DAFTAR UPAH PEKERJA
PROYEK PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
RUMAH SAKIT UMUM PROVINSI dr. SOEDONO MADIUN
JALAN Dr. SOETOMO No. 29 MADIUN - JAWA TIMUR
No. URAIAN TENAGA KERJA KOEF. HARGA ( Rp )
VOL SAT. SATUAN JUMLAH
1 Mandor 1.00 O-H 60,000.00 60,000.00
2 Kepala tukang Batu 1.00 O-H 55,000.00 55,000.00
3 Kepala tukang Besi 1.00 O-H 55,000.00 55,000.00
4 Kepala tukang Cat 1.00 O-H 55,000.00 55,000.00
5 Kepala tukang Galian Tanah 1.00 O-H 55,000.00 55,000.00
6 Kepala tukang Kayu 1.00 O-H 55,000.00 55,000.00
7 Kepala tukang Listrik 1.00 O-H 55,000.00 55,000.00
8 Kepala tukang Pipa. 1.00 O-H 55,000.00 55,000.00
31 Sewa bucket dan crane 1.00 jam 225,000.00 225,000.00
32 Concrete Pump 1.00 jam 285,000.00 285,000.00
33 Welding Set 1.00 jam 25,000.00 25,000.00
34 Sewa Crane 1.00 jam 225,000.00 225,000.00
35 Jack Hammer 1.00 jam 18,000.00 18,000.00
36 Theodholit 1.00 set 25,000.00 25,000.00
37 Surveyor 1.00 Oh 40,000.00 40,000.00
Surabaya, 23 November 2010
PT. ANGGREK MERAH
ALBERTINUS WIDYANTO
Direktur Utama
Page 21 of 334
DAFTAR HARGA BAHAN DAN MATERIALPROYEK PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
RUMAH SAKIT UMUM PROVINSI dr. SOEDONO MADIUNJALAN Dr. SOETOMO No. 29 MADIUN - JAWA TIMUR
No. URAIAN TENAGA KERJA KOOEF HARGA ( Rp )
VOL SAT. SATUAN JUMLAH
TANAH / PASIR1 Agregat Kelas A 1.00 m3 70,000.00 70,000.00 2 Agregat Kelas B 1.00 m3 60,000.00 60,000.00 3 Pasir Beton 1.00 m3 140,000.00 140,000.00 4 Pasir Cor 1.00 m3 140,000.00 140,000.00 5 Pasir Hitam 1.00 m3 150,000.00 150,000.00 6 Pasir Pasang 1.00 m3 135,000.00 135,000.00 7 Pasir Silikon 1.00 kg 7,800.00 7,800.00 8 Pasir Urug 1.00 m3 85,000.00 85,000.00 9 Sirtu 1.00 m3 85,000.00 85,000.00
10 Tanah Liat 1.00 m3 65,000.00 65,000.00 11 Tanah Urug 1.00 m3 75,000.00 75,000.00 12 Tanah urug taman / ketel 1.00 m3 70,000.00 70,000.00
BATU BATA /BETON BLOCK/PAVING/STENSLAG1 Bata Berongga 1.00 bh - 2 Bata 1.00 bh 590.00 590.00 3 Batako 1.00 bh - 4 Batu ampyang 1.00 zak - 5 Batu apung 1.00 kg - 6 Batu belah gunung 1.00 m3 - 7 Batu belah kali 1.00 m3 145,000.00 145,000.00 8 Batu granito 1.00 kg - 9 Batu kali 1.00 m3 -
10 Batu kapur 1.00 zak - 11 Batu kerikil pasir 1.00 m3 95,000.00 95,000.00 12 Batu kerikil tersaring 1.00 m3 90,000.00 90,000.00 13 Batu koral 1.00 m3 125,000.00 125,000.00 14 Batu lempeng 1.00 m2 135,000.00 135,000.00 15 Batu Palimanan 1.00 m2 - 16 Batu Pecah mesin 1/2 1.00 m3 150,000.00 150,000.00 17 Batu Pecah mesin 1/2 1.00 m3 150,000.00 150,000.00 18 Batu Pecah mesin 2/3 1.00 m3 150,000.00 150,000.00 19 Batu Pecah mesin 3/5 1.00 m3 150,000.00 150,000.00 20 Batu Pecah mesin 4/6 - 5/7 1.00 m3 150,000.00 150,000.00 21 Batu Terraso 1.00 kg - 22 Batu tempel hitam/Batu candi 1.00 m2 87,000.00 87,000.00 23 Batu Klingker 1.00 bj 11,500.00 11,500.00 24 Batu Ampyang 1.00 m2 - 25 Batu Gilang ex. Jember ( simetris ) 1.00 m2 - 26 Batu Gilang ex. Jember ( ansimetris ) 1.00 m2 - 27 Batu Gilang ex. Cirebon ( simetris ) 1.00 m2 175,000.00 175,000.00 28 Batu Gilang ex. Cirebon ( ansimetris ) 1.00 m2 - 29 Batu Bobos uk. 10 x 20 x 1,5 cm 1.00 m2 16,000.00 16,000.00 30 Rooster kerawangan 11 x 12 x 24 1.00 bh - 31 Rooster kerawangan 11 x 22 x 22 1.00 bh - 32 Rooster beton 11 x 20 x 22 1.00 bh - 33 Batu tempel kasar / marmo 1.00 m2 - 34 Bt temp halus ( candi/hitam dan palimanan ) 1.00 m2 88,000.00 88,000.00 35 Batu sirih / alur (hitam / kuning) 1.00 m2 39,000.00 39,000.00 36 Batu alur andesit hitam 1.00 m2 - 37 Batu koral hitam ex NTT 1.00 m2 - 38 Batu koral hitam ex. Tulungagung 1.00 m2 - 39 Batu tempel Terrakota / Karangpilang 1.00 m2 - 40 List batu andesit p=40 cm, lebar = 5cm 1.00 m' - 41 List batu candi p=40 cm lebar = 5 cm 1.00 m' - 42 Batako 1.00 bj 8,500.00 8,500.00 43 Concrete block ( CB 10 ) 1.00 bh - 44 Concrete block ( CB 15 ) 1.00 bh - 45 Concrete block ( CB 20 ) 1.00 bh - 46 Hollow Block ( HB.10 ) 1.00 bh - 47 Hollow Block ( HB.15 ) 1.00 bh - 48 Hollow Block ( HB.20 ) 1.00 bh - 49 Kansteen 1.00 m' - 50 Paving Block 1.00 m2 - 51 Paving stone natural 6 cm 1.00 m2 38,000.00 38,000.00 52 Paving Stone natural 8 cm 1.00 m2 54,000.00 54,000.00 53 Rooster 1.00 bh 4,500.00 4,500.00 54 Stenslag / batu pecah tangan 2/3 1.00 m3 - 55 Stenslag / batu pecah tangan 1/2 1.00 m3 - 56 Stenslag / batu pecah tangan 3/5 1.00 m3 -
Page 22 of 334
57 Stenslag / batu pecah tangan 4/6 - 5/7 1.00 m3 - 58 Glass Block 1.00 m3 30,000.00 30,000.00
SEMEN - 1 Delosit 1.00 zak 65,000.00 65,000.00 2 Gamping 1.00 kg - 3 Gamping Bongkahan 1.00 m3 - 4 Gamping Bubukan 1.00 m3 - 5 Kapur 1.00 m3 145,000.00 145,000.00 6 PC Gresik 1.00 kg 1,200.00 1,200.00 7 PC Grouting 1.00 kg - 8 PC Putih 1.00 kg - 9 PC Warna 1.00 kg 9,000.00 9,000.00
10 Semen 40 kg 1.00 zak 47,000.00 47,000.00 11 Semen 50 kg 1.00 zak 57,000.00 57,000.00 12 Semen Merah 1.00 m3 55,550.00 55,550.00 13 Semen putih 1.00 kg 61,000.00 61,000.00
- BUIS BETON -
1 Buis beton Ø 20 cm 1.00 bh - 2 Buis beton Ø 30 cm 1.00 bh - 3 Buis beton Ø 40 cm 1.00 bh - 4 Buis beton Ø 60 cm 1.00 bh - 5 Buis beton Ø 70 cm 1.00 bh - 6 Buis beton Ø 80 cm 1.00 bh - 7 Buis beton Ø 90 cm 1.00 bh - 8 Buis beton Ø 100 cm 1.00 bh 280,000.00 280,000.00 9 Buis beton U - Ø 20 cm 1.00 bh -
10 Buis beton U - Ø 30 cm 1.00 bh - 11 Pagar Panel (Precast Pabrik) tinggi 1.20 M 1.00 m' - 12 Pagar Panel (Precast Pabrik) tinggi 1.60 M 1.00 m' - 13 Pagar Panel (Precast Pabrik) tinggi 2.00 M 1.00 m' - 1415
BESI - 1 Baja WF dan Canal C 1.00 kg 9,800.00 9,800.00 2 Baut segala ukuran 1.00 kg - 3 Besi Bronjong 1.00 kg - 4 Besi baja paku-paku jembatan 1.00 kg - 5 Besi Plat Bordes 4"x8" tebal 3 mm 1.00 kg - 6 Besi plat 4"x8" tebal 2 mm 1.00 kg - 7 Besi plat strip uk. 3x30 mm - 6 m 1.00 kg 9,000.00 9,000.00 8 Walter Mour 1.00 bh - 9 Plat Besi tebal 1 cm 1.00 kg -
1 Paku 1½ " 1.00 kg 11,000.00 11,000.00 2 Paku 1¼ " 1.00 kg 11,000.00 11,000.00 3 Paku 1" 1.00 kg 11,000.00 11,000.00 4 Paku 2" 1.00 kg 11,000.00 11,000.00 5 Paku 2½ " 1.00 kg 11,000.00 11,000.00 6 Paku 3" 1.00 kg 11,000.00 11,000.00 7 Paku 4" 1.00 kg 11,000.00 11,000.00 8 Paku 5" 1.00 kg 11,000.00 11,000.00 9 Paku 6" 1.00 kg 13,000.00 13,000.00
10 Paku Asbes segala ukuran 1.00 kg 13,000.00 13,000.00 11 Paku Beton 1.00 kg 20,000.00 20,000.00 12 Paku Kait segala ukuran 1.00 kg - 13 Paku Kayu segala ukuran 1.00 kg 13,000.00 13,000.00 14 Paku Keling 1.00 bh 12,500.00 12,500.00 15 Paku Payung 1.00 kg 13,000.00 13,000.00 16 Paku Reng 1.00 kg 11,000.00 11,000.00 17 Paku Seng Segala ukuran 1.00 kg 9,000.00 9,000.00 18 Paku Sumbat segala ukuran 1.00 bh 13,000.00 13,000.00 19 Paku Triplex 1.00 kg 12,000.00 12,000.00 20 Paku Usuk 1.00 kg 11,000.00 11,000.00 21 Paku Skrup segala ukuran 1.00 bh 150.00 150.00
- KAYU UMUM -
1 Kayu begisting lokal 1.00 m3 2,500,000.00 2,500,000.00 2 Kayu Parancah 1.00 m3 2,500,000.00 2,500,000.00
KAYU BORNEO - 1 Balok 1.00 m3 5,200,000.00 5,200,000.00 2 Papan 2 x 20 cm 1.00 m3 5,250,000.00 5,250,000.00 3 Papan 3 x 20 cm 1.00 m3 5,250,000.00 5,250,000.00 4 Papan 2 x 30 cm 1.00 m3 5,250,000.00 5,250,000.00 5 Reng 2/3 - 3/5 1.00 m3 5,200,000.00 5,200,000.00 6 Usuk 5/7 - 4/6 1.00 m3 5,200,000.00 5,200,000.00
KAYU MERANTI - 1 Balok 1.00 m3 3,800,000.00 3,800,000.00 2 Papan 2 x 20 cm 1.00 m3 2,200,000.00 2,200,000.00 3 Papan 3 x 20 cm 1.00 m3 4,100,000.00 4,100,000.00 4 Papan 2 x 30 cm 1.00 m3 - 5 Reng 2/3 - 3/5 1.00 m3 - 6 Usuk 5/7 - 4/6 1.00 m3 2,500,000.00 2,500,000.00 7 Kayu Meranti Papan 2/20 1.00 m3 -
KAYU DAMAR LAUT - 1 Balok p= 4 M 1.00 m3 - 2 Papan l=20 CM 1.00 m3 - 3 Usuk / FP = 4 M 1.00 m3 -
KAYU KRUING - 1 Balok 1.00 m3 2,650,000.00 2,650,000.00 2 Papan 2 x 20 cm 1.00 m3 - 3 Papan 3 x 20 cm 1.00 m3 - 4 Papan 2 x 30 cm 1.00 m3 - 5 Reng 2/3 - 3/5 1.00 m3 - 6 Usuk 5/7 - 4/6 1.00 m3 -
KAYU BENGKIRAI - 1 Balok 1.00 m3 - 2 Papan 2 x 20 cm 1.00 m3 - 3 Papan 3 x 20 cm 1.00 m3 - 4 Papan 2 x 30 cm 1.00 m3 - 5 Reng 2/3 - 3/5 1.00 m3 - 6 Usuk 5/7 - 4/6 1.00 m3 -
KAYU KAMPER - 1 Balok 1.00 m3 8,800,000.00 8,800,000.00 2 Papan 2 x 20 cm 1.00 m3 - 3 Papan 3 x 20 cm 1.00 m3 - 4 Papan 2 x 30 cm 1.00 m3 8,900,000.00 8,900,000.00 5 Reng 2/3 - 3/5 1.00 m3 3,850,000.00 3,850,000.00
1 Balok 1.00 m3 7,600,000.00 7,600,000.00 2 Papan 2 x 20 cm 1.00 m3 - 3 Papan 3 x 20 cm 1.00 m3 - 4 Papan 2 x 30 cm 1.00 m3 17,500,000.00 17,500,000.00 5 Reng 2/3 - 3/5 1.00 m3 15,000,000.00 15,000,000.00 6 Usuk 5/7 - 4/6 1.00 m3 -
KAYU JATI Ex. MADIUN / NGAWI - 1 Balok 1.00 m3 - 2 Papan 2 x 20 cm 1.00 m3 - 3 Papan 3 x 20 cm 1.00 m3 - 4 Papan 2 x 30 cm 1.00 m3 - 5 Reng 2/3 - 3/5 1.00 m3 - 6 Usuk 5/7 - 4/6 1.00 m3 -
KAYU JATI Ex. BOJONEGORO - 1 Balok 1.00 m3 12,500,000.00 12,500,000.00 2 Papan 2 x 20 cm 1.00 m3 13,000,000.00 13,000,000.00 3 Papan 3 x 20 cm 1.00 m3 13,500,000.00 13,500,000.00 4 Papan 2 x 30 cm 1.00 m3 - 5 Reng 2/3 - 3/5 1.00 m3 - 6 Usuk 5/7 - 4/6 1.00 m3 -
KAYU LAIN-LAIN - 1 Kayu bakar 1.00 m3 - 2 Kayu Bambu Ø 10 cm 1.00 btng 20,000.00 20,000.00 3 Kayu Bambu Ø 6-8 cm 1.00 btng 20,000.00 20,000.00 4 Bilik bambu 1.00 m2 - 5 Kayu Dolken Ø8 cm 1.00 btng 14,000.00 14,000.00 6 Gedeg 2 x 3 m 1.00 lbr 25,000.00 25,000.00 7 Kayu Albasiah 1.00 m3 - 8 Kayu Ramin 1.00 m3 - 9 List Kayu 2/4 1.00 m' -
10 Bubung Pelentong Kecil 1.00 bh - 11 Bubung Genteng Pelentong besar / super 1.00 bh - 12 Bubung Genteng prss ex. Trenggalek 1.00 bh - 13 Bubung Atap seng galvalum 1.00 m2 - 14 Bubung Paten 0,92 m 1.00 lmb - 15 Bubung Paten 1,o5 m 1.00 lmb - 16 Bubung Paten 1,08 m 1.00 lmb - 17 Bubung Seng gelombang 1.00 lmb - 18 Bubung Stel Gelombang 0,92 m 1.00 lmb - 19 Bubung Stel Gelombang 1,05 m 1.00 lmb - 20 Bubung Stel Gelombang 1,08 m 1.00 lmb - 21 Bubung stel rata 0,92 m 1.00 lmb - 22 Bubung stel rata 0,92 m 1.00 lmb - 23 Genteng Aspal 1.00 lmb - 24 Genteng Beton 1.00 bh - 25 Genteng Beton Maestro Royal 1.00 bh - 26 Genteng Biasa ex. Malang 1.00 bh - 27 Genteng kaca 1.00 bh - 28 Genteng Kaca Beton Kupu-kupu 1.00 bh - 29 Genteng Kaca Kodok Kupu-kupu 1.00 bh - 30 Genteng Karangpilang ex. Malang 1.00 bh - 31 Genteng Karangpilang ex. Surabaya 1.00 bh 4,500.00 4,500.00 32 Genteng Karangpilang ex. Trenggalek 1.00 bh - 33 Genteng Keramik Natural KIA 1.00 bh - 34 Genteng Keramik Warna KIA 1.00 bh 6,800.00 6,800.00 35 Genteng Kodok Glazuur 1.00 bh - 36 Genteng Kodok Good Years 1.00 bh 6,800.00 6,800.00 37 Genteng Metal 1.00 bh - 38 Genteng Palentong kecil 1.00 bh - 39 Genteng kaca Palentong supr / besar 1.00 bh - 40 Genteng Press Trenggalek 1.00 bh - 41 Asbes Gelombang 4 mm 300 x 1,05 m 1.00 lmb - 42 Asbes Gelombang 4 mm 240 x 1,05 m 1.00 lmb - 43 Asbes Gelombang 4 mm 210 x 1,05 m 1.00 lmb - 44 Asbes Gelombang 4 mm 150 x 1,05 m 1.00 lmb - 45 Asbes Gelombang 5 mm 250 x 0,92 m 1.00 lmb -
Page 25 of 334
46 Asbes Gelombang 5 mm 225 x 0,92 m 1.00 lmb - 47 Asbes Gelombang 5 mm 180 x 0,92 m 1.00 lmb - 48 Asbes Gelombang 11 Atrisco 150 x 80 x 3,5 mm 1.00 lmb - 49 Asbes Gelombang 14 Atrisco 150 x105 x 4 mm 1.00 lmb - 50 Asbes Gelombang 4 Atrisco 150x105x4mm 1.00 lmb - 51 Asbes Gelombang 6,5 Atrisco 150x110x5mm 1.00 lmb - 52 Asbes Gelombang Besar Jabesmen 300x102x5 mm 1.00 lmb - 53 Asbes Gelombang Kecil Jabesmen 380x105x4mm 1.00 lmb - 54 Asbes Gelombang 200x0.92x 5mm 1.00 lmb - 55 Asbes Gelombang 270x108x6mm 1.00 lmb - 56 Asbes Gelombang 210x108x6mm 1.00 lmb - 57 Asbes Gelombang 180x108x6mm 1.00 lmb - 58 Asbes Nok Gelombang ex. Atrisco 11 - 30x80x3,5mm 1.00 lmb - 59 Asbes Nok Gelombang ex. Atrisco 14- 30x105x4mm 1.00 lmb - 60 Asbes Nok Gelombang ex. Atrisco 6,5 -50x110x5mm 1.00 lmb - 61 Asbes Gelombang 270x105x4 mm 1.00 lmb - 62 Atap Policarbonat 1.00 m2 105,932.20 105,932.20 63 Roof Light Fibreglass 1.00 m2 - 64 Seng Datar ex. Elephant 0,2x30 cm 1.00 lmb - 65 Seng Datar ex. Elephant 0,30 x 50 cm 1.00 lmb - 66 Seng Datar ex. Elephant 0,40 x 90 cm 1.00 lmb - 67 Seng Gelombang ex. Elephant 180x80x0,2 cm 1.00 lmb 44,000.00 44,000.00 68 Seng Gelombang ex. Elephant 210x80x0,20 cm 1.00 lmb - 69 Seng Gelombang ex. Elephant 240x80x0,2 cm 1.00 lmb - 70 Seng Gelombang ex. Elephant 300x80x0,2 cm 1.00 lmb - 71 Seng Plat BJLS L= 0,45 m 1.00 m' - 72 Seng Plat BJLS L= 0,60 m 1.00 m' - 73 Seng Plat BJLS L= 0,90 m 1.00 m' 38,000.00 38,000.00 74 Seng Plat BJLS 24 1.00 lmb - 75 Seng Plat BJLS 28 1.00 lmb - 76 Soft Board 1.00 lmb - 77 Talang Plastik Biasa 50 cm 1.00 bh - 78 Talang Plastik Biasa 60 cm 1.00 bh - 79 Talang Plastik Biasa 75 cm 1.00 bh - 80 Talang Plastik Biasa 90 cm 1.00 bh - 81 Talang PVC kotak 4 x 13 cm 1.00 bh - 82 Glass wol 1.00 Rol 925,000.00 925,000.00 83 Roof Mes 1.00 Rol 450,000.00 450,000.00 84 Alluminium foil /insulation double side 1.00 Rol 1,250,000.00 1,250,000.00 85 Allumunium Tape 1.00 Rol 26,500.00 26,500.00
PLAFOND - 1 Akustik 30x30 cm 1.00 lbr - 2 Akustik 30x60 cm 1.00 lbr - 3 Akustik 60x120 cm 1.00 lbr - 4 Asbes 100x100x6 mm 1.00 lbr 12,500.00 12,500.00 5 Asbes 100x100x5 mm 1.00 lbr - 6 Asbes 100x100x4 mm 1.00 lbr - 7 Asbes 100x100x3,5 mm 1.00 lbr - 8 Asbes rata jabesmen 50 x 100 mm 1.00 lbr - 9 Asbes super rata Atrisco 50 x 100 x 2,8 mm 1.00 lbr -
