Top Banner

of 59

Performance Audit Reports

Aug 07, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/20/2019 Performance Audit Reports

    1/142

    PERFORMANCE AUDIT REPORT

    ACQUISITION AND USE OF LANDS FOR

    GOVERNMENT PROJECTS

    Ministry of Housing and Lands

    July 2015

  • 8/20/2019 Performance Audit Reports

    2/142

  • 8/20/2019 Performance Audit Reports

    3/142

     Acquisition and Use of Lands for Government Projects i

    CONTENTS

    Page

    ABBREVIATIONS AND ACRONYMS iii

    EXECUTIVE SUMMARY1

    CHAPTER ONE: INTRODUCTION

    1.1 Motivation 3

    1.2 Audit Objectives 3

    1.3 Auditee 3

    1.4 Time Coverage 3

    1.5 Geographical Coverage 4

    1.6 Assessment Criteria 4

    1.7 Audit Methodology 4

    CHAPTER TWO: DESCRIPTION OF THE AUDITED ACTIVITY

    2.1 Role and Responsibility of MHL in the Acquisition Process 7

    2.2 Requests for Lands and Vesting Procedures 7

    2.3 Organisation Structure of MHL 8

    2.4 Key Players and Their Activities 8

    2.5 Recording of Vested Lands 8

    2.6 Project Plan Committee 9

    CHAPTER

    THREE

    : FINDINGS

    3.1 Land Acquisition 11

    3.2 Land Use 15

    3.3 Recording of Vested Lands 18

    3.4 Monitoring of Vested Lands by MHL 20

    3.5 Land Acquisition Recording and Payment System 20

    CHAPTER FOUR: CONCLUSIONS AND RECOMMENDATIONS

    4.1 Land Acquisition 21

    4.2 Land Use 22

    4.3 Recording and Monitoring of Vested Lands 23

    TABLES

    1 Sections of the LAA used as Assessment Criteria 4

    2 Time Taken to Complete Acquisition Procedures 11

    3 Effect of Late Handing Over of Site 13

    4 Number of Corrigenda Published 14

    5 Reply from the Valuation Department Exceeding Five Months 14

    6 Examples of Interest Paid 15

    7 Examples of Vested Lands not yet Developed 168 Examples of Vested Lands not Recorded at LIU 19

  • 8/20/2019 Performance Audit Reports

    4/142

     Acquisition and Use of Lands for Government Projects   ii 

  • 8/20/2019 Performance Audit Reports

    5/142

     Acquisition and Use of Lands for Government Projects   iii 

    ABBREVIATIONS AND ACRONYMS

    BOA Board of Assessment

    DSLR Digital State Land Register

    LAA Land Acquisition Act

    LAVIMS Land Administration, Valuation and Information Management System

    LIU Land Information Unit

    MHL Ministry of Housing and Lands

    MOFED Ministry of Finance and Economic Development

    MOLG Ministry of Local Government and Outer Islands

    MPI Ministry of Public Infrastructure and Land Transport

    MFRS Mauritius Fire and Rescue Service

    MYS Ministry of Youth and Sports

    NAO National Audit Office – Mauritius

    NDU National Development Unit

    PBB Programme Based Budget

    PPC Project Plan Committee

    RDA Road Development Authority

  • 8/20/2019 Performance Audit Reports

    6/142

     Acquisition and Use of Lands for Government Projects   iv 

  • 8/20/2019 Performance Audit Reports

    7/142

     Acquisition and Use of Lands for Government Projects 1

    EXECUTIVE SUMMARY

    The Ministry of Housing and Lands (MHL) acquires privately owned lands on behalf of 

    Ministries and Government Departments for construction of roads, drains and other projects1.

    Lands are acquired through private agreements and compulsorily. Compulsory acquisitionsare carried out within the legal framework of the Land Acquisition Act (LAA) 1982, as

    amended in 2013.

    The objective of this Performance Audit is to assess whether lands acquired by MHL and

    vested in Ministries and Government Departments have been used for the intended purposes.

    Further, it seeks to establish whether the acquisitions were done on a timely basis and in the

    most economical manner. The recording system was also reviewed.

     Key Findings

    For the past 10 years, MHL had disbursed some Rs 2.2 billion on acquisition of lands for

    various Government projects. Several plots of land acquired on or prior to year 2010 have

    remained undeveloped. Information on the extent of lands acquired, but not developed

    was not readily available as there were no established procedures for Ministries and

    Government Departments to give feedback on the current statuses of the lands. Moreover,

    it was not clearly defined as who should ensure that lands vested were used on a timely

    basis and for the intended purposes.

    Prior to year 2010, there was no mechanism in place at the MHL to ascertain that the

    requesting Ministries and Government Departments had the required funds forimplementing their projects before initiating acquisition for land. However, MHL has

    recently taken initiatives to ensure that the implementing agencies have the necessary

    fund for the project at the time of request for land.

    As for the plan of the project, MHL is still not ensuring the availability thereof at time of 

    request. For a few cases examined, the structural designs of the buildings were not yet

    completed, and in other cases, the requesting Ministries and Government Departments did

    not carry out a proper need analysis of the projects.

    For a few cases regarding construction of roads, MHL could not ensure availability of the

    lands on time. Hence, Government had to disburse additional funds. This was attributedto the fact that owner identification was time consuming.

    Lands acquired by MHL were not always in the most economical manner. The LAA

    provides for the offer of compensation to beneficiaries after the publication of notice

    under Section 8 and transcription of the land. However, the time frame to accept or reject

    an offer is not mentioned. A beneficiary made a counter claim to the original offer some

    seven years later, and MHL had to disburse interest amounting to some 73 per cent of the

    compensation payable.

    1Other projects include construction of stadiums, swimming pools, Fire Stations, and Multipurpose buildings.

  • 8/20/2019 Performance Audit Reports

    8/142

     Acquisition and Use of Lands for Government Projects   2

    The records for lands vested in the selected Ministries and Government Departments kept

    at the MHL were incomplete. For instance, several plots of land acquired and vested in

    the National Development Unit (NDU) were not found in the database kept at the Land

    Information Unit of MHL.

    Conclusion

    The acquisition of land for Government projects involves significant Government’s funds and

    impacts on the development of the projects. The timely acquisition of land at least cost is

    therefore essential. However, MHL has not always been able to acquire land on a timely basis

    and in the most economical manner. A complete database of all vested lands was not

    available. Information on their statuses was also not readily available. There are several plots

    of land that have been acquired, but have not yet been developed.

     Key Recommendations

    A mechanism should be put in place at MHL to ensure that land acquired is used for the

    intended purposes on a timely basis. Ministries and Government Departments should be

    requested to submit regular feedback on implementation of projects. In this respect, the

    role and responsibilities of MHL and requesting Ministries and Departments need to be

    clearly defined

    Recently, MHL has taken initiatives to ensure that the implementing agencies have the

    necessary fund for the project at the time of request for land. This measure could be

    extended to include availability of design of the project. In that respect, a consultative

    platform needs to be set up by the requesting Ministry/ Government Department bringingin all stakeholders so that there is a constructive dialogue and everyone knows his role,

    responsibilities and obligations. This will minimise any future unproductive vesting.

    Time lag for reply from beneficiaries also needs to be established

    MHL should ensure that all vested lands are properly recorded. The land acquisition

    system needs to be automated. A complete database on their current statuses should be

    maintained.

  • 8/20/2019 Performance Audit Reports

    9/142

     Acquisition and Use of Lands for Government Projects   3

    CHAPTER ONE

    INTRODUCTION

    During the past years, with the increasing public investment in the fields of education, road

    infrastructure and sports in particular, the demand for land from Ministries and Government

    Departments has increased considerably. State Lands that may be used for development are

    becoming scarce and Government has to acquire privately owned lands.

    1.1 Motivation

    The National Audit Office (NAO) has often reported that several plots of land acquired by

    the Ministry of Housing and Lands (MHL) on behalf of Ministries and Government

    Departments were not developed. Further, adverse press reports have highlightedGovernment projects kept in abeyance since the year 2005, thus indicating non achievement

    of the objectives set.

    For the past 10 years, the expenditure on land acquisition has been constantly increasing to

    reach a cumulative amount of some Rs 2.2 billion. For the period 2009 to 2013, more than 80

    per cent of the expenditure was meant for projects relating to construction of roads.

    In view of the sum spent and the adverse press reports, the NAO carried out this Performance

    Audit on “Acquisition and Use of Lands for Government Projects”.

    1.2 Audit Objectives

    The audit objectives were to assess whether:

    MHL ensures the availability of lands for the implementation of Government Projects at

    the right time and in the most economical manner

    The vested lands have been used for the intended purposes

    Records for lands acquired and vested are complete and reliable and their use monitored

    effectively.

    1.3 Auditee

    The auditee is MHL as it is responsible to acquire privately owned lands before vesting them

    in Ministries and Government Departments for implementation of projects.

    1.4 Time Coverage

    The audit covered acquisitions for the period 2009 to 2013.

  • 8/20/2019 Performance Audit Reports

    10/142

     Acquisition and Use of Lands for Government Projects   4

    1.5 Geographical Coverage

    The audit covered the Island of Mauritius.

