LABORATORIUM KONSTRUKSI - 3 JURUSAN TEKNIK SIPIL POLITEKNIK NEGERI BANDUNG Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext. 266 Bandung B AB I PERHITUNGAN KEBUTUHAN PANJANG PEMBENGKOKAN TULANGAN 1. Perhitungan Gambar 1 Nomor Dt (mm) Dpen (mm) Jumlah Tulangan a (mm) b (mm) 4 32 32 205 1775 8450 5 25 25 410 100 8450 6 32 32 205 100 8450 14 16 16 546 100 2850 Perhitungan tulangan nomor 4 a = 1775mm; b = 8450mm; Dt = 32mm Laa = La – ( Dp + Dt) = 1775 – ( x32 + 32) = 1727mm Lab = L2 – 2( Dp + Dt) = 8450 – 2( x32 + 32) = 8402mm R = п (2Dt + Dp) = п (2*32 + 32) = 75.36 mm Teknik Perancangan Jalan dan Jembatan | B AB I 1
25

Perhitungan BBS

Feb 04, 2023

Download

Documents

Taufiq Hidayat
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

B AB IPERHITUNGAN KEBUTUHAN

PANJANG PEMBENGKOKAN TULANGAN

1. Perhitungan Gambar 1

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b(mm)

4 32 32 205 1775 84505 25 25 410 100 84506 32 32 205 100 845014 16 16 546 100 2850

Perhitungan tulangan nomor 4a = 1775mm; b = 8450mm; Dt = 32mm

Laa = La – ( Dp + Dt) = 1775 – ( x32 + 32) = 1727mm

Lab = L2 – 2( Dp + Dt) = 8450 – 2( x32 + 32) = 8402mm

R = п (2Dt + Dp) = п (2*32 + 32) = 75.36 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 1

Page 2: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = 2Laa + La2b+ 2R =(2x1727) + 8402 + (2x75.30) = 12006.6 mm

= 12007 mm

Perhitungan tulangan nomor 5a = 100mm; b = 8450mm; Dt = 25mm

Laa = L1 – ( Dp + Dt) = 100 – ( x25 + 25) = 62,5mm

Lab = L2 – 2( Dp + Dt) = 8450 – 2( x25 + 25) = 8402mm

R = п (2Dt + Dp) = п (2*25 + 25) = 58.875 mm

Ltot = 2Laa + Lab + 2R =(2x62,5) + 8402 + (2x58.875) = 8644.75mm

= 8645 mm

Perhitungan tulangan nomor 6a = 100mm; b = 8450mm; Dt = 32mm

Laa = L1 – ( Dp + Dt) = 100 – ( x32 + 32) = 52mm

Lab = L2 – 2( Dp + Dt) = 8450 – 2( x32 + 32) = 8354mm

R = п (2Dt + Dp) = п (2*32 + 32) = 75.4 mm

Ltot = 2Laa + Lab + 2R =(2x52) + 8354 + (2x75.4) = 8608.8mm

= 8609 mm

Perhitungan tulangan nomor 14a = 100mm; b = 2850mm; Dt = 16mm

Laa = a – ( Dp + Dt) = 100 – ( x16 + 16) = 76mm

Lab = b – 2( Dp + Dt) = 2850 – 2( x16 + 16) = 2826mm

Teknik Perancangan Jalan dan Jembatan | B AB I 2

Page 3: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

R = п (2Dt + Dp) = п (2x16 + 16) = 37.68 mm

Ltot = 2Laa + Lab + 2R =(2x76) + 2826 + (2x37,68) = 3053.36 mm

= 3054 mm

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

L1 (mm)

9 13 - 90 4085010 13 - 150 4085015 13 - 40 4085016 13 - 40 4085017 13 - 12 4085019 16 - 6 845020 16 - 16 4300

Perhitungan tulangan nomor 9,10,15,16, dan 17L1 = 40850mm; Ltot = L1 = 40850mm

Perhitungan tulangan nomor 19 L1 = 8450mm; Ltot = L1 = 8450mm

Perhitungan tulangan nomor 20L1 = 4300mm;

