Top Banner
Performance Evaluation of Pekua Rubber Dam at Cox’s Bazar S.M. AZIZUL HOQUE March 2010 Department of Water Resources Engineering Bangladesh University of Engineering and Technology Dhaka, Bangladesh
109

PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Nov 30, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Performance Evaluation of Pekua Rubber Dam at

Cox’s Bazar

S.M. AZIZUL HOQUE

March 2010

Department of Water Resources Engineering

Bangladesh University of Engineering and Technology

Dhaka, Bangladesh

Page 2: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Performance evaluation of Pekua Rubber Dam at

Cox’s Bazar

A project submitted to

The Department of Water Resources Engineering

of

Bangladesh University of Engineering and Technology

In partial fulfillment of the requirement

for the degree

of

MASTER IN WATER RESOURCES ENGINEERING

by

S.M. AZIZUL HOQUE

ROLL NO : 040416045(P)

March 2010

Department of Water Resources Engineering

Bangladesh University of Engineering and Technology

Dhaka, Bangladesh

i

Page 3: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY

DEPARTMENT OF WATER RESOURCES ENGINEERING

CERTIFICATE OF APPROVAL

We hereby recommended that the M.Engg. Research work presented by S.M. Azizul

Hoque, Roll No. 040416045(P), session April 2004 entitled “Performance evaluation of

Pekua Rubber Dam at Cox’s Bazar” be accepted as fulfilling his part of the requirement

for the degree of Master of Engineering in water Resources Engineering.

Dr. Md. Sabbir Mostafa Khan Associate Professor, Department of Water Resources Engineering, BUET, Dhaka

.Chairman (Supervisor)

Dr. Umme Kulsum Navera Associate Professor, Department of Water Resources Engineering, BUET, Dhaka

Member

Jalaluddin Mohammad. Abdul Hye

Ex. Director General, WARPO, Dhaka

Member

ii

Page 4: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

DECLARATION

This is to certify that that this project work entitled “Performance Evaluation of Pekua

Rubber Dam at Cox’s Bazar” has been done by me under the supervision of Dr. Md.

Sabbir Mostafa Khan, Associate Professor, Department of Water Resources Engineering,

Bangladesh University of Engineering and Technology, Dhaka. I hereby declare that this

project or any part of it has not been accepted elsewhere for the award of any degree or

diploma from any other institution.

Signature of the candidate

…………………………..

S.M. Azizul Hoque

iii

Page 5: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

iv

TABLE OF CONTENTS Page CHAPTER -1 INTRODUCTION 1.1 Background 1

1.2 Objectives of the Study 4

1.3 Scope of the Work 4

1.4 Significance of the Study 5

1.5 Conceptual Framework of the Study 5

CHAPTRER -2 LITARATURE REVIEW 7

2.1 General 7

2.2 Review of Related Study 7

CHAPTRER -3 THE RUBBER DAM TECHNOLOGY 15

3.1 The rubber Dam Technology 15

3.2 What is a Rubber Dam 15

3.3 Use of Rubber Dam 16

3.4 Material of Rubber Dam 16

3.5 Life of Rubber Dam 17

3.6 Advantages of Rubber Dam 17

3.7 Disadvantage of Rubber Dam 19

3.8 The Design principle 19

3.9 Component of Rubber Dam 24

3.10 Salient Consideration for Construction of a Rubber Dam Body 26

3.11 Fitting and Fixing of Rubber Dam 27

3.12 Filling and Emptying System 29

3.13 Durability and Maintenance 31

Page 6: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

v

Page

3.14 Foundation 31

3.15 Flexible Control 32

3.16 Oscillation 32

3.17 Side slopes 33

3.18 Specification of Rubber Dam 34

3.19 Physical Property of Rubber Dam 34

3.20 Types of Rubber Dams 35

CHAPTER- 4 PEKUA RUBBER DAM PROJECT 41 4.1 General 41

4.2 Background of the Project 41

4.3 Dimension of Pekua Rubber Dam 44

4.4 Project Concept 45

4.5 Components of the Matamuhuri Irrigation Project (Pilot Project) 45

4.6 Purpose of Pekua Rubber Dam 46

4.7 The Project Implementation Time and Expenditure 46

CHAPTER-5 METHODOLOGY

5.1 General 48

5.2 Research Design 48

5.3 Research locale 48

5.4 Sample and Sampling Technique 48

5.5 Data Gathering Techniques and Tools 48

5.5.1 Primary Data Collection 49

5.5.2 Secondary Data Collection 49

5.5.3 Indicators 49

5.6 Data Processing and Analysis 50

Page 7: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

vi

Page CHAPTER- 6 RESULT AND DISCUSSION 51

6.1 General 51

6.2 Assessment Result of the Technical Aspect of Design of Pekua 51

Rubber Dam and Its Constructional Problems and their Mitigation

6.2.1 Water Retention Level 52

6.2.2 Length of the Rubber Dam 52

6.2.3 Height of Rubber Dam 53

6.2.4 Thickness of Rubber Sheet and Geometrical Shape of 54

Water filled Rubber Dam

6.2.5 Site Selection of the Pekua Rubber Dam 55

6.2.6 Floor Length of Pekua Rubber Dam 55

6.2.7 Foundation Design 56

6.2.8 Assessment of Construction Problems and its Mitigation 58

6.2.9 Fitting Fixing of Rubber Sheet 60

6.2.10 Fixation of Level of Over Flow Pipe and Procedure of 62

Commissioning Work

6.3 Assessment Result of Operation and Maintenance of Pekua 63

Rubber Dam

6.3.1 Operation System of Pekua Rubber Dam 63

6.3.2 Institutional Aspect of Operation and Management of Pekua 65

Rubber Dam Project

6.3.3 Operation and Management System of Pekua Rubber Dam 67

6.3.3.1 Damage and Repair of Rubber Dam Body 68

6.3.3.2 Disorder and Repair of Pump 69

6.3.3.3 Deposition of Silt over Rubber Bags and over U/S and D/S 70

Stilling Basin

6.3.3.4 Clogging of Foot Valve 71

6.3.3.5 Safety Device of Rubber Dam and Bed Level of Rubber Dam 71

Page 8: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

vii

Page

6.3.3.6 Problem in Boat Communication 71

6.3.4 Stakeholders’ Participation in the Management of Pekua Rubber Dam 72

6.4 Impact of the Pekua Rubber Dam Project 74

6.4.1 Impact on Socio-economic Status 75

6.4.2 Impact on Agriculture 78

6.4.3 Impact of Environment 79

6.4.3.1 Impact on Draught 79

6.4.3.2 Impact on Ground Water Table 80

6.4.3.3 Impact on Water Logging 80

6.4.3.4 Impact on Fisheries 80

CHAPTER- 7

CONCLUSION AND RECOMMENDATIONS 83

7.1 Conclusion 83

7.2 Recommendations 85

References 87

Page 9: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

viii

LIST OF FIGURE Page Figure 1.1 Conceptual Framework of the Study 6

Figure 3.1 Shape of Rubber Bag 23

Figure 3-2 3D view of Rubber Dam 24

Figure 3.3 Long section of Rubber Dam 25

Figure 3.4 Rubber Layers 27

Figure 3.5 Anchorage system of Rubber Dam 28

Figure 3.6 Anchorage system of Rubber Dam 28

Figure 3.7 Steel Clamps with Anchorage Bolts 29

Figure 3-8 Concrete Wedge Blocks 29

Figure 3-9 Filling and Emptying system of rubber dam 30

Figure 3.10 Cushioning system of rubber dam. 31

Figure 3.11 Flexible control 32

Figure 3.12 Oscillation Reduction 33

Figure 3.13 Variable side slope 33

Figure 3.14 Air-filled dam 36

Figure 3.15 Water-filled dam 36

Figure 3.16 Multiple Span of Rubber Dam 37

Figure 3.17 Layout of Multiple Bags Rubber Dam with dividing Pier 37

Figure 3.18 Pillow like dam 38

Figure 3.19 Inclined dam 38

Figure 3.20 Structural sketch of seamless rubber Bag 39

Figure 3.21

Figure 4.2 Location of Pekua Rubber Dam in Matamuhury 44

Structural sketch of traditional seamed rubber dam 39

Figure 3.22 Irrigation purpose served by rubber dam 40

Figure 3.23 Hydro power produced by rubber dam 40

Figure 3.24 Rubber dam used as reservoir 40

Figure 4.1 Project map of Matamuhury Irrigation Project 42

Page 10: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

ix

Page

Irrigation Project (Pilot Project)

Figure 4.3 Pekua Rubber Dam 47

Figure 6.1 Driving of sand pile of Pekua Rubber Dam 57

Figure 6.2 Driving of sand pile of Pekua Rubber Dam 58

Figure 6.3 Details of anchoring plate and anchoring bolt for 61

fitting & fixing rubber sheet for rubber dam

Figure 6.4 Commissioning of Pekua Rubber Dam 62

Figure 6.5 Inflated Pekua Rubber Dam for retention of U/S water 64

Figure 6.6 Deflated Rubber Dam 65

Figure 6.7 The Organization Chart of BWDB for Operation and 66

Maintenance of Pekua Rubber Dam

Figure 6.8 Special cushion system of Rubber Dam 69

Figure 6.9 Repair and Cleaning Work of Pump and its Accessories 70

LIST OF TABLE Table 4.1 Physical Features of Pekua Rubber Dam 45

Table 4.2 Implementation Schedule and Expenditure of 46

Pekua Rubber Dam Project

Table 6.1 Impact on Annual Income 75

Table 6.2 Amount of Annual Income Increase due to Construction of 76

Pekua Rubber Dam Project

Table 6.3 Poverty alleviation 76

Table 6.4 Impact on Employment due to Rubber Dam Project 77

Table 6.5 Impact of Agricultural Production 78

Table 6.6 Amount of annual agricultural production due to 78

rubber dam project:

Table 6.7 Amount of annual crop and fish production by stake holders 79

before and after implementation of the rubber dam project.

Table 6.8 Impact on Fish production 81

Page 11: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

x

ABBREVIATIONS AND ACRONYMS

ADG Additional Director General

BMC Bloc Management Committee

BUET Bangladesh University of Engineering and Technology

BWDB Bangladesh Water Development Board

CE Chief Engineer

CMC Central Management Committee

DG Director General

D/S Down Stream

DPEC Division of Project Evaluation Committee

EE Executive Engineer

EPDM Ethylene Propylene Diene Monomer

ECNEC Executive Committee of the National Economic Council

FCDI Flood Control, Drainage and Irrigation

GO Government Organization

GL Ground Level

IFMD Inflatable Flexible Membrane Dam

IMED Implementation, Monitoring and Evaluation Department

IWHR Institute of Water and Hydro-power Research

LGED Local Government Engineering Department

LLP Low Lift Pump

MPO Master Planning Organization

NGO Non government Organization

O & M Operation and Maintenance

OMC Operation and Maintenance Committee

PRA Participatory Rural Appraisal

PCP Project Concept Proforma

PWD Public Works Department

QHEPIL Qingdao Huahai Environmental Protection Industry Co. Ltd. China

Page 12: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

xi

Q Discharge

RCC Reinforce Cement Concrete

SDE Sub-Divisional Engineer

SAE Sub-Assistance Engineer

SO Sectional Officer

TNO Thana Nirbahi Officer

USA United States of America

U/S Up Stream

WRS Water Retention Structure

WRE Water Resource Engineering

WRL Water Retention Level

WUA Water User Association

Page 13: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

xii

ACKNOWLEDGEMENT The author acknowledges his indebtedness and sincere gratitude to his supervisor Dr. Md.

Sabbir Mostafa Khan, Associate Professor, Department of Water Resources Engineering,

BUET, Dhaka, for his continuous guidance, assistance and spirited encouragement

through the entire course of this research work.

The author is extremely grateful to Dr. Umme Kulsum Navera, Associate Professor,

Department of Water Resources Engineering, BUET, Dhaka, for being the member of the

examination board and for her valuable suggestions in writing this project.

The author is also grateful to Mr. Jalaluddin Mohammad. Abdul Hye, Ex. Director,

General, WARPO, Dhaka for being the members of the examination board and for

spirited encouragement and suggestions in completing this project work successfully.

The author is also grateful to all the teachers of the Department of Water Resources

Engineering for their cooperation and guidance for completing the research work.

The author is grateful to the librarian and the support staff of the library of Water

Resource Engineering Department, BUET, Dhaka.

The author wishes to express his sincere thanks to his friends and colleagues of

Bangladesh Water Development Board for their support, encouragement and co-

operation at various stages of doing this project work.

The author also express his gratitude to the anonyms respondents of the study as well as

the personnel who were contacted and discussed for collection of data for their valuable

contribution in providing the data and information.

Finally, the author is extremely grateful to his wife Dr. Selina Akhter for her continuous

support, encouragement and suggestions to complete the study.

Page 14: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

xiii

ABSTRACT

This study was conducted to evaluate the performance of the Pekua Rubber Dam

constructed over the Matamuhury River in Pekua upazila of Cox’s bazaar district. It was

implemented by BWDB as a pilot project. The objectives of the study were to evaluate

the technical status of the Pekua Rubber Dam in terms of its design and construction

aspects; To evaluate the operation and maintenance system of the dam in the light of

institutional provision and stakeholders’ participation in management process and to

evaluate the impact of the Pekua Rubber Dam Project on socio-economic life of the

stakeholders, local agricultural and environment.

Both primary and secondary data were collected to conduct the study. Primary data were

gathered by using a questionnaire from a sample of 50 stakeholders of the dam and

conducting focus group discussions with the design engineers; people in charge of

operation, maintenance and management of the dam; beneficiaries/stakeholders of the

project and people of relevant local organizations. For gathering secondary data, relevant

books, reports, articles, etc. on rubber dam as well as on the Pekua Rubber Dam Project

were consulted.

Major findings show that the rubber dam is functioning well since it implementation in

June 2004. The length, height, shape, site selection, foundation design, floor length, depth

of cut-off wall, fitting-fixing of rubber sheet, fixation level of overflow pipe, etc. of the

dam were ok in terms of the design parameters consideration. Besides, an increasing

trend of irrigated land and yield, yearly income of the stakeholders, employment

opportunity as well as socio-economic status of the stakeholders was observed. The local

environment also improved due to rise in underground water level and removing water

logging. This helped to decline drought in the area and increase fish production. The dam

also has some other strength in terms of implementation time, cost incurred and

simplicity of construction. However, the dam has minor maintenance problems, like

repair of pump machines, removal of clogging of foot valve and removal of silt from the

Page 15: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

xiv

dam body, U/S stilling basin & D/S stilling basin. Some other significant limitations as

detected are absence of any safety devise for automatically inflating and deflating the

dam body in case of emergency; too deep floor level of the pump house which incurs a

huge operation cost; interruption in boat communication; absence of any full time pump

operator; absence of local management committees and stakeholders’ formal

participation in management process. Another significant to mention limitation is lack of

coordination between BWDB local office and other local relevant organizations.

Based on the finding, this study suggests for some recommendations. They are: appoint

full time pump operator(s); form different kinds of local bodies/committees with

participation of the stakeholders; establish formal coordination system between BWDB

local office and local relevant organizations and implement more rubber dams to support

irrigation in other areas of Bangladesh. In doing so some change in technical aspects are

recommended. For example, introducing a safety devise for automatic inflation and

deflation of the dam body in case of emergency; a modified design of inlet and outlet

pipe so that the mouths of the pipes can not be blocked with silt deposition and a

submergible pump to curtail the huge costing of pump house.

Page 16: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Chapter 1

Introduction

1.1 Background

Bangladesh is one of the densely populated countries in the world. To keep pace with

the rapid growth of population, it has to produce increased amount of food grain every

year. The additional food production comes mostly from high yielding variety (HYV)

of rice, production of which largely depends on surface water irrigation as well as

ground water irrigation. In the National Water Plan Project-II (MPO, 1991) a medium

term strategy for development of surface water irrigation system was undertaken to

utilize main river water with the help of pumps. This surface water irrigation is

generally done by means of various water control structures such as barrage, regulator,

drainage sluice, earthen dam, weir, inlet, outlet, inflatable rubber dam, etc. However,

choosing an appropriate and sustainable structure, as per need of local topography, for

irrigation is important to derive maximum benefits from an irrigation project.

Bangladesh is situated in the delta of the three major rivers of the world (the Ganges,

the Brahmaputra and the Meghna). Apart from these three major rivers, there are so

many small and medium size rivers, khals and chara distributed all over the country. In

the district of Chittagong Hill Tracts there are so many chara, khals and medium size

rivers, which originate from hills, carry fresh water and fall into the Bay of Bengal. The

people of these localities usually build earthen dams in these streams to retain perennial

water for winter season irrigation for Boro and Rabi crops (EPC, 1996; LGED, 1994;

Hossain, 1992). In the monsoon period flash flood washes away these earthen dams or

in some cases these earthen dams need to be removed for easy flood flow through these

streams. So, these dams need to be reconstructed every year, which is not cost effective

as well as not supportive of providing a sustainable irrigation mechanism for the people

of Chittagong Hill tracts . The people of these localities, therefore, felt the need for a

permanent solution of this unsustainable financial investment for irrigation purposes.

In the hilly areas, there are so many surface water sources which can not be utilized in

effective way due to lack of required and sustainable water retention structures for

Page 17: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

2

which people have to suffer a lot of problems in irrigating their cropland. To overcome

this financial loss as well as troublesome winter season irrigation, people in the hilly

areas were in a great demand of a permanent, sustainable and effective mechanism to

retain fresh water for irrigation purpose, especially during dry season. In response to

these difficulties mentioned above, Bangladesh Water Development Board (BWDB)

has been entrusted with the task of managing the water resources of this region by

means of conducting studies as well as implementation, operation and maintenance of

water resource development projects to boost up agriculture of the area and improving

the local environment.

Besides the earthen dams some traditional RCC or brick structures were generally

constructed and practiced for irrigation purpose in these areas. These traditional water

control structures are generally provided with steel gate and wooden stop log.

Traditional water control structures with the steel gate and wooden stop log have some

disadvantages with their operation and maintenance. Operational difficulty of manually

operated gate and stop log is due to failure of the operator to remain present and

remove the stop log from the structure slot or open the gate at the time of occurrence of

sudden flash flood. Estimation of peak flood discharge is also difficult due to inaccurate

demarcation of hydrological boundaries in the ungaged hilly rivers (Hossain, 1992). To

overcome the problems mentioned above regarding the earthen dam, built by local

people, and concrete or brick water control structures, a rubber dam was introduced by

BWDB, under the Matamuhury Irrigation Project in Chittagong Hill Tracts, as an

alternative mode to support the local irrigation system.