    1.6 Assessment Criteria

    The Performance Indicator as set in the Programme Based Budget (PBB) Estimates 2010

    regarding completion of all procedures for acquisition of private lands for public projects

    within five months, and the Sections of the LAA as shown in Table 1 were used as

    assessment criteria.

    Table 1 Sections of the LAA used as assessment criteria

    Sections Brief  

    6 Issue of investigation notice in respect of land likely to be

    compulsorily acquired

    8(2) & 8(3) Publication of notices

    14(1) Compensation to beneficiaries

    18(6) Interest payable on compensation to beneficiaries

    Source : LAA

    1.7 Audit Methodology

    The audit was conducted in accordance with relevant standards of the International Standards

    of Supreme Audit Institutions. The following methodologies were used for the audit to

    understand the audit area, along with gathering sufficient, relevant and reliable audit evidence

    to support the conclusions and recommendations.

    1.7.1 Documents Reviewed 

    The audit team collected data mainly through file reviews. The data from the TreasuryAccounting System for the past 10 financial years were extracted to examine the trend of 

    expenditure on the acquisition of privately owned lands. The procedures for compulsory

    acquisitions and those through private agreements, as established by MHL were also

    reviewed. Further, as the land acquisition process is regulated, the different Sections of the

    LAA 1982, as amended in 2013 were referred to.

    1.7.2 Sampling

    A sample of acquisitions for the implementation of road projects for the Road Development

    Authority (RDA) over the period 2009 to 2013 was selected.

  • 8/20/2019 Performance Audit Reports

    11/142

     Acquisition and Use of Lands for Government Projects   5

    Another sample of plots of land acquired and vested on or prior to year 2010 in the following

    selected Ministries and Government Departments was also referred to in view of taking

    cognizance of their planning and recording systems, as well as their statuses as of February

    2015.

    Ministry of Local Government and Outer Islands (MOLG)

    Mauritius Fire and Rescue Service (MFRS)

    National Development Unit (NDU)

    Ministry of Youth and Sports (MYS)

  • 8/20/2019 Performance Audit Reports

    12/142

     Acquisition and Use of Lands for Government Projects   6

  • 8/20/2019 Performance Audit Reports

    13/142

     Acquisition and Use of Lands for Government Projects   7 

    CHAPTER TWO

    DESCRIPTION OF THE AUDITED ACTIVITY

    This Chapter describes the role and responsibilities of MHL and the activities of the other key

     players in relation to acquisition of land. It also briefly describes the responsibilities of selected  Ministries and Government Departments for requesting lands from MHL and those of RDA regarding acquisition of lands for construction of roads.

    2.1 Role and Responsibility of MHL in the Acquisition Process

    MHL acquires lands on behalf of Ministries and Government Departments through private

    agreements and compulsorily. Compulsory acquisitions are carried out within the legal

    framework of the LAA 1982, as amended in 2013.

    Sections 8 and 9 of the Constitution provide for the protection of the rights of any personfrom the deprivation of property and privacy of home and other property. The LAA confers

    on the State the right to compulsorily acquire any land provided, amongst others, the

    conditions laid down in the Constitution are fulfilled and adequate compensation is paid.

    2.2 Requests for Lands and Vesting Procedures

     2.2.1 Road Development Authority (RDA)

    The RDA is involved in land acquisition for construction of roads. Its Surveyors carry out the

    following tasks.

    A preliminary survey of ownership is carried out and the land owners are notified by

    letter. A list is prepared providing all details on ownership, and the area required for the

    project

    Searches are carried out at the Registrar General’s Department to confirm the legal

    ownership of each plot

    Notices as required under Sections 6 and 8 of the LAA are prepared by RDA and sent to

    MHL for vetting, approval by Minister and publication

     2.2.2 Other Selected Ministries and Government Departments

    The process starts with the identification of projects. All project proposals are sent to the

    Accounting Officers of respective Ministries and Government Departments for approval. The

    requests for lands are then addressed to the Senior Chief Executive of MHL. A joint site

    visit, involving the Ministry or Government Department and other stakeholders, is organised

    by MHL to assess the suitability and location of the land. Upon satisfaction, MHL undertakes

    acquisition and vesting procedures.

  • 8/20/2019 Performance Audit Reports

    14/142

     Acquisition and Use of Lands for Government Projects   8

    2.3 Organization Structure of MHL

    The mission and objectives of MHL include the management and the control of development

    on State Lands. To achieve the mission and the objectives, the activities of MHL are

    organized within several Divisions. The Planning and Survey Divisions are relevant for this

    audit.

     2.3.1 Planning Division

    The main activities of the Planning Division include the identification of land for

    Government projects in consultation with the relevant stakeholders.

     2.3.2 Survey Division

    The Survey Division provides information on availability of State Lands. Where State Landsare not available, it helps in identifying privately owned lands for acquisition. The Division

    includes the Land Acquisition and Project Unit, which carries out all the activities from

    notification to award of compensation to beneficiaries, and also monitoring same. It records

    the land acquisition data, such as date of request, the current statuses of different notices

    issued as required by the LAA and payment of compensation to beneficiaries.

    2.4 Key Players and Their Activities

    Besides MHL, there are other key players involved in the acquisition of lands, namely

     Registrar General's Department

    The registration and transcription of title deeds is done at the Registrar General’s Department.

    Valuation Real Estate and Consultancy Services (Valuation Department)

    The Valuation Department assesses compensation payable to land owners.

    Attorney General’ s Offi ce 

    It appoints Public Notaries on behalf of MHL and issues instructions for the drawing up of deeds of sale, as well as providing legal assistance for cases referred to the BOA.

    2.5 Recording of Vested Lands

    The Land Information Unit (LIU) at MHL maintains records of State Lands leased and

    acquired lands vested in Ministries and Government Departments for implementation of 

    projects in “Microsoft Office Access”. Some of the data that are input include Parcel ID,

    District, locality, file reference, type of lease, purpose, rent amount and name of lessee.

    Reports are generated accordingly.

  • 8/20/2019 Performance Audit Reports

    15/142

     Acquisition and Use of Lands for Government Projects   9

    With a view to coming up with a complete register of all private and State Lands throughout

    the country, MHL acquired in December 2008, the Land Administration and Valuation

    Information Management System (LAVIMS). It consists of four components, and has two

    main objectives, namely establishing an efficient and cost-effective land administration and

    online information register, and to set up a general valuation roll of some 350,000 residential

    properties, private or State owned. The System, which had cost some Rs 600 million inDecember 2008, would be a powerful web-based information management system to allow

    efficient interaction, retrieval and analysis of the data by all its potential stakeholders.

    2.6 Project Plan Committee

    A Project Plan Committee (PPC) was set up in the Ministry of Public Infrastructure and Land

    Transport in 2009. Its main objective is the assessment of the infrastructure needs of the

    various sectors of the economy. Its functions include the examination of the feasibility and

    cost benefits of infrastructure project proposals. All investment proposals above Rs 25

    million, excluding cost of land, have to be reviewed by the PPC, in consultation withimplementing agencies and other concerned Public Bodies prior to the development of a

    pipeline of projects. An Investment Project Proposal from the requesting Ministry and

    Government Department estimated at below Rs 25 million does not require the approval of 

    the PPC, but are submitted to the Ministry of Finance and Economic Development (MOFED)

    for approval.

  • 8/20/2019 Performance Audit Reports

    16/142

     Acquisition and Use of Lands for Government Projects   10

  • 8/20/2019 Performance Audit Reports

    17/142

     Acquisition and Use of Lands for Government Projects   11

    CHAPTER THREE

    FINDINGS

    This Chapter describes the findings related to land acquisitions and use, recording and monitoring mechanisms at MHL and the selected Ministries and Government Departments.

    3.1 Land Acquisition

    MHL has not always been able to acquire land on a timely basis and in the most economical

    manner. This was mainly attributed to long procedures, as well as the absence of a time frame

    for other parties to respond to MHL.

     3.1.1 Long Procedures

    During the past years, with the massive investment on Government projects, the demand for

    land has increased considerably. Hence, the timely acquisition and vesting of lands in the

    requesting Ministries and Government Departments is vital to ensure that projects are

    implemented on time.

    Targets not Met 

    One of the Performance Indicators of MHL, as stated in the PBB Estimates for 2010, was the

    completion of all acquisition procedures within five months.

    In the cases listed in Table 2, MHL has taken more than five months for completing the

    acquisition procedures.

    Table 2 Time Taken to Complete Acquisition Procedures

    Project Funding

    Ministry

    No. of Lots

    Acquired

    Request

    Date

    Transcription

    Date

    Time

    TakenConstruction of Football

    Ground at Quatre Bornes MPI - NDU 1 28.06.11 13.12.121 year 5

    months

    Widening of Belle Vue

    Road (B22) from Petite

    Retraite to LaventureMPI - RDA 35 26.02.10 28.06.11

    1 year 4

    months

    Extension of Trois Ilots

    Cemetery MOLG 1 19.11.07 15.05.124 years 5

    months

    Construction of Cremation

    Ground at Clavet MPI - NDU 1 30.01.03 29.03.1310 years 2

    months

    Incineration Project at

    Beau ChampMPI - NDU 1 23.05.12 18.03.13 9 months

    Source: MHL’s Records

  • 8/20/2019 Performance Audit Reports

    18/142

     Acquisition and Use of Lands for Government Projects   12

     Requests not Met 

    In other cases, for example the relocation of the two Fire Stations at Quatre Bornes and Port

    Louis (Case Studies 1 and 2), lands initially identified for the projects in years 1984 and 2010

    respectively were found unsuitable. Although MFRS made several requests for alternative

    sites, as of February 2015, MHL has not yet identified the appropriate lands for the relocationof the two Fire Stations. Government has already approved the required funds needed to

    implement the projects.