10 Kalsiboard 1,00x1,00 ex. Gresik 1.00 lbr - 11 Kalsiboard 1,20x2,40 ex. Gresik 1.00 lbr - 12 Gyp board 1,20x2,40 m tabal 9 mm 1.00 lbr 65,000.00 65,000.00 13 Gypsum board 1,20x2,40 m tabal 12 mm 1.00 lbr 110,000.00 110,000.00 14 List Gypsum lebar 7 cm 1.00 m' - 15 List Gypsum lebar 12 cm 1.00 m' - 16 List Gypsum lebar 15 cm 1.00 m' 15,000.00 15,000.00 17 List Profil Kayu Kamper 1/7 1.00 m' - 18 List Profil Kayu Kamper 1/10 1.00 m' 10,000.00 10,000.00 19 List Profil Kayu Kamper 1/15 1.00 m' - 20 List kayu jati profil 1.5/15 1.00 m' - 21 List kayu pelipit meranti 1.00 m' - 22 Papan GRC t= 9mm lebar= 20 cm 1.00 m' - 23 Papan GRC t= 9mm lebar= 30 cm 1.00 m' - 24 GRC lengkung tinggi 7,5 cm 1.00 m2 - 25 Rangka metal furing 1.00 m2 25,000.00 25,000.00 26 Stifenner 1.00 m2 10,000.00 10,000.00 27 Juster penggantung 1.00 m2 2,500.00 2,500.00 28 Joint Tape 1.00 m2 6,500.00 6,500.00 29 Jointing Compound 1.00 m2 8,500.00 8,500.00 30 Steger 1.00 m2 -
KAYU LAPIS - 1 Multiplex tebal = 6 mm 1.00 lbr 65,000.00 65,000.00 2 Multiplex tebal = 9 mm 1.00 lbr 125,000.00 125,000.00 3 Multiplex tebal = 10 mm 1.00 lbr 121,500.00 121,500.00 4 Multiplex tebal = 12 mm 1.00 lbr 100,000.00 100,000.00 5 Multiplex tebal = 18 mm 1.00 lbr 180,000.00 180,000.00 6 Plywood 30 x 60 cm x 4 mm 1.00 m2 59,700.00 59,700.00 7 Plywood 30 x 60 cm x 6 mm 1.00 m2 83,500.00 83,500.00 8 Plywood 60 x 120 cm x 3 mm 1.00 m2 54,250.00 54,250.00
Page 26 of 334
9 Plywood 60 x 120 cm x 6 mm 1.00 m2 83,500.00 83,500.00 10 Plywood 120 x 240 cm x 3 mm 1.00 m2 56,000.00 56,000.00 11 Plywood lapis Aluminium 1.00 m2 108,350.00 108,350.00 12 Teakwood 30 x 60 cm x 4 mm 1.00 lbr 95,000.00 95,000.00 13 Teakwood 60 x 120 cm x 4 mm 1.00 lbr 95,000.00 95,000.00 14 Teakwood 120 x 240 cm x 3 mm 1.00 lbr 75,000.00 75,000.00 15 Triplex 3 mm 1.00 m2 40,000.00 40,000.00 16 Triplex 4 mm 1.00 m2 48,000.00 48,000.00
K A C A - 1 Daun pintu kaca tempered 8 mm 1.00 unit - 2 Glass Block 1.00 bh 25,000.00 25,000.00 3 Jendela Naco + assesories 1.00 m2 - 4 Kaca Buram tebal = 3 mm 1.00 m2 - 5 Kaca Buram tebal = 5 mm 1.00 m2 - 6 Kaca Buram tebal = 8 mm 1.00 m2 - 7 Kaca Buram tebal = 12 mm 1.00 m2 - 8 Kaca Cermin tebal = 5 mm 1.00 m2 175,000.00 175,000.00 9 Kaca Cermin tebal = 6 mm 1.00 m2 -
10 Kaca Cermin tebal = 8 mm 1.00 m2 - 11 Kaca Stopsol Blue Grey 6 mm 1.00 m2 - 12 Kaca Stopsol Blue Grey 8 mm 1.00 m2 - 13 Cladding Wall ex. Indal 1.00 m2 - 14 Curtain Wall 1.00 m' - 15 Sealent 1.00 klg 21,000.00 21,000.00 16 Kaca hitam Asahi 3 mm 1.00 m' - 17 Kaca Patri 4 mm 1.00 m' - 18 Kaca polos tebal = 3 mm 1.00 m' 75,000.00 75,000.00 19 Kaca polos tebal = 5 mm 1.00 m' 70,000.00 70,000.00 20 Kaca polos tebal = 8 mm 1.00 m' 130,000.00 130,000.00 21 Kaca polos Asahi tebal = 3 mm 1.00 m' - 22 Kaca polos Asahi tebal = 5 mm 1.00 m' 75,000.00 75,000.00 23 Kaca polos Asahi tebal = 8 mm 1.00 m' 140,000.00 140,000.00 24 Kaca Polos tebal = 12 mm 1.00 m' 240,000.00 240,000.00 25 Kaca Rayben tebal = 12 mm 1.00 m' - 26 Kaca Rayben tebal = 3 mm 1.00 m' - 27 Kaca Rayben tebal = 5 mm 1.00 m2 115,000.00 115,000.00 28 Kaca Rayben tebal = 8 mm 1.00 m2 125,000.00 125,000.00 29 Kaca " Wireglass" 1.00 daun - 30 Kaca Panting 1.00 m2 -
41 Foam Lapisan Karpet 1.00 m2 - 42 Karpet Standart 1.00 m2 - 43 Vertical Blid 1.00 m2 - 44 Kunci 2 Slaag setara LOGO-CISA 1.00 set 245,000.00 245,000.00 45 Handle set ( lever handle) 1.00 bh - 46 Pull Handle 40 SST dia 11/4" 1.00 set - 47 Kunci Pintu KM/WC 1.00 set - 48 Engsel Cashment 24" 1.00 set - 49 Slot Jendela 1.00 bh - 50 Kunci Slot 1.00 bh - 51 Hak Angin ( tipe Geser ) 1.00 bh - 52 Rel Pintu Geser 1.00 bh - 53 Door Closer 1.00 set 1,240,000.00 1,240,000.00 54 Flust Bolt 1.00 bh - 55 Panic handle 1.00 bh - 56 Floor Hinge 1.00 set - 57 Kick plate SS 1.00 set - 58 Bottom Patch 1.00 bh - 59 Top Patch 1.00 bh - 60 Top Pivot Plate 1.00 bh - 61 Corner lock 1.00 bh - 62 Mohair 1.00 m1 - 63 Dinabolt D 12 mm 1.00 bh - 64 Pisher D 5 mm 1.00 bh -
CAT MARKA JALAN - 1 Cat Thermolpastic Aastho M.249-77 1.00 kg - 2 Cat Thermolpastic Aastho M.249-79 1.00 kg - 3 Glassbed pottes 1.00 kg -
CAT KAYU / BESI / TEMBOK / GENTING. - 1 Amplas kasar 1.00 kg 3,000.00 3,000.00 2 Cat anti karat ex. Avian 1.00 kg 55,000.00 55,000.00 3 Cat Besi ex. Avian 1.00 kg 40,000.00 40,000.00 4 Cat Besi EMCO 1.00 kg 42,500.00 42,500.00 5 Cat Besi Patna 1.00 kg - 6 Cat dasar Besi 1.00 kg 45,000.00 45,000.00 7 Cat dasar Kayu 1.00 kg 29,500.00 29,500.00 8 Cat dasar Tembok 1.00 kg 10,500.00 10,500.00 9 Thinner / Minyak cat type A Biasa 1.00 kg 22,500.00 22,500.00
10 Thinner / Minyak cat type A Spesial 1.00 kg 14,500.00 14,500.00 11 Thinner / Minyak cat type B 1.00 kg 9,000.00 9,000.00 12 Cat Genteng Impra 1.00 kg - 13 Cat Genteng / Seng Belmas 1.00 kg - 14 Cat Genteng Aga 1.00 kg - 15 Cat Genteng 1.00 kg 23,000.00 23,000.00 16 Cat Kayu 1.00 kg 40,000.00 40,000.00 17 Cat Kayu Avian 1.00 kg - 18 Dempul Padang 1.00 kg 27,100.00 27,100.00 19 Dempul Coklat 1.00 bh - 20 Dempul Jadi 1.00 kg - 21 Filler 1.00 kg - 22 Kalkarium 1.00 kg - 23 Kapur Sirih 1.00 kg - 24 Kertas Gosok 1.00 lmb - 25 Cat Tembok Ex. Decolith 1.00 kg - 26 Cat Tembok Ex. Paragon 1.00 kg - 27 Cat Tembok Ex. Catylac INTERIOR 1.00 kg 12,500.00 12,500.00 28 Cat Tembok Ex. Catylac EXTERIOR 1.00 kg 26,500.00 26,500.00 29 Cat Tembok Ex. Mowilex warna Standart 1.00 kg - 30 Cat Tembok Ex. Mowilex warna khusus 1.00 kg - 31 Cat Tembok Ex. Vinilex 1.00 kg - 32 Cat Tembok Ex. Avitex 1.00 kg - 33 Cat Tembok Ex. Altex 1.00 kg - 34 Cat Tembok Ex. Levi's Exterior 1.00 kg - 35 Cat Tembok Ex. Levi's Interior 1.00 kg - 36 Cat Tembok Ex. Flora. 1.00 kg - 37 Kuas ukuran 1 RRT 1.00 bh - 38 Kuas ukuran 1,5 RRT 1.00 bh - 39 Kuas ukuran 2 RRT 1.00 bh - 40 Kuas ukuran 2,5 RRT 1.00 bh - 41 Kuas ukuran 3 RRT 1.00 bh - 42 Kuas ukuran 4 RRT 1.00 bh - 43 Kuas ukuran 5 RRT 1.00 bh - 44 Kuas Rol 1.00 bh 7,500.00 7,500.00 45 Lem Vinyl 1.00 kg 62,500.00 62,500.00 46 Lem Kayu 1.00 ltr 22,000.00 22,000.00 47 Lem Rajawali 1.00 kg - 48 Lem pipa PVC 1.00 kg - 49 Plamur Besi 1.00 kg - 50 Plamur Besi ex. Pedang 1.00 kg - 51 Plamur Kayu 1.00 kg -
Page 28 of 334
52 Plamur Kayu ex. Pedang 1.00 kg - 53 Plamur Tembok ex. Paragon 1.00 kg - 54 Plamur Tembok 1.00 kg 7,500.00 7,500.00 46 Spirtus 1.00 ltr 10,500.00 10,500.00 47 Teak Oil 1.00 ltr - 48 Residu 1.00 ltr - 49 Politur dasar 1.00 ltr - 50 Politur jadi ex. Mowilex 1.00 ltr - 51 Water Proffing 1.00 kg 45,000.00 45,000.00 52 Vernish Jadi 1.00 ltr - 53 Wood Filler 1.00 kg 75,000.00 75,000.00 54 Pewarna 1.00 sach 75,000.00 75,000.00 55 Kertas gosok No. 150 1.00 lbr 3,000.00 3,000.00 56 Kertas gosok no280 1.00 lbr 3,000.00 3,000.00 57 Shanding 1.00 kg 65,000.00 65,000.00 58 Clear Doof 1.00 kg 45,000.00 45,000.00 59 Coumpond 1.00 klng 40,000.00 40,000.00 60 Sewa alat bantu ( 1 set @ 3 alat ) 1.00 set 1,500,000.00 1,500,000.00 61 Sewa compresor 1.00 jam - 62 Soda Api 1.00 kg - 63 Serat fiber 1.00 m2 - 64 Wallpaper Eksklusif 1.00 m' 20,000.00 20,000.00 65 Sirlak 1.00 kg 178,000.00 178,000.00
KERAMIK - UBIN - 1 Gymfloor 1.00 m2 287,000.00 287,000.00 2 Internal Cove 5 x 5 x 20 cm 1.00 bh - 3 Keramik Lantai Artistik 5 x 20 1.00 bh - 4 Keramik lantai Artistik 10 x 10 1.00 bh - 5 Keramik Dinding 20 x 20 1.00 m2 - 6 Keramik lantai 20 x 20 Motif 1.00 m2 38,000.00 38,000.00 7 Keramik lantai 20 x 20 KM/WC 1.00 m2 - 8 Keramik lantai 20 x 20 putih MULIA 1.00 m2 - 9 Keramik lantai 20 x 20 Warna /Motif 1.00 m2 -
10 Keramik Dinding 20 x 25 1.00 m2 46,000.00 46,000.00 11 Keramik Dinding 20 x 25 polos`MULIA 1.00 m2 46,000.00 46,000.00 12 Keramik Dinding 20 x 25 Warna / Motif Mulia 1.00 m2 - 13 Keramik Lantai 30 x 30 Putih 1.00 m2 - 14 Keramik Lantai 30 x 30 Putih Mulia 1.00 m2 - 15 Keramik Lantai 30 x 30 Warna Mulia 1.00 m2 - 16 Keramik Lantai 30 x 30 Warna / Motif 1.00 m2 65,000.00 65,000.00 17 Keramik Lantai 40 x 40 Putih 1.00 m2 - 18 Keramik Lantai 40 x 40 Warna / Motif 1.00 m2 60,000.00 60,000.00 19 Keramik Lantai 40 x 40 Warna Mulia 1.00 m2 - 20 Plint Keramik Lntai 10 x 20 1.00 bh - 21 Plint Keramik Lantai 10 x 30 1.00 bh - 22 Plint Keramik Lantai 10 x 40 1.00 bh 37,400.00 37,400.00 23 Plint Ubin Terraso 10 x 30 1.00 bh - 24 Plint Ubin PC abu-abu 15 x 20 1.00 bh - 25 Ubin Granito warna Essenza 30 x 30 1.00 m2 - 26 Ubin Granito warna Hitam Essenza 60 x 60 1.00 m2 250,000.00 250,000.00 27 Ubin Panel Accura 20 x 25 - 12 lembar 1.00 m2 - 28 Ubin Panel Accura 20 x 25 - 20 lembar 1.00 m2 - 29 Ubin Panel Accura 20 x 25 - 4 lembar 1.00 m2 - 30 Ubin Panel Accura 20 x 25 - 6 lembar 1.00 m2 - 31 Marmer 100 x 100 1.00 m2 265,000.00 265,000.00 32 Marmer kwalitas export warna pink 0,60x 1m 1.00 m2 - 33 Marmer kw export warna krem 0,60 x 1 m 1.00 m2 - 34 Marmer kw export warna trotol dasar 0,60 x 1 m 1.00 m2 - 35 Batu GRANIT import Italy 1.00 m2 325,000.00 325,000.00 36 Texture GRANITONE 1.00 m2 - 37 PAVINGST ( K.125 ) warna abu2 t=8cm 1.00 m2 - 38 PAVINGST ( K.125 ) warna abu2 t=6cm 1.00 m2 - 39 PAVINGST KW.I tebal=8cm ( K.300) 1.00 m2 - 40 PAVINGST KW.I tebal=6cm ( K.300) 1.00 m2 - 41 Gress Block Beton 10 x 40 x 60 cm 1.00 m2 - 42 Karpet World Class 1.00 m2 - 43 Wallpaper Eksklusif 1.00 m2 - 44 Kansteen BDCM 1.00 m2 - 45 Kansteen 1.00 M' - 46 Stoper / uskup tebal 6 cm 1.00 m2 - 47 Stoper / uskup tebal 8 cm 1.00 m2 - 48 Floor Hardener 1.00 kg 25,000.00 25,000.00 49 Granite Tile Ukuran 30 x 30 Polished 1.00 m² 175,000.00 175,000.00 50 Granite Tile Ukuran 30 x 30 Unpolished 1.00 m² - 51 Granite Tile Ukuran 60 x 60 Polished 1.00 m² 250,000.00 250,000.00 52 Granite Tile Ukuran 60 x 60 Unpolished 1.00 m² - 53 Kansteen Uk. 15.18.40 1.00 bh - 54 Bumper Guard terpasang 1.00 m' - 55 Rail Guard terpasang 1.00 m' - 56 Bed Head terpasang 1.00 m' -
23 Lampu XL ( Lilin ) 18 watt 1.00 bh - 24 Lampu XL ( Lilin ) 23 watt 1.00 bh - 25 Las doof 1.00 bh - 26 Pasang baru PLN 1.00 ls - 27 Pipa Arde 1.00 m' - 28 Pipa PVC 5/8 " 1.00 ljr - 29 Saklar Broco 1.00 bh - 30 Stop Kontak Broco 1.00 bh - 31 T Dos PVC 1.00 bh - 32 Tambah Daya 2200 watt 1.00 ls - 33 Zekering Kast Lokal 1 Group 1.00 unit - 34 Zekering Kast Lokal 2 Group 1.00 unit - 35 Zekering Kast Lokal 3 Group 1.00 unit - 36 Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 5m 1.00 unit - 37 Tiang Oktogonal Double Hot Dipped Galv + Flenders 5m 1.00 unit - 38 Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 7 m 1.00 unit - 39 Tiang Oktogonal Double Hot Dipped Galv + Flenders 7 m 1.00 unit - 40 Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 9 m 1.00 unit - 41 Tiang Oktogonal Double Hot Dipped Galv + Flenders 9 m 1.00 unit - 42 Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 12 m 1.00 unit - 43 Tiang Oktogonal Double Hot Dipped Galv + Flenders 12 m 1.00 unit -
LAIN - LAIN - 1 AC Wall Mounted 8900 BTU / H 1 PK 1.00 bh - 2 Alat bantu pasang rangka plafond 1.00 ls - 3 Bahan terraso cor 1.00 m3 - 4 Bak Kontrol 40 x 40 x 50 cm 1.00 lot - 5 Batacota 1.00 kg - 6 Besi Holo 1.00 ljr - 7 Bor Strous 1.00 ttk 17,500.00 17,500.00 8 Elektrode 1.00 kg - 9 Formika 90 x 120 cm 1.00 lbr -
10 Gedeg Guling 1.00 m2 - 11 Grease 1.00 kg - 12 Grill ( tutup Saluran Air Hujan ) 1.00 unit - 13 Grounding 1.00 bh - 14 Grounding penangkala petir 1.00 lot - 15 Halogeen spot DL 50 watt 1.00 bh - 16 Kabel Coaxial 2 x 30 mm 1.00 m' - 17 Kawat BC 1.00 m' - 18 Kolom Beton pracetak un. Pagar 1.00 bh - 19 Lampu Gantung 1.00 buah - 20 Ijuk 1.00 kg 15,000.00 15,000.00 21 Material bantu 1.00 ls - 22 Minyak Bekisting 1.00 ltr 50,000.00 50,000.00 23 Minyak Pelumas 1.00 ltr - 24 Ornamen Kolom 1.00 bh - 25 Pagar pengaman dan besi pipa 1.00 m2 - 26 Panel beton prcetak un. Pagar 1.00 bh - 27 Panel Induk 1.00 unit - 28 Polycarbonite 1.00 lbr - 29 Pompa submersible 1.00 unit - 30 Railling Tngga Virkan 1.00 m2 - 31 Railling Tangga Pipa 1.00 m2 - 32 Seal Tape / TBA 1.00 buah - 33 Sending daun jendela 1.00 buah - 34 Sending daun pintu 1.00 buah - 35 Sending kosen pintu / jendela 1.00 m' - 36 Sewa alat sandblasting 1.00 hr - 37 Sewa Genset 1.00 hr - 38 Sewa Mesin Las 1.00 hr - 39 Sew Mesin Bor 1.00 hr - 40 Sewa pompa Tes 1.00 hr - 41 Spot light 1.00 buah - 42 Sub panel 1.00 buah - 43 Sumur bor dalam 1.00 unit - 44 Sunscreen Alumunium 1.00 m3 - 45 Tali ijuk 1.00 kg - 46 Telephone outlet 1.00 buah - 47 Timah 1.00 kg - 48 Vertical Blind 1.00 m2 - 49 Vonetion Blind 1.00 m2 - 50 Wallpaper 1.00 m2 - 51 Waterstop lebar 200 mm 1.00 m' - 52 Waterstop lebar 150 mm 1.00 m' - 53 Waterstop lebar 230 mm 1.00 m' - 54 Waterstop lebar 250 mm 1.00 m' - 55 Waterstop lebar 300 mm 1.00 m' - 56 Waterstop lebar 320 mm 1.00 m' -
BAHAN MATERIAL TERPASANG - 1 Auning + Rangka hollow 1.00 m2 - 2 Polycarbonat ex. Twilite rangka hollow 1.00 m2 - 3 Polycarbonat ex. Twilite rangka stainless 1.00 m2 - 4 Baja Truss Prof C .Z-Alm bent lbh= 8m 1 sd 1.00 m2 - 5 Baja Truss Prof C .Z-Alm bent lbh= 8m 2 sd 1.00 m2 - 6 Baja Truss Prof C .Z-Alm bent krng= 8m 1 sd 1.00 m2 - 7 Baja Truss Prof C .Z-Alm bent krng= 8m 2 1.00 m2 - 8 Pasang kisdam 1.00 m' - 9 Membran sheet water profing ex. Foxroc 1.00 m2 60,000.00 60,000.00