Teknik Perancangan Jalan dan Jembatan | B AB I 3

Page 4: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = L1 = 4300mm

Nomor Dt(mm)

Jumlah Tulangan L1(mm)

7 22 658 43008 25 412 5975

Perhitungan tulangan nomor 7 L1 = 4300mm; Ltot = L1 = 4300mm

Perhitungan tulangan nomor 8L1 = 5900mm; Ltot = L1 = 5975mm

Teknik Perancangan Jalan dan Jembatan | B AB I 4

Page 5: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Nomor Dt (mm) Dpen(mm)

JumlahTulangan

a(mm)

b(mm)

1 25 25 409 1750 2000

Perhitungan tulangan nomor 1a = 1750 mm; b = 2000 mm; Dt = 25 mm

Laa = a – ( Dp + Dt) = 1750 – ( x25 + 25) = 1712,5 mm

Lab = b – ( Dp + Dt) = 2000 – ( x25 + 25) = 1962,5 mm

R = п (2Dt + Dp) = п (2x25 + 25) = 58.875 mm

Ltot = Laa + Lab + R =1712,5+ 1962,5+ 58.875 = 3733.88 mm

= 3734 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 5

Page 6: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Nomor Dt (mm) Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c(mm)

3 25 25 205 1750 8450 1750

Perhitungan tulangan nomor 3a= 1750mm; b= 8450mm; c= 875mm; d= 875mm Dt = 25mm

Laa = a – ( Dp + Dt) = 1750 – ( x25 + 25) = 1712,5mm

Lab = b – 2( Dp + Dt) = 8450 – ( x25 + 25) = 8412,5mm

Lac = c – 2( Dp + Dt) = 875 – ( x25 + 25) = 837,5mm

Lad = d – 2( Dp + Dt) = 875 – ( x25 + 25) = 837,5mm

R = п (2Dt + Dp) = п (25 + 25) = 58.875 mm

Ltot = Laa + Lab + Lac + Lad + 3R = 1712,5 + 8412,5 + 837,5 + 837,5 + (58.875x2) =11917.8mm =11918mm

Teknik Perancangan Jalan dan Jembatan | B AB I 6

Page 7: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Kode

Dt(mm)

Dpen(mm)

JumlahTulanga

n

a(mm)

b (mm)

11 25 25 410 100 175011a 25 25 410 100 2000

Perhitungan tulangan kode 11a = 100 mm; b = 100 mm; Dt = 25 mm

Laa = a – ( Dp + Dt) = 100 – ( x25 + 25) = 62.5 mm

Lab = b – ( Dp + Dt) = 1750 – ( x25 + 25) = 1712.5 mm

R1 = п (2Dt + Dp) = п (2x25 +25) = 58.875 mm

Ltot = Laa + Lab + R1 = 62.5 + 1712.5 + 58.875 = 1833.875 mm = 1834 mm

Perhitungan tulangan kode 11aa = 100 mm; b = 100 mm; Dt = 25 mm

Laa = a – ( Dp + Dt) = 100 – ( x25 + 25) = 62.5 mm

Lab = b – ( Dp + Dt) = 2000 – ( x25 + 25) = 1962.5 mm

R1 = п (2Dt + Dp) = п (2x25 +25) = 58.875 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 7

Page 8: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = Laa + Lab + R1 = 62.5 + 1962.5 + 58.875 = 2083.88 mm = 2084 mm

Kode

Dt(mm)

Dpen(mm)

JumlahTulangan a (mm) b

(mm)c

(mm)

12 25 25 656 150 1700 150

Perhitungan tulangan kode 12a = c = 150 mm; b = 1700 mm; Dt = 25 mm

Laa = Lac = a – ( Dp + Dt) = 150 – ( x25 + 25) = 112.5

mm

Lab = b – ( Dp + Dt) = 1700 – ( x25 + 25) = 1662.5 mm

R = п (Dt + Dp) = п (2x25 + 25) = 29.44 mm

Ltot = 2xLaa + Lab + 2R = (2x112.5) + 1662.5 + (2x29.44) = 1946,38 mm = 1947 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 8

Page 9: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c(mm)

d(mm)

e(mm)

f(mm)