    Case Study 1 - Relocation of Quatre Bornes Fire Station

    The relocation of Quatre-Bornes Fire Station dates back to 1976, in anticipation of the expiry of the

    lease agreement. It was also found that the Fire Station is situated in the middle of the town, being

    most of the time heavily congested due to numerous commercial activities taking place in the vicinity.

     Hence, the fire trucks are often found to be obstructed in traffic jams. A plot of land in Quatre Bornes

    vested for relocating the Fire Station in 1984 was found unsuitable for the project by the then

     Ministry of Works, being triangular in shape, thus offering no training and drilling facilities. The presence of a bus lay-by would also hinder visibility, and no direct access on St Jean Road was

    allowed. On 20 August 2009, MOLG expressed no objection to the release of the plot of land subject 

    to an alternative site be identified for the relocation of the Fire Station.

    On 25 March 2014, a plot of land of an extent of about 1A35P at Avenues des Tulipes, Quatre Bornes

    was identified. However, on 9 June 2014, MHL informed that the site was found inappropriate, due to

    sensitive uses in close proximity thereto. MFRS was requested to identify three alternative sites for the

    eventual relocation of the Quatre Bornes Fire Station. As of February 2015, the appropriate land was

    not yet identified.

    Case Study 2 - Relocation of Port-Louis Fire Station

    On 22 November 2006, MPI submitted a structural investigation report, which stated that the building

    suffers from structural defects and is unsafe and beyond economic repair. On 29 October 2009, the

    Occupational Safety and Health Unit submitted a report which stated that the wooden structure could 

    not be restored. Two sites were identified, one at Roche Bois to cater for a sub-station, and the other 

    one at Colline Monneron for a main station. At a meeting held on 21 June 2010, mention was made

    that the site at Roche Bois was located on a busy round about which could hamper the rapid turn out 

    of the fire fighting vehicles. Further, RDA did not agree to have a direct access on the roundabout as

    it represented a safety hazard.

     In March 2012, the Ex-Sea Training School at Victoria Square was being considered. At a meeting

    held in April 2012, it was decided to seek the views of the Traffic Management and Road Safety Unit 

    as the site is found in a congested area with the existence of Victoria Bus Station and narrow roads.

    On 1 November 2012, MFRS agreed to take possession of the 16A30 of State Land at Jin Fei in view

    of accommodating a Fire Station and the new Head Quarters and a Training Academy. The Colline

     Monneron Site was rejected by the PPC in 2010 and revived by the ex-Government Fire Services in

    2013. The project was submitted to the PPC, which stated that a feasibility study was required.

     At a meeting held on 23 July 2013, mention was made that it was not convenient to relocate the Port-

     Louis Fire Station at Jin Fei because the city of Port-Louis harbours intense trading activities which

    imply all sorts of fire hazards. If the time taken to reach the spot is too long, this may result in

    magnitude of fire taking shape becoming out of control and which in turn could lead to paralyzing the

    capital completely. As of February 2015, the appropriate land was not yet identified.

    Source: Selected Ministries and Government Departments

  • 8/20/2019 Performance Audit Reports

    19/142

     Acquisition and Use of Lands for Government Projects   13

     Late Handing Over of Sites

    There were also cases of lands not available on time to RDA that caused late handing over of 

    sites to Contractors for the construction of roads. This caused RDA to extend completion

    dates of the projects and to incur additional costs. Examples are given in Table 3.

    Table 3 Effect of Late Handing Over of Site

    ProjectNo. of 

    Days

    Additional Costs

    Rs

    Phoenix-Beau Songes Link Road 60 2,433,378

    Goodlands Bypass 123 12,603,815

    Port-Louis Ring Road 35 3,884,094

    Construction of Bidirectional Lane from St Jean to Pont Fer 67 4,829,857

    Schoenfeld Bypass II 63 4,941,482

    Upgrading of Avenue des Tulipes 14 408,748

    Source: RDA

    Publication of Corrigenda

    Compulsory acquisition under the LAA involves the publication of Notices by MHL as

    required under Sections 6 and 8. However, for construction of roads, it is the practice forRDA to carry out the preliminary survey of ownership on site, and title deed searches at theRegistrar General’s Department, and also to prepare Notices.

    Owner identification is time consuming. At times, after the notices were issued, errors were

    detected mainly regarding ownership of land and which required corrigenda to be published.

    These corrigenda involved use of additional resources in terms of money and take additional

    time for the republication of notices. In a few cases, MHL had to send several reminders for

    correction and resubmission of notices for finalizing acquisition procedures (for example in

    the case of the project for the Construction of Bidirectional Lanes from St Jean to Pont Fer,

    and enlargement of Belle Vue Road B22).

    During an examination of a sample of projects, several cases were noted where corrigenda

    were published as illustrated in Table 4.

  • 8/20/2019 Performance Audit Reports

    20/142

     Acquisition and Use of Lands for Government Projects   14

    Table 4 Number of Corrigenda Published 

    Project No. of  

    Portions

    No. of 

    Corrigenda

    Terre Rouge - Verdun Link Road 332 23

    Phoenix – Beau Songes Link Road 256 13

    Triolet Bypass 205 17

    Access Road to New Triolet Market 55 15

    South Eastern Highway Project 107 39

    Source: Land Acquisition and Project Unit 

     3.1.2 Absence of a Time Frame

    The current LAA does not cater for the situations as described below. This resulted in lands

    not available on time and at least cost.

    Time for Reply from ex Valuation Department not Prescribed 

    Compensation payable is assessed by the ex Valuation Department. A request for assessment

    is made to the Department in writing after the land has been transcribed, and as soon as a

    reply is received at MHL, an offer is made to the land owner. However, the LAA does not

    prescribe the time within which the Department should reply to MHL. In a few cases, repliesfrom the ex Valuation Department were received after more than five months, and this has

    caused delay in the completion of the acquisition procedures. Examples of such cases are

    given in Table 5.

    Table 5 Reply from the Valuation Department Exceeding Five Months

    Project Request for

    Assessment  Reply Date

      Months

    Taken

    Enlargement of Pamplemousses-Grand

    Baie Branch Rd 07.12.10 19.05.11 6

    Construction of Triolet BypassAug/Sep 09 Oct 09/ June 10 2 - 9

    Verdun-Trianon Link RdJan 11/Apr 11 Sep 11/July 12 8 - 15

    Construction of Bidirectional Lane from

    St Jean to Pont Fer Aug 10 April 12 9

    Source: Land Acquisition and Project Unit 

  • 8/20/2019 Performance Audit Reports

    21/142

     Acquisition and Use of Lands for Government Projects   15

    Time Lag for Reply From Former Landowners not Defined 

    The offer for compensation to the former landowners is made after the publication of Notice

    under Section 8 of the LAA and transcription of the land. However, the time lag to accept or

    reject an offer is not mentioned in the LAA. For example, one former landowner of a

    particular project was offered Rs 898,000 for his land on 21 May 2002. On 15 May 2009, thatis some seven years later, the landowner made a counter claim of Rs 4,474,024 for the land.

    After deliberations, the claim was reduced to Rs 1,691,700, and in March 2011, a sum of 

    Rs 2,937,949, including interest of Rs 1,246,249 (73 per cent of compensation) for the period

    April 2002 to October 2010 had to be disbursed by MHL.

    Payment of Interests

    In some cases, MHL had to disburse additional funds in terms of interest payments on

    compensation because of the time lag between the transcription date and the payment date.

    The cases listed in Table 6 are examples where interests had been paid. The time lag ranges

    between 311 to 543 days.

    Table 6 Examples of Interest Paid 

    Date of 

    Project Transcription Appointment

    of Notary

    No. of 

    Days

    Compensation

    Rs

    Interest

    RsPhoenix – Beaux

    Songes Link Road 05.01.10 21.04.11 472 22,000,000 2,275,945

    Verdun Trianon

    Link Road 11.04.11 05.10.12 543 35,200,000 4,189,282

    Port-Louis Ring

    Road 16.07.10 03.08.11 384 18,000,000 1,514,959

    Port Louis – Plaisance Dual Way 19.07.11 25.05.12 311 1,180,000 80,434

    Source: Land Acquisition and Project Unit 

    MHL contended that these interests were paid because the owners were deprived of their

    rights on the acquired lands. However, the longer the time taken to pay the compensation, the

    higher will be the interests. LAA does not provide for a time frame so as to reduce to a

    minimum the interests.

    3.2 Land Use

     3.2.1 Statuses of Lands Vested 

    The requests for lands by the ex-Government Fire Services, now MFRS, to MHL were

    initiated following a review carried out in 1991, whereby the construction of additional Fire

    Stations was recommended. As regards MYS, the requests for lands were made for the

    construction of sports infrastructures in view of promoting sports in different regions of the

    country, and to cater for both national and international sports events. Details are given inTable 7.