10 Kosen ALUMINIUM warna 4" ex. Elexindo 1.00 m' - 11 Kosen ALUMINIUM putih 4" ex. Elexindo 1.00 m' - 12 Kosen ALUM warna 4,5x10x0,1 ex. Indal 1.00 m' - 13 Kosen ALUM 4,5x10x0,1 putih ex. Indal 1.00 m' - 14 Keray aluminium 1.00 m2 - 15 Jalusi aluminium 1.00 m2 - 16 Vertical Blind 1.00 m2 - 17 Plafond rangka Hollow 1.00 m2 - 18 Plafond rangka hollow galvanis 1.00 m2 - 19 Exhaust fan kecil ex. Maspion 1.00 bh - 20 Exhaust fan besar ex. Maspion 1.00 bh - 21 Pintu KM/WC PVC 200x70 1.00 bh - 22 Pintu KM/WC Aluminium 185 x 65 cm 1.00 bh - 23 Daun pintu + assc ALPHA / ATT warna 1.00 m2 - 24 Daun pintu + assc ALPHA / ATT putih 1.00 m2 - 25 Daun jend kaca+assc ALPHA/ATT l warna 1.00 m2 - 26 Daun jend kaca+assc ALPHA/ATT putih 1.00 m2 - 27 Assesories pintu Floorhang "DORMA" 1.00 BH - 28 Assesories pintu Floorhang "ALPHA" 1.00 BH - 29 Kansteen Besar 15x30x50 cm 1.00 m' - 30 Kansteen Kecil 15x20x50 cm 1.00 m' - 31 Lampu SL ex. PHILLIPS watt 14 1.00 unit - 32 Lampu SL ex. PHILLIPS watt 18 1.00 unit - 33 Lampu dop )bolamp) ex. PHILLIPS 1.00 unit - 34 Downlicht PANASONIC 1.00 bh - 35 Downlicht lokal 1.00 bh - 36 Saklar Tunggal ex BROCO 1.00 bh - 37 Saklar Ganda ex BROCO 1.00 bh - 38 Stop kontak 1.00 bh - 39 Pas.Ins listrik non saklar/stop kontak 1.00 ttk - 40 Pintu rolling door Aluminium 1.00 m2 - 41 Box Cluvert U1000 K.350 (Besi 130 Kg 1.00 bh - 42 Cover Cluvert 1000x1000x2400; besi 160 kg 1.00 bh -
PERALATAN SEWA - 1 Buldozer 1.00 jam 283,000.00 283,000.00 2 Motor Grader 100 HP 1.00 jam 264,000.00 264,000.00 3 Hydraulic Excavator 1.00 jam 208,000.00 208,000.00 4 Pneumatic Tire Roller 1.00 jam 140,000.00 140,000.00 5 Vibrator Roller 1.00 jam 202,000.00 202,000.00 6 Pemecah Batu 1.00 jam 667,000.00 667,000.00 7 Mesin Penyaring 1.00 jam - 8 Wheel Loader 1.00 jam 237,000.00 237,000.00 9 Wheel Tractor 1.00 jam 202,000.00 202,000.00
10 Mesin Gilas 3 Roda besi 8-10 ton 1.00 jam 129,000.00 129,000.00 11 Mesin Gilas Tandem 6-10 ton 1.00 jam 129,000.00 129,000.00 12 Mesin gilas Bergetar / Vibro roller 10 ton 1.00 jam 202,000.00 202,000.00 13 Mesin Gilas Roda karet 8-15 ton 1.00 jam 140,000.00 140,000.00 14 Mesin Gilas bergetar 1 ton 1.00 jam 202,000.00 202,000.00 15 Stamper 4 HP 1.00 jam 21,000.00 21,000.00 16 Mesin Penyempro Aspal 1.00 jam 38,000.00 38,000.00 17 Mesin Penyampur aspal 1.00 jam 4,492,000.00 4,492,000.00 18 Mesin Penghambar Aspal 1.00 jam 236,000.00 236,000.00 19 Truck Tangki Air 1.00 jam 136,000.00 136,000.00 20 Sewa Truck klas 3 dalam kota 1.00 jam 126,000.00 126,000.00 21 Dump Truck 3,5 ton 1.00 jam 136,000.00 136,000.00 22 Dump Truck 5 ton 1.00 jam 261,000.00 261,000.00 23 Pompa Air 1.00 jam 20,000.00 20,000.00 24 Tractor Equipment, etc 1.00 jam 261,000.00 261,000.00 25 Truck Aspal ( Asphalt Distrubutor ) 1.00 jam 261,000.00 261,000.00 26 Genset 1.00 jam 74,000.00 74,000.00 27 Batching Plant 1.00 jam 667,000.00 667,000.00 28 Truck Mixer 1.00 jam 261,000.00 261,000.00 29 Concrete Vibrator 1.00 jam 16,000.00 16,000.00 30 Concrete Paver 1.00 jam 293,000.00 293,000.00 31 Sewa bucket dan crane 1.00 jam 225,000.00 225,000.00 32 Concrete Pump 1.00 jam 285,000.00 285,000.00 33 Welding Set 1.00 jam 25,000.00 25,000.00 34 Sewa Crane 1.00 jam 225,000.00 225,000.00
Page 34 of 334
35 Jack Hammer 1.00 jam 18,000.00 18,000.00 36 Theodholit 1.00 set 25,000.00 25,000.00 37 Surveyor 1.00 Oh 40,000.00 40,000.00
Surabaya, 23 November 2010PT. ANGGREK MERAH
ALBERTINUS WIDYANTODirektur Utama
Page 35 of 334
ANALISA HARGA SATUAN PEKERJAANPROYEK PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
RUMAH SAKIT UMUM PROVINSI dr. SOEDONO MADIUNJALAN Dr. SOETOMO No. 29 MADIUN - JAWA TIMUR
No. Vol. URAIAN KOOEF St.HARGA ( Rp)
SATUAN JUMLAH TOTALPEKERJAAN PERSIAPAN DAN TANAH
1 M' PEMBUATAN BOUPLANK 28,810.00 BAHAN
Kayu meranti papan 2/20 0.0042 m3 2,200,000.00 9,240.00 Kayu meranti usuk 5/7 0.0039 m3 2,500,000.00 9,750.00 Paku biasa 0.0200 kg 11,000.00 220.00 19,210.00
BAHAN Kayu Meranti papan 3/30 0.0330 m3 4,100,000.00 135,300.00 Kayu Meranti Usuk 0.0210 m3 2,500,000.00 52,500.00 Paku Klem 0.3000 kg 11,000.00 3,300.00 191,100.00
1 M2 PEMASANGAN TURAP BAMBU TINGGI 1,5-2 M 114,690.00 TENAGA
1 M2 PASANG BEKISTING UN. SLOOF + STRUKTUR PRAKTIS ( 3 kali pakai ) 92,365.00 LANTAI I 1.0000 92,365.00 92,365.00 LANTAI II 1.0900 92,365.00 100,677.85 LANTAI III 1.1200 92,365.00 103,448.80 LANTAI IV 1.1350 92,365.00 104,834.28 LANTAI V 1.1620 92,365.00 107,328.13 LANTAI ATAP
BAHAN Kayu Meranti 0.0200 m3 2,200,000.00 44,000.00 Paku Biasa 0.3000 kg 11,000.00 3,300.00 Minyak Bekisting 0.1000 ltr 50,000.00 5,000.00 Multiplex 12 mm 0.1750 m2 100,000.00 17,500.00 69,800.00
1 M2 PEMASANGAN PAGAR BESI 528,750.00 Lantai Satu 1.0000 528,750.00 528,750.00 Lantai Dua 1.0900 528,750.00 576,337.50 Lantai Tiga 1.1200 528,750.00 592,200.00 Lantai Empat 1.1350 528,750.00 600,131.25 Lantai Lima 1.1620 528,750.00 614,407.50
BAHAN Pagar Besi Komplit Assesories 1.0000 m2 450,000.00 450,000.00 450,000.00
TENAGA Pekerja Tak Terampil 1.0500 oh 35,000.00 36,750.00 Tukang 1.0500 oh 40,000.00 42,000.00 78,750.00
1 M2 PEMASANGAN PAGAR PANEL / FABRIKASI TINGGI 2.00 M 25,312.50 BAHAN
Precast Pagar Panel 1.0000 m' - - - TENAGA
Mandor 0.1250 oh 52,500.00 6,562.50 Tukang Batu 0.2500 oh 40,000.00 10,000.00 Pekerja Tak Terampil 0.2500 oh 35,000.00 8,750.00 25,312.50
1 M2 PEMASANGAN TERALIS JENDELA 143,104.60 BAHAN
Besi strip 0.0154 kg 9,000.00 138.60 4,729.60 Elektride Baja 0.2000 kg 22,955.00 4,591.00
TENAGA Mandor 0.0830 oh 52,500.00 4,357.50 Kepala Tukang 0.1670 oh 52,500.00 8,767.50 Tukang 1.6700 oh 40,000.00 66,800.00 Pekerja Tak Terampil 1.6700 m' 35,000.00 58,450.00 138,375.00
1 M' ONGKOS PEMASANGAN PIPA GALVANIS 4,136.00 BAHAN
Sewa Welding Set 0.0210 hari 25,000.00 525.00 651.00 Kawat Elektrode Baja 0.0060 Kg 21,000.00 126.00
TENAGA Mandor 0.0020 oh 52,500.00 105.00 Tukang Batu 0.0600 oh 40,000.00 2,400.00 Pekerja Tak Terampil 0.0280 oh 35,000.00 980.00 3,485.00
1 M' PEKERJAAN BESI PIPA GALVANIS Ǿ 1,5" ( MEDIUM ) 341,125.56 BAHAN
Besi Pipa Galvanis Ǿ1,5" ( Medium ) 1.0200 m' 322,500.00 328,950.00 TENAGA
Ongkos Pemasangan 2.9438 m' 4,136.00 12,175.56
1 M' PEKERJAAN BESI PIPA GALVANIS Ǿ 3" ( MEDIUM ) 765,581.60 BAHAN
Besi Pipa Galvanis Ǿ 3" ( Medium ) 1.0200 m' 738,000.00 752,760.00 TENAGA
Ongkos Pemasangan 3.1000 m' 4,136.00 12,821.60
1 M' PEKERJAAN RAILLING TANGGA PIPA STAINLESS 664,937.50 Lantai Satu 1.0000 664,937.50 664,937.50 Lantai Dua 1.0900 664,937.50 724,781.88 Lantai Tiga 1.1200 664,937.50 744,730.00 Lantai Empat 1.1350 664,937.50 754,704.06 Lantai Lima 1.1620 664,937.50 772,657.38 Lantai Enam 1.1970 664,937.50 795,930.19 Lantai Tujuh 1.2360 664,937.50 821,862.75
BAHAN Plat Tiang Railling Hot Deep Galvanis 1.5000 btg 105,000.00 157,500.00 Pipa Stainless Steel Ø 13 mm 4.0000 m' 110,000.00 440,000.00 Hand Railling Aluminium Ø 75mm 1.0000 m' 47,500.00 47,500.00 Dinabol dia. 8mm 3.0000 buah 1,500.00 4,500.00 Tutup Hand Railling 0.0500 buah 25,000.00 1,250.00 Tutup Hand Railling ke dinding 0.0250 buah 25,000.00 625.00 651,375.00
TENAGA Pekerja tak terampil 0.2500 oh 35,000.00 8,750.00 Tukang 0.0500 oh 40,000.00 2,000.00 Kepala Tukang 0.0250 oh 52,500.00 1,312.50 Mandor 0.0250 oh 60,000.00 1,500.00 13,562.50
1 M' HAND RAILLING ALUMUNIUM Ø 75 MM 260,322.92 Lantai Satu 1.0000 260,322.92 260,322.92 Lantai Dua 1.0900 260,322.92 283,751.98 Lantai Tiga 1.1200 260,322.92 291,561.67 Lantai Empat 1.1350 260,322.92 295,466.51 Lantai Lima 1.1620 260,322.92 302,495.23 Lantai Enam 1.1970 260,322.92 311,606.53 Lantai Tujuh 1.2360 260,322.92 321,759.13
BAHAN Pipa Stainless Steel Ø 13 mm 4.0000 m' 39,166.67 156,666.67 Hand Railling Aluminium Ø 75mm 1.0000 m' 86,250.00 86,250.00 Dinabol dia. 8mm 3.0000 buah 1,500.00 4,500.00 247,416.67
TENAGA Pekerja tak terampil 0.2500 oh 35,000.00 8,750.00 Tukang 0.0500 oh 40,000.00 2,000.00 Kepala Tukang 0.0125 oh 52,500.00 656.25 Mandor 0.0250 oh 60,000.00 1,500.00 12,906.25
1 M2 RAILLING BALKON DAN TERAAS BESI HOLLOW. 852,554.98 Lantai Satu 1.0000 852,554.98 852,554.98 Lantai Dua 1.0900 852,554.98 929,284.93 Lantai Tiga 1.1200 852,554.98 954,861.58 Lantai Empat 1.1350 852,554.98 967,649.90 Lantai Lima 1.1620 852,554.98 990,668.89
Page 46 of 334
Lantai Enam 1.1970 852,554.98 1,020,508.31 Lantai Tujuh 1.2360 852,554.98 1,053,757.96
TENAGA Fabrikasi 20 % 0.0200 ls 22,955.00 459.10 459.10
PEKERJAAN DINDING DAN PLESTERAN
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 2Ps. (TINGGI S/D 2.00M ) 79,808.00 Lantai Satu 1.0000 79,808.00 79,808.00 Lantai Dua 1.0900 79,808.00 86,990.72 Lantai Tiga 1.1200 79,808.00 89,384.96 Lantai Empat 1.1350 79,808.00 90,582.08 Lantai Lima 1.1620 79,808.00 92,736.90 Lantai Enam 1.1970 79,808.00 95,530.18 Lantai Tujuh 1.2360 79,808.00 98,642.69
BAHAN Semen PC 19.1100 kg 1,200.00 22,932.00 Pasir Pasang 0.0348 m3 135,000.00 4,698.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 58,310.00
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 2Ps. (TINGGI 2.00 - 5.00 M ) 83,061.25 Lantai Satu 1.0000 83,061.25 83,061.25 Lantai Dua 1.0900 83,061.25 90,536.76 Lantai Tiga 1.1200 83,061.25 93,028.60 Lantai Empat 1.1350 83,061.25 94,274.52 Lantai Lima 1.1620 83,061.25 96,517.17 Lantai Enam 1.1970 83,061.25 99,424.32 Lantai Tujuh 1.2360 83,061.25 102,663.71
BAHAN Semen PC 17.1600 kg 1,200.00 20,592.00 Pasir Pasang 0.0348 m3 135,000.00 4,698.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 55,970.00
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 3Ps. (TINGGI S/D 2.00M ) 74,942.00 Lantai Satu 1.0000 74,942.00 74,942.00 Lantai Dua 1.0900 74,942.00 81,686.78 Lantai Tiga 1.1200 74,942.00 83,935.04 Lantai Empat 1.1350 74,942.00 85,059.17 Lantai Lima 1.1620 74,942.00 87,082.60 Lantai Enam 1.1970 74,942.00 89,705.57 Lantai Tujuh 1.2360 74,942.00 92,628.31
BAHAN Semen PC 14.5150 kg 1,200.00 17,418.00 Pasir Pasang 0.0396 m3 135,000.00 5,346.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 53,444.00
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 3Ps. (TINGGI 2.00 - 5.00 M ) 80,535.25 Lantai Satu 1.0000 80,535.25 80,535.25 Lantai Dua 1.0900 80,535.25 87,783.42 Lantai Tiga 1.1200 80,535.25 90,199.48 Lantai Empat 1.1350 80,535.25 91,407.51 Lantai Lima 1.1620 80,535.25 93,581.96 Lantai Enam 1.1970 80,535.25 96,400.69 Lantai Tujuh 1.2360 80,535.25 99,541.57
BAHAN Semen PC 14.5150 kg 1,200.00 17,418.00 Pasir Pasang 0.0396 m3 135,000.00 5,346.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 53,444.00
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 4Ps. (TINGGI S/D 2.00M ) 71,937.50 Lantai Satu 1.0000 71,937.50 71,937.50 Lantai Dua 1.0900 71,937.50 78,411.88 Lantai Tiga 1.1200 71,937.50 80,570.00 Lantai Empat 1.1350 71,937.50 81,649.06 Lantai Lima 1.1620 71,937.50 83,591.38 Lantai Enam 1.1970 71,937.50 86,109.19 Lantai Tujuh 1.2360 71,937.50 88,914.75
- BAHAN
Semen PC 11.6850 kg 1,200.00 14,022.00 Pasir Pasang 0.0425 m3 135,000.00 5,737.50 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 50,439.50
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc :4Ps. (TINGGI 2.00 - 5.00 M ) 77,530.75 Lantai Satu 1.0000 77,530.75 77,530.75 Lantai Dua 1.0900 77,530.75 84,508.52 Lantai Tiga 1.1200 77,530.75 86,834.44 Lantai Empat 1.1350 77,530.75 87,997.40 Lantai Lima 1.1620 77,530.75 90,090.73 Lantai Enam 1.1970 77,530.75 92,804.31 Lantai Tujuh 1.2360 77,530.75 95,828.01
77,530.75 - BAHAN
Semen PC 11.6850 kg 1,200.00 14,022.00 Pasir Pasang 0.0425 m3 135,000.00 5,737.50 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 50,439.50
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 5Ps. (TINGGI S/D 2.00M ) 70,547.00 Lantai Satu 1.0000 70,547.00 70,547.00 Lantai Dua 1.0900 70,547.00 76,896.23 Lantai Tiga 1.1200 70,547.00 79,012.64 Lantai Empat 1.1350 70,547.00 80,070.85 Lantai Lima 1.1620 70,547.00 81,975.61 Lantai Enam 1.1970 70,547.00 84,444.76 Lantai Tujuh 1.2360 70,547.00 87,196.09
- BAHAN
Semen PC 9.9750 kg 1,200.00 11,970.00 Pasir Pasang 0.0474 m3 135,000.00 6,399.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 49,049.00
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc :5Ps. (TINGGI 2.00 - 5.00 M ) 76,140.25 Lantai Satu 1.0000 76,140.25 76,140.25 Lantai Dua 1.0900 76,140.25 82,992.87 Lantai Tiga 1.1200 76,140.25 85,277.08 Lantai Empat 1.1350 76,140.25 86,419.18 Lantai Lima 1.1620 76,140.25 88,474.97 Lantai Enam 1.1970 76,140.25 91,139.88 Lantai Tujuh 1.2360 76,140.25 94,109.35
- BAHAN
Semen PC 9.9750 kg 1,200.00 11,970.00 Pasir Pasang 0.0474 m3 135,000.00 6,399.00 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh 590.00 30,680.00 49,049.00
1 M2 PEMASANGAN GRANITE TILE 30X30 POLISH 253,475.00 Pemasangan Lantai I 1.0000 253,475.00 253,475.00 Pemasangan Lantai II 1.0900 253,475.00 276,287.75 Pemasangan Lantai III 1.1200 253,475.00 283,892.00 Pemasangan Lantai IV 1.1350 253,475.00 287,694.13 Pemasangan Lantai V 1.1620 253,475.00 294,537.95 Pemasangan Lantai VI 1.1970 253,475.00 303,409.58 Pemasangan Lantai VII 1.2360 253,475.00 313,295.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Granite Tile Ukuran 30 x 30 Polished 1.0000 m2 175,000.00 175,000.00 206,575.00