21 13 13 136 50 350 850 350 850 50

Perhitungan tulangan kode 21a = f = 50; b = d = 350 mm; c = e = 850 mm; Dt = 13 mm

Laa = Laf = a – ( Dp + Dt) = 50 – ( x13 + 13) = 30.5

mm

Lab = Lad = b – ( Dp + Dt) = 350 – ( x13 + 13) = 330.5

mm

Lac = Lae = c – ( Dp + Dt) = 850 – ( x13 + 13) =

830.5 mm

R1 = п (Dt + Dp) = п (2x13 + 13) = 15.3 mm

R2 = п (Dt + Dp) = п (2x13 + 13) = 30.6 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 9

Page 10: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = Laa + Lab + Lac + R1 + 3R2 = 2x30.5+ 2x330.5+ 2x830.5+ 15.3 + 3x30.6= 2490.1mm =

2491mm

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm)

18 13 13 410 250 233 1420

Perhitungan tulangan kode 18a = 250; b = 233 mm; c = 1420 mm; Dt = 13 mm

Laa = a – ( Dp + Dt) = 250 – ( x13 + 13) = 230.5 mm

Lab = b – ( Dp + Dt) = 233 – ( x13 + 13) = 213.5 mm

Lac = c – ( Dp + Dt) = 1420 – ( x13 + 13) = 1400.5 mm

R1 = п (Dt + Dp) = п (2x13 + 13) = 15.3 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 10

Page 11: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

R2 = п (Dt + Dp) = п (2x13 + 13) = 30.6 mm

Ltot = Laa + Lab + Lac + R1 + R2 = 230.5 + 213.5 + 1400.5 + 15.3 + 30.6= 1890.4mm = 1891

mm

2. Perhitungan Gambar 2

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan a (mm) b

(mm)1 25 25 206 1750 2000

Perhitungan tulangan kode 1a= 1750 mm; b = 2000 mm; Dt = 25 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 11

Page 12: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

R = п (2Dt + Dp) = п (2x25 + 25) = 58,88 mm

La = a – ( Dp + Dt) = 1750 – ( x25 + 25) = 1712,5 mm

Lb = b – ( Dp + Dt) = 2000 – ( x25 + 25) = 1962,5 mm

Ltot = La + Lb + R =1712,5 + 1962,5 + 58,88 = 3733,88 mm

= 3734 mmJumlah tulangan dibutuhkan: (41000/200) + 1 = 205+1=206

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm) d (mm)

3 25 25 206 1750 8765 450 300

Perhitungan tulangan kode 3a= 1750 mm; b = 8765 mm; c= 450 mm; d= 300 mm; Dt = 25 mm

R = п (2Dt + Dp) = п (2x25 + 25) = 58,88 mm

La = a – ( Dp + Dt) = 1750 – ( x25 + 25) = 1712,5 mm

Lb = b – 2( Dp + Dt) = 8765 – 2( x25+ 25) = 8690 mm

Lc = c – 2( Dp + Dt) = 450 – 2( x25+ 25) = 375 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 12

Page 13: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ld = d – ( Dp + Dt) = 300 – ( x25 + 25) = 225 mm

Ltot = La + Lb + Lc + Ld + 3R = 1712,5 + 8690 + 375 + 225+ 3(58,88)

= 11179,14 mm= 11780 mm

Jumlah tulangan dibutuhkan: (41000/200) + 1 = 205+1=206

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm) d (mm)

4 32 32 206 1775 8765 450 300

Perhitungan tulangan kode 4a= 1775 mm; b = 8765 mm; c= 450 mm; d= 300 mm; Dt = 32 mm

R = п (2Dt + Dp) = п (2x32 + 32) = 75,36 mm

La = a – ( Dp + Dt) = 1775 – ( x32 + 32) = 1727 mm

Lb = b – 2( Dp + Dt) = 8765 – 2( x32+ 32) = 8669 mm

Lc = c – 2( Dp + Dt) = 450 – 2( x32+ 32) = 354 mm

Ld = d – ( Dp + Dt) = 300 – ( x25 + 25) = 204 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 13