  • 8/20/2019 Performance Audit Reports

    22/142

     Acquisition and Use of Lands for Government Projects   16

    Table 7 Examples of Vested Lands not yet Developed 

    Ministry Vesting Date Purpose Extent

    (m2)

    Cost

    (Rs million)

    MOLG – MFRS 01.09.1999 Fire Station at Montagne Blanche 4,010 1.2

    06.05.2003 Fire Station at Goodlands 4,221 4.5

    MYS 19.01.2005 Gymnasium at Lallmatie 9,554 5.7

    15.04.2002 Swimming Pool at Camp Garreau 8,572 2.2

    09.03.2010 Swimming Pool at Riviere Des Anguilles 8,006 1.3

    Source: Selected Ministries and Government Departments

    As indicated in Table 7, these lands were acquired and vested in the Ministries and

    Government Departments on or before year 2010, and as of February 2015 they were not yetdeveloped. This was attributed to unavailability of funds to implement the projects.

     3.2.2 Funds for Projects

    MHL has taken good initiatives regarding confirmation from implementing agencies of 

    availability of funds before embarking on the acquisition process. However, the procedures

    need to be revisited because one of the conditions is that the implementing agencies should

    have land readily available for their projects before the proposals are submitted to the PPC.

    Funds for the implementation of projects are disbursed by MOFED after it has been approved

    by PPC. On the other hand, MPI has stated that unless there are appropriate funds available, itwill not embark on the conception of the preliminary drawings.

    Presently, there is no mechanism at MHL to ensure that the requesting Ministries and

    Government Departments have properly planned the projects implementation and that

    appropriate structural designs for the buildings are available at the time of request (Case

    Studies 3 to 7). In the case of the proposed Swimming Pool at Camp Garreau, MHL had to

    spend additional resources for carrying out site surveys on several occasions, upon request of 

    MPI.

    Case Study 3 – Construction of Rose Belle Fire Station

    Two plots of land of 3,000 m2 and 1,200 m2 were vested on 16 July 1998 and 5 September 2001

    respectively for the construction of the Rose-Belle Fire Station. The lands were acquired from the

     Rose Belle Sugar Estate under the Sugar Industry Efficiency Act, which implied that no funds were

    disbursed for acquiring the plots of land.

     Acquisition and vesting procedures had to be carried out twice. This was attributed to the non-

    availability of structural designs at the time of request, and as such, the extent of land needed for the

    construction of the Fire Station could not be ascertained.

     As of February 2015, the drawings for the Fire Station were completed, and tender procedures will be

    launched during the year.

  • 8/20/2019 Performance Audit Reports

    23/142

     Acquisition and Use of Lands for Government Projects   17 

    Case Study 4 – Construction of Goodlands and Montagne Blanche Fire Station

    Two portions of land of 4,010 m2 and 4,221 m2 costing some Rs 1.2 million and Rs 4.5 million were

    vested in the years 1999 and 2003 respectively.

     In August 2012, following a request from MPI, MHL submitted a detailed survey of the land and 

    location plan for both sites. MPI was requested to prepare the preliminary drawings and to submit a

    cost estimate to seek funds from MOFED. As of August 2014, the preliminary drawings for the Fire

    Station were not ready and reminders for that purpose were sent to MPI.

     In its reply, MPI stated that it is awaiting completion of design for the Rose Belle Fire Station as same

    might be used as a prototype for the new Fire Station at Montagne Blanche and Goodlands. As of 

    February 2015, the two plots of land were still not developed.

    Case Study 5 –  Proposed Swimming Pool at Camp Garreau

     A plot of land of an extent of 9,999 m2 at Camp Garreau was compulsorily acquired in March 2002

    and vested in MYS April 2002. In December 2004, the preliminary drawings were approved with

    amendments, as it was proposed that the size of the swimming pool be increased from 25 metres x 20

    meters to 25 meters x 25 meters in order to accommodate eight lanes instead of six lanes so as to meet 

    greater demand from the public.

     In January 2005, MPI submitted estimates of cost for both six and eight lanes swimming pools of Rs

    46.5 million and Rs 49 million respectively. In July 2010, the specifications of the swimming pool

    were revised to 50 meters with eight lanes, and MPI was again requested to prepare preliminary

    designs, drawings, scope of works and cost estimates.

     In a letter dated 10 December 2010, MHL informed MYS that due to encroachment on the land, the

    extent was reduced to 8,572 m2. In May 2011, MPI stated that the 50 metre swimming pool together 

    with ancillaries could not be adjusted on the given site.

     In August 2011, in view of the site constraints, MYS proposed to go ahead with the construction of a

    25 metre long swimming pool instead of a 50 metre one, and MPI was requested to prepare relevant 

    design and cost estimates to enable an early implementation of the project. In January 2012, MYS 

    requested MHL to acquire additional land to cater for an access to the site from the main road, and 

     for the construction of a kid’s pool. In March 2012, MPI worked out a tentative implementation

    schedule of the project.

     In April 2012, MYS submitted the Project Request Form (PRF) to MPI to be considered by the PPC.

    The PRF made mention of the construction of a 50 metre swimming pool, inclusive of changing

    rooms, showers, toilet, administrative blocks, a stand for spectators, parking facilities and toilets. The

    estimated total cost was Rs 123 million. In August 2012, the proposal was approved by the PPC.

     Although the PPC approved the construction of a 50 metre swimming pool, MYS decided in February

    2014, to revise the size to 25 meters. As of February 2015, the plot of land was still not developed.

  • 8/20/2019 Performance Audit Reports

    24/142

     Acquisition and Use of Lands for Government Projects   18

    Case Study 6 - Proposed Swimming Pool at Riviere des Anguilles.

     In March 2010, a plot of land of an extent of 8,006 m2 was vested in MYS for the construction of a

    swimming pool. MYS intended to proceed with the construction of a 50 metre swimming pool with

    eight lanes, and in July 2010, requested MPI to prepare preliminary designs, drawings and scope of works together with cost estimates.

    The swimming pool would include a Grand Stand to accommodate 1,000 persons together with

     parking facilities. Following a survey of the site, MPI informed that additional space would be

    required for the provision of parking facilities. On 15 October 2010, MHL was requested to acquire

    an additional extent of land. On 4 February 2011, a site of an extent of 1,500 m 2 was identified and 

    agreed.

     In May 2011, MYS informed MPI that due to constraints as regard the size of the site, it has decided 

    to go ahead with the construction of a 25 metre instead of a 50 metre swimming pool. As of February

    2015, the plot of land was still not developed.

    Case Study 7 - Multipurpose Gymnasium at Lallmatie

     In January 2005, two portions of land of extent of 4,686 m2 and 4,868 m2 respectively were vested in

     MYS for the construction of a Multipurpose Gymnasium at Lallmatie. In April 2006, it was agreed 

    that the project would be of international standard, including parking facilities.

     In November 2007, MYS requested MPI to include a Boulodrome in the drawings and the

    modifications to drawings were made in December 2007. In February 2008, MPI was requested to

     proceed with the preparation of scope of works and breakdown of cost estimates. As of February

    2015, the plot of land was still not developed.

    Source: Selected Ministries and Government Departments

    3.3 Recording of Vested Lands

    It is important to have a complete and accurate record of all vested lands as it helps to

    enhance and to support effective asset decision-making.

     3.3.1 Recording of Vested Lands at MHL

    The records of vested lands in Ministries and Government Departments kept at the LIU were

    not complete. The current system of record-keeping at the LIU is not appropriate to cater for

    the increase in number of plots of land acquired over the years. For example, the following

    plots of land acquired and vested in NDU, as mentioned in Table 8, were not found in the

    database. This was mainly attributed to insufficient input and monitoring controls.

  • 8/20/2019 Performance Audit Reports

    25/142

     Acquisition and Use of Lands for Government Projects   19

    Table 8: Examples of Vested Lands not Recorded at LIU 

    Projects Extent (m2) Vesting Date

    Football Ground at Quatre Bornes 10,552 18.01.13

    Cremation ground at Clavet 1,913 10.05.13

    Extension of Trois Ilots Cemetery 11,448 06.06.12

    Extension of Edgard Millen Government School 584 01.07.13

    Source: MPI-NDU 

     3.3.2 Land Administration, Valuation and Information Management System (LAVIMS)

    Most of the components of the LAVIMS were completed in September 2011. Thereafter,

    digitization process of properties deeds was initiated. It was decided that this process would

    cover a period of past 30 years from the year 2008.

    However, it was reported that all the deeds could not be uploaded onto the System, and this

    was attributed to the absence of a valid site plan attached to the deeds. The System could not

    also generate requested statistical reports and the input process excluded data on all State

    Lands completely.

     Digital State Land Register 

    Due to the limitations with the LAVIMS, MHL has initiated the Digital State Land Register

    Project (DSLR). This Project would entail a detailed inventory of all State Lands.

    Subsequently, in August 2012, the possibility of incorporating the DSLR into the LAVIMS

    was discussed. It was decided to create a program within LAVIMS to cater for State Lands.

    However, MHL would have to see if the contractor of LAVIMS would be agreeable to give

    the relevant codes.