Rubber Dam, a kind of fabric dam is now being practiced many countries of the world

according to their variety of uses (IWHR, 1994). It is an advanced technology; it is

made of high strength synthetic fabrics, supported by frame and prefabricated rubber,

anchored on RCC base. Rubber dams are cylindrical rubber fabrics placed across

channels, streams and weir or dam crests to raise the upstream water level when

inflated. The membrane is a multi-layer fabric made of synthetic fibre (usually nylon)

and rubberised on one or both sides. The fabric is quite flexible and yet exhibits good

wear-resistance characteristics. The inflatable flexible membrane dams (IFMD, or

rubber dams) were developed in the early 1950 (Flexidam – Imbertson). They are used

to divert water for irrigation, temporarily raising existing dams, flood control, water

Page 18: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

3

retention for aquifer recharge, reducing or preventing salt water intrusion into fresh

water areas, protect low-lying coastal areas from tidal flooding, enabling fish

passage(Wikipedia) The construction cost and construction time of rubber dam are less

than those of traditional RCC or brick structures. Rubber dam structures also have

certain advantages over conventional water control structures. Water conservation is

effective as the raising or lowering of the retained water level as per requirement. Less

operation and maintenance (O&M) problems are encountered and better navigation

facilities can be provided by the rubber dams. Additionally, it seems to be

environmentally sound and friendly. It has a design life of approximately 20 years

(IWHR, 1994; SEIL, 1985).

Considering the advantages of rubber dam, Local Government Engineering Department

(LGED) first time in the history of Bangladesh introduced two rubber dams as pilot

projects in 1995. One is Idgoan Rubber Dam and the other one is Bakkhali Rubber

Dam (Raquib, 1999). So far LGED has constructed about 12 rubber dams. In line with

this BWDB implemented its first rubber dam project over the Bhola Khal, a branch of

the Matamuhury River, in Pekua upazila of Cox’s Bazar district under the Matamuhury

Irrigation Project. This was introduced as a pilot project. The major goal was to give a

sustainable solution of water retention in the area instead of temporarily made earthen

dam. Some other objectives of construction of this Pekua Rubber Dam was to provide

irrigation facility to Boro crops during dry season (Nov-April) through retention of

sweet water in the upland river system and prevention of ingress of saline water from

downstream. The irrigation was provided by LLP which were installed on both banks

on the ponded river and channel systems (BWDB, EPC, 1996).

The project was implemented with a cost of Tk.1991.08 lakh. It included the cost of

construction of the dam and development cost of some other infrastructure directly

related with the functioning the dam. The benefited area at the 1st stage is gross 14000

ha and cultivable net area 5000 ha.

The project started its functioning in 2004 and as reported by the relevant people

contributing to the local irrigation system well without any apparent disruption. At this

stage an evaluation of this pilot project has become important to look into its efficiency

in terms of the project goals and objectives. It is particularly important to look into the

Page 19: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

4

performance of a pilot project in order to make a rational decision about its future

functioning and management as well as in replication of such project in other areas. So,

the researcher decided to conduct this study to assess the performance of the Pekua

Rubber Dam Project, which has already passed more than five years since its

implementation.

1.2 Objectives of the Study The specific objectives of this study were:

1. To evaluate the technical status of the Pekua Rubber Dam Project in terms

of its design and construction aspects;

2. To evaluate the operation and maintenance system of the rubber dam project

in the light of institutional provision and stakeholders’ participation in the

management process; and

3. To evaluate the impact on the Pekua Rubber Dam Project based on the

following aspects:

i. Socio-economic life of the stakeholders

ii. Local agricultural

iii. Local environment

1.3 Scope of the Study

The scope of the study included assessment of the technical status and operation and

maintenance aspects of the Pekua Rubber Dam. It also assessed the impact of the dam

on social-economic life of the local people as well as on agriculture and environment of

the catchments area of the Rubber Dam.

The technical performance was assessed based on the design parameters of Pekua

Rubber Dam and its constructional strengths and weaknesses. The operation and

maintenance (O&M) status were analyzed in the light of institutional aspects,

management aspects and stakeholders’ participation in management process. The other

points of evaluation of design were the sustainability of the dam during operation and

the sustainability of the bags during inflating them by injecting water into the bag. The

technical evaluation aspects included the constructional problems and the mitigation

measures as well as O&M problems. The agricultural impact due to construction of the

Page 20: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

5

dam were assessed in terms of various indicators, like area of pre and post project

irrigated area, crops and vegetables yield before and after the project implementation,

etc. To study socio-economic impact, indicators like change in life style of the

stakeholders, poverty level decrease, increase in annual income, employment

opportunity, etc. were assessed. To assess the impact on environment, indicators like

draught, water retention level, water logging, fish production were investigated. Thus,

based on the assessment result of all the above mentioned indicators the performance of

the Pekua Rubber Dam project was determined in this study.

1.4 Significance of the Study

The Pekua Rubber Dam is the first rubber dam constructed by BWDB. The history of

implmenting rubber dam also is a recent phenomenon in the country. In recent years

LGED has built a significant number of rubber dams. As a new technology, introduced

in the country, construction of the rubber dam should be subjected to evaluation to look

into its efficiency in terms of its construction, operation, maintenance as well as its

impact on different aspects of life, locality and environment. The Pekua Rubber Dam,

therefore, needs to be evaluated in order to investigate its performance in terms of the

abovementioned aspects. So, a decision was made to conduct this evaluative study on

the Pekua Rubber Dam Project. The findings of this study has provided some lights on

its effectiveness, impact as well as some of its limitations. The findings from this study

will hopefully be helpful in making rational decisions in desigining, implementing,

maintaining and managing any such project by BWDB or any other Organization. Also

the findings will be conducieve in improving the internal and external efficiencies of

the Pekua Rubber Dam Project.

1.5 Conceptual Framework of the Study

The study as was conceptualised is presented in the next page through a schematic

diagram. The performance of the dam was assessed based on three aspects- technical

efficiency, O&M and impact on some aspects. Technical status was evaluated based on

design and constructional aspects. Institutional provision to manage and operate the

dam as well as locals’ participation in it was considered to evaluate the dam’s operation

and maintenance status. Besides, the dam’s performance was assessed based on its

impact on the socio-economic life of the stakehoders as well as local agriculture and

Page 21: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

6

environment. The findings helped to identify specifically some strengths and

weaknesses of the project in terms of the abovementioned aspects. Finally, some

recommendations were made, implementation of which can help to improve the overall

performance of the Pekua Rubber Dam Project.

Performance

of

Pekua

Rubber

Dam

Technical Status • Design • Construction

O and M • Inst. Provision • Stakeholders’

participation in management

Impact on- • Socio-economic

status • Agriculture • Environment

Findings

Recommend-ations

Figure 1.1: Conceptual Framework of the Study

Page 22: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

7

Chaptrer 2

Literature Review

2.1 General

This chapter deals with literature review of performances evaluation of rubber dams

conducted by three researchers in Bangladesh and some other research conducted

abroad related with inflatable rubber dams. Efforts have been given to collect the

reports of different study related to these topics. A synopsis of some of the study report

is discussed in this chapter.

2.2 Review of Related Studies

Local Government Engineering Department (LGED) has constructed two rubber dams

for the first time in Cox’s Bazar district as pilot projects. One is in Idgoan khal and the

other is in Bakkali River (LGED, 1994). Another 10 rubber dams were constructed by

the year 2003. The performances of the Idgaon and Bakkhali rubber dams were

evaluated through a study conducted by Raquib (1999). The title of his study was

“Performance evaluation of rubber dam projects in Bangladesh”. In his study the

aspects of evaluation were engineering, agriculture, environmental and organizational.

Engineering evaluation involved identification of construction, operation and

maintenance problems and mitigative measures. Agricultural evaluation involved

assessment of impacts on irrigated area, cropping intensity and yield. Environmental

evaluation involved evaluation of impact on fisheries, drought, water logging, and

ground water level and boat communication. Organizational evaluation involved

evaluation of organizational set-up including people’s participation and operation and

maintenance cost recovery of the project.

The evaluation was carried out through collection of data and information after proper

discussion with the respondents using required checklist, making field visits and study

of relevant documents. Data and information were gathered from the project

beneficiaries, adversely affected local people and the service givers and the result were

verified with the relevant experts at the thana level.

Page 23: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

8

Major findings of his study were that the rubber dam project had no major problems in

construction, operation and maintenance. Moreover implementation period was short

due to simplicity in the construction work. Development cost was low compared to

traditional water retention structures. Construction work of the rubber dam had some

limitations as implementation work required special supervision and the rubber bag

were not manufactured in Bangladesh. There were no major operation and maintenance

problems. However, some minor problems such as leakage of rubber bags, disorder of

pump machine, siltation over the rubber bags, and clogging of foot valves were

encountered which could be mitigated easily at local level through participation of the

beneficiaries and the service givers. The project had positive impact on agriculture. An

increasing trend in irrigated areas and yield was observed. He concluded in his study

that this was mainly due to improved water management in the project area and

people’s confidence in project operation. It had good impact on environment except

little disruption in boat communication during irrigation period. Informal organizational

set up was there during the operation of the rubber dam. But, the organizational set-up

was weak and the people’s participation and operational and maintenance cost recovery

were not adequate. The existing organizational set-up was strengthened through

institutional intervention. Present organizations were operating satisfactorily in respect

of proper water management, resolution of conflicts, operation and maintenance and

cost recovery of the rubber dam.

It had no adverse environmental impact except little disruption in boat communication

during irrigation time.

Another study was conducted by Saleh and Mondol (2000) to evaluate the performance

of the same pilot projects of rubber dam of LGED in terms of some selected standard

indicators. The tile of his study was ”Performance evaluation of rubber dam porojects

in irrigation development” The performances indicators used in his evaluation have

been broadly classified in to three groups: hydraulic indicators, agriculture indicators

and non agriculture or socio-economic indicators. For the qualitative and quantitative

assessment of the indicators, field measurements and questionnaires surveys were

carried out during the study period. He mentioned that due to lack of basic data on the

targets or goals and designed values, evaluation of some of the selected indicators was

not possible. The water discharge at Bakkhali Rubber Dam Project (98%) is

satisfactory. The relative water supply of Bakkhali is adequate (1.21) but at Idgoan

Page 24: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

9

Project it is inadequate (0.8). The computed water delivery performances are very low

for both the project (0.19 and 0.38 for bakkhali and Idgoan project respectively)

because the targeted available volumes of water were overestimated in the feasibility

reports.

The total water used in irrigation for growing HYV Boro rice at Bakkhali and Idgoan

projects are 1133 and 819 mm respectively. The irrigated area performances of both

the projects are very poor (0.22 and 0.46 for Bakkhali and Idgoan projects

respectively). The yield performances of both the projects during 1998-99 are

satisfactory (0.90 and 0.88 at Bakkhalki and Idgoan projects respectively). The average

irrigation fee collection is excellent (97%), but at Bakkhali project it is only about 62%.

The O & M cost of both the rubber dams are very low (about Tk 100/ha). Growing

HYV Boro rice with irrigation is very profitable. The calculated potential command

area of Bakkhali project is 1320ha and the actual command area in 1998-99 was

1315ha. Thus the Bakkhali project is probably operating at its optimum level and

further increase in command area is not recommended unless the farmers resort to

improved irrigation management.

A study by Nahar (2004) was conducted in the field of rubber dam project to evaluate

the feasibility of rubber dam construction in Bangladesh with locally available material.

The title of her study was “Preliminary study on design of rubber dam in Bangladesh

with special reference to the use of locally available material. The major findings of

Nahar’s study were some significant and satisfactory findings. The study shows that

there is no problem in implementation of rubber dam in Bangladesh. Moreover it was

found that the time required for implementation of the rubber dam was relatively short

and the development cost was relatively low mainly due to simplicity in construction.

However, implementation of rubber dams required special supervision and rubber bags

are not manufactured in Bangladesh. The rubber dam projects did not have any adverse

environmental impact except minor disruption in boat communication. There was a

negative impact on communication due to construction of the rubber dams in place of

the earth dams. The laboratory investigation result shows that the elongation of rubber

increases with the increase of tensile strength. Therefore, actual strength of rubber

cannot be used for thickness calculation. She concluded that there is a good possibility

of use of locally made material and technology in designing and construction of rubber

Page 25: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

10

dam in the country. She further revealed that the local production of rubber bag will be

at cheaper cost and the rubber bags can easily have their recycle value.

Fahmida Khatun (Fahmida, K) Assistant Professor, Dept. of Water Resources

Engineering Bangladesh University of Engineering and Technology, Bangladesh,

developed a research proposal as group organiser on evaluation of Rubber Dam

Technology as an alternative to Traditional Dam Projects for sustainable development.

A number of global reports have documented the dramatic impact of human induced

water withdrawa1s. Incidentally, social, environmental, governance and compliance

aspects have been ignored in decision-making about the construction of a dam in the

past. The proposal incorporates the views of World Commission on Dams (WCD),

International Commission on Large Dams (ICOLD) and IUCN- World Conservation

Union about dams and development. The commission’s observations are based on the

emerging principle that the traditional concept of a balance sheet, that is calculating

costs and benefits, is no more acceptable.

A paper entitled as Aquifer Recharge Enhanced with Rubber Dam Installations

[(Michael R. Markus, Curtis A. Thompson, and Matt Ulukaya (From Water & Waste

Digest) 1995] is published by Water Engineering and management. In this paper it is

described that artificial recharge of groundwater has become a necessity in Orange

County, California, where natural recharge is insufficient to satisfy water demands. The

area is part of a semi-arid coastal plain with fewer than 20 in. of rainfall each year, and

the Orange County Water District is supplementing nature with artificial recharge to

supply 70 percent of the water needs of its more than two million residents. As part of

the program, the District has expanded its recharge capabilities with the Santa Ana

River Inflatable Rubber Dam Project.

Two inflatable rubber dams with bypass facilities to divert river flows to off-river

recharge basins have been constructed. These dams, both of which are 2.1 meters in

height and stretch 97.5 meters across the Santa Ana River, are among the largest single

span systems of this type in North America. They allow the District to recharge as

much of the river flows as practically possible by capturing excess flows that would

otherwise be lost to the ocean.

Page 26: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

11

Nearly 25 million cubic meters of storm water captured annually for recharge will

supply the water needs of 100,000 of the population within the service area. In the first

operating year (1993), with only the first dam completed, almost 17 million cubic

meters of water with an estimated value of $2 million, were saved. The cost to

construct the dams and appurtenant facilities was $4.7 million. Design work included

comparison of technologies previously used to control headwater surface levels, and

evaluation of design considerations for debris control, metering, flow control, hydraulic

conveyance, and energy dissipation.

The District extracts groundwater from an extensive aquifer below a rapidly developing

urban area. To replenish the reserves, it uses over 1,500 acres of land along the Santa

Ana River for percolation basins. These are maintained in the river itself, and several

off-river basins also are in use for retention and recharge. The off-river basins have a

combined volume of over 33 million cubic meters.

Sand levees in the river are used to create a serpentine path for the water, as well as

providing sufficient head to divert approximately 7.1 cubic meters per second (cms) of

water to the off-river basins. When flows in the river exceed 14.2 cms, however, the

sand levees collapse and are scoured away and the water flows unimpeded to the ocean.

It was envisioned that inflatable rubber dams could replace some of the sand levees to

increase the diversion capacity to 14.2 cms into the off-river basins. This would

increase the capture of the larger flows and reduce the time and effort needed to replace

the sand levees after storm flows have receded.

The project consists of one inflatable rubber dam (the Imperial Highway installation)

and bypass facilities at the head works of the recharge basins, and a second similar

installation (known as Five Coves) located approximately three miles downstream.

In addition to the use of the rubber dams, two other aspects of this project are

significant. First, the bypass at the Imperial Highway dam incorporates a relatively new

trashrack design with self-cleaning debris removal equipment. Second, since space for

the bypass facilities was limited, complex hydraulic problems for bypass flow control,

metering, and energy dissipation had to be solved.

Page 27: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

12

Structural design of the rubber dam foundation and anchoring system is

straightforward, with one caveat: the seepage and related uplift pressures created by the

new reservoir must be reviewed for their effect on the stability of the riverbed and local

riverbed structures. A typical rubber dam foundation has upstream and downstream

cutoff walls to increase the ground water seepage path and reduce uplift pressures

exerted by the ground water. Seepage analyses for the Santa Ana dams indicated that

the structural stability of river drop structures near the proposed dams could be

adversely affected. The locations of the foundations were adjusted to allow relief of the

The multiple uses of the Santa Ana River required the evaluation of several diversion

structure alternatives for the river. This is the largest river in southern California and

urban development along its course has made it an important water supply resource and

flood control channel. The U.S. Army Corps of Engineers has been engaged in a flood

control improvement project on the river since 1989, and reviewed the preliminary and

final designs to ensure compatibility between water diversion and flood control

activities on the river. The simplicity of the rubber dam concept, along with its proven

reliability, were key considerations in evaluating its suitability as a diversion structure.

Alternatives investigated included steel gates with variations on the operating

mechanism. Conditions that inhibited the use of steel gates were the corrosive

environment at the sites (approximately 19 kilometers from the ocean with the major

component of the base river flows being wastewater effluent); the high sediment

transport capability of the river (silt could clog gate operators and abrade steel gates

and hinges); additional maintenance (compared to rubber dams); and cost. While

inflatable rubber dams also have deficiencies, including increased exposure to

vandalism and a limited history (the oldest example in North America is less than 25

years old), their advantages justified their selection.

A typical rubber dam installation consists of a reinforced concrete foundation

constructed across a riverbed with a rubber bladder anchored to the foundation. In the

Santa Ana River project the two bladders extend 97.5 meters across the river bed

without need for intermediate piers or abutments. The bladder is inflated and deflated

through connected air piping. Most contemporary rubber dams use air for inflation, but

water may be suitable where hydraulic conditions are more demanding.

Page 28: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

13

uplift pressures upstream of the drop structure, however, and structural stability was

maintained.

A key benefit of this type of dam is the ability to serve as a reliable, low-maintenance

adjustable-crest weir. In the Santa Ana project the dam/weir creates a shallow diversion

pool that provides a hydraulic gradient to convey the water into the adjacent off-river

recharge basins. Each dam can be fully inflated or fully deflated to completely block, or

completely open, the flood channel-or can be set to operate at intermediate heights.

When a dam is inflated, river flows are diverted to the off-river recharge basins, or

bypassed around the dam and back into the river. If the flow is such that the water level

is rising and will overtop the dam, the bladder will automatically deflate. (These dams

are capable of withstanding overflows up to 0.6 meters above the top). Internal air

pressure is relatively low, and associated operating equipment is minimal. Redundant

electrical and mechanical controls ensure virtually failsafe operation under emergency

conditions-a capability essential in gaining approval from the Corps of Engineers.