1 M2 PEMASANGAN GRANITE TILE 60X60 POLISH 328,475.00 Pemasangan Lantai I 1.0000 328,475.00 328,475.00 Pemasangan Lantai II 1.0900 328,475.00 358,037.75 Pemasangan Lantai III 1.1200 328,475.00 367,892.00 Pemasangan Lantai IV 1.1350 328,475.00 372,819.13 Pemasangan Lantai V 1.1620 328,475.00 381,687.95 Pemasangan Lantai VI 1.1970 328,475.00 393,184.58 Pemasangan Lantai VII 1.2360 328,475.00 405,995.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Granite Tile Ukuran 60 x 60 Polished 1.0000 m2 250,000.00 250,000.00 281,575.00
1 M2 PEMASANGAN UBIN KERAMIK 30x30 WARNA MOTIF 143,475.00 Pemasangan Lantai I 1.0000 143,475.00 143,475.00 Pemasangan Lantai II 1.0900 143,475.00 156,387.75 Pemasangan Lantai III 1.1200 143,475.00 160,692.00 Pemasangan Lantai IV 1.1350 143,475.00 162,844.13 Pemasangan Lantai V 1.1620 143,475.00 166,717.95 Pemasangan Lantai VI 1.1970 143,475.00 171,739.58 Pemasangan Lantai VII 1.2360 143,475.00 177,335.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Keramik Lantai 30 x 30 Warna / Motif 1.0000 m2 65,000.00 65,000.00 96,575.00
1 M2 PEMASANGAN PELAPIS BATU CANDI 165,475.00 Pemasangan Lantai I 1.0000 165,475.00 165,475.00 Pemasangan Lantai II 1.0900 165,475.00 180,367.75 Pemasangan Lantai III 1.1200 165,475.00 185,332.00 Pemasangan Lantai IV 1.1350 165,475.00 187,814.13 Pemasangan Lantai V 1.1620 165,475.00 192,281.95 Pemasangan Lantai VI 1.1970 165,475.00 198,073.58 Pemasangan Lantai VII 1.2360 165,475.00 204,527.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Batu Candi 1.0000 m2 87,000.00 87,000.00 118,575.00
1 M2 PEMASANGAN UBIN KERAMIK 40X40 WARNA MOTIF 138,475.00 Pemasangan Lantai I 1.0000 138,475.00 138,475.00 Pemasangan Lantai II 1.0900 138,475.00 150,937.75 Pemasangan Lantai III 1.1200 138,475.00 155,092.00 Pemasangan Lantai IV 1.1350 138,475.00 157,169.13 Pemasangan Lantai V 1.1620 138,475.00 160,907.95 Pemasangan Lantai VI 1.1970 138,475.00 165,754.58 Pemasangan Lantai VII 1.2360 138,475.00 171,155.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Keramik Lantai 40 x 40 Warna / Motif 1.0000 m2 60,000.00 60,000.00 91,575.00
1 M2 PEMASANGAN GARNITE TILE WARNA EX. ESSENZA 60X60 328,475.00 Pemasangan Lantai I 1.0000 328,475.00 328,475.00 Pemasangan Lantai II 1.0900 328,475.00 358,037.75 Pemasangan Lantai III 1.1200 328,475.00 367,892.00 Pemasangan Lantai IV 1.1350 328,475.00 372,819.13 Pemasangan Lantai V 1.1620 328,475.00 381,687.95 Pemasangan Lantai VI 1.1970 328,475.00 393,184.58 Pemasangan Lantai VII 1.2360 328,475.00 405,995.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Ubin Granito warna Hitam Essenza 60 x 60 1.0000 m2 250,000.00 250,000.00 281,575.00
1 M2 PEMASANGAN MARMER 100 X 100 343,475.00 Pemasangan Lantai I 1.0000 343,475.00 343,475.00 Pemasangan Lantai II 1.0900 343,475.00 374,387.75 Pemasangan Lantai III 1.1200 343,475.00 384,692.00 Pemasangan Lantai IV 1.1350 343,475.00 389,844.13 Pemasangan Lantai V 1.1620 343,475.00 399,117.95 Pemasangan Lantai VI 1.1970 343,475.00 411,139.58 Pemasangan Lantai VII 1.2360 343,475.00 424,535.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Marmer 100 x 100 1.0000 m2 265,000.00 265,000.00 296,575.00
1 M2 PEMASANGAN GRANIT IMPORT 403,475.00 Pemasangan Lantai I 1.0000 403,475.00 403,475.00 Pemasangan Lantai II 1.0900 403,475.00 439,787.75 Pemasangan Lantai III 1.1200 403,475.00 451,892.00 Pemasangan Lantai IV 1.1350 403,475.00 457,944.13 Pemasangan Lantai V 1.1620 403,475.00 468,837.95 Pemasangan Lantai VI 1.1970 403,475.00 482,959.58 Pemasangan Lantai VII 1.2360 403,475.00 498,695.10
BAHAN - PC 10.0000 kg 1,200.00 12,000.00 Semen warna nut 1.5000 kg 9,000.00 13,500.00 Pasir pasang 0.0450 m3 135,000.00 6,075.00 Batu GRANIT import Italy 1.0000 m2 325,000.00 325,000.00 356,575.00
Glass wol 0.0183 Rol 925,000.00 16,958.33 Roof Mes 0.0153 Rol 450,000.00 6,875.00 Alluminium foil /insulation double side 0.0611 Rol 1,250,000.00 76,388.89 Allumunium Tape 0.0489 Rol 26,500.00 1,295.56 101,517.78
TENAGA Pekerja 0.1500 oh 40,000.00 6,000.00 Tukang kayu 0.0500 oh 52,500.00 2,625.00 Kepala tukang Kayu 0.0050 oh 55,000.00 275.00 Mandor 0.0080 oh 60,000.00 480.00 9,380.00
PEKERJAAN TALANG
1 M' PEMASANGAN TALANG SENG BJLS 40 ( LEBAR 90 CM ) 364,840.00 BAHAN
Kayu Kamper ( Papan ) 2/30 0.0160 m3 8,900,000.00 142,400.00 Kayu KamperUsuk 0.0073 m3 5,200,000.00 37,960.00 Seng Talang BJLS 40 Lebar 90 cm 1.0000 m' 38,000.00 38,000.00 Paku Sumbat 5.0000 bh 13,000.00 65,000.00 283,360.00
1 M2 PEMASANGAN PLAFOND ASBES DATAR RANGKA KAYU Kruing 69,738.45 Lantai Satu 1.0000 69,738.45 69,738.45 Lantai Dua 1.0900 69,738.45 76,014.91 Lantai Tiga 1.1200 69,738.45 78,107.06 Lantai Empat 1.1350 69,738.45 79,153.14 Lantai Lima 1.1620 69,738.45 81,036.08
BAHAN Kayu Balok Kamper 5/7 0.0116 m3 2,650,000.00 30,740.00 Asbes 100x100x6 mm 1.0500 m2 12,500.00 13,125.00 Paku Asbes 0.0324 kg 13,000.00 421.20 Paku biasa 0.0300 kg 11,000.00 330.00 44,616.20
1 M2 PEMASANGAN LIST PLAFOND GYPSUM PROFIL 10 CM 19,547.50 BAHAN
List Profil Gypsum, t = 5 - 10 cm 1.0000 m' 15,000.00 15,000.00 Jointing Compound 0.1000 Kg 8,500.00 850.00 Steger 0.1000 ls 15,850.00 1,585.00 17,435.00
1 M3 KOSEN PINTU DAN JENDELA KAYU KAMPER 11,585,250.00 Lantai Satu 1.0000 11,585,250.00 11,585,250.00 Lantai Dua 1.0900 11,585,250.00 12,627,922.50 Lantai Tiga 1.1200 11,585,250.00 12,975,480.00 Lantai Empat 1.1350 11,585,250.00 13,149,258.75 Lantai Lima 1.1620 11,585,250.00 13,462,060.50
BAHAN Kayu Kamper Balok 1.2000 m3 8,800,000.00 10,560,000.00 Paku Klem 1.2500 kg 13,000.00 16,250.00 Lem Kayu 1.0000 kg 22,000.00 22,000.00 10,598,250.00
1 M2 PASANG PINTU PANIL (80X230) KAMPER + MULTIPLEX 9 MM + TEAKWOOD 576,490.00 BAHAN
Kayu Papan Kamper 0.0291 m3 8,900,000.00 258,990.00 Multiplex 9 mm 0.6500 lmbr 125,000.00 81,250.00 Teakwood Jati 4 mm 1.0000 lmbr 95,000.00 95,000.00 Paku Triplex 0.2000 kg 11,000.00 2,200.00 Lem Putih Fox 0.0500 kg 22,000.00 1,100.00 Profil kayu 3.5000 m' 10,000.00 35,000.00 473,540.00
1 M2 PARTISI DOUBLE GYPSUM TEBAL 12 MM 214,313.89 Lantai Satu 1.0000 214,313.89 214,313.89 Lantai Dua 1.0900 214,313.89 233,602.14 Lantai Tiga 1.1200 214,313.89 240,031.56 Lantai Empat 1.1350 214,313.89 243,246.26 Lantai Lima 1.1620 214,313.89 249,032.74 Lantai Enam 1.1970 214,313.89 256,533.73 Lantai Tujuh 1.2360 214,313.89 264,891.97
Angkur Besi D.19 10.9720 kg 182,520.00 2,002,609.44 Besi beton 6 mm polos 9.5400 btg - - Kawat Beton 0.1735 kg 10,500.00 1,821.75 Pipa PVC Class D Ǿ 2 " 2.0000 m' - - Pasir Urug 0.0960 m3 85,000.00 8,160.00 Kayui Meranti Bekisting 0.0500 m3 2,500,000.00 125,000.00 Paku Reng 0.5000 kg 11,000.00 5,500.00 PC 219.2000 kg 1,200.00 263,040.00 Pasir Beton 0.3364 m3 140,000.00 47,096.00 Batu Pecah Mesin 2/3 0.0406 m3 150,000.00 6,090.00 Batu Pecah Mesin 1/2 0.3770 m3 150,000.00 56,550.00 2,515,867.19
ALAT Sewa Alat Bantu 0.2709 jam - - Sewa alat strouss 1.2000 jam 17,500.00 21,000.00 Sewa Vibrator Roller 0.0152 jam 202,000.00 3,070.40 Sewa Concrete Mixer 0.0152 jam 261,000.00 3,967.20 28,037.60
1 BH PEMASANGAN WASHTAFEL Ex. TOTO - 1,559,900.00 BAHAN -
Wastafel Meja Warna Standard Lengkap (L 546) 1.0000 bh 1,100,000.00 1,100,000.00 Kran Air ( Import ) 1.0000 bh 140,000.00 140,000.00 Flexible 60 cm 1.0000 m 60,000.00 60,000.00 Knee PVC Ø 11/2 " 1.0000 bh 6,900.00 6,900.00
Page 67 of 334
Rol TBA 1.0000 rol 115,000.00 115,000.00 1,421,900.00
TENAGA Pekerja Tak Terampil 1.2000 oh 40,000.00 48,000.00 Tukang 1.4500 oh 52,500.00 76,125.00 Kepala Tukang 0.1500 oh 52,500.00 7,875.00 Mandor 0.1000 oh 60,000.00 6,000.00 138,000.00
1 BH PEMASANGAN LUBANG AVOER - 15,975.00 BAHAN -
Pipa PVC Type C Ø 2 " 0.5000 m - - - Ijuk 0.0500 kg 15,000.00 750.00 750.00
TENAGA - Pekerja Tak Terampil 0.0600 oh 40,000.00 2,400.00 Tukang 0.0300 oh 52,500.00 1,575.00 Kepala Tukang 0.1000 oh 52,500.00 5,250.00 Mandor 0.1000 oh 60,000.00 6,000.00 15,225.00
1 BH URINOAR TYPE MUSLIM 1,590,364.00 BAHAN
Urinoar Type Muslim 1.0000 Bh 1,394,400.00 1,394,400.00 Perlengkapan ( 6% X Harga closet) 0.0600 ls 1,394,400.00 83,664.00 Semen PC/50 kg 6.0000 Kg 1,200.00 7,200.00 Pasir Pasang 0.0100 m3 135,000.00 1,350.00 1,486,614.00
TENAGA Pekerja 1.0000 oh 40,000.00 40,000.00 Tukang Batu 1.0000 oh 52,500.00 52,500.00 Kepala tukang Batu 0.1000 oh 52,500.00 5,250.00 Mandor 0.1000 oh 60,000.00 6,000.00 103,750.00
1 BH PARTISI PENYEKAT URINOAR 34,375.00 BAHAN
Patisi Penyekat Urinoir (TOTO A 100) 1.0000 Bh - - Perlengkapan ( 6% X Harga penyekat) 0.0600 ls - - -
TENAGA Pekerja 0.2500 oh 40,000.00 10,000.00 Tukang Batu 0.2500 oh 52,500.00 13,125.00 Kepala tukang Batu 0.1000 oh 52,500.00 5,250.00 Mandor 0.1000 oh 60,000.00 6,000.00 34,375.00
1 BH WASHTAFEL PADESTAL 146,550.00 Lantai Satu 1.0000 146,550.00 146,550.00 Lantai Dua 1.0900 146,550.00 159,739.50 Lantai Tiga 1.1200 146,550.00 164,136.00 Lantai Empat 1.1350 146,550.00 166,334.25 Lantai Lima 1.1620 146,550.00 170,291.10 Lantai Enam 1.1970 146,550.00 175,420.35 Lantai Tujuh 1.2360 146,550.00 181,135.80
BAHAN Wastafel Gantung (L 237 V3) 1.0000 Bh - - Perlengkapan ( 12% X Harga washtafel) 0.1200 ls - - Semen PC/50 kg 6.0000 Kg 1,200.00 7,200.00 Pasir Pasang 0.0100 m3 135,000.00 1,350.00 8,550.00
TENAGA Pekerja 1.2000 oh 40,000.00 48,000.00 Tukang Batu 1.4500 oh 52,500.00 76,125.00 Kepala tukang Batu 0.1500 oh 52,500.00 7,875.00 Mandor 0.1000 oh 60,000.00 6,000.00 138,000.00
1 BH WASHTAFEL MEJA 1,378,550.00 Lantai Satu 1.0000 1,378,550.00 1,378,550.00 Lantai Dua 1.0900 1,378,550.00 1,502,619.50 Lantai Tiga 1.1200 1,378,550.00 1,543,976.00 Lantai Empat 1.1350 1,378,550.00 1,564,654.25 Lantai Lima 1.1620 1,378,550.00 1,601,875.10 Lantai Enam 1.1970 1,378,550.00 1,650,124.35 Lantai Tujuh 1.2360 1,378,550.00 1,703,887.80
BAHAN Wastafel Meja Warna Standard Lengkap (L 546) 1.0000 Bh 1,100,000.00 1,100,000.00 Perlengkapan ( 12% X Harga washtafel) 0.1200 ls 1,100,000.00 132,000.00 Semen PC/50 kg 6.0000 Kg 1,200.00 7,200.00 Pasir Pasang 0.0100 m3 135,000.00 1,350.00 1,240,550.00
TENAGA Pekerja 1.2000 oh 40,000.00 48,000.00 Tukang Batu 1.4500 oh 52,500.00 76,125.00 Kepala tukang Batu 0.1500 oh 52,500.00 7,875.00 Mandor 0.1000 oh 60,000.00 6,000.00 138,000.00
1 BH SLOP SINK / SERVICE SINK 146,550.00 Lantai Satu 1.0000 146,550.00 146,550.00 Lantai Dua 1.0900 146,550.00 159,739.50 Lantai Tiga 1.1200 146,550.00 164,136.00 Lantai Empat 1.1350 146,550.00 166,334.25 Lantai Lima 1.1620 146,550.00 170,291.10 Lantai Enam 1.1970 146,550.00 175,420.35 Lantai Tujuh 1.2360 146,550.00 181,135.80
BAHAN Slop Sink 1.0000 Bh - - Perlengkapan ( 12% X Harga washtafel) 0.1200 ls - - Semen PC/50 kg 6.0000 Kg 1,200.00 7,200.00 Pasir Pasang 0.0100 m3 135,000.00 1,350.00 8,550.00
TENAGA Pekerja 1.2000 oh 40,000.00 48,000.00 Tukang Batu 1.4500 oh 52,500.00 76,125.00 Kepala tukang Batu 0.1500 oh 52,500.00 7,875.00 Mandor 0.1000 oh 60,000.00 6,000.00 138,000.00
1 BH BAK MANDI FABER 0,3 M3 248,700.00 Lantai Satu 1.0000 248,700.00 248,700.00 Lantai Dua 1.0900 248,700.00 271,083.00 Lantai Tiga 1.1200 248,700.00 278,544.00 Lantai Empat 1.1350 248,700.00 282,274.50 Lantai Lima 1.1620 248,700.00 288,989.40 Lantai Enam 1.1970 248,700.00 297,693.90 Lantai Tujuh 1.2360 248,700.00 307,393.20
Page 68 of 334
BAHAN Bak mandi fibergalss 1.0000 Bh - - Perlengkapan ( 18% X Harga washtafel) 0.1800 ls - - -
TENAGA Pekerja 1.8000 oh 40,000.00 72,000.00 Tukang Batu 2.7000 oh 52,500.00 141,750.00 Kepala tukang Batu 0.5400 oh 52,500.00 28,350.00 Mandor 0.1100 oh 60,000.00 6,600.00 248,700.00
1 BH KRAN AIR Ø 1/2 " ATAU Ø 3/4 " 138,940.63 Lantai Satu 1.0000 138,940.63 138,940.63 Lantai Dua 1.0900 138,940.63 151,445.28 Lantai Tiga 1.1200 138,940.63 155,613.50 Lantai Empat 1.1350 138,940.63 157,697.61 Lantai Lima 1.1620 138,940.63 161,449.01 Lantai Enam 1.1970 138,940.63 166,311.93 Lantai Tujuh 1.2360 138,940.63 171,730.61
BAHAN Kran air Ø 1/2" atau Ø 3/4" (TOTO T23 B13) 1.0000 Bh 132,250.00 132,250.00 SEAL TAPE 0.0250 Bh 8,625.00 215.63 132,465.63
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH KRAN SINK 6,690.63 Lantai Satu 1.0000 6,690.63 6,690.63 Lantai Dua 1.0900 6,690.63 7,292.78 Lantai Tiga 1.1200 6,690.63 7,493.50 Lantai Empat 1.1350 6,690.63 7,593.86 Lantai Lima 1.1620 6,690.63 7,774.51 Lantai Enam 1.1970 6,690.63 8,008.68 Lantai Tujuh 1.2360 6,690.63 8,269.61
BAHAN Kran Sink 1.0000 Bh - - SEAL TAPE 0.0250 Bh 8,625.00 215.63 215.63
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH FLOOR DRAIN 132,975.00 Lantai Satu 1.0000 132,975.00 132,975.00 Lantai Dua 1.0900 132,975.00 144,942.75 Lantai Tiga 1.1200 132,975.00 148,932.00 Lantai Empat 1.1350 132,975.00 150,926.63 Lantai Lima 1.1620 132,975.00 154,516.95 Lantai Enam 1.1970 132,975.00 159,171.08 Lantai Tujuh 1.2360 132,975.00 164,357.10
BAHAN Floor Drain (TOTO TX 1 B) 1.0000 Bh 126,500.00 126,500.00 126,500.00
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH SOAP HOLDER 37,725.00 Lantai Satu 1.0000 37,725.00 37,725.00 Lantai Dua 1.0900 37,725.00 41,120.25 Lantai Tiga 1.1200 37,725.00 42,252.00 Lantai Empat 1.1350 37,725.00 42,817.88 Lantai Lima 1.1620 37,725.00 43,836.45 Lantai Enam 1.1970 37,725.00 45,156.83 Lantai Tujuh 1.2360 37,725.00 46,628.10