Page 14: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = La + Lb + Lc + Ld + 3R = 1727 + 8669 + 354 + 204 +3(75,36) = 11180,08 mm

= 11181mmJumlah tulangan dibutuhkan: (41000/200) + 1 = 205+1=206

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm)

5 25 25 206 50 8765 50

Perhitungan tulangan kode 5a = c = 50 mm; b = 8765 mm; Dt = 25 mm

R = п (2Dt + Dp) = п (2x25 + 25) = 58,88 mm

La = Lc = a – ( Dp + Dt) = 50 – ( x25 + 25) = 12,5 mm

Lb = b – 2( Dp + Dt) = 8765 – 2( x25 + 25) = 8690 mm

Ltot = La + Lb + Lc + 2R= 12,5 + 8690 + 12,5 + 2(58,88) = 8832,76 mm

= 8833 mmJumlah tulangan dibutuhkan: (41000/200) + 1 = 205+1=206

Teknik Perancangan Jalan dan Jembatan | B AB I 14

Page 15: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm)

6 32 32 206 300 450 9075

Perhitungan tulangan kode 6a= 300 mm; b = 450 mm; c= 9075 mm; Dt = 32 mm

R = п (2Dt + Dp) = п (2x32 + 32) = 75,36 mm

La = a – ( Dp + Dt) = 300 – ( x32 + 32) = 252 mm

Lb = b – 2( Dp + Dt) = 450 – 2( x32+ 32) = 354 mm

Lc = c – 2( Dp + Dt) = 9075 – ( x32+ 32) = 9027 mm

Ltot = La + Lb + Lc + 2R = 252 + 354 + 9027 + 2(75,36) = 9783,72 mm

= 9784 mmJumlah tulangan dibutuhkan: (41000/200) + 1 = 205+1=206

Teknik Perancangan Jalan dan Jembatan | B AB I 15

Page 16: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

3. Perhitungan Gambar 3

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan a (mm)

1 22 22 329 66944 13 13 329 3505 13 13 329 350

Perhitungan tulangan kode 1a = 6694; Dt = 22 mmLtot = a = 6694 mmJumlah tulangan dibutuhkan: (41000/125)+1 = 328+1=329

Teknik Perancangan Jalan dan Jembatan | B AB I 16

Page 17: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Perhitungan tulangan kode 4a = 350; Dt = 13 mmLtot = a = 350 mmJumlah tulangan dibutuhkan: (41000/125)+1 = 328+1=329

Perhitungan tulangan kode 5a = 350; Dt = 13 mmLtot = a = 350 mmJumlah tulangan dibutuhkan: (41000/125)+1 = 328+1=329

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan a (mm)

2 13 13 165 98503 25 25 165 96506 13 13 165 8450

Perhitungan tulangan kode 2a = 9850; Dt = 13 mmLtot = a = 9850 mmJumlah tulangan dibutuhkan: (41000/250)+1 = 164+1=165

Perhitungan tulangan kode 3a = 9650; Dt = 25 mmLtot = a = 9650 mmJumlah tulangan dibutuhkan: (41000/250)+1 = 164+1=165

Teknik Perancangan Jalan dan Jembatan | B AB I 17

Page 18: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Perhitungan tulangan kode 6a = 8450; Dt = 22 mmLtot = a = 8450 mmJumlah tulangan dibutuhkan: (41000/250)+1 = 164+1=165

Nomor Dt(mm)

Dpen(mm)

JumlahTulangan

a(mm)

b (mm)

c (mm)

7 22 22 165 268 11611 882

Perhitungan tulangan kode 7a = 268; b = 11611; c = 882; Dt = 13 mm

R = п (2Dt + Dp) = п (2x22 + 22) = 25,905 mm

La = a – ( Dp + Dt) = 268 – ( x22 + 22) = 235mm

Lb = b – ( Dp + Dt) = 11611 – ( x22 + 22) = 11578 mm

Lc = c – ( Dp + Dt) = 882 – ( x22 + 22) = 849 mm

Teknik Perancangan Jalan dan Jembatan | B AB I 18

Page 19: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

Ltot = La + Lb + Lc + 2R = 235 + 11578 + 849 + 2(25,905)= 12713,81 mm

= 12714 mmOverlap = 2x40D = 2x40(22) = 2x880 = 1760Total = 12714 + 1760 = 14474Jumlah tulangan dibutuhkan: (41000/250)+1 = 164+1=165