A secondary benefit is the adaptability for automation. The labor intensive efforts of

constructing and maintaining sand levees and diversion dikes have been replaced by a

30-minute inflation task that can be performed by a local or remote push-button. Design

provisions were made to permit future installation of telemetry equipment for remote

monitoring and operation of the dams and most of the related ground water recharge

facilities. However, the District intends to gain practical experience with this flood

control system before getting into automation.

Two major manufacturers of inflatable rubber dams were consulted throughout the

design process (Bridgestone and Sumitomo). While their operating schemes appeared

virtually identical, there were differences in the fabric, anchoring systems, hydraulics,

and equipment costs. Key considerations in determining suitability of one type versus

another included the operational hydraulics (e.g., depth and frequency of dam

overtopping, trailrace depth on the downstream face, adjustment range for the dam

crest); potential for in situ dam fabric repairs; and the need for special coatings to

protection against vandalism, caustic conditions, or overflow of potentially damaging

debris.

Both designs were found to be acceptable for this project, and the specifications written

allowed competitive bidding between the two manufacturers. Each was selected as low

Page 29: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

14

bidder on one of the two facilities, and their products have improved the reliability and

safety of the river diversion facilities. Earth moving equipment works the river bed to

rebuild levees and diversion dikes less frequently. Also, the District can improve the

quality of diverted water by deflating the dams and allowing the silt- and debris-laden

"first flush" of storm water to bypass the recharge basins.

A study was conducted on Construction, Operation, and Maintenance of Rubber Dams

by Zhang X. Q., Tam, P. W. M., and Zheng, W (Zhang X. Q., Tam, P. W. M., and

Zheng, W. 2002).Rubber dams are inflatable and deflatable hydraulic structures.

Thousands of rubber dams have been installed worldwide for various purposes:

irrigation, water supply, power generation, tidal barrier, flood control, environmental

improvement, and recreation. Furthermore, rubber dams have been used in cold areas

where the temperature is as low as 40°C. The simplicity and flexibility of the rubber

dam structure and its proven reliability are key considerations in its wide scope of

applications. Based on the management practices of 20 rubber dams in Hong Kong in

the past 35 years, interviews with rubber dam experts and practitioners, and the

investigation to the construction of a recent rubber dam, this paper provides a detailed

discussion on various issues related to the construction, operation, maintenance, and

repair of rubber dams.

Page 30: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

15

Chapter 3

The Rubber Dam Technology

3.1 The Rubber Dam Technology

This sub-section gives an overview of what a rubber dam is? What technology is

applied in it? What are the advantages and disadvantages of rubber dam? What are the

materials used for rubber dam construction? And What are the design considerations?

Etc.

3.2 What is a Rubber Dam?

An inflatable and movable weir made of rubber cloth and installed on the river bed or

slope of banks across a river or a canal and work as a dam to control the flow of water

is called rubber dam. It is a kind of a large bag which is inflated or deflated by injecting

and discharging air or water. It is constructed across the river to retain water. Rubber

bags are used for blocking to prevent water flow. It is practically used to prevent

upward and downward flow of water. It is a new type of hydraulic structure compared

with steel sluice gate and it is made of high-strength fabric adhering with rubber, which

forms a rubber bag anchoring on basement floor of dam. (Geosynthetica.net)

Rubber dam construction is a relatively recent technology. It was developed in the USA

in the early 1960s. China constructed the first rubber dam in 1966 and since then China

developed its own expertise on designing, manufacturing and construction of rubber

dam. More then 2000 rubber dams have been constructed worldwide including

Australia, Japan, Taiwan, Hong Kong, China, Indonesia and Thailand (Nahar, 2004).

The present trend suggests an increased use of air-filled membranes because they can

be deflated or inflated more rapidly. The rubber dam is usually deflated for large

overflows. It is however common practice to allow small spillages over the inflated

dam. During overflows greater than 20% over-topping, vibrations might result from

fluid-structure interactions and the instabilities might damage or destroy the rubber

membrane (Ogihara and Maramatsu, 1985). In practice, a deflector (i.e. fin) is installed

on the downstream face of the rubber dam to project the nappe away from the

membrane, hence preventing rubber membrane vibrations. The inflatable flexible

membrane dams (IFMD, or rubber dams) were developed in the early 1950s (Flexidam)

Page 31: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

16

3.3 Use of Rubber Dam

Rubber dam has various uses. The main purpose of its use in our country is to provide

irrigation facilities of boro crops (one kind of paddy) during dry season (Nov-April)

through retention of sweet water in the upland river system and prevention of ingress of

saline water from downstream. Besides these, the broad use of rubber dam is as

follows:

• The dam is used as flood control structure

• Water retention for irrigation

• Water retention for aquifer recharge

• Water retention for fish production

• Reducing or preventing salt water intrusion into fresh water areas

• Protect low-lying coastal areas from tidal flooding

• Enabling fish passage past diversion works by deflation of dam

• Sewage retention/separation during flood events

• In rainy seasons, water contained in dam shall be discharged to help release

flood water from the river course.

• Intake Gate

a) Hydropower

b) Irrigation

c) Domestic water supply

d) Industrial water supply

• River Estuary Barrier

a) Tidal barrier

b) Storm surge barrier

c) Sand barrier

d) Wave barrier

3.4 Materials of Rubber Dam

The membrane is a multi-layer fabric made of synthetic fibre (usually nylon) and

rubberised on one or both sides. The fabric is quite flexible and yet exhibits good wear-

resistance characteristics (Chanson, H; 1996). A synthetic fibre, such as nylon is used

for tensile strength for fabric while the synthetic rubber coating provides high reistance

to weather, ozone and abrasion. Layers of rubber-coated fabric are bonded together in a

Page 32: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

17

sandwich construction to provide the required tensile strength. Chloroprene rubber is

employed for its known resistance to climate condition, ozone, wear etc. A layer of

stainless steel mesh or ceramic chips can be embedded in the surface layer to reduce or

prevent vandal damage (SEIL, 1985; Chanson, H, 1996). The layers of rubber coated

fabric are joined together in the longitudal dirrection. The actual number of layers of

rubber coated fabric for each rubber body depend on the gate height and the tension.

The rubber sheet may be of single layer, double layer and multi-layer as per its height

and strength. The fabric-bag should be water tolerant, water resistant, corrosion

resistant and durable in atmosphere. But now for better protection of the dam materials

against weathering and for operating over large temperature variation chloroprene and

ethylene propylene dyne monomer are being used as the dam material.

3.5 Life of Rubber Dam

Durability of rubber bag is excellent. Recently, a 35 year old dam in eastern Ontario,

Canada was replaced and was still functional in both freezing winter conditions when it

was air filled, and water filled in summer. It was deemed to have served its useful life.

The design life of rubber dam is approximately 20 years (IWHR, 1994; SEIL, 1985;

Raquib, 1999).

3.6 Advantages of Rubber Dam

The rubber dam has several advantages over its use as mentioned below.

• It replaces heavy gates, hoisting gears and piers of conventional structures by

light rubber-nylon shell body. It saves huge amount of steel, cement, timber and

other construction materials. Thus, it has been proved to be a cost effective

technology.

• The dam body can be fully deflated to lower it to flat level on base floor so that

flood flow passes without any obstruction. This provides rubber dams a

dominant position over conventional gated regulating structures.

• Rubber dams can have spans as long as 100 meters without dividing piers. This

provides full width of active cross-section of the river channel to release flood

flow. (Nahar, 2004)

• Load of dam body is evenly distributed on foundation. This lessens treatment

of foundation soil to a nominal or almost none.

Page 33: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

18

• Construction and installation are quicker compared to conventional gated

regulating structures.

• Total investment cost is approximately 30% lower than that of conventional

gated regulating structures.

• No gates and hoisting gears required. So it makes operation of the structure

simple. The dam bag needs very little maintenance. Repair to damages of the

dam bag is simple.

(geosynthetica.net; International Water Power and dam construction)

Cost benefit

• Capital Cost: Inflatable dams can be more cost effective compared with steel

gates.

• Installation Cost: Inflatable dams are quick and easy to install and can be

attached to existing dam crests at marginal extra cost. Minimal skills and

personnel are required to embed the anchorage system and pipe work into the

foundations and to attach the rubber membrane. Quick installation is an

advantage when considering the possibility of fluctuating water levels

interrupting completion.

• Operating Cost: Inflatable dams are economical to operate. The only significant

running costs are power requirements for the air blower or water pump during

bag inflation.

• Maintenance Cost: Inflatable dams are not subject to corrosion compared with

steel shutters that require periodic shutdowns for grinding and painting (with the

possible installation of coffer dams).

(geosynthetica.net; International Water Power and dam construction)

• The rubber dam technology compared to the traditional earthen cross dam, as

opined by the beneficiaries, are reliability and timeliness. The technology is

reliable as it can withstand the flash floods, high tides and surges without being

washed out. The easy inflation- deflation characteristic has resulted in timely

farming activities and also increased the reservoir storage compared to the prior

earthen cross dams.(Saleh, M, A and Mondol, 2000)

Page 34: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

19

3.7 Disadvantages of Rubber Dam

Despite the advantages mentioned above, it has some disadvantages.

• The soft rubber-nylon made shell of the dam body needs careful operation and

maintenance. Large floating materials like logs, trees, bamboos etc. may be

harmful to the dam body.

• Repair to dam bags is done only in dry condition. Underwater repair is not

possible.

• Service life of dam bags is about 20-30 years. Replacement of the dam bag may

be needed if design life of the dam is longer.

• During operation period, boat communication is hampered.

3.8 The Design Principle

For designing a rubber dam basic data shall be collected, processed, analyzed and

studied on the topography, meteorology, hydrology, engineering geology, hydrological

geology, traffic and transportation, comprehensive water conservancy utilization

planning, socio-economic status and environmental appraisal of the area of river basin

where the rubber dam is to be built. Topographic data shall include topographic maps

for the planned project area, the dam site and back water areas, longitudinal and lateral

profiles of the river course, etc.

The design principal of rubber dam is similar to that of any kind of hydraulic structure.

The forces involved in hydraulic structure construction are:

• Surface flow-which causes scour and erosion

• Sub surface flow- which causes seepage, piping, soil boiling.

As hydraulic structure is founded on a permeable foundation, so both the above forces

have to be considered during designing of hydraulic structure. When flow is controlled

by the hydraulic structure then surface flow governs and when flow is stopped then sub

surface flow governs. For designing different components of hydraulic structure

different physical conditions are have to be considered. Such as hydraulic jump height,

hydraulic jump length and hydraulic gradient which determines the floor thickness,

floor length and depth of cutoff wall. The design of rubber dam involves hydrologic

and structural design (super structure & sub-structure). Before designing of the rubber

dam, it is very much important to select the dam site at first.

Page 35: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

20

Selection of Dam Site

Dam site shall be determined after conducting comparative technical and economic

investigations according to rubber dam features and its operation requirements in

consideration of the factors, such as topography, geology, water flow, silt deposition

and environmental protection. The dam should be built preferably on relatively straight

river or channel segment with smooth water flow and stable bank slopes. It is

unsuitable to choose the dam site located on the river segments where scouring and silt

deposition as well as profiles are changing greatly and frequently. Rubber dam site

should be selected on the following considerations:

• The site should be such that the dam at that location can command the

maximum cultivated land.

• The beneficiaries have to be consulted and the site of proposed dam will

provide them the desired benefits of irrigation of the neighboring lands.

• The site should be easily approached by road

• The channel reach should be relatively straight and smooth water flow

• Bank of the river/channel should be stable one

• Land should have uniform slope.

• Optimum utilization of scarce water to derive maximum benefits.

• Canal network should be such that water can flow by gravity.

• When gravity is not possible, water is withdrawn by LLP.

Hydraulic Design

The design data/parameters required for hydraulic design of a rubber dam are as

follows:

Design Data/Parameters:

Design discharge (1:20 year)

Design water level (1:20 year)

Average LWL (March-April)

Average lowest bed level of the river

Water retention level of the project

Soil information

Embankment crests Level.

Cross section of the river up to 7-10 Km U/S and up to 2 Km D/S

Long section of the river

Page 36: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

21

Slope of the water surface of the river

Catchments area of the project ( command area of the dam)

Dam Height

The standard state of the rubber dam should be such that its upstream water level

corresponds to the dam height and its downstream water level is zero and the dam

height under this condition is used as standard dam height and the internal pressure at

this time is used as the standard internal pressure. The standard internal pressure is

usually about 1.5 times as high as the head pressure of dam height for water filled

rubber dam. The dam height is selected from the necessity of the purpose. If the rubber

dam is used as irrigation purpose, the dam height is selected as water retention level of

the project. The water retention level is again selected from land elevation of the

project. As for example the dam height of Pekua Rubber Dam is fixed as four meter

and water retention level is fixed as 3.00 m (PWD).

Length of Rubber Dam

The length of rubber dam shall be so fixed that the sectional area at dam section nearly

equals the average sectional area of the existing river. If the river is flashy, existing

waterway should not constrict for easy passing of maximum flood flow. When the dam

will be in inflated position, design flood for pre-monsoon season should pass over the

dam without causing spillover of the existing bank and shaking of the dam. Maximum

design discharge for 20 year flood is to be considered. Clear water way is determined as

L=4.83Q1/2

, where Q is design discharge. Considering the existing waterway and

considering cross sections of the channel or river at different U/S locations, the length

of the dam is to be fixed.

U/S & D/S Apron Level

U/S & D/S apron level of the dam structure has to be fixed in such a way so that there

will be no appreciable afflux and there by high velocity of flow necessitating energy

dissipation device. However, considering probable adverse situation which occur

during life time of structure, the U/S apron level has been set in average lowest bed

level of the river while D/S apron level is set at less than U/S level as per the necessity

of stilling basin design.

Page 37: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

22

Depth of Cutoff Wall

Depth of cutoff wall is fixed based on design of scour depth which is 1.25 times the

Laceys regime scour depth at upstream of the structure and that of 1.50 times at down

stream. A silt factor of 0.40~0.60 is assumed. Floor length is fixed on the basis on exit

gradient of 1/7 for seepage head equal to the difference of upstream retention level and

design tide level or difference of downstream maximum tide level and upstream

drawdown level whichever is higher during irrigation season.

Floor Thickness

Floor thickness at various parts of the structure is selected considering uplift pressure

computed by Khosla’s theories of independent variable for seepage head as considered

for finding the floor length above. Protective works comprising cutoff wall, inverted

filter and launching apron are designed based on design scour depth.

Strength of Rubber Dam

The main design loads acting on the dam bag are the static hydraulic pressure from

outside the dam bag and the pressure inside it caused by the filled water or air.

• =Design ratio between internal and external water pressure shall be chosen first with

value 1.25~ 1.60 for water filled rubber dam and 0.75~ 1.10 for air filled rubber dam.

Design factor safety is used as not less than 6.00 for water filled rubber dam and that

for air filled not less than 8.00 ( QHEPIL, 1999). Various design parameters for this

kind of dam bags is used from mathematical analysis by using the formulae given

below.

Radial strength of dam bag:

Radial strength Where unit wt. of water Kn/m3

=α Internal pressure ratio= H0

Design height of dam in m

Design tensile strength of rubber bag per meter strip width is

= internal pressure water head in m

=wγ

1H

Ho

=1H

212

1

2

1HT w

−= αγ

( ) KTwarpT = ( ) ( )warpTweftT3

2= 8~5== FSK

Page 38: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

23

The radial strength of rubber Dam is required for determination of the thickness of

rubber sheet and tensile strength of rubber sheet.

Shape of Rubber Bag

The shape of dam bag after inflation is divided into four parts: (1) length of curved

segment of dam surface in the upstream direction S1; (2) length of curved segment of

dam surface in the downstream direction S; (3) length of ground touching segment in

the upstream direction N and (4) length of ground touching segment in the downstream

direction X0.

Effective Circumference (excluding the distance between two anchorage) of the dam

body is L0 = S1+S

Effective length of bottom pad is D= N+X0

Equation of calculation of N, S1, S & X0

••

••

••

• • •

• •

are as follows:

Figure 3.1: Shape of Rubber Bag (QHEPIL, 1999)

)1(2

1

−∂=N H1 S1 θR = if 5.1≤∂ , =θ sin R

N-1 5.1≥∂ , if ,

−= πθ Sin R

N-1

∂−

2

11 S= H1 . ( )2/,πkF

X0

∂+−∂

2

11= H

2,π

kF1 ∂− H

2,π

kE1 ( )14

12

−∂−∂

R= H1

U/S D/S

Page 39: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

24

k2 2

12

∂−∂

=

From this equation the parameters are calculated.

3.9 Components of a Rubber Dam

Rubber dam is mainly divided into four parts. They are:

• Dam body or dam bag

• Anchorage system

• Control system (including water or air filling and emptying system, monitoring

system and safety control system)

• Foundation (including base floor, abutment and side walls etc.).

3D view and schematic diagram of a rubber dam is shown in Figure 3.2 and long

section of Pekua Rubber Dam is shown on Figure 3.3 below.

Figure 3.2: 3D View of Rubber Dam (Nahar, 2004)

Page 40: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

25

25500

56000

80000

5600083000

22000

11000

SECTION S-S (From sheet no. )

4500019000

EL.(-) 1.50

SECTION P-P (From sheet no. )

13500

4000 11000

EL.(-) 1.00

EL.7.50

3000

OVER FLOW PIPE

EL.3.50

CL. OF PUMP HOUSE

10500

PUMP HOUSE

600EL.4.00

450x450x300 CC BLOCK

350x350x350 CC BLOCK(2 layers)

SHEET PILE(4000)

1000

1500

RUBBER BAG ( Inflated position)

GRADED FILTER

4450

EL.(-) 1.00

15000

EL.3.50

6100

SECTION A-A (From sheet no. )

4450

EL.(-) 4.00

500

RUBBER DAM

50040003000500

32001200

EL.(-) 2.00750 EL.(-) 1.00

4000

FOOT BRIDGE

U/S

EL.400

EL.6.00EL.7.00

2250EL.3.50

CL OF STORAGE

2250

WATER STORAGE

EL.4.00

EL.3.00

PUMP HOUSE

EL.7.50

EL3.00

13500

27500

Details "A"1000

SM.AZIZUL HOQUECHECKED

DATE : 16-10-2002S. M. AZIZUL HAQUE

DESIGNED

DRAWNSM.AZIZUL HOQUE

1500

EL.3.00

GEOTEXTILE

450x450x300 C.C BLOCK

60006000

SHEET PILE (8000)

SAND FILTER

EL.(-) 1.00

EE

( MD. MOZAMMEL HOQUE)CHIEF ENGINEER, DESIGNDWG. NO.MIP-RDP- 3147-36

EE

(KAZI GOLAM MUSTOFA)SUPERINTENDING ENGNEERAPPROVED

RECOMMENDED

EE

EL.3.50

400x 400x 200 CC BLOCK

D/S

SHEET NO 36

Figure 3.3: Long Section of a Rubber Dam (Design Catalogue, BWDB, 2003)

Some other Components of Rubber Dam

Besides the four main components, there are some other components, which are

mentioned below.