BAHAN Soap Holder (TOTO S 11 N) 1.0000 Bh 31,250.00 31,250.00 31,250.00
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH TISSEU HOLDER 6,475.00 Lantai Satu 1.0000 6,475.00 6,475.00 Lantai Dua 1.0900 6,475.00 7,057.75 Lantai Tiga 1.1200 6,475.00 7,252.00 Lantai Empat 1.1350 6,475.00 7,349.13 Lantai Lima 1.1620 6,475.00 7,523.95 Lantai Enam 1.1970 6,475.00 7,750.58 Lantai Tujuh 1.2360 6,475.00 8,003.10
BAHAN Tisue Holder (TS 116 R) 1.0000 Bh - - -
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH JET WASHER 115,725.00 Lantai Satu 1.0000 115,725.00 115,725.00 Lantai Dua 1.0900 115,725.00 126,140.25 Lantai Tiga 1.1200 115,725.00 129,612.00 Lantai Empat 1.1350 115,725.00 131,347.87 Lantai Lima 1.1620 115,725.00 134,472.45 Lantai Enam 1.1970 115,725.00 138,522.82 Lantai Tujuh 1.2360 115,725.00 143,036.10
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00
Page 69 of 334
Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH TEMPAT HANDUK (TOWELSHELF) SETARA TOTO TYPE TX.4A 6,475.00 Lantai Satu 1.0000 6,475.00 6,475.00 Lantai Dua 1.0900 6,475.00 7,057.75 Lantai Tiga 1.1200 6,475.00 7,252.00 Lantai Empat 1.1350 6,475.00 7,349.13 Lantai Lima 1.1620 6,475.00 7,523.95 Lantai Enam 1.1970 6,475.00 7,750.58 Lantai Tujuh 1.2360 6,475.00 8,003.10
BAHAN Towel Shelf (TOTO TX 4 A) 1.0000 Bh - - -
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH PEGANGAN (GRAB BAR) SETARA TOTO TYPE TX.3 A2 (550MM) 6,475.00 Lantai Satu 1.0000 6,475.00 6,475.00 Lantai Dua 1.0900 6,475.00 7,057.75 Lantai Tiga 1.1200 6,475.00 7,252.00 Lantai Empat 1.1350 6,475.00 7,349.13 Lantai Lima 1.1620 6,475.00 7,523.95 Lantai Enam 1.1970 6,475.00 7,750.58 Lantai Tujuh 1.2360 6,475.00 8,003.10
BAHAN Grab Bar (TOTO TX3 A2) 1.0000 Bh - - -
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH GANTUNGAN HANDUK (TOWEL RING) SETARA TOTO TYPE TS 115 S 6,475.00 Lantai Satu 1.0000 6,475.00 6,475.00 Lantai Dua 1.0900 6,475.00 7,057.75 Lantai Tiga 1.1200 6,475.00 7,252.00 Lantai Empat 1.1350 6,475.00 7,349.13 Lantai Lima 1.1620 6,475.00 7,523.95 Lantai Enam 1.1970 6,475.00 7,750.58 Lantai Tujuh 1.2360 6,475.00 8,003.10
BAHAN Towel Ring (TOTO TS 115 S) 1.0000 Bh - - -
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH KAIT PAKAIAN (DOUBLE ROBE HOOK) SETARA TOTO TYPE TS.118 WS 6,475.00 Lantai Satu 1.0000 6,475.00 6,475.00 Lantai Dua 1.0900 6,475.00 7,057.75 Lantai Tiga 1.1200 6,475.00 7,252.00 Lantai Empat 1.1350 6,475.00 7,349.13 Lantai Lima 1.1620 6,475.00 7,523.95 Lantai Enam 1.1970 6,475.00 7,750.58 Lantai Tujuh 1.2360 6,475.00 8,003.10
TENAGA Pekerja 0.0100 oh 40,000.00 400.00 Tukang Batu 0.1000 oh 52,500.00 5,250.00 Kepala tukang Batu 0.0100 oh 52,500.00 525.00 Mandor 0.0050 oh 60,000.00 300.00 6,475.00
1 BH PASANG KACA CERMIN 120 X 240 CM, T=5mm DI BEVEL 2 CM 129,350.00 Lantai Satu 1.0000 129,350.00 129,350.00 Lantai Dua 1.0900 129,350.00 140,991.50 Lantai Tiga 1.1200 129,350.00 144,872.00 Lantai Empat 1.1350 129,350.00 146,812.25 Lantai Lima 1.1620 129,350.00 150,304.70 Lantai Enam 1.1970 129,350.00 154,831.95 Lantai Tujuh 1.2360 129,350.00 159,876.60
BAHAN Kaca Cermin 5 mm + Bevel 2 cm 2.8880 M2 37,500.00 108,300.00 108,300.00
TENAGA Pekerja 0.0200 oh 40,000.00 800.00 Tukang Batu 0.2500 oh 52,500.00 13,125.00 Kepala tukang Batu 0.0500 oh 52,500.00 2,625.00 Mandor 0.0750 oh 60,000.00 4,500.00 21,050.00
1 BH BAK CUCI STAINLESS STEEL 18,615.00 Lantai Satu 1.0000 18,615.00 18,615.00 Lantai Dua 1.0900 18,615.00 20,290.35 Lantai Tiga 1.1200 18,615.00 20,848.80 Lantai Empat 1.1350 18,615.00 21,128.03 Lantai Lima 1.1620 18,615.00 21,630.63 Lantai Enam 1.1970 18,615.00 22,282.16 Lantai Tujuh 1.2360 18,615.00 23,008.14
BAHAN Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) 1.0000 Bh - - Perlengkapan ( 18% X Harga Bahan) 0.1000 ls - - -
TENAGA Pekerja 0.0300 oh 40,000.00 1,200.00 Tukang Batu 0.3000 oh 52,500.00 15,750.00 Kepala tukang Batu 0.0300 oh 52,500.00 1,575.00 Mandor 0.0015 oh 60,000.00 90.00 18,615.00
1 BH TOP TABLE BATU GRANITE 428,957.50 Lantai Satu 1.0000 428,957.50 428,957.50 Lantai Dua 1.0900 428,957.50 467,563.68 Lantai Tiga 1.1200 428,957.50 480,432.40 Lantai Empat 1.1350 428,957.50 486,866.76 Lantai Lima 1.1620 428,957.50 498,448.62
Page 70 of 334
Lantai Enam 1.1970 428,957.50 513,462.13 Lantai Tujuh 1.2360 428,957.50 530,191.47
BAHAN Batu GRANIT import Italy 1.0520 m2 325,000.00 341,900.00 Semen PC/50 kg 14.1500 Kg 1,200.00 16,980.00 Pasir Pasang 0.0390 m3 135,000.00 5,265.00 Semen Warna 2.0000 Kg 9,000.00 18,000.00 382,145.00
TENAGA Pekerja 0.6200 oh 40,000.00 24,800.00 Tukang Batu 0.3500 oh 52,500.00 18,375.00 Kepala tukang Batu 0.0350 oh 52,500.00 1,837.50 Mandor 0.0300 oh 60,000.00 1,800.00 46,812.50
PEKERJAAN INFRASTRUKTUR
1 M2 PEMASANGAN PAVING T= 8 CM - 15,225.00 BAHAN -
PAVINGST ( K.125 ) warna abu2 t=8cm 1.0500 m2 - - - TENAGA -
1 Theodol 1 Rp - 282 Alat las 1 Rp 250,000.00 303 Bar Cut 2 Rp 150,000.00 304 Vibrato 3 Rp 125,000.00 305 Bucket 2 Rp 200,000.00 306 Water P 1 Rp 100,000.00 307 Lampu 10 Rp 25,000.00 308 Scafold 520 Rp 10,000.00 30
Genset 1 Rp 150,000.00 30
Total
No. Daftar Sewa Alat Kapasitas Jumlah
1 Theodolit 22 Vibrator 33 Bar Bender 14 Bar Cutter 15 Genset 10 KVA 16 Mesin Las 17 Beton Molen 28 Baby Roller 1 Ton 19 Wales 10 Ton 1
10 Mobil Crane 5 Ton 5 Ton 111 Dozer 5 Ton 112 Concrete Pump 113 Scafolding 414 Lampu Sorot 10
JUMLAH
Jumlah
Rp - Rp 7,500,000.00 Rp 9,000,000.00 Rp 11,250,000.00 Rp 12,000,000.00 Rp 3,000,000.00 Rp 7,500,000.00 Rp 156,000,000.00 Rp 4,500,000.00
Rp 210,750,000.00
Harga Sewa Unit TOTAL
Rp 100,000.00 6 hari Rp 1,200,000.00 Rp 150,000.00 30 hari Rp 13,500,000.00 Rp 150,000.00 30 hari Rp 4,500,000.00 Rp 150,000.00 30 hari Rp 4,500,000.00 Rp 250,000.00 60 hari Rp 15,000,000.00 Rp 100,000.00 30 hari Rp 3,000,000.00 Rp 150,000.00 6 hari Rp 1,800,000.00 Rp 300,000.00 2 hari Rp 600,000.00 Rp 500,000.00 2 hari Rp 1,000,000.00 Rp 1,500,000.00 48 hari Rp 72,000,000.00 Rp 150,000.00 24 jam Rp 3,600,000.00 Rp 2,000,000.00 10 hari Rp 20,000,000.00 Rp 300,000.00 45 hari Rp 54,000,000.00 Rp 25,000.00 90 hari Rp 22,500,000.00
JUMLAH Rp 217,200,000.00
KURVA "S" RENCANA STRUKTUR
PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
RUMAH SAKIT UMUM DAERAH dr. SOEDONO MADIUN
JALAN Dr. SOETOMO No. 29 MADIUN - JAWA TIMUR
No. URAIAN PEKERJAAN Durasi BobotWaktu Bulan Ke-3
Hari 7 8 9
A. LANTAI - I (di atas ± 0.00)
A.1. PEKERJAAN STRUKTUR
1 Beton Kolom
Bekisting 7 1.22% 0.012
Pembesian 6 1.78% 0.018
Ready Mix K-250 7 0.52%
2 Beton Balok
Bekisting 7 2.55%
Pembesian 6 5.98%
Ready Mix K-250 7 2.39%
3 Pek. Tangga Utama
Bekisting 4 0.83%
Pembesian 3 0.30%
Ready Mix K-250 3 0.11%
4 Pek. Lift Utama
Bekisting 4 0.49% 0.002 0.002 0.002
Pembesian 3 0.29% 0.001011 0.001011
Ready Mix K-250 3 0.10%
5 Pek. Ramp Beton
Bekisting 14 0.48%
Pembesian 14 0.46%
Ready Mix K-175 14 0.46%
6 Pek. Plat
Bekisting 7 2.68%
Pembesian 6 3.23%
Ready mix K-250 7 1.79%
B. LANTAI - II (di atas + 4.50)
B.1. PEKERJAAN STRUKTUR
1 Beton Kolom
Bekisting 4 1.23%
Pembesian 3 2.09%
Ready Mix K-250 3 0.48%
2 Beton Balok
Bekisting 4 2.72%
Pembesian 3 5.45%
Ready Mix K-250 3 1.81%
3 Pek. Tangga Utama
Bekisting 4 0.98%
Pembesian 3 0.76%
Ready Mix K-250 3 0.28%
4 Pek. Lift Utama
Bekisting 4 0.49%
Pembesian 3 0.47%
Ready Mix K-250 3 0.09%
5 Pek. Tangga Darurat
Bekisting 7 0.59%
Pembesian 5 0.27%
Ready Mix K-175 7 0.09%
6 Pek. Plat
Bekisting 4 2.92%
Pembesian 3 2.69%
Ready mix K-250 3 1.63%
C. LANTAI - III (di atas +8.50)
C.1. PEKERJAAN STRUKTUR
1 Beton Kolom
Bekisting 4 1.01%
Pembesian 3 1.74%
Ready Mix K-250 3 0.46%
2 Beton Balok
Bekisting 7 2.18%
Pembesian 5 5.55%
Ready Mix K-250 7 1.85%
3 Pek. Tangga Utama
Bekisting 7 1.22%
Pembesian 5 0.68%
Ready Mix K-250 7 0.25%
4 Pek. Lift Utama
Bekisting 7 0.54%
Pembesian 5 0.29%
Ready Mix K-250 7 0.11%
5 Pek. Tangga Darurat
Bekisting 7 1.09%
Pembesian 5 0.20%
Ready Mix K-175 7 0.11%
6 Pek. Plat
Bekisting 4 2.51%
Pembesian 3 2.85%
Ready mix K-250 3 1.60%
D. LANTAI - IV (di atas+12.50)
D.1. PEKERJAAN STRUKTUR
1 Beton Kolom
Bekisting 12 0.83%
Pembesian 5 1.45%
Ready Mix K-250 9 0.38%
2 Beton Balok
Bekisting 12 1.41%
Pembesian 9 4.74%
Ready Mix K-250 9 1.74%
3 Pek. Lisplank
Bekisting 4 0.48%
Pembesian 3 1.21%
Ready Mix K-250 3 0.66%
4 Pek. Tangga Utama
Bekisting 4 1.05%
Pembesian 3 0.54%
Ready Mix K-250 3 0.20%
5 Pek. Lift Utama
Bekisting 4 0.60%
Pembesian 3 0.27%
Ready Mix K-250 3 0.11%
6 Pek. Tangga Darurat
Bekisting 4 1.09%
Pembesian 3 0.20%
Ready Mix K-175 3 0.09%
7 Pek. Plat
Bekisting 4 0.94%
Pembesian 3 2.40%
Ready mix K-250 3 2.01%
E. LANTAI -R. LIFT V (di atas+16.50)
E.1. PEKERJAAN STRUKTUR
1 Beton Kolom
Bekisting 12 0.16%
Pembesian 9 0.55%
Ready Mix K-250 9 0.15%
2 Beton Balok
Bekisting 4 0.22%
Pembesian 3 0.73%
Ready Mix K-250 3 0.25%
3 Pek. Plat
Bekisting 4 0.09%
Pembesian 3 0.33%
Ready Mix K-250 3 0.18%
Total Pekerjaan 100%
Progres (%) 0.002063 0.033116 0.003074
Progres kumulatif (%) 0.002063 0.035179 0.038254
KURVA "S" RENCANA STRUKTUR
PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
KURVA "S" RENCANA & REALISASI
No. URAIAN PEKERJAAN Durasi Bobot
Waktu Bln K-3
Hari 07-13/03/11 14-20/03/11 21-27/03/11
Minggu ke- 8 9 10
A. LANTAI - I (di atas ± 0.00)A.1. PEKERJAAN STRUKTUR
Beton K-250 untuk Plat Lantai 4 tebal 12 cm ( + 12.50 ) + Plat
Beton K-250 untuk Plat Lisplang beton 10/80 atap ruang tunggu
LANTAI - IV - (di atas + 12.50)
1 KOLOM DAN BALOK
Beton K-250 untuk Kolom Utama 50/50 posisi CL. B type K1
Beton K-250 untuk Kolom Utama 50/50 posisi CL. C type K1
Beton K-250 untuk Kolom Utama 50/50 posisi CL. D type K1
Beton K-250 untuk Kolom Utama 50/50 posisi CL. E type K1
Beton K-250 untuk Balok Utama 35/70 posisi CL. 1 type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. 2 type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. 3 type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. 5 type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. B type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. C type B1
Beton K-250 untuk Balok Utama 35/70 posisi CL. E type B1
Beton K-250 untuk Balok Anak 30/60 type B2
Beton K-250 untuk Balok Anak 20/40 type B3
2 PEKERJAAN LISPLANG ATAP + PENUTUP CLADDING WALL
Beton K-250 untuk Balok Anak 20/40 type B3 Konsol LisplangBeton K-250 untuk Balok Anak 20/40 type B3 LisplangBeton K-250 untuk plat lisplang/talang t=10 cm - U=1.50 m + 16.50Beton K-250 untuk plat penutup Clidding Wall t=10 cm + 17.30Beton K-175 un. Ring lisplank 15/15 + kolom 15/15
3 PEKERJAAN TANGGA UTAMA
Beton K-250 untuk Kolom 30/30 type K-2
Beton K-250 untuk Balok Utama 35/70 posisi CL. 3A type B1
Beton K-250 untuk Balok Anak 30/60 type B2
Beton K-250 untuk Plat lantai tangga T = 12 cm
4 PEKERJAAN LIFT UTAMA
Beton K-250 untuk Kolom 30/30 type K - 2
Beton K-250 untuk Balok Anak 30/60 type B2
Beton K-250 untuk Balok Anak 20/40 type B3
5 PEKERJAAN TANGGA DARURAT
Beton K-250 untuk Balok Anak 20/40 type B3
Beton K-175 un. Ring Bulustrade 15/15
Beton K-250 untuk Plat lantai tangga T = 12 cm
Beton Praktis K-175 un. Kolom 15/15
Beton Praktis K-175 un. Balok Ring 15/15 di atas Pas. Dinding
Beton Praktis K-175 un. Balok Latei 15/15 di atas Kosen Pas. Dinding
Beton Praktis K-175 un. Canopy Jend (50 x 120 x 10) CL. B (4-5) - CL. 5
B. PEK. SUB STRUKTUR DIBAWAH ±0.00B.1 PEKERJAAN PONDASI UTAMA #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #VALUE!B.2 PEKERJAAN PONDASI PENDUKUNG #DIV/0! #DIV/0!
C. LANTAI - I -(Di atas ± 0.00)C.1. PEKERJAAN SIPIL #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
C.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKALC.3.1. PEKERJAAN ELEKTRIKAL #DIV/0! #VALUE! #DIV/0! #DIV/0!C.3.3. PEKERJAAN INSTALASI AIR
A INSTALASI TALANG VERTICAL #DIV/0! #DIV/0!B. INSTALASI AIR KOTOR + KOTORAN CLOSET #DIV/0! #DIV/0! #DIV/0!C. INSTALASI AIR BERSIH #DIV/0! #DIV/0!
D. LANTAI - II - (DI ATAS + 4.50) 75.00%D.1. PEKERJAAN SIPIL #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
D.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKALD.3.1. PEKERJAAN ELEKTRIKAL #DIV/0! #DIV/0!D.3.3. PEKERJAAN INSTALASI AIR
A INSTALASI TALANG VERTICAL #VALUE! #VALUE!B. INSTALASI AIR KOTOR + KOTORAN CLOSET #DIV/0! #DIV/0!C. INSTALASI AIR BERSIH #DIV/0! #DIV/0!
E. LANTAI - III - (DI ATAS + 8.50)E.1. PEKERJAAN SIPIL #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Surabaya, .......................... 2011PT.ANGGREK MERAH
ALBERTINUS WIDYANTODirektur Utama
Page 293 of 334
Page 294 of 334
18.25
1 54.75
1 73.000000 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #VALUE!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #VALUE!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #VALUE!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #VALUE!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 AHAAAAAA...
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
1 AHAAAAAA...
1 #DIV/0!
1 #DIV/0!
1 #DIV/0!
Page 295 of 334
ANALISA HARGA SATUAN PEKERJAANPROYEK PEMBANGUNAN GEDUNG MENEJEMEN 4 LANTAI
RUMAH SAKIT UMUM PROVINSI dr. SOEDONO MADIUNJALAN Dr. SOETOMO No. 29 MADIUN - JAWA TIMUR
No. Vol. URAIAN KOOEF St. Vol.