Teknik Perancangan Jalan dan Jembatan | B AB I 19

Page 20: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

BAB IIPERHITUNGAN KEBUTUHAN TULANGAN

1. Tulangan diameter 13

KodeDt(mm)

KebutuhanTulangan

(mm)Jumlah

JumlahTulangan dalam1 Lente

TotalTulanga

n(Lente)

SisaPerlente

(mm)

TotalPanjang SisaTulangan(mm)

G1-9 13 12000 360 1 360 0 013 6410 90 1 90 5590 0

G1-10 13 12000 450 1 450 0 013 6410 150 1 150 5590 195650

G1-15 13 12000 120 1 120 0 013 6410 40 1 40 5590 223600

G1-16 13 12000 120 1 120 0 013 6410 40 1 40 5590 223600

G1-17 13 12000 36 1 36 0 013 6410 12 1 12 5590 67080

G1-21 13 2491 136 1 136 1059 144024G1-18 13 1891 410 2 205 1808 370640G2-2 13 9850 165 1 165 2150 118250G2-4 13 350 329 6 55 50 2750G2-5 13 350 329 6 55 50 2750G2-6 13 8450 165 1 165 3550 102950

Total 2952 1451294

a. Untuk membuat tulangan G2-4 dan G2-5, bisa menggunakan sisatulangan G2-2 sebanyak 110 lente, sehingga pada perhitungan

Teknik Perancangan Jalan dan Jembatan | BAB II 20

Page 21: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

ini panjang tulangan awal yang digunakan yaitu 2150 mm, jadisisa tulangan G2-2 yang memiliki panjang 2150 mm tinggal 55lente.

b. Untuk membuat tulangan G21-21, bisa menggunakan sisa tulanganG2-6 sebanyak 136 lente, sehingga pada perhitungan inipanjang tulangan awal yang digunakan yaitu 3550 mm, jadi sisatulangan G2-6 yang memiliki panjang 3550 mm tinggal 29 lente.

c. Untuk membuat tulangan G1-18, bisa menggunakan sisa tulanganG1-9 yang panjangnya 5590 sebanyak 90 lente dan menggunakansisa tulangan G1-10 yang panjangnya 5590 sebanyak 115 lente,sehingga pada perhitungan ini panjang tulangan awal yangdigunakan yaitu 5590 mm. Jadi sisa tulangan G1-9 yangmemiliki panjang 5590 mm tinggal 0 lente dan sisa tulanganG1-10 yang memiliki panjang 5590 mm tinggal 35 lente.

2. Tulangan diameter 16

Kode Dt(mm)

Kebutuhan

Tulangan(mm)

Jumlah

Jmltul.dlm 1Lente

Totaltulangan

(lente)

Sisaper

lente(mm)

Totalpanjangsisa

tulangan(mm)

G1-14 16 3054 546 3 182 2838 516516G1-19 16 8450 6 1 6 3550 21300G1-20 16 4300 16 2 8 3400 27200

Total 568 565016

3. Tulangan diameter 22

Kode

Dt(mm)

KebutuhanTulangan

Jumlah

JumlahTulanga

TotalTulanga

SisaPer

TotalPanjang

Teknik Perancangan Jalan dan Jembatan | BAB II 21

Page 22: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

(mm) n dalam1 Lente

n(Lente)

lente(mm)

SisaTulangan (mm)

G1-7 22 4300 658 2 658 3400 557600

G2-1 22 6694 329 1 329 5306 1745674

G2-7

22 12000 165 1 165 0 022 2474 165 1 165 926 15790Total 1317 2319064

d. Untuk membuat tulangan G2-7 yang panjangnya 2474 mm,bisa menggunakan sisa tulangan G1-7 yang panjangnya 3400mm sebanyak 165 lente, sehingga pada perhitungan inipanjang tulangan awal yang digunakan yaitu 3550 mm, jadisisa tulangan G1-7 yang memiliki panjang 3400 mm tinggal164 lente,