• U/s and D/s massive concrete floor(Apron)

• Massive concrete base (Dam Base)

• Slope wall

• Inverted filter at river bed

• Filter material

• Bank protection Work

Dam Body

Dam body is made of rubber reinforced by woven synthetic fabric that provides the

tensile strength with rubber acting as the adhesive and water proofing elements. The

fabric reinforcement is used in layers. The layers depend on the design strength

requirements.

Page 41: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

26

3.10 Salient Consideration for Construction of a Rubber Dam Body

The following aspects should be considered during construction of a rubber dam.

• The material should be strong, resistant to tearing / puncturing and should not

deteriorate with exposure to sunlight. It is recommended to use of Ethylene

Propylene Diene Monomer (EPDM) compounded rubber with nylon

reinforcement.

• The body of the dam should be supplied in one unit to avoid the need for site

welding of seams.

• Rubber dam tube is made of high strength canvas and rubber layer that convey

the assurance of airtight.

• Rubber layer include outer layer, middle layer and inner layer.

• Outer layer is the rubber with characteristic heat-resisting, wearing-resisting and

ozone-resisting.

• Middle layer have the function to defend the canvas and joint canvas layers.

• Inner layer defend the canvas and keep watertight and airtight. The layer of

rubber dam is shown in the following

Page 42: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

27

figure

3.11 Fitting and Fixing of Rubber Dam

Anchorage of Dam Bag with Concrete Base

Many types of anchorage system are generally used. Major types are stated below.

Steel Clamps with Anchor Bolts

For fitting and fixing of rubber sheet on the bed, steel clamp elements and stainless

steel anchor bolts and nuts are used. Stainless steel ensures against reduction of strength

of threads of the nuts and bolts by rusting. This arrangement has been shown in the Fig

3.5. Fitting and fixing of rubber sheet are not as simple as like as other construction

work of the rubber dam project. At first, the anchoring slot is kept open for second

stage concrete for positioning and fitting and fixing the anchor bolt with dowel bar of

the slot. Then lower anchoring plate is fixed with the help of anchor bolt and the anchor

bolt is fixed with dowel bar with welding work. The design level of lower plate is done

with the help of level machine and this level is adjusted with the help of bottom nut of

Figure 3.4: Rubber Layers (SEIL, (1985)

Page 43: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

28

anchor bolt. Then second stage concrete is cast up to bottom level of lower plate. The

thickness of lower and upper plate is designed with the height of rubber dam. The

details of fitting and fixing rubber sheet are shown in figure 3.5 & figure 3.6. The

works are done very carefully with maintaining proper alignment of the anchor bolt,

because any deviation of anchor bolts will create problems in fitting of anchor plate.

800

POLYTHINE CAP ON NUT-BOLT AFTER APPLYING GREESEFILLER RUBBER(TH=10mm)

150

500

165

150FILLER RUBBER (TH=10mm)

DOUBLE NUT

BOTTOM PLATE(TH=16mm)

ANCHOR BOLT-25mm Dia

325

200

UPPER PLATE(TH=25mm)30

100

81

RUBBER BAG (TH=12mm)

Figure 3.6: Anchorage System of Rubber Dam (QHEPIL, 1999 )

Figure 3.5: Anchorage System of Rubber Dam (Design Catalogue, BWDB, 2003)

Upper Plate

Lower plate

Anchor bolt

Rubber sheet

Page 44: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

29

Figure 3.7: Steel Clamps with Anchorage Bolts (QHEPIL, 1999)

Concrete Wedge Blocks

This system of anchoring the rubber sheet is old system. It was practiced in China. This

system does not work properly. Slots are provided in the base slab and the ends of the

rubber sheet are anchored by two sets of pre-cast concrete wedge blocks; the front

wedge blocks pressing the rubber sheet against the face of floods and the back wedge

blocks hammered into position ensuring the grip. The slots and the blocks should be in

accurate dimension and sharpness for quality work. For low height dams of simple

hydraulic forces, wooden anchorage blocks may also be used. This arrangement is

shown in the following figure (Figure 3.8)

back wedge Front wedge Wooden blocks Dam bag

Figure 3-8: Concrete Wedge Blocks (QHEPIL, 1999 )

3.12 Filling and Emptying System

The dam bag can be inflated either by filling with air or water. Water filling method

requires fresh water and normally a reservoir is provided with the dam. Where silt or

any foreign suspended materials present in water, then instead of water reservoir a deep

tube well is used for dam body for fresh water filling. Air filling is quicker but it needs

Page 45: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

30

relatively sophisticated pumping and pipe-valve system. Water filling is relatively slow

but ordinary pumps can be used with less complicated pipe-valve system. A centrifugal

pump is used for water filling purpose. Shorter and smaller pumps are used for the

longer filling/emptying time. Generally the dam bag is filled water from the U/S of the

dam. This water is filled through some device in order to avoid silt. To avoid silt, a wire

mesh frame wrapped with geo-textile filter is used on the mouth of the intake pipe.

Filling system also usually includes safety measures against overfilling through

overflow outlets and pressure manometers. A typical filling system is shown in the

following figure (3.9).

DEFLATING BY PUMP

DEFLATING BY GRAVITY

INFLATING

MODE

Pressure pipe

Pump House

EL. 4.00

(-) 4.00

(-) 3.00

(-) 0.65 Pump well

BA

CD E

F

OTHERS CLOSEDE, C, F OPEN

PIPE JOINTREDUCING PIPE

OTHERS CLOSED

OTHERS CLOSEDOPEN VALVES A, C, D, E

OPERATION

E, D, F OPEN

VALVE OPERATION SEQUENCE

REGULATING BALVE

Inlet/Outlet water cap

LEGENDGATE BALVE

7.50{200Ø}

90° BendOverflow pipe

EL. (-) 1.50

Downstream flowOutlet end

90° Bend

3.50

Figure 3.9: Filling and Emptying System of Rubber Dam (Design Catalogue,

BWDB, 2003)

The procedure for operation of the system is as follows:

1) Filling water from upstream into dam bag by pump:

Open valves A, C, D & E and all others will be closed.

2) Emptying water from dam bag to downstream by pump:

Open valves E,C & F and all others will be closed;

3) Draining out of water from dam bag to downstream by gravity:

Open valves E,D & F and all others will be closed at same time.

Page 46: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

31

3.13 Durability and Maintenance

The required strength can be achieved by using materials of varying thickness.

However, practice has shown that using thicker cover has undoubted advantages with

respect to durability. Thinner cover are particularly susceptible to puncture and tearing

damage from hydraulically transported materials. Durability is also improved by use of

best quality of rubber sheet and strong nylon fabric. The nylon gives the fabric its

tensile strength while the synthetic rubber coating provides a resistance to weather,

ozone and abrasion. Layers of rubber coated fabric are bonded together in a sandwich

construction to provide the required tensile strength. Durability also can be enhanced

by providing a special type of cushioning system. This protects the rubber sheet from

tearing and puncturing the rubber bag. A special type of cushioning system is shown in

Figure 3.10. This provides minimum resistance against the current and maximum

protection against damage. Maintenance of rubber dam should be minimal. It should

be easy to repair in case of puncture or tear.

Figure 3.10: Cushioning System of Rubber Dam (SEIL, 1985)

3.14 Foundation

Foundation includes base floor, apron, stilling basin and slope protection. Except base

floor all other components are designed like conventional regulators or barrage.

Page 47: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

32

The width of the base floor should be considered for the requirement of the additional

deformation in dam body. The stability analysis has been made taking into account all

horizontal and vertical loads for the following conditions.

a) Full Operation Condition: Dam bag fully inflated to the design level and full

storage to dam height.

b) Dam Test Condition: Dam fully inflated without upstream storage.

3.15 Flexible Control

Inflation & deflation can be manual or automatically controlled. The automatic control

system can monitor the upstream water level and adjust the air pressure in the dam to

maintain a prescribed water level in the upstream pool.

Figure 3.11: Flexible Control

3.16 Oscillation

The early experience using air filled dam were unsuccessful owing to oscillation caused

during heavy flow because they did not have the ballast that water provided. Also, these

dams suffered excessive premature wear owing to oscillation included abrasion.

Bridgestone provide and answer to this by introducing the “:FIN” into the design.

Oscillation Reduction

When inflated, the FIN structure works as a deflector to create aeration below the fin.

This effectively reduces the phenomenon of oscillation up to a 50% overflow when

compared to FIN-LESS bladders.

Page 48: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

33

Figure 3.12: Oscillation Reduction

3.17 Side Slopes

There are two types of side slope. One type is vertical side slope and the another one is

variable side slope.

Vertical Side Slope

Dams with vertical side slopes have natural disadvantages:

a) Disruption of the natural water flow when opened altering the downstream

movement affecting river bed condition, especially during flooding,

b) Vertical side walls require more supporting members, more reinforcement and

more difficult construction than sloping side walls.

c) Vertical side slopes are less in harmony with the aesthetic of river and thereby

unnatural and

d) Experience has shown that rubber dams with vertical sided are more susceptible

to damage.

Variable Side Slope

Rubber Dams can be installed in rivers with any side slope angle, eliminating the necessity of

modification to river bank, unlike steel gates which can only be installed on vertical side slopes.

Figure 3.13: Variable Side Slope (Nahar, 2004)

Page 49: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

34

3.18 Specification of Rubber Dam

The specification of rubber dam is very much important. Before ordering the rubber

dam body from foreign country, the concerned supplier has to know the specification of

the rubber dam. This specification is made as per design consideration of that rubber

dam. The following specification with respect to stress is mentioned below.

Allowable Stress

• The thickness of the rubber dam body should not be less than 10.00mm and to

be reinforced by not less than 2 layers of nylon canvas.

• Tensile strength in water course direction shall have a safety factor of 8 under

loading condition. The tensile strength in longitudinal direction shall be more

than 2/3 of that water course direction.

• Tensile strength in watercourse direction after heat aging at 1000

• Tensile strength in watercourse direction after hot water aging at 70

C for 4 days

shall be more than 80 % of initial strength and safety factor shall be more than 8

under normal loading condition. 0

• Adhesion between nylon canvas and rubber shall be more than 6 and 4 kg/cm

for 4 days

shall conform to the requirement of tensile strength in watercourse direction. 2

at initial property and under hot water resistance test at 700

• The clamping materials and anchoring bolts shall be of either galvanized steel

or stainless steel material and shall have at least two ridges to form dual sealing

line to prevent any leakages.

C for 4 days

respectively.

• Dual anchoring line is required to cater for the situation when upstream water

level is higher than down stream water level or visa versa.

• Safety factor of clamping bolts shall be more than 3 times against tensile

strength of materials used under normal loading condition.

3.19 Physical Property of Rubber Dam

The dam body shall be of ethylene propylene diene monomer (EPDM) compound or

chloprene rubber or equivalent with nylon reinforcing fabric. An external surface shall

be abrasion resisting nature. The external rubber cover thickness shall not be less than

4.0 mm which forms part of the rubber body ( total thickness shall not less than

10.0mm) and the surface must be textured to reduce the possibility of the debris

Page 50: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

35

dragging across the surface of the rubber body during the fully deflated stage. It should

gain high water resistance for tropical area, high durability and capable of operating in

accordance with the specified conditions, abrasion resistance, tear resistance, impact

resistance, ultra violet resistance. The body shall use water as inflating media. Fin or

deflectors shall be formed as an internal part of the rubber body during manufacturing

of the rubber body, lamination to the rubber body after manufacturing is not allowed.

The clamping plates and anchor plates shall be designed to fix uniformly the body and

transmit hoop tension of the body to the concrete foundations. The clamping plates and

anchor plates shall have complete water and air tight construction at both inflated and

deflated conditions of the body. It shall be liable for deterioration of the rubber

materials throughout the life of the rubber dam.

3.20 Types of Rubber Dams

The rubber dam can be divided into three types. They are:

• Sail type

• Mixed type

• Bag type

Sail type fabric-dam belongs to open category known as sail gate for which the gate-

lifting device is necessary. The mixed type fabric-dam is composed of soft and rigid

structures. The bag type structure is often used for most of the soft-shell hydraulic

structures.

Classification based on the Filling Media:

Based on filling media, rubber dam is of three types:

1. Air filled dam

2. Water filled dam

3. Combined air and water filled dam

Recently air inflated dams are generally constructed. This type of dam is superior to

water inflated dam in terms of the ease of inflation and maintenance but needs

sophisticated pumping unit. But, due to the passage of water over the dam body, air

inflated dams have vibration problems, water filling is relatively slow but ordinary

pumps can be used for filling and emptying.

Page 51: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

36

Air Filled Rubber Dam: Filling media is air. In Thailand this type of rubber dam is

seen. In small stream or small channel, this type of rubber dam gives a good result.

Figure 3.14: Air-filled Dam (Yantai C.S.I. Rubber Co. Ltd)

Water Filled Rubber Dam: Filling media is water. The Pekua Rubber Dam is an

example of water filled rubber dam.

Figure 3.15: Water-filled dam (Yantai C.S.I. Rubber Co. Ltd)

Classification Based on the Number of Bags

In one rubber dam structure there may be single bag (single span) or multiple bag

(multiple span). Multiple bag rubber dam is divided by RCC pier. Figure 3.16 and

Figure 3.17 show Multiple Bags Rubber Dam with dividing Pier.

Page 52: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

37

SECTION S-S (From sheet no.14)

56000

52000

60000

159000

159000186000

12000

60000

13500

600

1000

43000Details "A"

95001000

1500

RUBBER BAG (Inflated position)EL.3.50

2000 1200060000

13500

4300095001000

1500

2000

2950

EL.3.002000

400

SECTION B-B

46000

Details "A"

EL.(-) 1.00

2950

1500

EL.3.50

400

Figure 3.17: Layout of Multiple Bags Rubber Dam with Dividing Pier

(Nahar, 2004)

Figure 3.16: Multiple Span of Rubber Dam (Design

Catalogue, BWDB, 2003)

Page 53: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

38

Classification based on the Form of Dam Tube:

Pillow-like dam:

Figure 3.18: Pillow Like Dam (Yantai C.S.I. Rubber Co. Ltd)

Inclined dam:

Figure 3.19: Inclined Dam (Yantai C.S.I. Rubber Co. Ltd)

Classification based on the Seam of Rubber Bag:

Rubber dam may be another two types, depending on the seam of rubber bag.

• Seamless Rubber Dam

• Seamed Rubber Dam

Seamless Rubber Dam

Seamless rubber dam is mainly used on slope dam over 4 meters high when water

filling is up to certain height, dams over 4 meters high will not only bear lateral strain

Page 54: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

39

on its slope but also form rather great longitudinal strain and cutting force, which will

get the dam bag under complicated supporting-power state.

Seamless rubber dam is formed once for all by the heat presser in the factory, so the

problem of seam joining part will not occur (Nahar, 2004).

Figure 3.20 and Figure 3.21 shows seamless and seamed rubber dam.

Figure 3.20: Structural Sketch of Seamless Rubber Bag (Nahar, 2004)

Seamed Rubber Dam

Seamed rubber dam is formed by adhesion of pieces of adhesive rubber after grinding.

Due to human factors and the limitation of technology, the seam joining part usually

has defects and is easy to be damaged if under complicated supporting-power condition

in the section of slope, which will affect the life of dam bag and will cause the tearing

of the dam bag if under serious condition.

Figure 3-21: Structural Sketch of Traditional Seamed Rubber Dam (Nahar, 2004)

Classification based on the Purpose Served by the Rubber Dam:

Rubber dam can also be classified depending on the purpose of use. Rubber dam can be

used for irrigation, hydro power generation, reservoir etc. Some examples of the use of

rubber dam for irrigation purpose are shown in the Figures 3.22, 3.23 and 3.24.

Page 55: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

40

Figure 3.22: Irrigation Purpose Served by Rubber Dam (Nahar, 2004)

Figure 3.23: Hydro Power Produced by Rubber Dam (Nahar, 2004)

Figure 3.24: Rubber Dam Used as Reservoir (Nahar, 2004)

Page 56: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

41

Chapter 4

Pekua Rubber Dam Project 4.1 General

This chapter gives a brief description of the Pekua Rubber Dam Project, performance of

which was evaluated in this study. It focuses on some salient features of the project,

such as background, concepts, components, purpose, implementation schedule and

expenditure of the project as well as the physical dimensions of the rubber dam.

4.2 Background of the Project

The Matahmuhuri is a hilly and trans border river. It originates from hilly region of

Myanmar and after flowing about 110 km through Myanmar hill tracts and Chittagong

hill tracts of Bangladesh (Figure 4.1), it takes meandering shape near Champabati. At

Champabati it has narrowed down and flows about 37km over the low lying coastal

zone and falls into the Bay of Bengal near Moheskhali-Kutobdia channel. The

Mathamuhuri River then flows to the west from the east under the Chirringa Bridge at

Chittagong- Cox’s Bazar highway and splits into the three branches as the

Mathamuhuri River, the Manikchari River and the Bhola Khal. During the past 30

years, the people of this locality were suffering from scarcity of irrigation water during

dry season. They used to get limited dry season irrigation water by building temporary

earthen dam every year, on their own initiatives, over these three rivers and retained

sweet water with the assistance of local administration. The earthen dam had to be built

in several times in a year. It created several problems in the locality like unplanned

irrigation, water logging, etc. So the local people felt a need of a comparatively better

and sustainable solution of their irrigation problem. In response to the demand of the

local people and on the basis of reality, BWDB took initiatives to implement a full

stage FCDI project on the three branches of the Mathamuhuri River. This project is

known as Mathamuhuri Irrigation Project. The figure 4.1 shows the project map of

Mathamhuri Irrigation Project. Accordingly the final feasibility study on the

Mathamuhuri Irrigation Project was prepared in 1996 with an aim of a detail study on

the technical, economical, social and environmental aspect of the project (IMED,

Page 57: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

42

2007). The project from the beginning emphasized on twin objectives of alleviating the

two most frequently articulated problems of the local people namely:

• A permanent solution of water retention structure instead of temporary earthen

dams on the three rivers which are washed away during monsoon.