PEKERJAAN PERSIAPAN DAN TANAH
1 M' PEMBUATAN BOUPLANK #REF!BAHAN
Kayu meranti papan 2/20 0.0042 m3 #REF! m3 Kayu meranti usuk 5/7 0.0039 m3 #REF! m3 Paku biasa 0.0200 kg #REF! kg
1 M2 PEMBERSIHAN LAPANGAN RINGAN
1 M2 PEMBERSIHAN LAPANGAN BERAT
1 Hr. UITZET DENGAN WATERPASS / THEODOLITHBAHAN
Sewa Theodolit 1.0000 set
1 M2 PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG, T= 2 M #REF!BAHAN
Dolken Kayu Gelam 8-10 / 400 cm 1.2500 btg #REF! btg PC 2.5000 kg #REF! kg Seng Gelombang 1.2000 lbr #REF! lbr Pasir beton 0.0050 m3 #REF! m3 Batu pecah 2-3 0.009 m3 #REF! m3 Kayu meranti 5/7 0.0720 m3 #REF! m3 Paku asbes 0.0600 kg #REF! kg Cat Meni Besi 0.0450 ltr #REF! ltr
1 M2 PEMBUATAN DIREKSI KEETBAHAN 72
Dolken Kayu gelam 8-10 / 400 cm 1.2500 btg 90 btg Kayu meranti 5/7 0.1800 m3 12.96 m3 Paku biasa 0.8500 kg 61.2 kg Besi plat strip 1.1000 kg 79.2 kg PC 35.000 kg 2520 kg Pasir pasang 0.1500 m3 10.8 m3 Pasir beton 0.1000 m3 7.2 m3 Batu pecah mesin 2/3 0.1500 m3 10.8 m3 Bata merah 30.0000 bh 2160 bh Seng gelombang BJLS 30 0.2500 lembr 18 lembr Kaca polos 3 mm 0.0800 m2 5.76 m2 Kunci tanam 0.1500 buah 10.8 buah Lapis triplex 4 mm 0.0600 lembr 4.32 lembr
1 M3 BONGKARAN BETON BERTULANG
1 M2 PEMBUATAN STEGGER BAMBU UNT ANDANGBAHAN
Bambu dia.6-8 cm / 600 cm 1.2500 btg Tali ijuk 0.2500 kg
1 M3 GALIAN TANAH KONSTRUKSI
1 M2 PERATAAN TANAH
1 M3 PENGANGKUTAN TANAH KELUAR PROYEK ALAT
Sewa Dumptruck 5 T ( Min. 5 jam ) 0.2500 jam
1 TTK PEMBUATAN LUBANG STROUS DIA.20-30 CM ALAT
Sewa alat bantu strouss pile 1.2000 jam
1 M3 GALIAN TANAH KERAS
1 M3 GALIAN TANAH LUMPUR
1 M3 GALIAN TANAH LUMPUR DENGAN ALAT ALAT
Sewa Dump Truck 5 T ( Min. 5 Jam ) 0.0740 jam Sewa Bucket dan Crane 0.0528 jam
1 M3 GALIAN TANAH DENGAN ALAT BERAT ALAT
Sewa Dump Truck 5 T ( Min. 5 Jam ) 0.0700 jam Sewa Escavator 0.0670 jam
1 M3 PENGURUGAN TANAH KEMBALI UNTUK BANGUNAN
1 M3 PENGURUGAN TANAH DENGAN PEMADATAN ALAT
Sewa alat bantu ( 1 set @ 3 alat ) 0.0213 jamBAHAN
Tanah Urug 1.2000 m3
1 M3 PENGURUGAN PASIR PADAT LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620 LANTAI ATAP 1.1970
ALAT Sewa alat bantu ( 1 set @ 3 alat ) 0.0213 jam
BAHAN Pasir Urug 1.2000 m3
Page 296 of 334
1 M3 PENGURUGAN SIRTU PADAT ALAT
Sewa alat bantu ( 1 set @ 3 alat ) 0.0000 jamBAHAN
Sirtu 1.2000 m3
1 M3 PENGURUGAN PUDEL 1 Kp : 6 Ps ALAT
Sewa alat bantu ( 1 set @ 3 alat ) 0.0213 jamBAHAN
Kapur Pasang 0.1720 m3 Pasir Urug 1.028 m3
1 M3 PENGURUGAN SIRTU PADAT DENGAN PEMADATAN MENGGUNAKAN ALAT ALAT
Sewa Dump Truck 3,5 T 0.0880 jam Sewa Motor Grader 125-140 PK (min.5 Jam) 0.0080 jam Sewa Pneumatic Tire Roller (min.5 jam) 0.0040 jam Sewa Truck Tangki Air (min.5 jam) 0.0120 jam Sewa Vibrator Roller (min.5 Jam) 0.0120 jam Sewa Escavator 6 m3 0.0220 jam
BAHAN Sirtu 1.2000 m3
1 M3 PENGERUGAN SALURAN MANUAL ALAT
Sewa Truck klas 3 dalam kota 0.0100 jamBAHAN
Glansing 25 kg ( isi 150 kg sedimen) 12.0000 bh
1 M3 PENGERUGAN SALURAN DENGAN ALAT BERAT ALAT
Sewa Truck klas 3 dalam kota 0.0800 jam Sewa Bucket dan Crane / Graglin scrapper 0.1500 jam
1 M3 PENGURUGAN PASIR UNTUK PAVING BAHAN
Pasir Urug 1.2000 m3
1 M3 PENGURUGAN SIRTU UNTUK PAVING BAHAN
Sirtu 1.2000 m3
PEKERJAAN PONDASI
1 M2 PEMASANGAN TURAP PAPAN TEBAL 3 CM BAHAN
Kayu Meranti papan 3/30 0.0330 m3 Kayu Meranti Usuk 0.0210 m3 Paku Klem 0.3000 kg
1 M2 PEMASANGAN TURAP BAMBU TINGGI 1,5-2 M BAHAN
Bambu 10-12 cm 3.0000 btg Gedeg Guling 1.6500 m2 Kawat Ikat Beton 0.1090 kg
1M' PANCANG PILE + PENGADAAN PILE 35X35 - 16 m SISTIM INJECTION BAHAN
Tiang Panc. K-600, 30/30,L=16m' 1.0000 m' Join las 1.0000 m'
PERALATAN Alat bantu 0.2000 set Sewa Crane 0.1030 jm/hr Alat Injection 0.1030 jm/hr
1M' PANCANG PILE + PENGADAAN PILE 35X35 - 16 m SISTIM HAMMER BAHAN
Tiang Panc. K-600, 35X35,L=16m' 1.0000 m' Join Las 1.0000 titik
PERALATAN Alat bantu 0.2400 set Sewa Crane 0.1236 jm/hr Sewa Hammer Pancang 0.2266 jm/hr
1M3 PASANG PONDASI BATU KALI 1PC : 4PS BAHAN
Batu belah 15/20 1.2000 m3 PC 163.0000 kg Pasir Pasang 0.5200 m3
1M3 PASANG PONDASI BATU KALI 1PC : 5 PS BAHAN
Batu belah 15/20 1.2000 m3 PC 136.0000 kg Pasir Pasang 0.5440 m3
1M3 PASANG PONDASI BATU KOSONG / AANSTAMPENG T= 20 CM BAHAN
Batu belah 15/20 1.2000 m3 Pasir Urug 0.0000 m3
1 KG PASANGAN IJUK BAHAN
Ijuk 1.2000 kg
1 M3 PEMBUATAN LUBANG STROUSS Ǿ20 CM DALAM 3 M BAHAN
Alat Bantu Stroys Pile 1.2000 m3
1 M3 PEMBUATAN LUBANG STROUSS Ǿ30 CM DALAM 3 M BAHAN
Alat Bantu Stroys Pile 1.2000 m3
1M3 PEMAKAIAN SPESI CAMP.STROUS (1Pc:1,5Ps:2,5Kr) BAHAN
Page 297 of 334
Semen PC 358.0150 kg Pasir Cor 0.4882 m3 Batu Kerikil 0.8137 m3
PEKERJAAN STRUKTUR BETON
1 M2 PASANG BEKISTING UN. PONDASI BAHAN
Kayu Meranti 0.0400 m3 Paku Biasa 0.4000 kg Minyak Bekisting 0.1000 ltr
1 M2 PASANG BEKISTING UN. SLOOF + STRUKTUR PRAKTIS ( 3 kali pakai ) LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620 LANTAI ATAP
BAHAN Kayu Meranti 0.0200 m3 Paku Biasa 0.3000 kg Minyak Bekisting 0.1000 ltr Multiplex 12 mm 0.1750 m2
1 M2 PASANG BEKISTING UNTUK KOLOM ( 3 kali pakai ) 260.8 LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Kayu Meranti 0.0200 m3 Paku Biasa 0.4000 kg Minyak Bekisting 0.2000 ltr Balok Kayu Kruing 0.0180 m3 Multiplex 12 mm 0.1400 lbr Kayu Dolken 8-10 cm 0.6670 btg
1 M2 PASANG BEKISTING UNTUK BALOK ( 3 kali pakai ) LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Kayu Meranti 0.0200 m3 Paku Biasa 0.4000 kg Minyak Bekisting 0.2000 ltr Balok Kayu Kruing 0.0180 m3 Multiplex 12 mm 0.1400 lbr Kayu stoot 2.0000 btg
1 M2 PASANG BEKISTING UNTUK LANTAI ( 3 kali pakai ) LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Kayu Meranti 0.0200 m3 Paku Biasa 0.4000 kg Minyak Bekisting 0.2000 ltr Balok Kayu Kruing 0.0180 m3 Multiplex 12 mm 0.1400 lbr Kayu stoot 3.0000 btg
1 M2 PASANG BEKISTING UNTUK TANGGA LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Kayu Meranti 0.0200 m3 Paku Biasa 0.4000 kg Minyak Bekisting 0.1500 ltr Balok Kayu Kruing 0.0180 m3 Multiplex 12 mm 0.1400 lbr Kayu stoot 0.6670 btg
1 KG PEMBESIAN BESI POLOS U-24 LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Besi beton ( Polos ) 1.0500 kg Kawat beton 0.0150 kg
1 KG PEMBESIAN BESI ULIR U-39 LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Besi beton Ulir 1.0500 kg Kawat beton 0.0150 kg
Page 298 of 334
1 KG PEMASANGAN WIREMESH BAHAN
Besi beton Polos 1.0200 kg Kawat beton 0.0050 kg
1 M2 MEMBUAT LANTAI KERJA BETON TUMBUK, 1 PC : 3 PS : 5 KR, TEBAL 5 CM LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN PC 10.0000 kg Pasir Beton 0.0200 m3 Batu Pecah 2-3 0.0444 m3
1 M3 MEMBUAT BETON MUTU f'c=7,4 Mpa ( K-100), SLUMP (12+2) CM, W/C = 0.87BAHAN
PC 218.0000 kg Pasir Beton 0.0621 m3 Batu Pecah 2-3 0.7400 m3
1 M3 MEMBUAT BETON MUTU f'c= 14.5 Mpa ( K-175), SLUMP (12+2) CM, W/C = 0.6 LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN PC 326.0000 kg Pasir Beton 0.5430 m3 Batu Pecah 2-3 0.7622 m3
1 M3 MEMBUAT BETON MUTU SITEMIX f'c= 21,7 Mpa ( K-250), SLUMP (12+2) CM, BAHAN
PC 384.0000 kg Pasir Beton 0.4343 m3 Batu Pecah 2-3 0.7636 m3
1 M3 BETON READYMIX K-175, BERIKUT POMPA : LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Beton Readymix K-175 1.0200 m3
PERALATAN Peralatan bantu ( pompa+vibrator+tes lab ) 0.0450 ls
1 M3 BETON READYMIX K-225, BERIKUT POMPA : LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN Beton Readymix K-225 1.0200 m3 528000
PERALATAN Peralatan bantu ( pompa+vibrator+tes lab ) 0.0450 ls
1 M3 BETON READYMIX K-250, BERIKUT POMPA : LANTAI I 1.0000 LANTAI II 1.0900 LANTAI III 1.1200 LANTAI IV 1.1350 LANTAI V 1.1620
BAHAN BETON READYMIX K-250, BERIKUT POMPA : 1.0200 m3 526500
PERALATAN Peralatan bantu ( pompa+vibrator+tes lab ) 0.0450 ls
1 M3 MEMBUAT BETON STROUS DIA 20 CM Spesi Beton Strous 1.0000 m3 Besi polos 5 dia 10, Dia 6-150mm 80.0000 kg
1 M3 MEMBUAT BETON STROUS DIA 25 CM Spesi Beton Strous 1.0000 m3 Besi polos 6 dia 10, Dia 6-150mm 98.3300 kg
1 M3 MEMBUAT BETON STROUS DIA 30 CM Spesi Beton Strous 1.0000 m3 Besi polos 7 dia 10, Dia 6-150mm 105.0000 kg
1 M3 PEMBONGKARAN CETAKAN DAN PENYIRAMAN TENAGA
Pekerja / Buruh tak terampil 3.0000 oh
PEK.BETON DIBAWAH LANTAI ± 0.00
1 M3 Poer type P1/. (165x90x70) Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 2.0000 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P2. (1750x1750x70) Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 2.0000 m2 Pembongkaran cetakan 0.1000 m3
Page 299 of 334
1 M3 Poer type P3. (2000x2000x70) Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.6670 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P4/. (2400x2400x70) Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.5320 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P5. (900X900X50) RAMP Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.6670 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P2. (1750x1750x70) unt. TANGGA UTAMA Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.6670 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P1/P7 (tangga). (165x90x70) UN.T.UTMA Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.6670 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P4/. (2400x2400x70)g un.LIFT Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.2857 m2 Pembongkaran cetakan 0.1000 m3
1 M3 Poer type P1. (165x90x70) UN.LIFT Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 1.1667 m2 Pembongkaran cetakan 0.1000 m3
1 M3 BETON SLOOF 30/40 BESI ULIR TYPE S2 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6700 m2 Pembongkaran cetakan 0.1000 m3
1 M3 BETON SLOOF 40/60 BESI ULIR TYPE S1 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6700 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR UN.LIFT Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 13.3330 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 13.3700 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON PLAT T=15 CM LIFT LANTAI/DINDING DASAR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton POLOS #REF! kg Bekisting 6.6670 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON PONDASI PLAT LAJUR KHUSUS TANGGA Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir U-39 #REF! kg Bekisting 2.9952 m2 Pembongkaran cetakan 1.0000 m3
PEK. BETON DIATAS LANTAI.1 ( ± 0.00 )
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR
Page 300 of 334
Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 11.4286 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.8690 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 35/70 K-250 BESI ULIR type B-1 Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 5.9810 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 30/60 K-250 BESI ULIR type B-2 Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 20/40 K-250 BESI ULIR type B-3 Pekerjaan Beton Struktur K-250 1.0000 m3 ;..; #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 15/25 BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton Polos #REF! kg Bekisting 3.0814 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON LANTAI BESI POLOS Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 8.3333 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON TANGGA BESI POLOS Pekerjaan Beton Struktur K-250 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 14.2175 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON CANOPY JENDELA BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.1662 m2 Pembongkaran cetakan 0.0000 m3
PEK. BETON DIATAS LANTAI.2 ( + 4.50 )
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 11.4286 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.8690 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 35/70 K-300 BESI ULIR type B-1 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 5.9810 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 30/60 K-300 BESI ULIR type B-2 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.0400 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 20/40 K-300 BESI ULIR type B-3 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 15/25 BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton Polos #REF! kg Bekisting 3.2354 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON LANTAI BESI POLOS
Page 301 of 334
Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 8.3333 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON TANGGA BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 14.2175 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON CANOPY JENDELA BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.1662 m2 Pembongkaran cetakan 0.0000 m3
PEK. BETON DIATAS LANTAI.3 ( + 8.50 )
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 11.4286 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.8690 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 35/70 K-300 BESI ULIR type B-1 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 5.9810 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 30/60 K-300 BESI ULIR type B-2 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.0400 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 20/40 K-300 BESI ULIR type B-3 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 15/25 BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton Polos #REF! kg Bekisting 3.2354 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON LANTAI BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 8.3333 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON TANGGA BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 14.2175 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON CANOPY JENDELA BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.1662 m2 Pembongkaran cetakan 0.0000 m3
PEK. BETON DIATAS LANTAI.4 ( + 12.50)
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 11.4286 m2 Pembongkaran cetakan 0.0000 m3
Page 302 of 334
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.8690 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 35/70 K-300 BESI ULIR type B-1 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 5.9810 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 30/60 K-300 BESI ULIR type B-2 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.0400 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 20/40 K-300 BESI ULIR type B-3 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 15/25 BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton Polos #REF! kg Bekisting 3.2354 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON LANTAI BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 8.3333 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON TANGGA BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 14.2175 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON CANOPY JENDELA BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.1662 m2 Pembongkaran cetakan 0.0000 m3
PEK. BETON DIATAS LANTAI.ATAP ( + 16.50 )
1 M3 BETON KOLOM UTAMA 50/50 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.3334 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 40/40 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.6667 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM UTAMA 30/30 BESI ULIR Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 11.4286 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON KOLOM PRAKTIS 15/15 K-175 BESI POLOS Pekerjaan Beton Struktur K-175 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.8690 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 35/70 K-300 BESI ULIR type B-1 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 5.9810 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 30/60 K-300 BESI ULIR type B-2 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 7.0400 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 20/40 K-300 BESI ULIR type B-3 Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton ulir #REF! kg Bekisting 6.7692 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON BALOK 15/25 BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton Polos #REF! kg Bekisting 3.2354 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON LANTAI BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 8.3333 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON TANGGA BESI POLOS Pekerjaan Beton Struktur K-300 1.0000 m3