    In October 2013, a meeting was held with an officer of the Central Informatics Bureau to

    discuss on the drafting of the Terms of Reference for the setting up of a DSLR. It was

    proposed that the tool would require to be well defined to meet all the requirements in respect

    of retrieval of information for various purposes. It was agreed that the base should beLAVIMS wherein the DSLR would only be a component.

    On 25 August 2014, MHL sought advice from the Attorney General’s Office and MOFED as

    to whether the former contractor of LAVIMS might be contacted directly without having

    recourse to open tender exercise. As of February 2015, no reply was obtained.

    I am given to understand that a high level committee will be set up to work on the technical

    specifications of the DSLR

  • 8/20/2019 Performance Audit Reports

    26/142

     Acquisition and Use of Lands for Government Projects   20

    3.4 Monitoring of Vested Lands by MHL

    Several plots of land acquired on or prior to year 2010 have remained undeveloped.

    Monitoring of these plots of land is important as MHL had disbursed funds to acquire same.

    Information on the extent of lands acquired but not developed was not readily available at

    MHL, as it does not have a complete database on the statuses of vested lands. It was notclearly defined as who should ensure that lands vested were used on a timely basis and for the

    intended purposes. Moreover, there were no established procedures for Ministries and

    Government Departments to give feedback on the current statuses of the lands.

    3.5 Land Acquisition Recording and Payment System

    The land acquisition process consists of different steps from the time requests are received at

    MHL to payment of compensation to beneficiaries. Bottlenecks at one or more steps result in

    long delays in the acquisition of lands. Monitoring of the activities, based on appropriate and

    readily available information, at each step is therefore essential for timely acquisition of theland.

    However, information relating to outstanding payments of compensation, outstanding

    requests, outstanding cases to BOA and follow-up of replies from other stakeholders was not

    readily available at the Land Acquisition and Project Unit. This did not help the Ministry to

    monitor the different activities and to identify bottlenecks in the acquisition process. These

    are illustrated in the examples below:

    Improvement of the Quartier Militaire Road (B6) and the construction of a Bypass at

    Valetta SN11  – The Valuation Department recommended the case to be referred to the

    BOA on 23 August 2011. It was only one year later, on 27 August 2012, that the Ministry

    initiated action to refer the case to the BOA.

    Cremation Ground at Clavet - MHL initiated the purchase of land for the project in

    January 2003. The acquisition procedures went on till July 2006. Thereafter, there was no

    follow up on the project till June 2008, when NDU sought information from the Ministry

    about the status of the project.

     3.5.1 Present Acquisition and Payment Systems

    Government acquires lands through either private agreements or compulsorily. Compulsory

    acquisitions are carried out as per the provisions of the LAA. Presently, all requests for land

    acquisitions from Ministries and Government Departments are directed to MHL and

    payments to the land owners are effected by MHL from funds under its Vote. Under the

    current system, Ministries and Departments disbursed funds under their Vote only for the

    infrastructural works, whereas MHL paid for the land. There is no single Ministry/ 

    Government Department accountable for the whole project, including the land.

  • 8/20/2019 Performance Audit Reports

    27/142

     Acquisition and Use of Lands for Government Projects   21

    CHAPTER FOUR

    CONCLUSION AND R ECOMMENDATIONS

    Several plots of land acquired and vested in the selected Ministries and GovernmentDepartments on or prior to year 2010 were still not developed. Acquisitions were made

    without a firm commitment to implement projects. Hence, the objectives set have not been

    achieved. This has resulted from the absence of a proper mechanism at MHL to ensure that

    the requesting Ministries and Government Departments had funds and structural designs

    available at the time of requests. For few cases regarding construction of roads, MHL could

    not ensure availability of the lands on time and in the most economical manner. Records of 

    vested lands and their current statuses at MHL were incomplete.

     In the light of the audit findings and conclusion, hereunder are the recommendations

    4.1 Land Acquisition

     4.1.1 Funding

    Consideration may be given for the requesting Ministry and Government Department to make

    provision for the payment of compensation to land owners in their respective budgets. The

    latter will be accountable for the implementation of the project, including the acquisition of 

    land. MHL will effect payment on receipt of a Departmental Warrant from them.

     4.1.2 Time Frame for Acquisition and Reply

    MHL should attend to all requests for land acquisitions and ensure that acquisitions and

    vesting are completed within a reasonable time. As regards the relocation of the two

    existing Fire Stations at Quatre Bornes and Port Louis respectively, the appropriate lands

    need to be identified and acquired

    Time frame for reply from beneficiaries also needs to be established.

    Ministry’s Reply 

    MHL has considered the regularization of a time frame for the acceptance/ rejection of an

    offer.

     4.1.3 Time Frame For Payment of Compensation

    Procedures need to be established to reduce the time lag between the transcription date and

    payment date so as to minimize interests.

  • 8/20/2019 Performance Audit Reports

    28/142

     Acquisition and Use of Lands for Government Projects   22

     4.1.4 Computerised Land Acquisition System

    MHL needs to improve its monitoring and follow-up of requests at each step in the

    acquisition process. This will require more up to date and readily available information. A

    better approach could be to automate the land acquisition system. This would have the added

    advantages, such as:

    Improving the time taken to complete the land acquisition process

    Records are updated automatically

    Keeping track of the land records will become less complicated

    Better monitoring and follow-up to eliminate bottlenecks

     4.1.5 On-line Facilities of LAVIMS to RDA

    Owner identification is time-consuming. To speed up procedures and to facilitate RDA to

    search for ownership of land and title deeds, the latter needs to be provided with an access to

    LAVIMS.

    Ministry’s Reply 

    As RDA is not within GIN Network, no access could be established with LAVIMS server.

    However, RDA’s officers are granted full access to LAVIMS at the Cadastre Unit to carry

    out searches.

    4.2 Land Use

     4.2.1 Responsibility for Administration of Vested Lands should be Established 

    The role and responsibility of MHL and requesting Ministries and Government Departments

    in respect of project implementation on vested lands should be clearly established. It should

    also be defined who should ensure that lands vested are used on a timely basis and for the

    intended purposes.

     4.2.2 Preparation of Need Analysis Before Requesting for Land Acquisition

    Need Analysis and project design and description should be prepared much ahead before

    embarking on request for acquisition of land for a project. Appropriate extent according to

    project specifications should be acquired so that there is judicious use of land.

     4.2.3 Setting up of a Committee for Project Implementation

    Ministries and Government Departments should have recourse to MPI for the preparation of preliminary designs, drawings and scope of works together with cost estimates only after it is

  • 8/20/2019 Performance Audit Reports

    29/142

     Acquisition and Use of Lands for Government Projects   23

    confirmed that MOFED would disburse the funds. A consultative platform needs to be set up

    by the requesting Ministry/ Government Department bringing in all stakeholders so that there

    is a constructive dialogue and everyone knows his role, responsibilities and obligations. This

    will minimise any future unproductive vesting.

    As regards lands vested and which have so far not been developed, Ministries andGovernment Departments should liaise with MOFED as soon as possible to ensure that funds

    would be disbursed for implementing the outstanding projects.

    Land acquired and vested should be utilized within reasonable time. If not used, MHL should

    be notified so that the lands can be retrieved and vested in other Ministries and Government

    Departments to ensure their optimum economic use.

    4.3 Recording and Monitoring of Vested Lands

    A database of lands acquired is not enough to exercise proper control over land utilization. Acomplete database on status of all lands vested in Ministries and Government Departments

    should be built up. Ministries should then be requested to submit feedback at regular intervals

    on implementation of projects. To ensure that Government funds are used effectively and

    efficiently, it is vital that MHL maintains control on all State Lands. The DSLR should be

    developed.

    Ministry’s Reply 

    Action is being taken for updating the records.