• Providing unhampered navigation obstructed by earthen cross dams.

Figure 4.1 Project map of Matamuhury Irrigation Project (BWDB, EPC, 1996)

The project concept focused on these two issues mainly by improving the existing

system of water retention earthen dams the farmers were constructing for last 20 years.

There were a number of additional factors which also came to light due to the

emphasis given in the feasibility report to carryout the inventories of embankments,

structure, irrigation/drainage channels and river training works of the existing polder of

Pekua Rubber Dam

Page 58: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

43

the project and recommendation for further development.(BWDB; EPC, 1996). These

have affected the design of the scheme which could not be kept limited to only the

above mentioned objectives but to some other issues. These issues came out from local

participation program carried out in the field. These were:

• Dissatisfaction among the local people with the way influential people were

able to change the location of earthen dam when it was constructed.

• Failure of local people to construct earthen dam on the Kataferry khal due to

high torrential current compelling them to shift the site to Pekua on the Bhola

Khal.

• Resectioning of deteriorated embankment for prevention measure against flood

and saline intrusion.

• Maitigation of crop failure by removing drainage congestion by re-exavation of

drainage channels.

• Improvement of drainage system by rehabilitation/replacement and

construction of new drainage sluices.

• Improvement of drainage sluices to irrigation inlets modifying the flap gate

lifting system.

• Control of river erosion by river bank revetments.

• Removal of flood detention by loop cut of river.

• Redress of conflict between agricultural farmers and shrimps / salt farmers.

• Poor maintenance of infrastructure.

Considering the above aspects the major highlights of the Matamhuhuri Irrigation

Project were to build a permanent dam instead of earthen dam over these three rivers to

overcome the problems. This permanent dam may be any water retention structure like

Rubber Dam or Barrage (BWDB; EPC, 996). On the basis of recommendation of the

Feasibility Study Report, the main PCP of the Mathamuhuri Irrigation Project with

estimated cost of Tk.8929.357 lakh was prepared during March/1999. The main works

of the project were to construction of rubber dams and development of some other

infrastructure which were directly related to the project. But the Pre-ECNEC meeting,

held on 07/09/1999, considered the project as an expensive one and found that the

whole project was not possible to implement at a time. So, it was decided to primarily

construct a Rubber Dam over the Bhola Khal named as the Mathamuhuri Irrigation

Page 59: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

44

Project (Pilot Project) with an estimated cost of Tk.2243.70 lakh, which was approved

on 20/06/2000. To carry on the decision of the meeting of ECNEC, held on 20/06/2000,

the project of estimated cost of Tk. 2062.27 lakh was recommended for approval in the

meeting of DPEC and accordingly implementation of the project started. But the

project was again revised through the DPEC meeting held on 18/05/2003 with a revised

cost of Tk.2012.88 lakh and its implementation time was extended upto June/2005. The

final cost incurred for this pilot project was Tk.1991.08 lakh (IMED, 2007). The

Figures 4.2 shows the location of Pekua Rubber Dam in Matamuhury Irrigation Project

(Pilot Project).

Pekua Rubber Dam

Km.63.00

P-64/2A

Km.59.00

Km.54.00Km.55.00

Km.60.00KM.61.00

Km.62.00

Km.65.00

Ch. at Km. 55.00....................57.50 mCh. at Km. 56.00....................65.00 mCh. at Km. 57.00....................61.00mCh. at Km. 58.00....................59.00mCh. at Km. 59.00....................54.00mCh. at Km. 60.00....................42.00mCh. at Km. 61.00....................36.00mCh. at Km. 62.00....................39.00mCh. at Km. 64.00....................31.00mCh. at Km. 65.00....................35.00mCh. at Km. 66.00....................65.00mCh. at Km. 67.00....................78.00m

P-65

Bhol

a Kh

al

PEKU

A

MAN

IK C

HARI

RIV

ER

Figure 4.2 Location of the Pekua Rubber Dam in Matamuhury Irrigation Project (Pilot Project) (BWDB, 2004)

4.3 Dimension of Pekua Rubber Dam Project

The physical feature of the Pekua Rubber dam is given in Table 4.1. The dam is 83

meter long and 4 meter in height. It is a single span dam where centre to centre distance

N

Page 60: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

45

is 6.1 meter. It can provide irrigation facilities to grossly 1400 ha of land and its net

coverage of area is 5000ha.

Table 4.1: Physical Features of Pekua Rubber Dam

Length 83 meter

Height 4 meter

Span Single

Distance between centre

to centre of slot

6.1 meter

Area coverage Gross 14000 ha, net 5000 ha

4.4 Project Concept

The overall approach to development of the Matamuhuri Irrigation Project (Pilot

Project) was based on a number of concepts, which were as follows:

• The operation of the scheme should be as simple as possible with minimum

interventions required for satisfactory operational functions.

• Optimum utilization of scarce water to derive maximum benefits,

• Proper water distribution at minimum structural cost so that operation and

maintenance cost may be brought down to minimum taxation limit when

management and supervision can be taken up by the Water User Association

(WUA).

4.5 Components of the Matamuhuri Irrigation Project (Pilot Project)

The feasibility report of the Matamuhuri Irrigation Project included a number of

components like barrage/rubber dams for gravity flow with water distribution by

gravity from canals system or Low Lift Pumps (LLP) with unhampered navigation. The

consultants proposed for options of barrage or rubber dam. These were proposed to be

constructed at Pekua on Kataferry khal, at Chowdhury Hat on Manikchari River and at

Palakata on the Matamuhuri River in consideration of public demand (BWDB; EPC,

996). Finally on the basis of the PCP approved by ECNEC a rubber dam was built on

the Bhola Khal near Pekua upazilla, considering the following aspects (IMED, 2003):

• Command of maximum cultivable land

Page 61: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

46

• Strong Public demand

• Easy approachable road to and from the dam site

• Easy construction opportunity with keeping the river flow as it

• Minimum land acquisition

• Cost effectiveness

4.6 Purpose of the Pekua Rubber Dam

The main objective of this project was to control the flood, drainage improvement,

provide irrigation facilities to boro crop cultivation during dry season (November to

May) through retention of sweet water in the upland river system and prevention of

ingress of saline water and improve fisheries by providing proper irrigation in the area

of Pekua under Cox’s Bazar District. The benefited area of implemented 1st stage of

this Project is gross 14000 ha and net 5000 ha.

4.7 The Project Implementation Time and Expenditure

Table 4.2 shows the expenditure and time line of the Matamuhury Irrigation Project

(pilot project).

Table 4.2: Implementation Schedule and Expenditure of Pekua Rubber

Dam Project

Estimated Cost ( in Tk.Lakh)

Real Expenditure

( in Tk.Lakh)

Planned Implementation Time

Real Implementation

Time Main Last

Revised

Main Last Revised

1 2 3 4 5 6

2062.27 2012.88 1991.08 2000-2003 2000-2005 2000-2005

Initially plan was made to implement the Pekua Rubber Dam Project in a three years

time period spanned over 2000 to 2003. Later on the project implementation time was

revised and extended up to June/05. The actual construction of the rubber dam

commenced in November 2003 and was completed in June 2004. The Pekua Rubber

dam started its functioning from November 2004. The total time for construction of the

Page 62: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

47

dam was eight month (field data). Figure 4.3 in shows a picture of the Pekua Rubber

Dam during its construction period.

Figure 4.3: Pekua Rubber Dam (BWDB)

Page 63: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

48

Chapter 5

Methodology

5.1 General

This chapter describes the research methodology followed in the present study. It

includes the description of research design, research location/area, population, sample

and sampling technique, data gathering techniques and tools, data analysis procedure,

criteria/indicators of evaluation, etc. as adopted in this study.

5.2 Research Design

This study made use of a descriptive research design to evaluate the performance of the

Pekua Rubber Dam in terms of its design, operation and maintenance aspects as well its

impact on socio-economic life of the people, local agriculture and environment of the

project area of the rubber dam. To this end this study used the procedures of both

quantitative and qualitative analysis to determine the efficiency of the project.

5.3 Research locale

The study was conducted in the catchments area of the Pekua Rubber dam located in

the Pekua upazila of Chittagong Hill Tracts. The people live in that catchments area

served as the population of this study.

5.4 Sample and Sampling Technique

The sample size, who responded to the questionnaire, of this study was 50. The

respondents were selected from among the beneficiaries and stakeholders of the project

living in the project area. Besides, groups of stakeholders, BWDB officials and staff

(design, operation and maintenance officers and staffs), NGO people, agriculture

extension department people and people related with fisheries were consulted and

discussed to get qualitative data for conducting the study. Purposive sampling

technique was employed in selecting the sample and others.

5.5 Data Gathering Techniques and Tools

Data gathering process involved collection of both primary and secondary data. For this

a list of indicators was identified first. Based on the indicators a questionnaire was

Page 64: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

49

developed for primary data collection. The secondary data were also collected based on

the identified indicators. The procedures followed in primary and secondary data

collection are described below.

5.5.1 Primary Data Collection

Primary data were collected through a questionnaire administered on 50 respondents. It

included both quantitative and qualitative types of inquiry for assessment of the impact

of the Pekua Rubber Dam on socio-economic status of the stakeholders as well as local

agriculture and environment. Data on the technical status of design, operation and

maintenance were collected through discussion with the stakeholders and related people

like designers, local BWDB office staff, concerned BWDB Executive Engineer and

concerned Sectional Officer of Pekua Rubber as well as through field visit and

observation. Besides, discussion was made with local agriculture extension officer and

concerned staff of that office. The researcher himself collected the data through field

visit and with the help of local people and field officials.

5.5.2 Secondary Data Collection

Secondary data were collected through literature review of IMED report, design report

of the Pekua Rubber Dam, other related reports and feasibility study of the Matamuhuri

Irrigation Project.

5.5.3 Indicators

The criteria/indicators selected as the basis for data collection were as follows:

• Yearly income increase of the people

• Range of yearly increase

• Employment opportunity

• Poverty level

• Agricultural production before and after the project

• Boat Navigation

• Movement of people

• Fish and fisheries activities (production, migration, biodiversity).

• Changes in amount of cultivable land

Page 65: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

50

• Vegetation coverage and other natural resources.

• Water retention, water supply to the agricultural land.

• Local weather

• Upstream water retention level maintenance.

• Design parameters of Pekua Rrubber Dam.

• Constructional aspects of Pekua Rubber Dam project.

• Institutional aspect, such as water user group formation (WUG).

• Management of operation and maintenance of Pekua Rubber Dam.

• Maintenance of the Rubber Dam.

• Stakeholders’ participation in maintenance of the project.

5.6 Data Processing and Analysis

Both the primary and secondary data were processed based on the indicators and

inquiries of the questionnaire. In analysis of data simple descriptive statistics like

frequency and percentage distribution were used. Details of the data and their analysis

and interpretation are presented in the following chapter (Chapter 6).

Page 66: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Chapter- 6

Result and Discussion

6.1 General

This chapter presents, analyzes and interprets the data collected against the research

objectives of this study. They are discussed under three major sections (6.2, 6.3 and

6.4). Section 6.2 deals with the findings on the technical aspect of design of the Pekua

Rubber Dam as well as its construction problems and their mitigation. In section 6.3 the

operation and maintenance aspects of the rubber dam has been described. Section 6.4

presents the findings and analysis of the data collected for evaluation of the impact of

the rubber dam on socio-economic life of the people living in the project area as well as

on local agriculture and environment.

6.2 Assessment Result of the Technical Aspect of Design of Pekua

Rubber Dam and Its Constructional Problems and their

Mitigation

Technical aspect of design considered for any construction has important implication

on the durability and functionality of that project. The Pekua Rubber Dam was

designed by Design Circle-2 of Bangladesh Water Development Board. It was

constructed by Cox’s Bazar Division of BWDB and is being operated and maintained

by that division. In designing the Pekua Rubber Dam various design parameters, such

as design water retention level, discharge were considered. On the basis of these design

parameters, the dam height, length of the dam, the total floor length, the depth of cut-

off wall, the detailing of rubber dam body, the geometric shape of dam, etc. were

computed by the concerned design engineers (Design Report, 2003). Whether these

design parameters were properly selected by the design engineers in the light of

technical aspect were evaluated as part of this performance assessment study. This was

done by reviewing the design report of the Pekua Rubber Dam Project and by

conducting discussions with various groups of people, like the design engineers, field

engineers and technicians, pump operator, stakeholders, NGO people, BWDB staff, etc.

involved directly and indirectly with design, implementation, operation and

maintenance of the dam. In the following paragraphs, the design parameters, considered

for design, and their assessment results are discussed briefly.

Page 67: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

52

6.2.1 Water Retention Level

One of the major design parameters was consideration of water retention level of Pekua

Rubber Dam. The water level was considered from the project land elevation. The land

elevation varies from + 1.80 m (PWD) to 2.0 m (PWD) near the dam site, +2.00 m

(PWD) to 2.50 m (PWD) in the middle part of the project area and 2.50 m (PWD) to

3.00 m (PWD) on the U/S area of the project. The U/S part of the project area is higher

elevation. The average elevation of the whole project is 2.50 m (PWD). In order to get

available water to the whole project area, the proposed water retention level was

selected by the designer as 3.00 m (PWD) (Design Report, 2003). The criteria of

selection of this water retention level were made through open discussion with various

groups/levels of beneficiaries or stakeholders of the project by the field office. The

objective of this water retention level was to supply irrigation water to cultivable land

of the U/S area of the project by LLP and near the dam site area with simple gravity

system. On the upper part of the project area, water is supplied to the intake channel

through inlet structure. Stakeholders/beneficiaries irrigate their lands by using LLP

installed on both of the banks on the main channel (Bhola khal) as well as intake

channel in this area. On the other hand, stakeholders/beneficiaries of the dam site area

used irrigation water by simple gravity system by cutting earthen drain from the

distributor channel system with controlling the flow of water through gated inlet/outlet

structures whenever needed. Through open discussion with the stakeholders and other

groups of beneficiaries as well as the groups of people involved in operation and

maintenance of the project no problem was found regarding irrigation of their own

lands, in terms of water retention level. From the above discussion it is clear that the

design water retention level of Pekua Rubber Dam i.e. +3.00 m (PWD) is quite satisfied

for their irrigation scheme. So, the consideration of design parameter in the light of

technical ground for keeping water retention level +3.00 m (PWD) could be considered

as ok.

6.2.2 Length of the Rubber Dam

The length of the Pekua Rubber Dam was fixed on the basis of some criteria. Since the

Bhola Khal is flashy river, the design engineers decided not to constrict the existing

waterway for easy passing of maximum flood flow. The design discharge was also

considered for deciding the length. The maximum design discharge for 20 year flood

for this structure was considered as 306 cumec. Clear water way was determined as L=

Page 68: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

53

4.83Q1/2 = 4.83x3061/2= 84.49m (Design Report, 2003). Considering the existing

waterway and considering cross sections of Bhola Khal up to 8-10 Km of U/S at

different locations and keeping the existing conveyance of the Bhola Khal

uninterrupted, the length of the dam was fixed as 83.00m (Design Report, 2003). As till

to date no morphological change at dam site (erosion / deposition) was seen and no

protective work was needed at the dam site. So, this length of the Dam satisfies the

design parameter consideration for design work (These information is collected from

filed office). These findings support that the design parameters for designing of Pekua

Rubber Dam (Discharge and cross section) for determining the length of dam are ok.

6.2.3 Height of Rubber Dam

The height of the Pekua Rubber Dam was fixed on the basis of necessity of Water

Retention Level (WRL). WRL was fixed as 3.00 m PWD on the basis of project land

elevations. This WRL was selected by field office through open discussion with various

groups of people living in the project area. Before construction of the Pekua Rubber

Dam, local peoples used to build earthen cross dam on this point every year. These

cross dam levels were reviewed by the field office for selection of the dam height. In

this area ground level (GL) varies between. 2.00m ~3.00 m PWD, so irrigation to the

cultivable land by means of gravity flow or LLP installed on both banks of ponded

channel. Keeping WRL as 3.00 m (PWD), dam height was fixed as 4.00m with top

elevation 3.00m (PWD). Dam height is directly related for storing water in the channel

and which is also responsible for supplying of irrigation water to the cultivable land.

Through open discussion with beneficiaries/stakeholders of the project and concerned

field officials, it was found that the height of Pekua Rubber Dam was ok in respect to

supply of irrigation water to the cultivable land through maintaining desired water level

in Bhola Khal and other branches of the khal. This satisfies the design parameters

consideration for planning concept of the project. Because, there raised no problems

regarding supplying irrigation water to the cultivable land. So, it can be assumed that

the design dam height with respect to the water retention level (design parameter) is ok

(Design Report, 2003)

Page 69: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

54

6.2.4 Thickness of Rubber Sheet and Geometrical Shape of Water

filled Rubber Dam

Various design parameters for determining the thickness and shape of the Pekua

Rubber Dam bags were used through the use of the formulae given in the chapter-3

(Para 3.2.7, the design principle). Radial strength of dam bags was calculated as 560

Kn./m of rubber dam. From this radial strength the design thickness was calculated as

12mm.The shape of dam bags after inflation was divided into four parts as mentioned

in the figure 3.1 in chater-3. Length of curved segment of dam surface in the upstream

direction S1=6.41m, length of curved segment of dam surface in the downstream

direction S=6.80m, length of ground touching segment in the upstream direction N and

length of ground touching segment in the downstream direction X0 were determined

considering the design parameters. Effective Circumference (excluding the distance

between two anchorage) of the dam body was decided as L0 = S1+S=13.21m.

Effective length of bottom pad was calculated as D= N+X0=6.10m (Design Report,

2003). Calculations of N, S1,S & X0 were taken from the equations mentioned in the

formulae in the chapter-3 (Para 3.2.7, the design principle).

From these equations the above parameters were calculated as follows:

D= 6.10m, H1= 4.00m (dam height), H0= 5.80m, Radial Strength = 76 Kn/m with FS

5~ 8 it was designed T(warf) = 560 Kn/m, • = 1.45 was considered. S=6.80 m S1=

6.41m (Design Report, 2003).

Here design parameters like, water retention level which again related to dam height

was considered for calculating the rubber thickness of rubber sheet.

Through open discussion, on functioning of the rubber bags, with the concerned field

officials of BWDB and the beneficiaries of the project, it was found that till to date

there did not happen any puncture of the rubber bag body. It was also learnt from the

concerned field officials that during commissioning of the dam, the geometrical shape

dimensions of the bags were measured and found ok. These assessment results of the

parameters reveal that the design parameter as selected by the design engineers in

respect to determine the thickness of rubber dam body as well as its geometrical shape

was appropriate. So, it was ok with respect to technical aspect of the design.

