a suitable indelible marker. On completion of the work and cancellation of the Permit, the straps may be removed and the tag plates wiped clean

• Long Term Isolations require locking-off

8.58.5 Gas TestsGas Tests • The persons responsible for conducting and monitoring Gas Tests

are the Gas Tester and the Safety Authority. Their roles and responsibilities are detailed in sub-sections 3.6 and 3.8

Page 24: Permit To Work presentation - original

P/TM/TRG/S/PW/00124 TSP Training

SOUTH PARS

Gas testing is required for:

• All Naked Flame and other Hot Work activitiesAll Naked Flame and other Hot Work activities• Electrical work in designated Hazardous areasElectrical work in designated Hazardous areas• Entry into Vessels or Confined SpacesEntry into Vessels or Confined Spaces

• A dedicated section is provided on the reverse side of the top white copy of each Main Hot Work (Naked Flame) and Main Hot Work Permit to record the resulta of any atmospheric sampling. This section must be completed by a nominated Gas Tester prior to such work commencing. Gas Tests must be repeated periodically throughout the validity of the Permit

Page 25: Permit To Work presentation - original

P/TM/TRG/S/PW/00125 TSP Training

SOUTH PARS

9.09.0 PTW Step-by-Step ProceduresPTW Step-by-Step Procedures• Step-by-Step procedures of how the Permit is first raised

and the complete sequence of activities, is outside the scope of this course.

• For specific detail on this topic refer to the MS Word Training Document : P/TM/TRG/S/PW/001 : P/TM/TRG/S/PW/001

10.010.0 SummarySummaryThe purpose of this course was to describe the various types of Permits available for issue under the Permit to Work System for the South Pars Phases 2 & 3 onshore facilities, plus any other facilities to be operated by TSP. It has identified the persons responsible for the issue and use of the Permits and the circumstances under which they should be used