4. Tulangan diameter 25

Nomor Dt Kebutuha Jumlah Jml Total Sisa Total

Teknik Perancangan Jalan dan Jembatan | BAB II 22

Page 23: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

(mm)n

Tulangan(mm)

tul.dlm 1Lente

tulangan(lente)

perlente(mm)

PanjangSisa

Tulangan (mm)

G1-1 25 3734 409 3 137 798 109326G1-3 25 11918 205 1 205 82 16810G1-5 25 8645 410 1 410 3355 1375550G1-8 25 5975 412 2 206 50 10300G1-11 25 1834 410 6 69 996 68724G1-11a 25 2084 410 5 82 1580 129560

G1-12 25 1947 656 6 110 318 34980G2-1 25 3734 206 3 69 798 55062G2-3 25 11780 206 1 206 220 45320G2-4 25 11181 206 1 206 819 168714G2-5 25 8833 206 1 206 3167 652402G2-6 25 9784 206 1 206 2216 456496G3-3 25 9650 165 1 165 2350 387750

Total 4107 3510994

5. Tulangan diameter 32

Nomor Dt(mm)

KebutuhanTulangan(mm)

JumlahJml tul.dlm 1Lente

Totaltulangan(lente)

Sisaper

lente(mm)

G1-4 32 12000 205 1 205 0G1-6 32 8609 205 1 205 3391Total 410 3391

Teknik Perancangan Jalan dan Jembatan | BAB II 23

Page 24: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

BAB IIIKESIMPULAN

Total batang tulangan yang dibutuhkan untuk kebutuhanpembengkokan tulangan, total sisa pemotongan tulangan danpresentase sisa pemotongan tulangan pada gambarReinforcement Detail Box Cilvert STA. 202+738 pada proyek CikampekPalimanan Tol Road antara lain:

1. Diameter 13 mm adalah 2952 lente dengan panjang total(1 lente = 12 m) adalah 35424 m dengan sisapemotongan yang dihasilkan sepanjang 1451,294 m, makapresentase sisa yang dihasilkan oleh pembelian

tulangan diameter 19 mm adalah = x100% =

4,097 %2. Diameter 16 mm adalah 568 lente dengan panjang total

(1 lente = 12 m) adalah 6816 m dengan sisa pemotonganyang dihasilkan sepanjang 565,016 m, maka presentasesisa yang dihasilkan oleh pembelian tulangan diameter

16 mm adalah = x100% = 8,289 %

3. Diameter 22 mm adalah 1317 lente dengan panjang total(1 lente = 12 m) adalah 15804 m dengan sisapemotongan yang dihasilkan sepanjang 2319,064 m, makapresentase sisa yang dihasilkan oleh pembelian

tulangan diameter 22 mm adalah = x100% =

14,674%4. Diameter 25 mm adalah 4107 lente dengan panjang total

(1 lente = 12 m) adalah 49284 m dengan sisapemotongan yang dihasilkan sepanjang 3510,994 m, makapresentase sisa yang dihasilkan oleh pembelian

Teknik Perancangan Jalan dan Jembatan | BAB III 24

Page 25: Perhitungan BBS

LABORATORIUM KONSTRUKSI - 3JURUSAN TEKNIK SIPIL

POLITEKNIK NEGERI BANDUNGJl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022)

2013789, Ext. 266 Bandung

tulangan diameter 25 mm adalah = x100% =

7,124 %5. Diameter 32 mm adalah 410 lente dengan panjang total

(1 lente = 12 m) adalah 4920 m dengan sisa pemotonganyang dihasilkan sepanjang 3,391 m, maka presentasesisa yang dihasilkan oleh pembelian tulangan diameter

32 mm adalah = x100% = 0,069 %

Rata-rata presentase sisa pemotongan tulangan adalah

= 6,851 %. Maka

dapat disimpulkan bahwa proyek Cikampek Palimanan Tol Roadekonomis karena presentase sisa pemotongan tulangan yangdihasilkan tidak lebih besar dari 10%.

Teknik Perancangan Jalan dan Jembatan | BAB III 25