Page 70: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

55

6.2.5 Site Selection of the Pekua Rubber Dam

In designing and construction of the Pekua Rubber Dam, proper selection of the

location/site was considered with due importance. This was done in consideration of

the points mentioned in the feasibility study report of the dam. For example, the site

should be such that the dam at that location can command the maximum cultivated

land. The beneficiaries should be consulted and the site of proposed dam will provide

them the desired benefits of irrigation of the adjacent lands. The site should be easily

approached by road. The channel should be straight reach and stable channel. Land

should be uniform sloping for optimum utilization of scarce water to derive maximum

benefits. Canal network should be such that water can flow by gravity. When gravity is

not possible, water will be withdrawn by LLP. Lastly, considering all the parameters

and through open discussion with all beneficiaries residing in the project/dam the site

was selected at ch. 53.881 km on Bhola Khal of Pekua, location of which could be seen

in figure 4.2 in Chapter 4. Through open discussion with various levels of beneficiary

groups and NGO and GO officials and staff it was clear that until now no problem with

respect to supplying of irrigation water to the whole project created. So the selection of

site could be termed as proper and suitable for achieving the project objectives. In other

words the selection of site was appropriate in terms of the parameters considered during

selection as well as from the technical background.

6.2.6 Floor Length of Pekua Rubber Dam

The total floor length was computed based on Exit Gradient of 1/7 for seepage head

equal to the difference of upstream retention level and design tide level or difference of

down stream maximum tide level and upstream drawdown level whichever is higher

during irrigation season. By using Khosla’s theory

Where

Where H = Design head.=4.50m (dam height+ spillover) D = Length of cut-off wall.

b= floor length. Depth of cut-off wall was selected as 8.00m at D/S and 4.00m at U/S.

From this formulae and considering some additional factors of safety the total floor

λπ1

.d

HGE =

.2

11 2αλ

++=

d

b=α

Page 71: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

56

length was computed as 45.00m (Design Report, 2003). Here design parameter like

design head, which comes from water retention level was considered for determining

the floor length.

There was no reported sign of seepage under the foundation of the dam during

maximum head difference. This head difference was created in the time of rubber dam

commissioning (U/S fully ponded and D/S was remained dry). This maximum head

difference was the critical condition of WRS. In this situation as there was no sign of

seepage under the foundation it may be concluded that the design floor length was ok

with respect to design computation and in consideration of the design parameters.

6.2.7 Foundation Design

In the soil test as well as during foundation work of the dam the soil below the

foundation of the rubber dam was found very weak. From bore log it was explored that

up to 37 feet from the existing bed level of the channel, the N value was 0 to 1. Type of

soil was clay traced silt (Soil Investigation Report, 2002). Due to the weak soil the

foundation treatment was needed for construction of the dam. Acute problems during

construction of foundation were faced by the site and construction engineers. Soil was

found very weak to bear the foundation of the dam. To avoid seepage flow due to high

head difference under the foundation no RCC pile was used (Design Report, 2003) in

foundation construction. This was done based on an experience of a hydraulic structure,

done by BWDB, located at Borguna and Patuakhali, where RCC pile was used under

the drainage sluice and after some years of construction, seepage flow was seen below

the foundation of this sluice. As a result of this problem presently the sluices are not

working at all and are standing above the RCC pile. From this experience and

considering a big head difference, the concerned design engineers decided to use sand

pile instead of RCC pile under the foundation (Design Report, 2003). Sand pile of this

site also faced some problems. As the soil was clay and the site was on the river bed,

the rate of pore water release was slow. After sand piling, soil test was done and

foundation soil was found improving (SPT value range 4-10). Under this situation the

allowable bearing capacity of soil under the foundation was computed by using

empirical bearing capacity equation with one inch tolerable settlement (Terzaghi and

Peck, 1948).

Page 72: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

57

Terzaghi & Peck Equation For 25 mm settlement

Where qa

Figure 6.1: Driving of sand pile of Pekua Rubber Dam (Design Catalogue,

BWDB, 2003)

= Allowable bearing capacity of soil below foundation of dam body.

N = SPT value (From Soil Investigation Report, 2002)

The construction of dam was completed in June-2004. Till now no sign of seepage

under the foundation or any crack on foundation was reported by the concerned field

office. So, the foundation design could be considered as ok with respect to the design

parameter considerations. Some procedures of sand piling are shown as steel pictures in

figures 6.1 and 6.2.

( )

+

−=B

BNqa 2

13720

Page 73: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

58

Figure 6.2: Driving of sand pile of Pekua Rubber Dam (Design Catalogue,

BWDB, 2003)

6.2.8 Assessment of Construction Problems and its Mitigation

The construction process including the period of implementation, problems faced

during construction and the ways of mitigation have been presented in the following

paragraphs.

The construction work of the Rubber Dam was started during November - 2003 and

completed in June - 2004. As reported by the field office, at the beginning of the

construction work, two earthen cross dams were built on both the U/S and D/S of the

dam. During construction, the U/S cross dam was damaged due to flash flood. First

time the cross dams were built near to the main structure. The seepage water was

continued to flow from the cross dams. Second time the cross dams were built 50

meters away from the dam structure site. These dams were successfully implemented.

Some acute problems were faced during the foundation works. As the dam had to

construct on the existing river bed, a huge amount of water had to be bailed out. The

bed materials were very soft clay with traced silt. The SPT value was 0 to 1. The

foundation treatment was needed. As mentioned in para 6.2.7 RCC pile for hydraulic

structure was not good and faced seepage problems, it was decided by the design

engineers to provide sand pile instead of RCC pile for the foundation work (Design

Report, 2003). Sand piling also faced some problems. As the soil was clay, and the site

Page 74: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

59

was on the existing river bed, the rate of pore water release was slow. Result of the first

time sand piling was not satisfactory. Second time modified design of sand pile was

done. According to the modified design sand pile was executed with the supervision of

expert design engineers. After execution of sand piling work, foundation soil was found

improving and the SPT value range finally reached at 6 to 8. This SPT value was

satisfactory for this raft foundation.

There are also some other limitations in case of construction of a rubber dams. The

construction of rubber dam is not so simple as it requires some special supervision by

the foreign experts during fitting and fixing of the rubber sheet and commissioning of

the rubber dam. Moreover, the rubber sheets are not manufactured in Bangladesh and

need to import from foreign countries, whereas the construction materials of water

retention structure (regulator, barrage) are available in the local market in our country.

However, these construction problems could easily be minimized through a time bound

work plan as was done for Pekua Rubber Dam Project. Besides, the need of foreign

experts could be supplemented by developing expert people in the country.

Despite some construction problems, rubber dam construction has some positive

aspects in terms of construction time and cost. For example the actual construction time

of the Pekua Rubber Dam was from November-03 to June-04 i.e. only eight month was

needed for construction of this structure. But, if a barrage was constructed in that place

instead of the rubber dam, this short time (eight months) would never allow

constructing a barrage. It would have taken at least two years to complete the

construction. The reason for lesser time for construction of a rubber dam is that there is

no need of construction of any RCC super structure as well as additional structure like

piers, installation of steel angles and channel in piers and bed, vertical lift gate

assembly of the gated water retention structures which are time consuming and

laborious. In the rubber dam only RCC work in foundation is needed, which was done

in a month. In respect to costing, the construction cost of a rubber dam is much lesser

than a conventional RCC barrage. A comparison of the cost between a rubber dam and

a RCC barrage at Pekua was made in the feasibility study report of Matamuhuri

Irrigation Project, Vol-2, page 11-20) by BWDB through a consulting firm EPC

(BWDB, EPC.1996). In this comparison, the costing of rubber dam was found

Page 75: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

60

Tk.6,21,40,830/ and the costing of RCC barrage was Tk.11,35,45,000/, almost double

of a rubber dam cost.

From the above findings and analysis it is clear that despite some constructional

problems, rubber dam is less costly and time saving irrigation structure than traditional

irrigation structure. This finding also found supported by the discussions included in

literature review and in technical aspects of rubber dam. For this rubber dam is being

implemented in many countries (China, Korea, Canada, etc.) by replacing barrage and

other traditional kind of irrigation structures for irrigating agricultural land. So,

Bangladesh can effectively make use of rubber dam as a cost effective and short term

technology for solution of its irrigation problem, particularly in the hilly regions.

6.2.9 Fitting Fixing of Rubber Sheet

Fitting and fixing of rubber sheets is not as simple as like as other construction work of

the rubber dam project. At first, the anchoring slot is kept open for positioning, fitting

and fixing of the anchor bolts with dowel bar of the slot. Then lower anchoring plate is

fixed with the help of anchor bolt and the anchor bolt is fixed with dowel bar with

welding work. The design level of lower plate is done with the help of level machine

and this level is adjusted with the help of bottom nut of anchor bolt. Then second stage

concrete was done up to bottom level of lower plate. The thickness of lower plate of

Pekua Rubber Dam was designed as16mm. The thickness of upper plate was designed

as 25mm. The details of fitting and fixing rubber sheet are shown in figure 6.3 (Design

Report, 2003). The fitting fixing was done with the help of foreign experts. The works

were done very carefully with maintaining proper alignment of the anchor bolt, because

any deviation of anchor bolts can create a problem for fitting anchor plate. This work

was done successfully by local experts with the help of foreign expert. During

commissioning of the Pekua Rubber Dam, a sign of water leakage was noticed. Then

the rubber dam was deflated and the top nut of the bolt was tightened. When the dam

was inflated again, no water leakage was noticed. It was learn from field officials that

after commissioning of the rubber dam, no problem related to fitting & fixing of the

dam was noticed. So this procedure of work could be considered as ok with respect to

technical ground.

Page 76: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

61

600

63

98 400 98400

DETAILS OF 25mm DIA ANCHOR BOLT

996

TYPE 'D' PLATE (UPPER & LOWER PLATE)

325

6320

0

200

D10 MS plain bar welded to upper plate

D10 MS plain bar welded to lower plate

200

SECTION A-A

200

ANCHOR BOLTMaterial : AISCA 325

325

UPPER PLATE(TH=25mm)

POLYTHINE CAP ON NUT-BOLT AFTER APPLYING GREESE

200

30

100

RUBBER BAG (TH=12mm)

FILLER RUBBER(TH=10mm)

81

BOTTOM PLATE(TH=16mm)

ANCHOR BOLT-25mm Dia

DOUBLE NUT

LEAN SAND CEMENT(1:6) MORTAR

Figure 6.3: Details of anchoring plate and anchoring bolt for fitting & fixing

rubber sheet for rubber dam (Design Catalogue, BWDB, 2003)

Page 77: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

62

6.2.11 Fixation of Level of Over Flow Pipe and Procedure of

Commissioning Work

The fixation of level of over flow pipe was done through trial and error method. First

from the design calculation, the design level was fixed. With this level water was filled

in the bags. The level of height of bags was measured. If desired height was not found,

then the level of over flow pipe was adjusted until getting the desired level of the dam

body. After getting the desired height of the dam body, the over flow pipe was

permanently fixed. This work was done at dry condition as well as in water retained

position (Commissioning of the pipe is shown in the Figure 6.4). This was successfully

done as per field report. Through the open discussion with the beneficiaries/

stakeholders of the project and also with concerned filed officials of BWDB, there

found no problem for irrigation water supply to the cultivable land. As the water supply

by this dam is directly related with its height and the dam height is controlled by this

over flow pipe, so from the findings it is concluded that the level fixed for over flow

pipe and the procedure of fixation were done properly from technical viewpoint.

Figure 6.4: Commissioning of Pekua Rubber Dam (BWDB, 2003)

Page 78: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

63

6.3 Assessment Result of Operation and Maintenance of

Pekua Rubber Dam

The state of operation and maintenance of the Pekua Rubber Dam was assessed on the

basis of various aspects related to their operation, maintenance and management. The

assessment findings have been furnished in the following paragraphs under three sub-

headings, namely (1) Institutional aspects of operation maintenance of Pekua Rubber

Dam (6.3.2), (2) Operation and management system of Pekua Rubber dam (6.3.3), and

(3) Stakeholders’ Participation in the management of Pekua Rubber Dam (6.3.4). In

addition, a brief theoretical and functional description (6.3.1) of the operation system of

Pekua Rubber dam has been attached at the beginning of the following discussions.

6.3.1 Operation System of Pekua Rubber Dam

Operation of a rubber dam means inflating and deflating of the rubber bags. Inflating of

rubber bags means, increase the height of rubber dam body by filling the rubber bags

with water or air for water retention during irrigation season. Deflating the rubber dam

means decrease in the dam height by taking out air/water from rubber dam bags. For

operation of the Pekua Rubber Dam, a centrifugal pump has been installed for both

inflation and deflation of the rubber bags with water. This pump has been installed in

the pump house built near the rubber dam site. Water is drawn from the channel bed

through the intake pipe lines from water storage. The inlet and outlet PVC pipes and

other accessories which are used in inflating and deflating the rubber dam are shown in

Figure 3.9

The inflating & deflating position of the Pekua Rubber Dam have been shown in

Figures 6.5 & 6.6. Figure 6.5 also shows a water retained condition of the dam for

irrigation in the catchments area of Bhola Khal, on which the dam is located. Deflating

is also required partly to release major flash floods and to remove inundation in the

depression areas in the upstream of the dam during irrigation period. Deflating is

required fully during the monsoon when the empty dam bags lie flat on the foundation

level to allow free flood flow and boat communication when there is no more necessity

of water retention for irrigation purpose. Outlet valves are opened to deflate the rubber

dam when water comes out of the rubber bag automatically by gravity. When water

does not come out of rubber bag by gravity system, then pump is to be operated for

Page 79: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

64

outing the water from bag by manipulating the valves (Fig. 3.9). The pump operator

operates this pump when necessity. The rubber dam is inflated in the month of

November to close Bhola Khal for water retention and deflated to bed level to open the

channels for navigation in late May every year.

Figure 6.5: Inflated Pekua Rubber Dam for retention of U/S water (BWDB, 2003).

Page 80: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

65

Figure 6.6: Deflated rubber dam (BWDB, 2003)

6.3.2 Institutional Aspect of Operation and Management of Pekua

Rubber Dam Project

The Pekua Rubber Dam has been constructed by Bangladesh Water Development

Board. This Project is under the jurisdiction of Bhadarkhali Water Development Sub-

Division under Cox’s Bazar Water Development (WD) Division. Cox’s Bazar WD

Division is under the jurisdiction of Chittagong Operation and Maintenance Circle. One

Superintending Engineer (SE) is posted in this circle. Again this circle is under the

jurisdiction of Chief Engineer, South Eastern Zone, Chittagong. The Chief Engineer is

under Additional Director general (ADG), O & M-1 and the ADG is under the Director

General (DG) of BWDB. There are three Section Officer’s Office under the

Bhadakhali Sub-Division. One of the Section Offices of this sub-division is located at

Pekua Up-Zilla. The Rubber Dam is under the jurisdiction of this office. The primary

responsibility of O & M of this dam is lying upon this Section Office. All activities

concerned to the operation and maintenance of the dam are done through the concerned

Division Office. The span of organizational chart of BWDB related to the Pekua

Rubber Dam is given below as Fig. 6.7.

Page 81: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

66

Figure 6.7: The organizational chart of BWDB for operation and maintenance of

Pekua Rubber Dam (BWDB)

There is a pump operator under Pekua SO office to operate the pump machine of the

dam. The pump operator is not a regular employee of BWDB. In the standard set up of

BWDB there is provision of some permanent posts for pump operator. Despite this

provision, no permanent pump operator was appointed for running the pump machine

of the dam. The practice as found is that the concerned BWDB officials hired pump

operator(s) from the local area of the project on master role basis. He received some

training in respect to the operation of the pump machine of the rubber dam. Thus the

dam is being operated by temporarily appointed operator(s). As quoted by the field

officials, this irregular system of operator appointment creates some problems. As the

pump operator is not a regular employee, he may escapes or remains absent for some

days during the irrigation period. Then a crisis may occur in absence of a permanent

pump operator. A sense of job insecurity also prevails in him. This creates mental in

him, which may create some other irresponsibility. So, there is a need to resolve this

situation with required departmental initiative.

All operational and maintenance activities of the Pekua Rubber Dam are performed by

the concerned SO office with maintaining proper official communication and

coordination with the Divisional Office of Operation and Maintenance. Any problem or

dysfunctionality of the rubber dam during operation and maintenance as well as

Cox’s Bazar WD Division

HQ Sub-Division Badarkhali Sub-Division Kutubdia Sub-Division

HQ SO office Chiringa SO office Pekua SO office

Pekua Rubber Dam Project

Page 82: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

67

resolving the problems lie on the SO and Divisional Office. But as found through the

discussion with the Divisional Engineer and SO, no mentionable problem created

regarding operation and maintenance of the dam, which means the institutional

arrangement of BWDB was supportive to proper functioning of the rubber dam. But

one finding, significant to mention, came out of the discussion was that in absence of

appointment of any full time pump operator, the operation of the pump might suffer in

the long run. It may affect both the internal and external efficiency of the functioning of

the dam.

6.3.3 Operation and Management System of Pekua Rubber Dam

The Pekua Rubber dam project has no local level operation and management

committees like Block Management Committee (BMC), Operation Management

Committee (OMC) and Central Management Committee (CMC). Operation of the

project is done in coordination between the BWDB local officials and the local

administrative unit [Thana Nirbahi Officer (TNO)]. When the stakeholders are in need

of water for irrigating their land during dry season, they make contact with the local

TNO and concerned BWDB officials for operation of the rubber dam. Then the TNO

makes request to the BWDB field officials to operate the dam. As per the request from

the TNO the concerned BWDB officials takes initiative to activate the pump.

Thereafter the stakeholders start to irrigate their farmlands through the khals and

channels. For this irrigation purpose they do not need to pay any charge or fees. The

Rubber Dam is kept in inflated position at starting time of irrigation and is deflated as

per requirement of the stakeholders during monsoon period. The main purpose of this

dam is to provide irrigation facilities to boro crops during dry season (Nov-May)

through retention of sweet water in the upland river system (Bhola Khal) and

prevention of saline water intrusion from downstream.

During the functioning of the Pekua Rubber Dam Project, as was reported, a number of

aspects related to its operation and maintenance occurred. They were: damage and

repair of rubber dam body, disorder and repair of pump, silt deposition over dam body,

over U/S and D/S stilling basin, clogging of foot valve, etc. How were the magnitudes

of these problems and what measures were needed to be taken to mitigate the problems

Page 83: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

68

were assessed also as part of this evaluative study. Findings from this assessment are

presented in the following subsections.