  • 8/20/2019 Performance Audit Reports

    30/142

    PERFORMANCE AUDIT REPORT

    LEASE AND USE OF

    GOVERNMENT OFFICE ACCOMMODATION

    Ministry of Public Infrastructure and Land Transport

    July 2015

  • 8/20/2019 Performance Audit Reports

    31/142

  • 8/20/2019 Performance Audit Reports

    32/142

     Lease and Use of Government Office Accommodation i

    CONTENTS

    Page

    ABBREVIATIONS AND ACRONYMS iii

    EXECUTIVE SUMMARY 1

    CHAPTER ONE: INTRODUCTION

    1.1 Government Office Accommodation 3

    1.2 Motivation 3

    1.3 Audit Objective 3

    1.4 Audit Scope 3

    1.5 Selected Ministries 4

    1.6 Methodology and Sources of Information 5

    CHAPTER TWO: GOVERNMENT OFFICE ACCOMMODATION IN MAURITIUS

    2.1 System Description for Renting GOA (New Request) 7

    2.2 System Description for Renewal of Lease Agreement and/ or Renting of AdditionalSpace within Same Building

    7

    2.3 Responsibilities and Functions of Stakeholders 8

    2.4 Audit Criteria 8

    CHAPTER THREE: FINDINGS

    3.1 Expenditure Relating to GOA 9

    3.2 Initiatives Taken 12

    3.3 Government Office Accommodation Policy 15

    CHAPTER FOUR: CONCLUSION AND RECOMMENDATIONS

    4.1 Conclusion 19

    4.2 Recommendations 19

    TABLES

    1 International Benchmarking and Audit Criteria 6

    2 Expenditure Incurred on Rent of GOA during the Past Five Years 9

    3 Annual Cost per Employee – Year 2014 10

    4 Occupancy Rate per Employee at some Ministries and Government Departments 11

    APPENDIX

    Clearances from Stakeholders before awarding Contract to Lessor 21

  • 8/20/2019 Performance Audit Reports

    33/142

     Lease and Use of Government Office Accommodation ii

  • 8/20/2019 Performance Audit Reports

    34/142

     Lease and Use of Government Office Accommodation iii

    ABBREVIATIONS AND ACRONYMS

    GOA Government Office Accommodation

    GOMU General Office Management Unit

    MOFED Ministry of Finance and Economic Development

    MOHQL Ministry of Health and Quality of Life

    MPI Ministry of Public Infrastructure

    MFRS Mauritius Fire and Rescue Service

    ESD Ministry of Renewable Energy and Public Utilities - Energy Services Division

    NAO National Audit Office – Mauritius

    OAS Office Accommodation System

    OSHA Occupational Safety and Health Act

    PMO Prime Minister’s Office

    PPA Public Procurement Act

    PPO Procurement Policy Office

    TMRSU Traffic Management and Road Safety Unit

    TAS Treasury Accounting System

  • 8/20/2019 Performance Audit Reports

    35/142

     Lease and Use of Government Office Accommodation iv

  • 8/20/2019 Performance Audit Reports

    36/142

     Lease and Use of Government Office Accommodation 1

    EXECUTIVE SUMMARY

    Government Office Accommodation (GOA) portfolio includes both owned and leasedpremises and is considered a key factor in supporting the general administration and

    operations, including client service functions in Ministries/ Government Departments. Thetotal expenditure on rental of office accommodation for the years 2010 to 2014 was someRs 2.8 billion.

     Key Findings

    Rental of office accommodation remains a significant annual financial commitment forboth Ministries/ Government Departments. Most of the Government officeaccommodation is concentrated in the region of Port Louis, where Government leases itsdifferent office spaces located in some 50 privately owned buildings with an annualcommitment of some Rs 380 million in year 2014, that is, 76 per cent of the totalexpenditure on lease in Mauritius.

    Cost per employee and occupancy rate are two metrics used to measure cost efficiency.An analysis of the data available for a sample of Ministries and Government Departmentsshowed that there are significant variations in these metrics.

    Government decided in year 2000 to rationalize the use of office space for public servicesthrough the setting up of a Unit, namely, the General Office Management Unit (GOMU)under the aegis of the Ministry of Public Infrastructure, and Land Transport (MPI).

    However, this Unit has not been able to take off. As of date (January 2015), MPI is stillcommitted to implement Government’s decision to set up GOMU.

    Government in the past came up with some construction projects, mainly to cut downexpenditure on rent, to relocate some offices away from the City in order to ease the thengrowing traffic problem in Port Louis, and to decentralise the economy and business.However, these projects did not take off although provisions for some of the projectswere made in the Capital Estimates.

    Government took the following initiatives to rationalise office accommodation, but wasunsuccessful in

    setting up a database of all buildings, rented and owned

    regrouping different Divisions of the same Ministry/ Government Department underone roof 

    developing guideline on standard space requirement for various grades of officers

    GOMU was responsible to formulate policies and strategies regarding officeaccommodation for both owned and leased buildings. However, pending the setting up of GOMU, Government has not yet come up with a written accommodation policy paper,

    accompanied with strategic and/ or long term plan.

  • 8/20/2019 Performance Audit Reports

    37/142

     Lease and Use of Government Office Accommodation 2

    Conclusion

    The cost of leased Government Office Accommodation is still significant, and is likely toincrease in future. The absence of an office accommodation policy and the current practice of leasing office space do not help Ministries and Government Departments to be cost efficient.

    There have been several initiatives taken by Government but these were not successfullyimplemented.

     Key Recommendations

    A long term GOA plan should be developed to rationalize office accommodation. Theplan should have clear objectives, strategies and measurable standards, along withappropriate time frame for the implementation of the strategies.

    Government may consider a coordinated, whole-of-Government approach in the planning

    and management of GOA. This should be accompanied with clearly defined role andresponsibility for the development of appropriate policy and strategies. All potentialstrategies must be evaluated as a whole rather than separately in order to identify a set of preferred strategies.

    Guidelines or directives on different aspects of office accommodation, such as areaoccupied per employee and the rental cost per employee could be developed andcommunicated to all Ministries/ Government Departments. A comprehensive database onoffice accommodation can help in the development of these guidelines. The database caninclude information, such as proportion of office owned and rented, location of buildings,rates, number of employees housed and details of lessors. A database of all potentiallandlords willing to lease their buildings could also be kept for greater efficiency.

    All the above recommendations can be achieved by putting in place a mechanism that willoversee all the activities related to Government Office Accommodation.

  • 8/20/2019 Performance Audit Reports

    38/142

     Lease and Use of Government Office Accommodation 3

    CHAPTER ONE

    INTRODUCTION

    1.1 Government Office Accommodation

    Government Office Accommodation (GOA) portfolio includes both owned and leasedpremises, and is considered a key factor for supporting the general administration andoperations, including client service functions, in Ministries and Government Departments.

    1.2 Motivation

    The rental of office accommodation which is a major expense for Government has been

    going up constantly over the years. Since year 2000, Government decided to rationalize theuse of office space for public services by taking several initiatives, but was not successful.

    On the other hand, the National Audit Office (NAO) conducted two Special Reviews onrental of GOA in 1994-95 and 2005-06 respectively. Both reviews arrived at the sameconclusion that Government expenditure in connection with rental was on the high side asMinistries and Government Departments were disbursing large amount of funds on rental of office building.

    This has prompted NAO to carry out this Performance Audit on GOA.

    1.3 Audit Objective

    The audit objective is to assess whether Government has adequate mechanism that ensuresoffice accommodation is leased and used in a rational way.

    1.4 Audit Scope

    1.4.1 Auditee

    GOA is a subject that cuts across all the Ministries and Government Departments. The mainauditee is the Ministry of Public Infrastructure and Land Transport (MPI). The Ministry of Finance and Economic Development (MoFED) is another auditee in so far as funding isconcerned.

    For the purpose of this audit, Parastatal Bodies, Mauritius Embassies, High Commissions andTourist Offices found abroad were excluded.

    1.4.2 Audit Object

    The audit focused on the mechanism put in place for acquiring and utilising office space.

  • 8/20/2019 Performance Audit Reports

    39/142

     Lease and Use of Government Office Accommodation 4

    1.4.3 Time Coverage

    Financial records relating to the years 2010 to 2014 were examined. These five financialyears were considered for trend analysis, and ease of comparison because of the transitionfrom fiscal year to calendar year basis.

    1.4.4 Geographical Area

    This report examines the existing processes and procedures to acquire and use GOA inMauritius as a whole.

    1.5 Selected Ministries

    The following Ministries and Government Departments were visited:

    Prime Minister’s Office (PMO)

    Ministry of Finance and Economic Development (MoFED)

    Ministry of Public Infrastructure and Land Transport (MPI)

    Ministry of Agro Industry and Food Security

    Ministry of Fisheries

    Ministry of Foreign Affairs, Regional Integration and International Trade

    Ministry of Gender Equality, Child Development and Family Welfare

    Ministry of Labour, Industrial Relations, Employment and Training (Labour Division)

    Valuation Real Estate Consultancy Services (ex Valuation Department)Procurement Policy Office (PPO), and

    Electoral Commissioner’s Office

    These Ministries/ Government Departments were selected on the following basis

    Offices of the Ministries and Government Departments in different buildings

    Responsibility for setting policy/ strategy, and

    Recent relocation of Ministries/ Government Departments in year 2010.

    This sample, which represents some 30 per cent of the total number of Ministries andDepartments, allows a better understanding of the mechanism put in place for the acquisitionand use of GOA.

  • 8/20/2019 Performance Audit Reports

    40/142

     Lease and Use of Government Office Accommodation 5

    1.6 Methodology and Sources of Information

    1.6.1 Interviews

    Interviews of officers from Senior and Middle Management, as well as Technical and

    Support Staff were conducted across 10 Ministries/ Government Departments. The objectivewas to better understand their roles, responsibilities and involvement in the acquisition anduse of GOA.

    1.6.2 Files and Documents Reviewed 

    Files were reviewed to corroborate information obtained through interviews. Proceduresfollowed by Ministries/ Government Departments to shift to another location were alsoassessed. Needs analysis, tender procedures, seeking clearances and approvals from otherGovernment Departments were some of the aspects that have been perused to ensure that

    Ministries/ Government Departments comply with established procedures.

    Files were also examined to obtain information regarding the terms of the lease, the areasrented, number of employees housed in the building, rates per square metre and the purposefor renting the building.

    Ministries’ procurement plan, Programme Based Budget Estimates and tender documentsrelating to the rental of new office were reviewed.

    Rent paid for the past years were obtained through the Treasury Accounting System (TAS).