Page 303 of 334
Pekerjaan Pembesian beton polos #REF! kg Bekisting 14.2175 m2 Pembongkaran cetakan 0.0000 m3
1 M3 BETON CANOPY JENDELA BESI POLOS Pekerjaan Beton Struktur K-225 1.0000 m3 Pekerjaan Pembesian beton polos #REF! kg Bekisting 1.1662 m2 Pembongkaran cetakan 0.0000 m3
PEKERJAAN BETON RABAT DAN BETON LAIN
1 m2 BETON SCREED 1 : 3 Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC/50 kg 10.0000 kg Pasir Beton I 0.0260 m3 Batu Koral Beton 0.0440 m3
1 M2 MEMBUAT LANTAI KERJA BAHAN
PC 10.0000 kg Pasir Beton 0.0200 m3 Batu kerikil 0.0444 m3
1 M3 CHIPPING & CONCRETING / JACKETING BAHAN
PC 43.2000 kg Pasir Pasang 0.4200 m3 Batu kerikil 0.7700 m3
ALAT Sewa Concrete Mixer 0.2520 jam Sewa Concrete Pump 0.0840 jam Sewa Concrete vibrator 1.0800 jam
1M' SALURAN BETON PRECAST (PABRIK) PENURUNAN DAN PEMASANGAN BAHAN
U.Guffer U.1000 K-350; besi 130 kg 0.4166 bh Cover 1000x1000x2400; besi 160 kg 0.4166 bh
ALAT Sewa Crane 0.1736 jam Sewa alat bantu 0.1000 jam
1M' PEMASANGAN SALURAN BUIS BETON Ǿ 1.00 M BAHAN
Buis Beton bulat ukuran 100x100 1.0000 bhALAT
Sewa alat bantu 0.1000 jam
PEKERJAAN BESI ( BAJA-PAGAR-PIPA )
1 KG PEK.PABRIKASI DAN PEMASANGAN BAJA ( ELEKTRODE ) BAHAN
Elektrode Baja 1.0000 kg Bahan bakar solar 0.0100 kg Pelumas 0.0010 kg
TENAGA Pekerja 0.0010 oh Tukang besi profil 0.0010 oh Kepala Tukang besi profil 0.0002 oh Operator Alat berat 0.0002 oh Pembantu operator 0.0002 oh Mandor 0.0001 oh
ALAT Sewa Welding Set 0.0700 jam
1 KG PEKERJAAN BESI PLAT BORDES BAHAN
Besi Plat Bordes 4"x8" Tebal 3 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 KG PEKERJAAN BESI PLAT TEBAL 2 MM BAHAN
Besi Plats 4"x8" Tebal 2 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 KG PEKERJAAN BESI PLAT STRIP BAHAN
Besi Plat Strip Uk. 30x30 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 KG PEKERJAAN BESI BAJA PROFIL WF ≤ 200 MM BAHAN
Besi Profil WF ≤200 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 KG PEKERJAAN BESI BAJA PROFIL WF ≥ 200 MM BAHAN
Besi Profil WF ≥ 200 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 KG PEKERJAAN BESI BAJA PROFIL C 100 - 150 MM BAHAN
Besi Profil C 100 mm - 150 mm 1.1000 kg Pabrikasi ( 20 % ) 0.2000 kg
1 M2 RANGKA ATAP GALVALUM / TRUSS TEBAL 0.8 MM
Page 304 of 334
BAHAN Rangka Galvalum Truss 0.8 mm 1.1000 m2
1 M2 RANGKA ATAP GALVALUM / TRUSS TEBAL 0.5 MM BAHAN
Rangka Galvalum Truss 0.5 mm 1.1000 m2
1 M2 PEMASANGAN PAGAR BESI Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
BAHAN Pagar Besi Komplit Assesories 1.0000 m2
1 M2 PEMASANGAN PAGAR PANEL / FABRIKASI TINGGI 2.00 M BAHAN
Precast Pagar Panel 1.0000 m'
1 M2 PEMASANGAN TERALIS JENDELA BAHAN
Besi strip 0.0154 kg Elektride Baja 0.2000 kg
1 M' ONGKOS PEMASANGAN PIPA GALVANIS BAHAN
Sewa Welding Set 0.0210 hari Kawat Elektrode Baja 0.0060 Kg
1 M' PEKERJAAN BESI PIPA GALVANIS Ǿ 1,5" ( MEDIUM ) BAHAN
Besi Pipa Galvanis Ǿ1,5" ( Medium ) 1.0200 m'
1 M' PEKERJAAN BESI PIPA GALVANIS Ǿ 3" ( MEDIUM ) BAHAN
Besi Pipa Galvanis Ǿ 3" ( Medium ) 1.0200 m'
1 M' PEKERJAAN RAILLING TANGGA PIPA STAINLESS Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Plat Tiang Railling Hot Deep Galvanis 1.5000 btg Pipa Stainless Steel Ø 13 mm 4.0000 m' Hand Railling Aluminium Ø 75mm 1.0000 m' Dinabol dia. 8mm 3.0000 buah Tutup Hand Railling 0.0500 buah Tutup Hand Railling ke dinding 0.0250 buah
1 M' HAND RAILLING ALUMUNIUM Ø 75 MM Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Pipa Stainless Steel Ø 13 mm 4.0000 m' Hand Railling Aluminium Ø 75mm 1.0000 m' Dinabol dia. 8mm 3.0000 buah
1 M2 RAILLING BALKON DAN TERAAS BESI HOLLOW. Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 2Ps. (TINGGI S/D 2.00M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 19.1100 kg Pasir Pasang 0.0348 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 2Ps. (TINGGI 2.00 - 5.00 M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
Page 305 of 334
Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 17.1600 kg Pasir Pasang 0.0348 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 3Ps. (TINGGI S/D 2.00M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 14.5150 kg Pasir Pasang 0.0396 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 3Ps. (TINGGI 2.00 - 5.00 M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 14.5150 kg Pasir Pasang 0.0396 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 4Ps. (TINGGI S/D 2.00M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 11.6850 kg Pasir Pasang 0.0425 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc :4Ps. (TINGGI 2.00 - 5.00 M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 11.6850 kg Pasir Pasang 0.0425 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc : 5Ps. (TINGGI S/D 2.00M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 9.9750 kg Pasir Pasang 0.0474 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M2 PEMASANGAN 1/2 BATU BATA CAMP 1Pc :5Ps. (TINGGI 2.00 - 5.00 M ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 9.9750 kg Pasir Pasang 0.0474 m3 Batu Bata lokal uk. 22 x 11 x 5 cm 52.0000 bh
1 M3 PASANGAN BATU MERAH KOSONGANBAHAN
Batu Bata lokal uk. 22 x 11 x 5 cm 755.0000 bh
1 M2 PLESTERAN CAMP 1Pc :2Ps. (TTEBAL 1 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 6.2550 kg Pasir Pasang 0.0119 m3
Page 306 of 334
1 M2 PLESTERAN CAMP 1Pc :2Ps. (TTEBAL 1,5 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 8.5000 kg Pasir Pasang 0.0171 m3
1 M2 PLESTERAN CAMP 1Pc :3Ps. (TTEBAL 1 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 5.2000 kg Pasir Pasang 0.0130 m3
1 M2 PLESTERAN CAMP 1Pc :3Ps. (TTEBAL 1,5 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 6.8200 kg Pasir Pasang 0.0200 m3
1 M2 PLESTERAN CAMP 1Pc :4Ps. (TTEBAL 1 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 3.8150 kg Pasir Pasang 0.0139 m3
1 M2 PLESTERAN CAMP 1Pc :4Ps. (TTEBAL 1,5 CM ) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 5.1500 kg Pasir Pasang 0.0215 m3
1 M2 MERAPIKAN PERMUKAAN PAS.DENGN SPESI 1Pc : 2 PsBAHAN
Semen PC 3.1300 kg Pasir Pasang 0.0060 m3
1 M' BENANGAN Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Semen PC 1.2000 kg Pasir Pasang 0.0000 m3
1M2 PEKERJAAN ACIAN Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN PC 3.2500 kg
1M' KOL-KOLAN BAHAN
Pasir Pasang 0.0040 m3 PC 3.2500 kg
1M2 BERAPEN 1 PC : 5 PS, Tebal 15 mmBAHAN
PC 5.6700 kg Pasir Pasang 0.0230 m3
1M2 PLESTERAN BETON 1 PC : 3 PS tebal 15 mm
Page 307 of 334
Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN PC 7.0700 kg Pasir Pasang 0.0210 m3
1M2 PASANGAN GLASS BLOCK Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Glass Block 25.0000 bh PC 5.0000 kg
1M2 PASANGAN BATACO BAHAN
Bataco tebal 10 cm 12.5000 bh PC 14.0000 kg Pasir Pasang 0.0420 kg
1M2 PASANGAN BATU KLINGKER BAHAN
Batu Klingker 52.5000 bh PC 6.2550 kg Pasir Pasang 0.0119 kg
1M2 PASANGAN BATU AMPYANG BAHAN
Batu Ampyang 1.1000 m2 PC 12.5100 kg Pasir Pasang 0.0238 kg
1M2 PASANGAN BATU CANDI HITAM BAHAN
Batu Candi Hitam 1.1000 m2 PC 12.5100 kg Pasir Pasang 0.0238 kg
1M2 PASANGAN BATU GILANG Ex. JEMBER - ASIMETRIS BAHAN
Batu Gilang Ex. Jember 1.2000 m2 PC 12.5100 kg Pasir Pasang 0.0238 kg
1M2 PASANGAN BATU GILANG Ex. CIREBON - SIMETRIS BAHAN
Batu Gilang Ex. Cirebon 1.1000 m2 PC 12.5100 kg Pasir Pasang 0.0238 kg
1M2 PASANGAN BATU GILANG Ex. CIREBON - ASIMETRIS BAHAN
Batu Gilang Ex. Cirebon 1.2000 m2 PC 12.5100 kg Pasir Pasang 0.0238 kg
1M2 PASANGAN BATU BOBOS BAHAN
Batu Bobos uk. 10x20x1,5 1.0000 m2 PC 6.4800 kg Pasir Pasang 0.0210 kg
PEKERJAAN CAT-CATAN-W.PROOFING-W.PAPER
1M2 CAT TEMBOK INTERIOR DAN PLAFOND Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Plamuur Tembok 0.1500 Kg Cat dasar 0.2000 lt Cat Dinding Interior Catylac 0.2600 Kg Roll Cat 0.0100 bh Kertas Gosok 0.5000 lbr Steigger 0.1500 lot
1M2 CAT TEMBOK EXTERIOR (WEATHERSHIELD) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Plamuur Tembok 0.1500 Kg Cat dasar 0.1000 lt
Page 308 of 334
Cat Dinding Exxterior Catylac 0.2600 Kg Roll Cat 0.0100 bh Kertas Gosok 0.5000 lbr Steigger 0.1500 lot
1M2 CAT MENI BESI / KAYU BAHAN
Cat Meni kayu / besi 0.8400 kg Minyak Cat 0.0440 kg
1M2 PENGCATAN 3X SERTA MENGGOSOK TANPA MENI ( BESI / KAYU ) BAHAN
Cat Besi 0.4250 kg Dempul 0.0800 kg Minyak Cat 0.0570 lmb Kertas Gosok 1.0000 lmb
1M2 POLITUR 2 X SAMPAI RATA BAHAN
Cerlax 0.0340 kg Spirtus 0.6600 ltr Kerta Gosok No. 150 0.5000 lmb
1M2 PEMASANGAN WALLPAPER BAHAN
Wall Paper lbar 55 cm 2.0000 m Lem 0.2000 kg
1M2 PELAPISAN WATERPROOFING BAHAN
Water Proofing 0.3500 kg Serat Fiber 1.0000 m2
1M2 PENGECATAN TEXTURE GRANITONE BAHAN
Texture GRANITONE 1.1000 m2 Peralatan ( 10 % dr Bahan ) 0.1000 ls
1M2 PELAPISAN WATERPROOFING MEMBRAN BAHAN
Water proofing bithuthene sheet 3000 1.0500 m2 Peralatan 1.0000 ls
1 M2 PENGECATAN MELAMINE NATURALBAHAN
WoodFiller 0.2000 kg Pewarna 0.5000 sct Kertas gosok No. 150 1.0000 lbr Kertas gosok No. 280 1.0000 lbr Shanding 0.5000 kg Clear doof 0.2000 kg Thinner A special 0.3700 kg Coumpound 0.2000 klng Sewa alat bantu ( 1 set @ 3 alat ) 1.0000 set
1 M2 PENGECATAN GENTING BARUBAHAN
Cat Genting 0.2000 kg
1M2 PENGECATAN KAYU BAHAN
Cat Kayu 0.4250 kg Minyak Cat 0.0570 ltr Kertas Gosok 1.0000 lmb
PEKERJAAN LANTAI
1 M2 PEMASANGAN GRANITE TILE 30X30 POLISH Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Granite Tile Ukuran 30 x 30 Polished 1.0000 m2
1 M2 PEMASANGAN GRANITE TILE 60X60 POLISH Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Granite Tile Ukuran 60 x 60 Polished 1.0000 m2
1 M2 PEMASANGAN UBIN KERAMIK 30x30 WARNA MOTIF Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970
Page 309 of 334
Pemasangan Lantai VII 1.2360BAHAN
PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Keramik Lantai 30 x 30 Warna / Motif 1.0000 m2
1 M2 PEMASANGAN PELAPIS BATU CANDI Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Batu Candi 1.0000 m2
1 M2 PEMASANGAN UBIN KERAMIK 40X40 WARNA MOTIF Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Keramik Lantai 40 x 40 Warna / Motif 1.0000 m2
1 M2 PEMASANGAN PELAPIS DINDING CLADDING Ex. INDAL BAHAN
Bahan Cladding Ex. Indal 1.0500 m2 Paku baut 50.0000 bh Sewa alat pmbntu 1.0000 ls Rangka Hollow 1.0000 m2
1 M2 PEMASANGAN GARNITE TILE WARNA EX. ESSENZA 60X60 Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Ubin Granito warna Hitam Essenza 60 x 60 1.0000 m2
1 M2 PEMASANGAN MARMER 100 X 100 Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Marmer 100 x 100 1.0000 m2
1 M2 PEMASANGAN GRANIT IMPORT Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 10.0000 kg Semen warna nut 1.5000 kg Pasir pasang 0.0450 m3 Batu GRANIT import Italy 1.0000 m2
1 M2 PASANG LANTAI KERAMIK 20 X 20 MOTIF Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 3.3000 kg Semen warna nut 1.3400 kg Pasir pasang 0.0180 m3 Keramik Lantai 20/20 motif 1.0000 m2
1 M2 PASANG DINDING KERAMIK 20 X 25 MOTIF Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350
Page 310 of 334
Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 3.3000 kg Semen warna nut 1.3400 kg Pasir pasang 0.0180 m3 Keramik Dinding 20 x 25 1.0000 m2
1 M' PASANG PLINT KERAMIK UKURAN 10X40 Pemasangan Lantai I 1.0000 Pemasangan Lantai II 1.0900 Pemasangan Lantai III 1.1200 Pemasangan Lantai IV 1.1350 Pemasangan Lantai V 1.1620 Pemasangan Lantai VI 1.1970 Pemasangan Lantai VII 1.2360
BAHAN PC 0.0330 kg Semen warna nut 0.1000 kg Pasir pasang 0.0032 m3 Plint Keramik Lantai 10 x 40 2.6600 bh
1 M2 PEMASANGAN METAL CLADDING WARNA BAHAN
Alat bantu 1.0000 ls Sealent 0.4000 klng Clidding Wall Colour + Rangka 1.1000 m2
1 M2 PEMASANGAN HARDENER FLOOR BAHAN
Floor Hardener 3.0000 kg
1 M2 PEMASANGAN LANTAI KARPET BAHAN
Karpet World Class 1.0500 m2 Lem 0.5000 kg
1 M2 PEMASANGAN LAPISAN FOAM UNTUK KARPET BAHAN
Foam Lapisan Karpet 1.0500 m2 Lem 0.3750 kg
1 M2 PEMASANGAN LANTAI KAYU ( GYMFLOOR) BAHAN
Gymfloor 1.0500 kg Lem 0.6000 m2
PEKERJAAN KUDA-KUDA, RENG USUK
1 M3 KUDA-KUDA KAYU JATI ( BENTANG MAX.7.00 M) BAHAN
Kayu Jati ( Balok 6/12 ) Ex. Malang 1.1000 m3 Besi Plat strip 15.0000 kg Paku Klem No.4 5.6000 kg
1 M3 KUDA-KUDA KAYU MERANTI ( BENTANG MAX.7.00 M) BAHAN
Kayu Balok Meranti 1.1000 m3 Besi Plat strip 15.0000 kg Paku Klem No.4 5.6000 kg
1 M3 GORDING KAYU KAMPER BAHAN
Kayu Kamper Balok 1.1000 m3 Besi Plat strip 15.0000 kg Paku Klem No.4 0.2000 kg
1 M2 PEMASANGAN RENG KAMPER / USUK KAMPER BAHAN
Kayu Kamper Reng 0.0039 m3 Kayu Kamper Usuk 0.0108 m3 Paku Reng 0.2000 kg
1 M2 PEMASANGAN RENG KAMPER / USUK MERANTI BAHAN
Kayu Kamper Reng 0.0039 m3 Kayu Meranti Usuk 0.0108 m3 Paku Reng 0.2000 kg
1 M2 PEMASANGAN RENG JATI / USUK KAMPER BAHAN
Kayu jatir Reng 0.0039 m3 Kayu Kamper Usuk 0.0108 m3 Paku Reng 0.2000 kg
PEKERJAAN PENUTUP ATAP
1 M2 PEMASANGAN GENTENG KARANGPILANG Ex. SURABAYA Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
BAHAN Genteng Karangpilang ex. Surabaya 25.0000 bh
1 M2 PEMASANGAN GENTENG KERAMIK WARNA Ex.KIA BAHAN
Genteng Keramik Warna KIA 11.0000 bh
Page 311 of 334
1 M2 PEMASANGAN GENTENG KODOK GOOD YEARS BAHAN
Genteng Kodok Good Years 25.0000 bh
1 M2 PEMASANGAN ATAP POLY CARBONIT BAHAN
Polycarbonite 1.0000 m2
1 M' PEMASANGAN WUWUNG GENTENG KARANGPILANG Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
BAHAN PC 11.8500 kg Pasir Pasang 0.0323 m3 Bubung Genteng Karangpilang ex. Surabaya 3.0000 bh
1 M' PEMASANGAN WUWUNG GENTENG KODOK GLAZUR BAHAN
PC 11.8500 kg Pasir Pasang 0.0323 m3 Bubung Genteng kodok glazur 3.0000 bh
1 M' PEMASANGAN WUWUNG GENTENG PELENTONG BESAR BAHAN
PC 11.8500 kg Pasir Pasang 0.0323 m3 Bubung Genteng Pelentong besar / super 3.0000 bh
1 M' PEMASANGAN WUWUNG GENTENG KARANGPILANG GEDUNG BERTINGKAT BAHAN
PC 11.8500 kg Pasir Pasang 0.0323 m3 Genteng kaca Palentong supr / besar 3.0000 bh
1 M2 ALUMINIUM FOIL / INSULATION BAHAN
Glass wol 0.0183 Rol Roof Mes 0.0153 Rol Alluminium foil /insulation double side 0.0611 Rol Allumunium Tape 0.0489 Rol
PEKERJAAN TALANG
1 M' PEMASANGAN TALANG SENG BJLS 40 ( LEBAR 90 CM ) BAHAN
Kayu Kamper ( Papan ) 2/30 0.0160 m3 Kayu KamperUsuk 0.0073 m3 Seng Talang BJLS 40 Lebar 90 cm 1.0000 m' Paku Sumbat 5.0000 bh
1 M' PEMASANGAN TALANG PEMBULUH PVC Ø 3" BAHAN
Pipa PVC Ø 3" 0.1667 lnjr Klem PVC 1.0000 buah
1 M' PEMASANGAN TALANG PEMBULUH PVC Ø 4 " BAHAN
Pipa PVC Ø 4 " 0.1667 lnjr Klem PVC 1.0000 buah
1 M' PEMASANGAN TALANG PEMBULUH PVC Ø 5 " BAHAN
Pipa PVC Ø 5 " 0.1667 lnjr Klem PVC 1.0000 buah
1 M' PEMASANGAN TALANG PEMBULUH PIPA GALVANIS Ø 3" BAHAN
Pipa Galvanis Ø 3" 0.1667 lnjr Klem Galvanis 1.0000 buah
Kayu Jati Papan ex. Malang 0.0099 m3 Paku Biasa 0.0500 kg
1 M' PEMASANGAN LISPLANK KAYU KAMPER 2/30 BAHAN
Kayu Papan kamper 0.0099 m3 Paku Biasa 0.0500 kg
1 BH BAK KONTROL 30X30 TINGGI 35 CM BAHAN
bata Merak 83.9120 bh Semen PC/50 kg 44.0000 Kg Pasir Pasang 0.0700 m3 Koral Beon 0.0700 m3 Besi beton 1.6000 Kg Pasir Beton 0.0600 m3
PEKERJAAN PLAFOND
Page 312 of 334
PEKERJAAN PLAFOND