6.3.3.1 Damage and Repair of Rubber Dam Body

Damage of any material is a common phenomenon. It can happen any time from any

reasons over time and use. The Pekua Rubber Dam has possibility of damage of rubber

bags from many reasons such as trespassing of the local people over the rubber dam

area, walking over the rubber bag and throwing of brickbats on the rubber bag. There

also have the tendency of cuts and leakage in the rubber bag. As the Pekua Rubber

Dam has been declared as a Key Point Installation (KPI), some precautionary measures

have been taken by BWDB. For examples, seven (7) guards have been appointed by

BWDB on full time basis to prevent local people from entering into the rubber dam site

to avert any such man made damage. Their duty is maintained as roaster duty. To

avoid free passing over the dam body, which may create possible damage of rubber

bag, a foot bridge has been built over the upstream stilling basin so that people can

easily cross the Pekua Khal without creating any harm to the dam. The bridge, in

addition to creating a safety measure to the dam, is playing a vital role in local people’s

physical communication process. There is another possibility of damage of rubber bag

by floating wood, bamboo raft, debris and other type of floating materials which may

be responsible for puncturing the deflated rubber dam. This type of damage can lead to

malfunctioning of the dam and decrease the resistance of rubber layer. To avoid such

damage, a precautionary measure was included in the design of Pekua Rubber Dam

which is shown in Fig. 6.8. In this figure it is seen that a special type of cushion

materials has been used inside the bag so that when debris pass over the dam body it

shocks the pressure of the debris or any other materials like this, which may cause

damage of the dam body. Through open discussion with stakeholders of the project and

concerned filed office it was found that till to date no puncture or crack on the rubber

bag was noticed. It is possibly due to number of precautionary measures, mentioned

above, as taken by the concerned authority during, implementation and post

implementation period of the dam. Despite this precautionary measures if any puncture

or crack is identified that can be easily repair/solve by BWDB through applying a

special type of gum and spices of 12mm thick rubber sheet as like as repairing of

puncture of tyre and tube of motor vehicle.

Page 84: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

69

Anchor bolt

CUSHION MATERIALS

RUBBER COATED FABRIC

RUBBER BASE COVER SHEET

Figure 6.8: Special cushion system of rubber dam (Design Catalogue, BWDB,

2003)

6.3.3.2 Disorder and Repair of Pump

Disorder of pump machine involves electro-mechanical trouble of pump machines.

Through discussion with concerned field officials it was learnt that a little disorder of

pump machineries were detected in the Pekua Rubber Dam sites. The pump operators

were reported to be capable of doing the minor repair works of the pump machines. In

the case of the major repair, the local technicians were called for and the said repair

works were accomplished at the rubber dam site with locally available materials. There

was no need of sending the pump machines to the workshops for any significant repair

work. From this experience, it could be said that disorder of the machine is easily

repairable with local technicians and without any major cost and manpower

involvement. One of the repairing processes of the pump is shown Fig. 6.9.

Page 85: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

70

Figure 6.9: Repair and cleaning work of pump and its accessories (Field office,

BWDB)

6.3.3.3 Deposition of Silt over Rubber Bags and over U/S and D/S

Stilling Basin

Through open discussion with field office it was learnt that deposition of silt of about

200mm-300mm depth was detected over the deflated dam bag as well as at upper

stream (U/S) and down stream (D/S) of stilling basin of the dam. This silt was removed

from the top surface of the bag by using water injector. A huge amount of silt was also

deposited in the water storage well. As quoted by the field office 200mm~300mm silt

was deposited every year on the stilling basin. So, before inflating the rubber dam these

silt were to remove every year by the concerned filed office of BWDB. Another major

problem created every year was clogging of inlet and out let pipe fitted on U/S and D/S

stilling basin of the dam by silt deposition. These were also needed to be removed

every year for opening the mouth of inlet and outlet pipe. From the above findings it is

clear that clogging due to silt deposition is a big operation and maintenance problem of

the Pekua Rubber Dam site which happens every year. Though this problem is solved

by BWDB local office every year by removing the silt before inflating the dam body

however recurrent siltation of every year and its removal is troublesome. Therefore,

Page 86: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

71

there is a need of exploring an alternative/modified design or mechanism of inlet and

outlet pipe so that the problems mentioned above could be removed or reduced.

6.3.3.4 Clogging of Foot Valve

The field officials and staff reported that clogging of foot valve of the intake pipe of the

dam by silt was sometimes detected in Pekua Rubber Dam. When it happened the foot

valve was cleaned by the pump operator with the help of skilled laborers engaged by

BWDB field office before raising the rubber bag every year. Every year a big amount

of silt also was deposited in the water storage well. So, before inflating the rubber dam,

this huge amount of silt was to remove with the help of ordinary laborers under

departmental arrangement. Before pump operation, every valve of the pump house was

cleaned by departmental people assigned for operation and maintenance of the pump. It

is clear from the above findings that despite recurrent clogging of foot valve and

removal of it was not so difficult and could easily be done under departmental initiative

with the help of local laborers and departmental peoples.

6.3.3.5 Safety Device of Rubber Dam and Bed Level of Rubber Dam

As found from the discussion with the people engaged in operation of the dam, there is

no safety device for automatically inflating or deflating the rubber dam body. In case of

flash flood, emergency deflating of the bag requires for easy flood pass over the dam.

In this case safety device automatically works, in absence of pump operator, to control

the situation. So it was suggested by the field people to provide safety device for auto

inflation and deflation of the Pekua Rubber Dam.

Another significant finding was that the bed level of the pump house is as the same

level of the bed of rubber dam. It is too deep to work. So, costing of the pump house

was very high with respect to the overall project. This costing can be reduced by

introducing a submergible pump instead of centrifugal pump.

6.3.3.6 Problem in Boat Communication

Through the open discussion with the concerned field office of BWDB and local

people, it was learned that in the Pekua Rubber Dam Project boat communication

remains stopped over the inflated rubber dam during the irrigation season (November-

Page 87: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

72

May) every year. During irrigation period the inflated dam works as a barrier to boat

movement from one side to another side of the dam. So, boatmen have to station their

boats on either side of the dam from where boats ply outwards. Boats are only allowed

to pass over the lowered position of rubber bag if enough water depth, not less than 1.5

meter, is attained. Boat movement activity starts only when irrigation period is ended

and monsoon starts, when the depth of water is sufficient. In this respect, it could be

said that the dam has little negative impact on water communication system. However,

considering the overall benefits of the dam on people’s life, economy, agriculture,

environment, etc. the stakeholders were found to exhibit a positive perception with

regard to usability of the dam. However, any solution to the problem will definitely

enhance the efficiency of the dam.

6.3.4 Stakeholders’ Participation in the Management of Pekua

Rubber Dam

One of the aspects of evaluating the performance of the Pekua Rubber Dam was

assessing the stakeholders’ participation in the operation, management and maintenance

of the dam. The information collected in this regard show that there was satisfactory

participation of the stakeholders’ in the planning, design and construction of the project

(BWDB & EPC, 1996). However, they were found lack of formal participation in

operation, maintenance and management of the rubber dam. Neither BWDB nor the

local administration took any initiative to involve them formally in the management

process, which could easily be done through forming different

management/implementation committees with practical participation of the

stakeholders.

The users of the dam have some potential role to play in connection with the

management and implementation of the dam facilities, such as operation and

maintenance of intake channel and other distributaries channels system, delivery of

irrigation water by LLP, delivery of irrigation water as per roster, preparation of the list

of the irrigated area, maintain the inlet/outlet gate operation during the irrigation period,

maintaining the field drains for proper irrigation, resolving the conflicts among the

water users, etc. The findings show that the users of the dam were not involved

institutionally in these activities.

Page 88: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

73

As mentioned before, when the inflating time comes the stakeholders contact with the

TNO for inflating the rubber dam. Then the TNO requests the concerned BWDB

officials for taking initiative. Similarly, after the irrigation period, the stakeholders

make request for deflating the rubber dam for free flood flow and navigation of the

Khal through TNO. The desired water level is maintained through open discussion with

stakeholders. Throughout the process different problems arise. For example, during the

irrigation time the users sometimes become involved in disputes over the distribution of

water for irrigation. Sometimes the beneficiaries show irresponsibility in maintaining

the channels and controlling the gates. After inflation of the dam different stakeholders

make different opinions in regard to maintaining the water level. This makes conflict

among the stakeholders. The stakeholders of upstream want the water level at their land

elevation. This higher elevation of water level may cause inundation of lands owned by

the stake holders residing near rubber dam. Therefore, the stakeholders residing near

rubber dam want the water level at their land level, which make problem of supplying

water to U/S area. These problems need to be solved properly for efficient

management of the dam without which overall impact of the project may suffer. It also

might affect fulfillment of the project goals and activities in terms of proper and desired

usability of the irrigation facilities, agricultural productivity, environment, fisheries,

etc. One of the possible reasons for these shortcomings may be absence of different

management committees with the participation of the stakeholders and institutionalized

responsibility of them in settling the issues and problems.

But, active involvement of the beneficiaries/stakeholders in running and management

of the projects is very much important. It can help to develop a mentality of shouldering

various responsibilities for running the project well and thereby create a sense of

oneness in them with the project. Considering the issue importantly, the Ganga

Kapotakho (G.K.) Project and the Pabna Irrigation and Rural Development Project of

BWDB and the Eidgah and Bakkhali Rubber Dam Projects of LGED formed different

implementation and maintenance committees of the stakeholder. For example, Block

Management Committee (BMC), Operation Management Committee (OMC) and

Central Management Committee (CMC) have been formed in the LGED projects. In

Pekua Rubber Dam Project formation of these kinds of implementation committees is

necessary for its proper and democratic management. Moreover, it is a recognized fact

that villagers in Bangladesh have extensive knowledge of the behavior of water on the

Page 89: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

74

flood plane and its use for agriculture. Indeed they have a vested interest in

understanding the problems and the benefits of that water holds for them since their

lives depend upon this knowledge. So it is very much necessary to formally involve

them in management process of the facilities of Pekua Rubber Dam through forming

different management bodies composed of the stakeholders.

Coordination between the parent department with local organizations, who are directly

or indirectly related with the project benefits and their use, is another important aspect

to achieve long term sustainability of a project benefits through its good management

and maintenance. This was found absence in case of BWDB in Pekua Rubber Dam

project. There was lack of coordination between BWDB and Water User Group,

Agriculture Extension Officer, Fishery Officers, NGOs, etc., who were responsible for

local irrigation management, agriculture, fisheries, environmental management, etc.

From the above discussion it is clear that there was absence of formal participation of

the stakeholders in management of the project. Also there was lack of coordination

between BWDB and other local organizations. As a result, the local office of BWDB

failed to develop required responsibility and skills of the local people in managing the

rubber dam project well. So, there is a need to different local level management

committee(s) for running the Pekua Rubber Dam Project as like as the Bakkhali &

Idgha Rubber Dam Projects of LGED where the stakeholders have formed different

implementation committees for managing the project and its benefits (Raquib, 1999)

and build up coordination with different organizations.

6.4 Impact of the Pekua Rubber Dam Project

Performance evaluation of the Pekua Rubber Dam project was also done based on its

impact on socio-economic status of the local people, agriculture and environment.

Socio-economic impact was analyzed through some indicators, namely annual income,

range of annual income increase, poverty alleviation and employment. The impact on

agriculture was evaluated on the basis of increase of agricultural production. The

environmental impact was evaluated by measuring the dam’s impact on draught,

ground water table, water logging and fisheries. Data were collected through

administering a questionnaire on a group of 50 respondents, who were beneficiaries of

Page 90: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

75

the rubber dam project. The questionnaires were administered through field visit of the

researcher with the help of BWDB officials and local people. Besides, data were also

collected from some other sources like NGO and GO officials working in the research

locality through open discussion. The findings are presented in the following

paragraphs under three major headings, namely impact on socio-economic status

(6.4.1), impact on agriculture (6.4.2) and impact on environment (6.4.3).

6.4.1 Impact on Socio-economic Status

Impact of the dam on socio-economic status was assessed based on annual income

increase of the stakeholders and the range of increase as well as considering the

changes in their poverty and employment levels.

Annual Income Increase

The impact of Pekua Rubber Dam in terms of annual income increase of the

stakeholders is presented in the following table.

Table 6.1: Impact on Annual Income

Income increased Income did not increase

41

(82%)

09

(18%)

Quite majority of the respondents (82%) opined that their yearly income increased after

implementation of the Pekua Rubber Dam Project. Less than one fifth reported no

increase in their income level. Respondents (41), who answered positively, were again

asked if their income increased then to what extent it had increased. The data collected

in this regard are presented in Table 6.2.

Page 91: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

76

Table -6.2 Amount of Annual Income Increase due to Construction of

Pekua Rubber Dam Project

Amount of annual income increase

(In Taka)

No. of stakeholders Percentage

01 – 10,000 02 05

10,001 – 20,000 06 15

20,001 – 30,000 12 29

30,001 – 40,000 13 32

40,001 – 50,000 08 19

Total 41 100

The data in the above table show varied levels of income increase of the beneficiaries.

Majority of the respondents (32%) mentioned that their yearly income increased

between Tk. 30,001 - 40,000. Almost similar percentage (29%) of the respondents

reported an increase of Tk.20,001 - 30,000. A good number of the respondents (19%)

reported the highest level of increase in their yearly income. Combining these three

groups, it is seen that absolute majority (29%+32%+19%=80%) of the respondents had

significant increase in their income level. Only 20% reported of yearly income less than

Tk. 20,000. Thus, the data in Tables 6.1 and 6.2 clearly indicates significant

improvement in economic status of the Pekua Rubber Dam stakeholders due to

construction of the project.

Impact on Poverty Alleviation

The findings on impact on poverty alleviation are presented in Table 6.3 of next page.

Out of the 50 Respondents, 56% agreed that due to the rubber dam project poverty level

of the locality decreased significantly while 24% mentioned that it remained the same.

The discussion made with the stakeholders revealed that due to irrigation facilities

created under the rubber dam project significant amount of non-cultivable land has

Table 6.3: Poverty alleviation

Poverty decreased

Poverty remained same

38

(76%)

12

(24%)

Page 92: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

77

transformed into cultivable land due to regular irrigation facilities. Consequently, the

amount of agricultural land of the stakeholders has increased, which resulted in

increased total agricultural production of the area. Because of improvement in soil

condition more plants and vegetables are growing there. Moreover, due to the improved

water facilities fish production has increased than before. All these are helping to

improve the poverty level of the people. So, their economic condition has improved.

Impact on Employment

To assess the impact of socio-economic condition due to the construction of the rubber

dam project the respondents were asked whether their employment increased or

decreased as a result of the construction of the rubber dam, findings of that are

presented in Table 6.4.

Table 6.4: Impact on Employment due to Rubber Dam Project

Employment opportunity increased Employment opportunity did not increase

36

(72%)

14

(28%)

According to the data in Table 6.4, out of the 50 respondents, 36 (72%) opined

positively i.e. employment opportunity increased and 28% opined negatively. From the

open discussion the overall scenarios stands that due to the rubber dam project

employment rate increased through increased agriculture land and production, fish

production, business, etc.

The stakeholders further mentioned that development of the above mentioned aspects

(income, poverty and employment opportunity) helped to enhance socio-economic

condition by reducing poverty, creating more employment opportunity and increasing

income level. All these are helping their family in terms of schooling opportunity of

their children, better food, better clothing, better housing facilities, etc. In other words,

the rubber dam project is helping to establish a better quality of socio-economic life for

the stakeholders of the Pekua Rubber Dam project.

Page 93: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

78

6.4.2 Impact on Agriculture

To assess the impact of the rubber dam on local agriculture, the respondents were asked

whether their agricultural production increased as a result of the construction of the

rubber dam, if increased then to what extent it increased and how was the amount of

increase of different agricultural products. Findings of these inquiries are presented in

Tables 6.5, 6.6 and 6.7.

According to the data in Table 6.5, 94% of the respondents opined in favor of increased

agricultural productions. Only 6% said that their agricultural production did not

increase.

Table 6.5: Impact of Agricultural Production

Production increased Production did not increase

47

(94%)

3

(6%)

The responses regarding the investigation - “if increase, how much” the responses are

presented in the following table.

Table 6.6: Amount of annual increase in agricultural production

Amount of annual agricultural

production increased

(In mound per acre)

No. of Stakeholders Percentage

5- 10 25 50

10- 15 15 30

15-20 10 20

The data reveal that for 50% of the respondents the amount of increase was 5 to 10

mound per acre. For a significant portion (30%) the production raised for 10 to 15

mounds per acre, while it was 15 to 20 mounds for 20 percent of the respondents. The

findings mentioned above clearly indicate a very positive impact of the rubber dam on

the agricultural production of the catchments areas of the rubber dam. It is very much

Page 94: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

79

obvious from general idea and proved in research that the higher the facility of

irrigation the higher the agricultural production is. So, people always employ various

ways and means to irrigate their crop land as much as possible and if they are unable to

provide it they suffer from huge loss in terms of quantity of production. The rubber

dam has made the life of the local farmer easy in terms of irrigation facilities and

everybody is getting this facilities and being benefited from the rubber dam.

Table 6.7: Amount of annual crop production before and after implementation of

the rubber dam project

Types of crops Amount production after rubber dam project (Mound per acre)

Amount of production before rubber dam project (Mound per acre)

Paddy 60 45

Vegetable 16 3

Salt 320 420

Pan 12 6

From Table 6.7 it is seen that before implementation of the rubber dam project, the

amount of production of paddy, vegetable and pan were lesser and after implementation

of the rubber dam the crop production increased significantly. But the result of salt

production was reverse. As agriculture land increased due to the rubber dam project,

the land for salt production naturally decreased. So, after the rubber dam project salt

production decreased.

6.4.3 Impact of Environment

For assessing the impact of the rubber dam on environment, its impact on draught,

ground water table, water logging and fish production were considered. Data in these

regards were collected through open discussion with relevant people, findings of which

are presented in the following paragraphs.

6.4.3.1 Impact on Draught

As reported by the respondents, a mild draught used to prevail in the locality during dry

season before construction of the rubber dam project. This has now been removed and

the weather has become soothing. The reason for this, as mentioned by them, is that due

Page 95: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

80

to the rubber dam sweet water retains in the upstream of the dam and is distributed over

the land by means of gravity or LLP. As a result green crops grow in the area and no

draught can occur in dry period.