    1.6.3 Relevant Acts

    Particular attention was given to the three Acts listed below:

    The Public Procurement Act (PPA) was referred to obtain information on the functionsand powers of the PPO and the Central Procurement Board, the different types of procurement methods that Ministries and Government Departments can resort to for theprocurement of works and services and the bidding process. However, in year 2012, thePPA was amended, and procurement undertaken by any Public Body in respect of rental

    of office space no longer falls under the purview of the Act.

    The Occupational Safety and Health Act (OSHA) was referred to understand the legalframework in connection with the minimum space allowed per employee at their place of work.

    The Landlord and Tenant (Amendment) Act was consulted to take cognizance of themethod of calculating any increase in rent regarding business premises let on or before1 July 2005.

  • 8/20/2019 Performance Audit Reports

    41/142

     Lease and Use of Government Office Accommodation 6 

    1.6.4 International benchmarking

    Benchmarking was carried out to understand how foreign countries and states are managingtheir office accommodation. (Table 1 refers).

    Table 1 International Benchmarking and Audit Criteria

    Country

    Policy

    Papers

    Occupancy

    Rate per

    Employee

    Whole of 

    Government

    Approach

    Interior

    Design

    Policy

    Database Centrally

    Managed

    Space

    New Zealand  

    Canada  

    United Kingdom  

    New South Wales(Australia)

     

    South Australia  

    Western Australia  

    Victoria (Australia)  

    Queensland(Australia)

    Source: NAO Analysis

  • 8/20/2019 Performance Audit Reports

    42/142

     Lease and Use of Government Office Accommodation 7 

    CHAPTER TWO

    GOVERNMENT OFFICE ACCOMMODATION IN MAURITIUS

    This Chapter describes the process for renting office space and renewing lease agreements, the

    roles and functions of key players and the audit criteria used in pursuing the audit. It also

    examines the expenditure incurred by Government with respect to GOA for the past five years.

    2.1 System Description for Renting GOA (New Request)

    The process of renting new accommodation is described below:

    Accounting Officers of Ministries/ Government Departments are allowed to make theirown arrangements to find out appropriate accommodation to house different sections of their Ministries/ Departments. This is usually done through tender procedures

    The need for office accommodation is specified in an Annual Procurement Plan. Thisinvolves the Public Body to engage in procurement planning with a view to achievingmaximum value for public expenditure

    The Ministry/ Department sends a draft press tender notice to MPI for vetting purposesprior to the issue of a press communiqué

    Tenders are invited through press notice giving precise specifications of the requirementson the building to be rented

    Bidders are required to use the Standard Bidding Documents as prescribed by the PPO

    A Bid Evaluation Committee is set up at the level of the Ministry/ Department to evaluatethe bids

    Clearances from different Public Bodies (Appendix ) should be obtained before the Letterof Award is issued to successful bidder, and

    Lease Agreement is vetted by Attorney General’s Office before being signed by lessorand lessee.

    2.2 System Description for Renewal of Lease Agreement and/ or Renting of Additional

    Space within Same Building

    In case, a Ministry/ Government Department wishes to renew the lease for a further period orto rent additional space within same building, clearances must be sought from the PublicBodies which are listed below:

    MoFED - on the availability of funds, that is, the rental cost is met either within theMinistry’s budget ceiling or additional funding is requested from MoFED

    Valuation Real Estate Consultancy Services - on the quantum of rent payable

  • 8/20/2019 Performance Audit Reports

    43/142

     Lease and Use of Government Office Accommodation 8 

    Mauritius Fire and Rescue Service (MFRS) - on safety aspects

    In year 2008, Ministries and Government Departments were advised by MPI to submit theirrequest along with the necessary clearances, as mentioned above, well before the expiry of the lease agreement for further approval. Location of building, purpose, area to be occupied,

    monthly rent and period of lease are some information that are also required when submittingrequest to MPI. Finally, MPI gives its no objection, based on clearances obtained for therenewal of lease agreement.

    2.3 Responsibilities and Functions of Stakeholders

    There are several stakeholders who are involved when a Ministry/ Government Departmentdecides to rent a new office space. In the first instance, the Ministry/ Department itself isallowed to arrange for necessary office space. However, during the process, clearances fromseveral key players such as MFRS, Commissioner of Police, Ministry of Health and Quality

    of Life, MPI and Valuation Real Estate Consultancy Services are required before awardingthe contract to the successful bidder.

    2.4 Audit Criteria

    The audit criteria are based on good practices related to policies and strategies identified inforeign countries. Emphasis has been laid on four Anglo-Saxon countries which havecommon socio-political heritage with Mauritius. (Table 1) They also have writtenaccommodation policy papers accompanied with strategies and long term plan.

  • 8/20/2019 Performance Audit Reports

    44/142

     Lease and Use of Government Office Accommodation 9

    CHAPTER THREE

    FINDINGS

    This Chapter analyses the rent paid for office accommodation. It describes the initiatives taken,as well as constraints faced by Ministries/ Government Departments in acquiring, utilising and

    rationalizing office space in view of minimizing cost and delivering better services.

    3.1 Expenditure Relating to GOA

    The rent paid for office accommodation remains a significant annual financial commitmentfor both Ministries and Government Departments. Expenditure incurred in respect of rentalduring the past five years totalled some Rs 2.8 billion as shown in Table 2.

    Table 2 Expenditure Incurred on Rent of GOA during the Past Five Years

    Year Rs

    2010 514,334,348

    2011 537,338,991

    2012 573,325,860

    2013 597,963,030

    2014 630,836,639

    2,853,798,868

    Source: Treasury Accounting System and Statistics Mauritius

    For year 2014, out of a total amount of some Rs 631 million spent, some Rs 501 million werefor office accommodation in Mauritius. This is likely to increase in the future.

    One of the major factors that drive cost is the location of the offices. Our analysis of expenditure for the year 2014 showed that most of the Government office accommodation isconcentrated in the region of Port Louis. Government leases its different office spaces locatedin some 50 privately owned buildings in Port Louis, with an annual commitment of someRs 380 million, that is, 76 per cent of the total expenditure on office accommodation inMauritius. The remaining 24 per cent of the total amount was spent on office accommodationscattered over the island. Most of these buildings have been rented since a long time, withsuccessive renewal of contracts, some for more than 10 years. At present, each Ministry andGovernment Department manages its own office accommodation. This system hasencouraged the practice for most of the Ministries and Departments to locate in Port Louis.

  • 8/20/2019 Performance Audit Reports

    45/142

     Lease and Use of Government Office Accommodation 10

     3.1.1 Variations in Cost per Employee

    Cost per employee is one of the metrics used to measure the cost efficiency.

    An analysis of a sample of rent paid by Ministries and Government Departments showed that

    there are significant variations in the cost per employee as shown in the Table 3.

    Table 3 Annual Cost per Employee – Year 2014

    Ministries and Government Departments Annual

    Lease Costs

    (Rs)

    No. of 

    Employees

    Annual Cost

    per Employee

    (Rs)

    Electoral Commissioner’s Office 9,493,428 76 124,913

    Public Bodies Appeal Tribunal 1,089,851 15 72,655

    Valuation Real Estate Consultancy Services 16,200,000 163 99,386

    MPU- Radiation Centre 1,234,800 14 88,200

    Pay Research Bureau 2,115,816 46 45,996

    Employment Relation Tribunal 4,836,624 22 219,846

    Source: TAS and PBB Estimates 2014

     3.1.2 Variations in Occupancy Rate per Employee

    Occupancy rate per employee is another measure used to assess the performance of anypublic entity. It is another factor that drives cost of office accommodation. Presently,Government does not have a prescriptive standard in occupancy rate per employee. Ananalysis of a sample of Ministries and Government Departments showed significantvariations in occupancy rate per employee, and it ranged from 12 to 32 square metres during2014. (Table 4 refers).

  • 8/20/2019 Performance Audit Reports

    46/142

     Lease and Use of Government Office Accommodation 11

    Table 4 Occupancy Rate per Employee at some Ministries and Government Departments

    Ministry / 

    Department

    Location Space Rented

    (sq metre)

    No of 

    Employees

    Occupancy Rate

    per Employee

    (sq metre/staff)ElectoralCommissioner’s

    Office

    Max City Bldg 2,402 76 32

    Ministry of GenderEquality, ChildProtection andFamily Welfare

    Chan Sui Ko Bldg 1,858 126 15

    Newton Tower 752 32 23

    Ministry of Fisheries

    Trade andMarketing Center(CompetentAuthority)

    272 16 17

    Trade andMarketing Center(One Stop Shop)

    186 15 12

    LIC Centre 1,028 87 12

    Ministry of Labour,

    Industrial Relations,Employment &Training (LabourDivision)

    Victoria House 4,831 198 24

    Source: NAO Analysis

     3.1.3 Scattered Offices

    The activities of some Ministries and Government Departments have been growing over

    time. Due to unavailability of the required space, they had to spread in different buildings tomeet their needs. This has resulted in variation in the cost per employee and occupancy ratein the different buildings. This has also added to the administrative inconvenience whenoperations are far from Head Office. Examples of Ministries housed in different buildingsinclude Ministry of Agro Industry and Food Security, and Ministry of Gender Equality, ChildDevelopment and Family Welfare.

  • 8/20/2019 Performance Audit Reports

    47/142

     Lease and Use of Government Office Accommodation 12

    3.2 Initiatives Taken

    Government has taken several initiatives to address the problems of rising cost of rentingoffice space, but has not been successful in implementing same. These are described below:

     3.2.1 Setting up of GOMU 

    In December 2000, Government agreed on the setting up of the Government OfficeManagement Unit (GOMU) as a permanent structure under the aegis of the MPI to look intothe rationalization of office space for the public service.

    The functions of GOMU are as follows:

    To formulate policies and strategies regarding office accommodation for both owned andleased buildings

    To develop and issue guidelines in respect of space requirements for various grades of officers

    To issue standard lease agreement containing standard compulsory clauses, together withprovisions for other optional clauses

    To formulate norms and standards of office buildings

    To give final approval to the leasing of office accommodation

    To build up and maintain a database containing relevant details of all rented and ownedbuildings

    To build up and maintain a database of all landlords willing to lease their buildings toGovernment, and

    To deal with all requests relating to office accommodation received from Ministries andGovernment Departments.

    Up to now, Government has not been successful in setting up GOMU.

    Ad – hoc Committees have been set up at the level of MPI to look into the setting up of GOMU, and also to find ways and means to carry some of its functions. The Committees hadmet on 23 occasions during the period 2001 to 2011.

    The ad-hoc Committees took some decisions. However, they were either not fullyimplemented or not put in practice by MPI as GOMU has not been set up. These are

    Developing draft guidelines in respect of the space requirements for various grades of officers (Guideline for renting of private building for Government use)

    Developing a draft lease agreement duly vetted by the Attorney General’s Office

  • 8/20/2019 Performance Audit Reports

    48/142

     Lease and Use of Government Office Accommodation 13

    Inviting Ministries and Government Departments to submit information required to buildup a database

    Inviting potential landlords willing to lease their buildings to Government for use asoffice accommodation;

    Developing an Office Accommodation System, on a standalone basis.

    I am given to understand that MPI still intends and willing to set up GOMU. In this context,as of October 2014, a few officers were assigned to work on GOMU.

    Despite the fact that GOMU has not been set up, some stakeholders took some otherinitiatives to rationalise office space used by Ministries and Government Departments, butthese were however not successfully implemented. These initiatives are described in theparagraphs below.

     3.2.2 Initiatives to Rationalize GOA

     Leasing versus Ownership

    The issue of leasing versus ownership is influenced by several factors, such as Governmentobjectives, financial analysis, and economic development.The New Zealand Property Management Guidelines 2012 stated that the cost benefit of leasing versus owning its own office space must be robustly considered when acquiringspace. Similarly, according to Queensland Policy Guidelines 2009, when making decisionsregarding the acquisition of an asset, public sector entities should satisfy themselves that thebest-cost alternative is used.

    Government in the past came up with the decision to construct its own buildings, mainly forthe following reasons:

    to cut down expenditure on rent

    to relocate some offices away from the City in order to ease the then growing trafficproblem in Port Louis, and

    to decentralise the economy and business

    Mention was made of the construction of some administrative blocks, such as Finance House,Agriculture House, Education House, Marine House and Youth Head Quarters toaccommodate offices. Provisions for some of the projects were made in the CapitalEstimates, but these projects remained at conceptual stage. This explains why, most of theadministrative blocks are still being leased in private owned buildings.

    However, two of the disadvantages of leasing are the exposure to market rent fluctuations andrent increases after agreed time period. On the other hand, construction involves structuraland organisational issues regarding property management and maintenance. It is important to

    consider these issues when developing policy and strategy in relation to lease or buy decision.

  • 8/20/2019 Performance Audit Reports

    49/142

     Lease and Use of Government Office Accommodation 14

     Database

    A database generating meaningful information would operate as a management tool to assistin decision making.

    In year 2010, MOFED and MPI, through surveys, initiated action to set up a database of allbuildings, rented and owned, forming part of GOA. The database was considered necessaryin order to better manage office space in the public sector. At the request of MPI, the CentralInformation System Division, in year 2010, finalized the development of an OfficeAccommodation System (OAS) to accommodate data on office accommodation. Moreover,in April 2013, MoFED intended to set up a database for potential bidders in respect to rentalof office spaces. The aim was to ensure transparency and a reasonable time frame for theprocurement.

    MoFED and MPI have in their custody a list of buildings rented and owned by Government,including the area occupied, number of employees and rent paid by each Ministry and

    Department as of 2011 and 2012 respectively. The responsibility of keeping database wasassigned to GOMU. However, as at time of audit (January 2015), neither a database of potential landlords nor of office space rented and owned by Government has beenestablished. The OAS developed in year 2010 at the request of MPI has never been put in useas GOMU has not been set up.

    Consolidation of Ministries and Government Departments Under one Roof 

    In year 2010, PMO and MoFED took laudable initiatives separately towards regroupingdifferent Divisions of the same Ministry under one roof. PMO, in August 2010, carried out asurvey. The aim was to regroup different divisions of the same Ministries, which are scatteredin different buildings, under one roof, while at the same time making maximum use of Government owned spaces. In December 2010, MoFED, also proposed to developappropriate policy measures to rationalize office space used by Ministries and GovernmentDepartments with a view to bringing efficiency gains and centralizing as far as possibledifferent Units of same Ministry under one roof.

    Attempts have been made in this direction by both MOFED and PMO. However, the idea of consolidation did not materialize.

    Procurement Regulations on Office Space

    The Public Procurement Act (PPA) was amended in December 2012 whereby officeaccommodation no longer falls under its purview. Subsequently, in January 2014, the PPOprepared procurement regulations on rental of office space. As of date (March 2015), theregulations have remained at draft stage. Pending the finalisation of the draft, PPO has sinceJanuary 2013 been guiding Ministries and Government Departments on a case to case basison procurement of rental of office space.

    Standard Occupancy Rate per Employee

    A standard occupancy rate per employee helps to reduce rental costs and lower expenses for

    office fit out, electricity, security and maintenance. Prescriptive space allocation standardmaximises an agency's capacity to determine its own internal office layout requirements. By

  • 8/20/2019 Performance Audit Reports

    50/142

     Lease and Use of Government Office Accommodation 15

    calculating accurate occupation density, prime consideration is given in determining the costof offices and the potential for savings.

    In year 2011, MPI prepared a draft guideline on standard space requirement for variousgrades of officers. As at time of audit (January 2015), the draft has not yet been finalized. In

    other countries, standards set form part of policy paper, and this is considered in carryingneeds assessment when office space is required.

    3.3 Government Office Accommodation Policy

    A GOA policy is important as it ensures that Ministries and Government Departments makeoffice accommodation decisions in the best interest of Government. However, presently,Government does not have an accommodation policy accompanied with strategies and plans.

    All the four Anglo-Saxon countries we benchmarked with have a written accommodation

    policy accompanied with strategies and long term plan. On the other hand, a whole of Government approach is being adopted by several countries and states to develop strategiesand plans. (Table 1 refers). The objective of a well-functioning strategies and long-termaccommodation planning process is to ensure the availability of the right facilities at the righttime in the most economic manner to meet existing and projected demands. It also ensuresthe optimal use of existing facilities.

    The foreign countries accommodation policy includes, inter alia, the process to acquireoffice, standard occupancy rate per employee, interior design policy, whether space has to becentrally managed, setting up of a database and whole of government approach (Table 1). Inthe local context, these issues, except for the interior design policy and whole of Governmentapproach, were already contemplated by Government. However, they were not fullyimplemented. In addition, they did not form part of a policy document as compared to othercountries.

    The adoption of the above mentioned strategies by some foreign countries has resulted insome benefits as illustrated in Case Studies 1 to 3.

  • 8/20/2019 Performance Audit Reports

    51/142

     Lease and Use of Government Office Accommodation 16 

    Case Study No 1 - New Zealand

    The Property Management Centre of Expertise of New Zealand developed a Property ManagementGuidelines for Office Space in August 2012. The Guidelines refer to principle on Government OfficeAccommodation policy, Whole-of-Government Approach, Office Space Occupancy Density Goal and

    Interior Design Policy. In 2013, the Crown Office Estate of New Zealand reported that the adoption of these guidelines started to bring the expected benefits. For example

    The Ministry of Business, Innovation and Employment’s agreement for its National Officeresulted in baseline savings of $60.62 million over 20 years, cost avoidance of $187.98 millioncompared to the projected status quo, and a space reduction of 36 per cent (32,906 m2 to 20,904m2). This was an area per person reduction from 21.4 m2 to 13.6 m2

    The Ministry of Social Development’s agreement for its National Office would achieve areduction of 13 per cent in its property footprint (from 27,788 m2 to 24,255 m2), an occupancydensity of 12.8 m² per person from 17 m2, and achieves cost avoidance of $6.10 million comparedto the projected status quo.

    Crown Law co-located with the Ministry of Justice, utilising surplus space and resulting in shared

    facilities and a reduction in the overall Crown footprint of 4,800 m2

    .

    Source: New Zealand Crown Office Estate Report 2013

    Case Study No 2 – United Kingdom

    The UK NAO Report 2007  – “Improving the Efficiency of Central Government’s Office Property”assesses whether departments are effectively managing and achieving value for money from their ownoffice space. It considers whether departme