6.4.3.2 Impact on Ground Water Table

The local people informed that the level of ground water table was low before the

construction of the rubber dam project, but the level has become high than before the

project implementation. It is also seen from the soil boring test that higher water table

remains there than the post project condition. Before the project, the non cultivable

plants and vegetation like bamboo, jack fruit, mango trees and other trees in both

upstream and downstream of the project turned into yellow due to lack of optimum soil

moisture content during dry period. After the rubber dam project, the plants and

vegetation remain green due to supply of optimum soil moisture content during dry

period. This is due to the rise of ground water table as result of constant water retention

in the upstream of the rubber dam project. It is also noticed that after the project,

varieties of plants like Mehagani, Rain tree, Jack trees are being cultivated. The

adjoining area of the project has become saline free due to prevention of saline

intrusion in to the project area by building rubber dam project in dry period. Uncultured

plants and vegetation are getting soil moisture properly due to rise of water table in the

project area and have become green. These findings reveal that there is positive impact

on environment with respect of ground water table due to the construction of the Pekua

Rubber Dam. It definitely indicates a positive impact of the dam on environment

6.4.3.3 Impact on Water Logging

Before the construction of Pekua Rubber Dam, there was no scope to change the height

of the earthen dam, constructed by local people, which created more water logging in

the adjacent area of the earthen dam. After construction of Rubber Dam, the dam height

can be raised or lowered according to necessity. As a result no water logging is

occurred due to the Rubber Dam Project.

6.4.3.4 Impact on Fisheries

Data in Table 6.8 reveal a positive impact of the project on fish production. More than

Page 96: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

81

Table 6.8: Impact on Fish production

Fish production increased Fish production did not increase

35

(70%)

15

(30%)

two-thirds (70%) of the respondents opined in favor of increased fish production and

30% opposed it. Through open discussion with beneficiaries of the project it is learned

that after the project there is an increase of about 15% in fisheries and especially prawn,

putty has marked production. Culture fisheries like Rui, Katla, Telapia have also

increased as reported by local people.

Increase of fisheries is due to constant sweet water retention in dry season in the

catchments area of the upstream of the rubber dam project. In the pre-project condition

deep water pool could not be maintained due to failure of earthen dam. In that case fish

production was not good as like as post project period. So, there has positive impact on

environment with consideration of fish production due to the rubber dam project.

In brief, the overall findings from the analysis of design, maintenance and management

aspects as well as the impact on socio-economy, agriculture and environment indicate

that the Pekua Rubber Dam Project has many positive and few unfavorable

performances. For example:

• The design parameters and the design principles set for the dam were ok

• Minor operation and maintenance problems, like repair of rubber bags and pump

machines, removal of silt over the deflated rubber dam bag, removal of silt over U/S

& D/S stilling basin, cleaning work for clogging of foot valve

• Maintenance of the machineries of the dam is possible to do locally and institutionally

• Absence of any user committee/body for implementing and maintaining the project is

a threat to its proper management

• Stakeholders lack formal participation in the management of rubber dam.

• Lack of institutionalized management system

• Boat communication is hampered during the irrigation time

• Silt deposition at different level and parts of the rubber dam is a common phenomena

• The Alternative foot bridge is helpful for easy communication

Page 97: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

82

• The dam has positive socio-economic impact in terms of yearly income, reducing

poverty and increasing employment opportunity

• Agricultural production has increased due to increase of agricultural land and

irrigation facilities

• Local environment has improved through curtailing drought, elimination water

logging, and increasing ground water table and fish production.

Page 98: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Chapter 7

Conclusion and Recommendations

7.1 Conclusion

Based on the performance evaluation of the Pekua Rubber Dam the following

conclusions have been drawn.

1 The length, height, shape, site selection, foundation design, floor length, depth

of cut-off wall, fitting-fixing of rubber sheet, fixation level of overflow pipe,

etc. of the dam were ok in terms of the design parameters consideration.

2 The rubber dam was working well since its implementation and during the last

five and a half years of operation (since June-2004).

3 The dam had minor maintenance problems, like repair of pump machines,

removal of clogging of foot valve and removal of silt from the dam body, U/S

stilling basin & D/S stilling basin, which easily can be solved with local level

expertise and service providers.

4 The rubber dam suffered from any safety devise for automatically inflating and

deflating the dam body in case of emergency.

5 The rubber dam had both positive and negative impact on local communication

system. The foot bridge, constructed over the upstream of stilling basin to save

the dam from trespassing of the public, has improved the local communication

process. But the dam is interrupting boat communication between the two sides

of the dam during the irrigation period i.e. dam activation time.

6 Implementation of the dam helped to increase annual income of the

stakeholders, alleviating poverty and creating more employment opportunity.

All these helped to increase the socio-economic status of the local people.

Page 99: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

84

7 The dam had positive impact on local agriculture through increasing cultivable

land and various agricultural productions.

8 The dam helped to improve the environment of the locality by removing mild

draught and water logging from the project area and increasing the ground water

table which has good impact on all kind of green vegetation, plantation,

agriculture, flora and fauna as well as in declining salinity.

9 The stakeholders of the dam had lack of formal participation in maintenance

and management of the rubber dam. As a result, some management problems

were created among the users, like distribution of water through the channels,

differences of opinion in maintaining water level, irresponsibility in maintaining

the channels and gates, etc.

10 There found a lack of coordination among the local level institutions, like

BWDB, Agriculture Extension Group and other local Water User Groups

responsible for local level irrigation management, agriculture, fisheries,

environmentalist etc.

11 The institutional aspect of BWDB was supportive for operation of the dam. But

the dam no full time operator to pump the machine. The master role basis pump

operator can create problem in operating the dam.

12 The present study shows that rubber dam had some specific strengths in terms

of implementation time, cost incurred and simplicity of construction. The time

required for implementation of the rubber dam was relatively shorter than

construction a regulator or barrage; the construction cost was relatively low and

construction of the rubber dam was comparatively simple.

13 In fine it could be concluded that the Pekua Rubber Dams Project was

technically attractive, economically viable and less costly, socially acceptable,

environmentally sustainable and agriculturally helpful to increase various

production. Thus it is helping to lift local economy and alleviating poverty. The

little problems as identified in this study were not big issues and could be easily

Page 100: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

85

solved with local technology and initiatives. Therefore, the rubber dam

technology could be quite appropriate for irrigation in the hilly regions as well

as in other areas of Bangladesh.

7.2 Recommendations Based on the findings and the above mentioned conclusions the following

recommendations have been proposed.

1. In order to enhance the overall performance of the Pekua Rubber Dam, its

maintenance and management process should be strengthened. For this the

following measures should be taken by BWDB:

Appoint full time pump operator(s) to run the pump machine of

the dam.

Form different kinds of local bodies/committees with

participation of the stakeholders for efficient management of the

dam.

Establish coordination between BWDB local office and different

local relevant organizations, who are directly or indirectly related

with the dam benefits, through forming coordination committee.

2. As the Pekua Rubber Dam showed good performance in terms of the aspects

assessed in this study, BWDB should take more such projects replicating the

ideas gathered from it. In doing so the following should be considered.

• A safety devise should be introduced for automatically inflating and

deflating the dam body in case of emergency.

• A modified design of inlet and outlet pipe should be developed so that

the mouths of the pipes can not be blocked with silt deposition.

• A submergible pump should be introduced for curtailment of the huge

costing of pump house.

3. Recommendations for Future Study

The following study could be undertaken in the future:

Page 101: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

86

3. A water filled rubber Dam takes 8~10 hrs for filling the rubber dam body

according to its pump capacity and embedded pipe line and its regulating

devices. But an air filled Rubber Dam’s inflation time is shorter than water

filled bag. Pekua Rubber Dam was a water filled rubber dam project. Another

project may be taken by BWDB as pilot project to investigate to compare the

performance of two types of rubber dam.

4. A study should be undertaken to compare the performance of a rubber dam with

that of a conventional water retention structure based on primary data.

5. The environmental impact of the dam was assessed in terms different aspects

like weather, water logging, plantation etc. However, as a rubber product its

impact on chemical effect is very important. Therefore, a chemical assessment

of the rubber dam body under water and above water should be done to look at

its impact on environment.

Page 102: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

87

REFERENCES

BWDB, 2003 Some still picture of rubber dams constructed by BWDB. BWDB & EPC, 1995. The Feasibility Study of Matamuhuri Irrigation Project under BWDB. CHANSON, H. 1996. "Some Hydraulic Aspects during Overflow above Inflatable Flexible Membrane Dam." Report CH47/96, Dept. of Civil Engineering, University of Queensland, Australia. CHANSON, H. 1998. "Hydraulics of Rubber Dam Overflow : a Simple Design Approach." Proc. 13th Australasian Fluid Mech. Conf., Melbourne, Australia, 13-18 December, M.C. THOMPSON & K. HOURIGAN Ed., Vol. 1, pp. 255-258. Design catalogue, BWDB, 2003 Design catalog of Pekua Rubber Dam under Matamhuri Irrigation Project, prepared by Bangladesh Water Development Board (BWDB). Design Report, 2003. Design report of Pekua Rubber Dam, Prepared by Design Office of BWDB. Fahmida, K, Dept. of WRE, BUET, Dhaka; Develop a research proposal on evaluation of Rubber Dam Technology as an alternative to Traditional Dam Projects for sustainable development Geosynthetica.net. Inflatable Rubber Dam; International Water Power and dam construction; WWW/ Geosynthetica.net Hossain, A. 1992. Diagnostic Study of Failures of Hydraulic Structure in Bangladesh Case studies of failure in Chittagong district, M. Engg. Thesis Department of Water Resource Engineering, BUET, Dhaka IWHR, 1994. Rubber Dam – a new type of flexible hydraulic structure , a paper prepared by Institute of Water Conservancy & Hydroelectric Power Research & Beijing Keyu Water Engineering Technology, China. IMED, 2007. The Impact Evaluation of Matamhuri Irrigation Project 1st Phase of BWDB (Pilot Project) LGED, 1994. Study Report on Feasibility of Rubber Dam in Bangladesh. Institute of Water Conservancy & Hydroelectric Power Research (IWHR), People Republic of China and Technical Design Unit, Institutional Support Project (ISP), Rural Employment Sector Programme -11 (RESP-11), Local Government Engineering Department, Dhaka, Bangladesh.

Page 103: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

88

MPO, 1991. National Water Plan Project Phase-II, Ministry of Water Resource, Dhaka. Michael R. Markus, Curtis A. Thompson, and Matt Ulukaya (From Water & Waste Digest) 1995. Aquifer Recharge Enhanced with Rubber Dam Installations published by Water Engineering and Management, January, 1995. Nahar, J, 2004. Preliminary Study on Design of Rubber Dam in Bangladesh with special reference to the use of locally available materials. Undergraduate Thesis, Department of Water Resource Engineering, BUET, Dhaka. OGIHARA, K., and MARAMATSU, T. 1985. "Rubber dam: Causes of Oscillation of Rubber Dams and Countermeasures." Proc. 21st IAHR Congress, Melbourne, Australia, QHEPIL, 1999 Qingdao Huahai Environmental Protection Industry Co. Ltd. China. The Rubber Dam and the Technical Standard of Rubber Dam. Raquib, M.A. 1999. Performance evaluation of Rubber Dam Projects in Bangladesh. M. Engg. Thesis, Department of Water Resource Engineering, BUET, Dhaka. Saleh, M., Fazal, A. and Modol, M. S. 2000. Performance Evaluation of rubber dam projects in irrigation development. A publication under Institute of flood control and drainage research, BUET, Dhaka. SEIL, 1985. Sumitomo Electric Industries Ltd, Japan. Technical description of SUMIGATE Inflatable Rubber Ram. Soil investigation report, 2002. Soil investigation report of Pekua Rubber Dam site, prepared by Ground Water Division-1, BWDB Terzaghi and Peck, 1948. The allowable bearing pressure based on tolerable settlement. Wikipedia –the free encyclopedia. Inflatable Rubber Dam, http:// en.wikipedia.org/wiki/inflatable_Rubber_Dam Yantai C.S.I. Rubber Co. Ltd, http://www csirubber.com Zhang X. Q., Tam, P. W. M., and Zheng, W. 2002. Construction, Operation, and Maintenance of Rubber Dams. Canadian Journal of Civil Engineering, 29(3):409-420.

Page 104: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …
Page 105: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Design & Features

Strong Body Secure Anchor Simple & Reliable

An inflatable bladder made of heavy-duty, nylon-reinforced rubber, with EPDM cover to withstand ozone and ultraviolet light. Thickness of bladder ranges from 9.5 to 25mm, depending upon the dam height. The minimum safety factor for the bladder is 8.0.

The bladder is anchored to the foundation using a simple clamping system composed of anchor bolts and steel clamping plates. This simple design produces an extremely dependable air-tight seal. The system can be installed quickly but firmly with standard tools. The minimum design safety factor for the anchor system is 3.0.

A low pressure system, usually between 0.05kgf/cm2 to 0.6kgf/cm2

depending on dam height. Air is supplied using air blowers. No overhead structure or hydraulic system are required. Inflation & deflation of rubber dams is highly reliable and little maintenance is required.

Page 106: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

Flat On Foundation Longer Span Flexible Control

The FIN structure allows the fabric to Lay-Flat when deflated. This prevents damage from debris or ice. The lay flat characteristic eliminates the bulge at the end of the deflated body, which is prone to serious vibration & abrasion. It also permits passage of debris.

The Bridgestone Rubber Dam permits very long spans, thus reducing the need for intermediate piers necessary in steel gate installations. The long span of the rubber dams also maximizes discharge as there are few piers obstructing the water flow.

Inflation & deflation can be manual or automatically controlled. The automatic control system can monitor the upstream water level and adjust the air pressure in the dam to maintain a prescribed water level in the upstream pool.

Oscillation Reduction Variable Side Slope Low Maintenance

When inflated, the FIN structure works as a deflector to create aeration below the fin. This effectively reduces the phenomenon of oscillation up to a 50% overflow when compared to FIN-LESS bladders.

Rubber Dams can be installed in rivers with any side slope angle, eliminating the necessity of modification to river bank, unlike steel gates which can only be installed on vertical side slopes.

Other than normal maintenance of control equipment, blowers and actuators, rubber dams are virtually maintenance free. This is a big advantage over steel gates, where removal of rust, painting and changing of hydraulic oil are required.

Copyright © 2002 Bridgestone Corporation. All Rights Reserved.

Page 107: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

‡cKzqv ivevi W¨v‡gi cÖfve g~j¨vqvb m¤ú©wKZ mgx¶v

myweav‡fvMxi bvg t

wVKvbv t

‡ckv t

eqm t

cwiev‡ii m`m¨ msL¨v t

evwl©K Avq t wbR¯̂ Avq t ................UvKv cwiev‡ii Avq t ............UvKv

wk¶vMZ †hvM¨Zv t (K) wbgœgva¨wgK (L) cÖv_wgK (M) D”Pgva¨wgK (N) mœvZK (O) mœvZ‡KvËi

wb‡Pi cÖkœ̧ ‡jv fvj K‡i co–b Ges Avcbvi DËi Abyhvqx ÕnuvÕ ev ÕbvÕ N‡i wUK (√ ) wPý w`‡q DËi w`b|

cÖ‡qvRbxq †¶‡Î cÖ‡kœi wb‡Pi Lvwj RvqMvq wj‡L Avcbvi DËi w`b|

1. ivevi W¨vg cÖKí nIqv‡Z Avcbvi Avevw` Rwgi cwigvb e„w× †c‡qwQ wK ? hw` e„w× †c‡q

_v‡K Z‡e Kx cwigvb e„w× †c‡q‡Q wb‡P D‡j­L Ki“b|

------------- GKi/weNv…

n&uv

bv

2. ivevi W¨vg cÖKí nIqv‡Z Avcbvi c~‡ei †P‡q eZ©gvb dmj Drcv`‡bi cwigvb e„w× †c‡qwQ

wK ? hw` e„w× †c‡q _v‡K Z‡e Kx cwigvb e„w× †c‡q‡Q wb‡P D‡j­L Ki“b|

....................gb GKi cÖwZ

n&uv

bv

3. ivevi W¨vg cÖKí nIqv‡Z Avcbvi evwl©K Avq c~‡e©i †P‡q eZ©gv†b e„w× †c‡qwQ wK ? e„w×

†c‡j AvbygvwbK KZ UvKv e„w× †c‡q‡Q?

..................... UvKv

n&uv

bv

4. ivevi W¨vg cÖKí nIqv‡Z gvQ Pvl c~‡e©i †P‡q eZ©gv†b e„w× †c‡qwQ wK ? e„w× †c‡j

AvbygvwbK Kx cwvigvb e„w× †c‡q‡Q?

..................... UvKv

n&uv

bv

5. ivevi W¨vg cÖKí nIqv‡Z GjvKv‡Z RbM‡Yi `vwi ª̀Zv n«vm †c‡q‡Q wK ? †c‡j Kxfv‡e Avcwb

Kxfv‡e Zv eyS‡Z cvi‡Qb?

n&uv

bv

6. ivevi W¨vg cÖKí nIqv‡Z cwiev‡ii m`m¨‡`i g‡a¨ Kv‡iv Kg© ms ’̄vb n‡qwQ wK ? Kg© ms ’̄vb

e„w× †c‡j eZ©gv‡b Zviv Kx ai‡bi Kv‡R wb‡qvwRZ Av‡Q?

n&uv

bv

Page 108: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

7. ivevi W¨vg cÖKí nIqv‡Z †hvMv‡hvM e¨e ’̄v DbœZ n‡q‡Q wK ? DbœwZ n‡q _vK‡j Kx ai‡Yi

DbœwZ n‡q‡Q wb‡P D‡j­L Ki“b|

n&uv

bv

8. ivevi W¨vg cÖKí nIqv‡Z jeb Pv‡li cwigvb e„w× †c‡q‡Q Kx ? e„w× ‡c‡j Kx cwigvY e„w×

†c‡q‡Q?

..................... ‡KwR

n&uv

bv

9. ivevi W¨vg cÖKí nIqv‡Z cwi‡ki ‡Kvb cÖfve c‡i‡Q wK ? c‡i _vK‡j †Kvb †Kvb †¶‡Î

cÖfve c‡i‡Q Zvnv D‡j­L Ki“b|

n&uv

bv

10. cÖKí ev¯—evq‡bi c~‡e© I c‡i GKi cÖwZ wb‡gœv³ dmj Drcv`‡bi cwigvY (g‡b) cÖKvk

Ki“b|

dm‡ji bvg eZ©gv‡b cwigvb (gb ) c~‡©ei cwigvb ( gb)

avb

kvKmewR

gvQ

jeb

cvb

Page 109: PERFORMANCE EVALUATION OF PEKUA RUBBER DAM AT COX’S …

ANNEXURE

Questionnaires