1 M2 PEMASANGAN PLAFOND ASBES DATAR RANGKA KAYU KAMPER BAHAN
Kayu Balok Kamper 5/7 0.0116 m3 Asbes datar t= 4 mm 1.0500 m2 Paku Asbes 0.0324 kg Paku biasa 0.0300 kg
1 M2 PEMASANGAN PLAFOND ASBES DATAR RANGKA KAYU Kruing Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
BAHAN Kayu Balok Kamper 5/7 0.0116 m3 Asbes 100x100x6 mm 1.0500 m2 Paku Asbes 0.0324 kg Paku biasa 0.0300 kg
1 M2 PEMASANGAN PLAFOND TRIPLEX RANGKA KAYU KAMPER BAHAN
Kayu Balok Kamper 5/7 0.0116 m3 Triplex 4 mm 0.3819 lbr Paku Triplex 0.0324 kg Paku biasa 0.0300 kg
1 M2 PEMASANGAN PLAFOND GYPSUM + RANGKA METAL FURING Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Gypsumboard 122 x 244 t = 9 mm 0.3472Lembar Sekrup 11.0000 bh Rangka metal furing 0.9900 btg Stifenner 3.0000 btg Juster penggantung 4.0000 bh Joint Tape 0.8000 m' Jointing Compound 0.3000 Kg Steger 0.1000 ls
1 M2 PEMASANGAN PLAFOND KLASIBOARD TANPA RANGKA BAHAN
1 M2 PEMASANGAN LIST PLAFOND GYPSUM PROFIL 10 CM BAHAN
List Profil Gypsum, t = 5 - 10 cm 1.0000 m' Jointing Compound 0.1000 Kg Steger 0.1000 ls
PEKERJAAN KOSEN DAN PINTU
1 M3 KOSEN PINTU DAN JENDELA KAYU JATI Ex. MALANG BAHAN
Kayu Jati Balok 1.1000 m3 Paku Klem 1.2000 kg Lem Kayu 1.0000 kg
1 M3 KOSEN PINTU DAN JENDELA KAYU KAMPER Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
BAHAN Kayu Kamper Balok 1.2000 m3 Paku Klem 1.2500 kg Lem Kayu 1.0000 kg
1 M' PASANG KOSEN PINTU DAN KOSEN JENDELA DARI ALUMINIUM Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620
Page 313 of 334
BAHAN Jendela alumunium putih ex. INDALEX 1.2000 m' Sealent 8.0000 m'
1 M2 DAUN PINTU PANIL JATI Ex. MALANG BAHAN
kayu Jati Papan 3 cm 0.0400 m3 Skrup 25.0000 bh
1 M2 DAUN PINTU PANIL KAMPER BAHAN
Kayu Kamper Papan 3 cm 0.0400 m3 Skrup 25.0000 bh
1 M2 PASANG PINTU PANIL (80X230) KAMPER + MULTIPLEX 9 MM + TEAKWOOD BAHAN
Kayu Papan Kamper 0.0291 m3 Multiplex 9 mm 0.6500 lmbr Teakwood Jati 4 mm 1.0000 lmbr Paku Triplex 0.2000 kg 22000 Lem Putih Fox 0.0500 kg Profil kayu 3.5000 m'
1 M2 PINTU / JENDELA KACA ALUMUNIUM BAHAN
Aluminium Jendela 4.0000 m' Sealent 0.1000 kg Kaca Polos tebal 5mm 0.6500 m'
1 M2 PINTU / JENDELA KACA PAPAN KAYU KAMPER BAHAN
Kayu Papan Kamper 0.0350 m3 Paku biasa 1.4000 m2 Kaca Polos tebal 5mm 0.3000 m2
Kayu Kamper 0.0196 m3 Multiplex 9 mm 0.7000 m2 Teakwood Jati 4 mm + Formika 0.7000 m2 Pembuatan Kisis2 kayu kamper 0.3000 m2
1 M2 PASANG KACA MATI 5 MM BAHAN
Alat bantu 1.0000 m3 Sealent 0.4000 kg Kaca Gelap 5 mm 1.0000 m2
1 M2 PASANG KACA BURAM 5 MM BAHAN
Alat bantu 1.0000 m3 Sealent 0.4000 kg Kaca Buram tebal = 5 mm 1.0000 m2
1 M' PASANG PROFIL KAYU KAMPER 7 CM BAHAN
List Profil Kayu Kamper 1/7 1.0500 m' Paku biasa 0.0020 kg Lem Kayu 0.3000 ltr
1 M' PASANG PROFIL KAYU KAMPER 10 CM BAHAN
List Profil Kayu Kamper 1/10 1.0500 m' Paku biasa 0.0020 kg Lem Kayu 0.3000 ltr
1 M' PASANG PROFIL KAYU KAMPER 15 CM BAHAN
List Profil Kayu Kamper 1/15 1.0500 m' Paku biasa 0.0020 kg Lem Kayu 0.3000 ltr
1 M' PASANG PROFIL KAYU JATI 15 CM BAHAN
List kayu jati profil 1.5/15 1.0500 m' Paku biasa 0.0020 kg Lem Kayu 0.3000 ltr
1 M2 PASANG KACA STOPSOL BLUEGREY 6 MM BAHAN
Alat bantu 1.0000 ls Sealent 0.4000 klng Kaca Stopsol Blue Grey 6 mm 1.0500 m2
1 M2 PASANG KACA STOPSOL BLUEGREY 8 MM BAHAN
Alat bantu 1.0000 ls Sealent 0.4000 klng Kaca Stopsol Blue Grey 8 mm 1.0500 m2
1 M2 PASANG KACA TEMPERED 12 MM BAHAN
Alat bantu 1.0000 ls Sealent 0.4000 klng Kaca Temprd 12 mm 1.1000 m2
1 M2 PASANG KACA NACO TEBAL 5 MM RAYBEN BAHAN
Page 314 of 334
Krepyak Naco 10.0000 daun Kaca Rayben 5 mm 1.3600 m2 Sekrup 10.0000 kg
1 M2 METAL CLIDDING COLOUR BAHAN
Alat bantu 1.0000 ls Sealent 0.4000 klng Clidding Wall Colour + Rangka 1.2000 m2
1 M' PASANG KOSEN CURTAIN WALL ALUMINIUM BAHAN
Aluminium Curtain 1.1000 m' Sealent 2.0000 klng
1 UNIT PINTU FRAME LESS TEMPERED Kaca tempered 12 mm 3.7800 m2 Aluminium profil warna 4" 0.0000 m' Patch Fitting Handle SS Complete Dekkson+Floorhinge Dorma 2.0000 set Kunci Ex Dorma 2.0000 set Handel Stainless Steel 2.0000 set
PEKERJAAN PARTISI
1 M2 PARTISI DOUBLE TEAKWOOD BAHAN
Teakwood 3 mm 1.0000 lbr Kayu Kamper Usuk 0.0154 m3 Paku Klem 0.1000 kg
1 M2 PARTISI DOUBLE GYPSUM TEBAL 12 MM Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Gypsum Board 12 mm 0.6944Lembar Skrup 22.0000 bh Hollow 2/4 0.5000 btg Hollow 4/4 1.0000 btg Skrup Fisher 2.0000 bh Joint Tape 2.0000 m' Jointing Compound 0.3000 Kg
PEKERJAAN ASSESORIES PINTU / JENDELA
1 BH PASANG KUNCI PINTU DOUBLE SLAAG SETARA LOGO - CISA BAHAN
1 UNIT PEMASANGAN TIAN OKTOGONAL 7 M SINGLE + FLANDERS BAHAN
Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 7 m 1.0000 unit
Page 316 of 334
ALAT Sewa Crane 0.5000 jam
1 UNIT PEMASANGAN TIAN OKTOGONAL 7 M DOUBLE + FLANDERS BAHAN
Tiang Oktogonal Double Hot Dipped Galv + Flenders 7 m 1.0000 unitALAT
Sewa Crane 0.5000 jam
1 UNIT PEMASANGAN TIAN OKTOGONAL 9 M SINGLE + FLANDERS BAHAN
Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 9 m 1.0000 unitALAT
Sewa Crane 0.5000 jam
1 UNIT PEMASANGAN TIAN OKTOGONAL 9 M DOUBLE + FLANDERS BAHAN
Tiang Oktogonal Double Hot Dipped Galv + Flenders 9 m 1.0000 unitALAT
Sewa Crane 0.5000 jam
1 UNIT PEMASANGAN TIAN OKTOGONAL 12 M SINGLE + FLANDERS BAHAN
Tiang Oktogonal Singgle Hot Dipped Galv + Flenders 12 m 1.0000 unitALAT
Sewa Crane 0.5000 jam
1 UNIT PEMASANGAN TIAN OKTOGONAL 12 M DOUBLE + FLANDERS BAHAN
Tiang Oktogonal Double Hot Dipped Galv + Flenders 12 m 1.0000 unitALAT
Sewa Crane 0.5000 jam
1 UNIT PONDASI BIASA PJU 5 M - 7 M BAHAN
Angkur Besi D.16 10.9720 kg Pipa PVC Class D Ǿ 2 " 2.0000 m' Pasir Urug 0.0640 m3 Kayui Meranti Bekisting 0.0500 m3 Paku Reng 0.5000 kg PC 94.3750 kg Pasir Beton 1.1784 m3 Batu Pecah Mesin 2/3 0.0406 m3 Batu Pecah Mesin 1/2 0.1889 m3
ALAT Sewa Alat Bantu 0.1767 jam Sewa Vibrator Roller 0.0076 jam Sewa Concrete Mixer 0.0076 jam
1 UNIT PONDASI BIASA PJU 7 M - 9 M BAHAN
Angkur Besi D.19 10.9720 kg Pipa PVC Class D Ǿ 2 " 2.0000 m' Pasir Urug 0.0960 m3 Kayui Meranti Bekisting 0.0500 m3 Paku Reng 0.5000 kg PC 181.2950 kg Pasir Beton 0.3364 m3 Batu Pecah Mesin 2/3 0.0406 m3 Batu Pecah Mesin 1/2 0.3770 m3
ALAT Sewa Alat Bantu 0.2709 jam Sewa Vibrator Roller 0.0152 jam Sewa Concrete Mixer 0.0152 jam
1 UNIT PONDASI STROUSS PJU BAHAN
Angkur Besi D.19 10.9720 kg Besi beton 6 mm polos 9.5400 btg Kawat Beton 0.1735 kg Pipa PVC Class D Ǿ 2 " 2.0000 m' Pasir Urug 0.0960 m3 Kayui Meranti Bekisting 0.0500 m3 Paku Reng 0.5000 kg PC 219.2000 kg Pasir Beton 0.3364 m3 Batu Pecah Mesin 2/3 0.0406 m3 Batu Pecah Mesin 1/2 0.3770 m3
ALAT Sewa Alat Bantu 0.2709 jam Sewa alat strouss 1.2000 jam Sewa Vibrator Roller 0.0152 jam Sewa Concrete Mixer 0.0152 jam
PEKERJAAN SANITAIR / FICTURE UNIT
1 M' PEMASANGAN SALURAN Ǿ 40 SEGMEN BAHAN
Buis beton Ø 40 cm 1.0000 bh
1 M' PEMASANGAN SALURAN Ǿ 60 SEGMEN BAHAN
Buis beton Ø 60 cm 1.0000 bh
1 M' PEMASANGAN SALURAN Ǿ 80 SEGMEN BAHAN
Buis beton Ø 80 cm 1.0000 bh
1 M' PEMASANGAN SALURAN Ǿ 100 SEGMEN BAHAN
Buis beton Ø 100 cm 1.0000 bh
1 M' PEMASANGAN SALURAN U- Ǿ 20 SEGMEN BAHAN
Page 317 of 334
Buis beton U - Ø 20 cm 1.0000 bh
1 M' PEMASANGAN SALURAN U- Ǿ 30 SEGMEN BAHAN
Buis beton U - Ø 30 cm 1.0000 bh
1 M' PEMASANGAN PIPA AIR BERSIH Ǿ ½ " BAHAN
Pipa PVC Type AW Ø ½ " 1.1000 m' Lem PVC 0.1000 bh
1 M' PEMASANGAN PIPA AIR BERSIH Ǿ ¾ " BAHAN
Pipa PVC Type AW Ø ¾ " 1.1000 m' Lem PVC 0.1000 bh
1 M' PEMASANGAN PIPA AIR BERSIH Ǿ 1 " BAHAN
Pipa PVC Type AW Ø 1 " 1.1000 m' Lem PVC 0.1000 bh
1 M' PEMASANGAN PIPA AIR BERSIH Ǿ 1½ " BAHAN
Pipa PVC Type AW Ø 1½ " 1.1000 m' Lem PVC 0.1000 bh
1 M' PEMASANGAN PIPA AIR KOTOR Ǿ 1½ " BAHAN
Pipa PVC Type C Ø 1½ " 1.1000 m' Lem PVC 0.2000 bh
1 M' PEMASANGAN PIPA AIR KOTOR Ǿ 2 " BAHAN
Pipa PVC Type C Ø 2 " 1.1000 m' Lem PVC 0.2000 bh
1 M' PEMASANGAN PIPA AIR KOTOR Ǿ 3 " BAHAN
Pipa PVC Type C Ø 3 " 1.1000 m' Lem PVC 0.2000 bh
1 M' PEMASANGAN PIPA AIR KOTOR Ǿ 4 " BAHAN
Pipa PVC Type C Ø 4 " 1.1000 m' Lem PVC 0.2000 bh
1 BH PEMASANGAN KRAN AIR IMPORT BAHAN
Kran Air ؾ" 1.0000 bh Rol TBA 1.0000 roll
1 BH PEMASANGAN KRAN AIR LOKAL BAHAN
Kran Air ؽ" 1.0000 bh Rol TBA 1.0000 roll
1 BH PEMASANGAN CLOSET DUDUK Ex. INA BAHAN
Closet Duduk ex. INA 1.0000 bh
1 BH PEMASANGAN CLOSET DUDUK Ex. INA BAHAN
Closet Duduk Putih Porselin Komplit ex. INA 1.0000 bh
1 BH PEMASANGAN CLOSET DUDUK MONOBLOCK Ex. TOTO BAHAN
Closet Duduk Standard lengkap TOTO C 48 1.0000 bh
Perlengkapan ( 6% X Harga closet) 0.0600 ls
1 BH PEMASANGAN CLOSET JONGKOK Ex. INA BAHAN
Closet Jongkok putih ex. INA 1.0000 bh
1 BH PEMASANGAN CLOSET JONGKOK Ex. TOTO BAHAN
Closet Jongkok Warna ex. TOTO 1.0000 bh
1 BH PEMASANGAN WASHTAFEL BAHAN
Washtafel lokal besar 1.0000 bh Kran Air ( Import ) 1.0000 bh Flexible 60 cm 1.0000 m Knee PVC Ø 11/2 " 1.0000 bh Rol TBA 1.0000 rol Sifon Wasser 1.0000 set Waltermoor 1.0000 bh
1 BH PEMASANGAN WASHTAFEL Ex. TOTO BAHAN
Wastafel Meja Warna Standard Lengkap (L 546) 1.0000 bh Kran Air ( Import ) 1.0000 bh Flexible 60 cm 1.0000 m Knee PVC Ø 11/2 " 1.0000 bh Rol TBA 1.0000 rol
1 BH PEMASANGAN LUBANG AVOER BAHAN
Pipa PVC Type C Ø 2 " 0.5000 m Ijuk 0.0500 kg
1 BH URINOAR TYPE MUSLIM BAHAN
Urinoar Type Muslim 1.0000 Bh
Page 318 of 334
Perlengkapan ( 6% X Harga closet) 0.0600 ls Semen PC/50 kg 6.0000 Kg Pasir Pasang 0.0100 m3
1 BH PARTISI PENYEKAT URINOAR BAHAN
Patisi Penyekat Urinoir (TOTO A 100) 1.0000 Bh Perlengkapan ( 6% X Harga penyekat) 0.0600 ls
1 BH WASHTAFEL PADESTAL Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Wastafel Gantung (L 237 V3) 1.0000 Bh Perlengkapan ( 12% X Harga washtafel) 0.1200 ls Semen PC/50 kg 6.0000 Kg Pasir Pasang 0.0100 m3
1 BH WASHTAFEL MEJA Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Wastafel Meja Warna Standard Lengkap (L 546) 1.0000 Bh Perlengkapan ( 12% X Harga washtafel) 0.1200 ls Semen PC/50 kg 6.0000 Kg Pasir Pasang 0.0100 m3
1 BH SLOP SINK / SERVICE SINK Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Slop Sink 1.0000 Bh Perlengkapan ( 12% X Harga washtafel) 0.1200 ls Semen PC/50 kg 6.0000 Kg Pasir Pasang 0.0100 m3
1 BH BAK MANDI FABER 0,3 M3 Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Bak mandi fibergalss 1.0000 Bh Perlengkapan ( 18% X Harga washtafel) 0.1800 ls
1 BH KRAN AIR Ø 1/2 " ATAU Ø 3/4 " Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Kran air Ø 1/2" atau Ø 3/4" (TOTO T23 B13) 1.0000 Bh SEAL TAPE 0.0250 Bh
1 BH KRAN SINK Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Kran Sink 1.0000 Bh SEAL TAPE 0.0250 Bh
1 BH FLOOR DRAIN Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Floor Drain (TOTO TX 1 B) 1.0000 Bh
1 BH SOAP HOLDER Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970
Page 319 of 334
Lantai Tujuh 1.2360BAHAN
Soap Holder (TOTO S 11 N) 1.0000 Bh
1 BH TISSEU HOLDER Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Tisue Holder (TS 116 R) 1.0000 Bh
1 BH JET WASHER Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Jet Washer (TOTO TX 423 SVINCR) 1.0000 Bh
1 BH TEMPAT HANDUK (TOWELSHELF) SETARA TOTO TYPE TX.4A Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Towel Shelf (TOTO TX 4 A) 1.0000 Bh
1 BH PEGANGAN (GRAB BAR) SETARA TOTO TYPE TX.3 A2 (550MM) Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Grab Bar (TOTO TX3 A2) 1.0000 Bh
1 BH GANTUNGAN HANDUK (TOWEL RING) SETARA TOTO TYPE TS 115 S Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Towel Ring (TOTO TS 115 S) 1.0000 Bh
1 BH KAIT PAKAIAN (DOUBLE ROBE HOOK) SETARA TOTO TYPE TS.118 WS Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Double robe hook (TS 118 WS) 1.0000 Bh
1 BH PASANG KACA CERMIN 120 X 240 CM, T=5mm DI BEVEL 2 CM Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Kaca Cermin 5 mm + Bevel 2 cm 2.8880 M2
1 BH BAK CUCI STAINLESS STEEL Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Kitchen Zink Stainless Standard Lokal ( 1 Lobang ) 1.0000 Bh Perlengkapan ( 18% X Harga Bahan) 0.1000 ls
1 BH TOP TABLE BATU GRANITE Lantai Satu 1.0000 Lantai Dua 1.0900 Lantai Tiga 1.1200 Lantai Empat 1.1350 Lantai Lima 1.1620 Lantai Enam 1.1970 Lantai Tujuh 1.2360
BAHAN Batu GRANIT import Italy 1.0520 m2 Semen PC/50 kg 14.1500 Kg Pasir Pasang 0.0390 m3
Page 320 of 334
Semen Warna 2.0000 Kg
PEKERJAAN INFRASTRUKTUR
1 M2 PEMASANGAN PAVING T= 8 CM BAHAN
PAVINGST ( K.125 ) warna abu2 t=8cm 1.0500 m2
1 M2 PEMASANGAN PAVING T= 6 CM BAHAN
PAVINGST ( K.125 ) warna abu2 t=6cm 1.0500 m2
1 M2 PEMASANGAN PAVING T= 8 CM BAHAN
PAVINGST ( K.125 ) warna abu2 t=8cm 1.0500 m2
1 M2 PEMASANGAN GRESS BLOCK BAHAN
Gress Block Beton 10 x 40 x 60 cm 1.0500 m2
1 M' PEMASANGAN KANSTEEN BDCM BAHAN
PC 18.0000 kg Pasir Pasang 0.0010 m3 Kansteen BDCM 1.0000 m'
1 M' PEMASANGAN KANSTEEN TRAP BAHAN
PC 18.0000 kg Pasir Pasang 0.0010 m3 Kansteen 1.0000 m'
B. PEK. SUB STRUKTUR DIBAWAH ±0.00B.1 PEKERJAAN PONDASI UTAMA 21.32% 2.60% 3.71% 5.35% 4.99% 3.54% 1.13%B.2 PEKERJAAN PONDASI PENDUKUNG 0.13% 0.13%
C. LANTAI - I -(Di atas ± 0.00)C.1. PEKERJAAN SIPIL 12.71% 0.28% 1.92% 4.42% 4.59% 1.50%
1 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. A type K1 0.18% 0.09% 0.09%2 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. B type K1 0.29% 0.15% 0.15%3 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. C type K1 0.29% 0.15% 0.15%4 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. D type K1 0.29% 0.15% 0.15%5 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. E type K1 0.29% 0.15% 0.15%7 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 1 type B1 0.23% 0.12% 0.12%8 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 2 type B1 0.23% 0.12% 0.12%9 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3 type B1 0.23% 0.12% 0.12%
10 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 4 type B1 0.18% 0.09% 0.09%11 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 5 type B1 0.17% 0.08% 0.08%12 Pekerjaan Beton K-250 untuk Balok Utama 30/60 posisi Cl. A type B2 0.14% 0.07% 0.07%13 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. B type B1 0.31% 0.16% 0.16%14 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. C type B1 0.31% 0.16% 0.16%15 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. D type B1 0.33% 0.16% 0.16%16 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. E type B1 0.33% 0.16% 0.16%17 Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 1.44% 0.72% 0.72%18 PEKERJAAN TANGGA UTAMA
Pekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.01% 0.01%Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3A type B1 0.05% 0.05%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.03% 0.03%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.36% 0.36%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.01% 0.01%Pek.Plesteran halus 1 : 4 0.01% 0.01%Pek. Acian 0.00% 0.00%Pek. Pengecatan 0.00% 0.00%Pek. Railling stailess steel Ø 2" tebal 2 mm 0.10% 0.10%
19 PEKERJAAN LIFT UTAMAPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.15% 0.15%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.09% 0.09%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.04% 0.04%Pek. Pas. 1/2 bata 1 : 4 setinggi + 4.50 0.06% 0.03% 0.03%Pek.Plesteran halus 1 : 4 0.05% 0.02% 0.02%Pek. Acian 0.03% 0.03%
20 PEKERJAAN RAMP BETONPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.01% 0.01%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.08% 0.08%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.52% 0.52%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm dari lantai Tangga sisi tengah 0.10% 0.05% 0.05%Pek.Plesteran halus 1 : 4 0.08% 0.04% 0.04%Pek. Acian 0.05% 0.05%Pek. Pengecatan 0.04% 0.04%Pek. Pagar Besi Kotak Finh. Cat EMCO 0.95% 0.95%
Pek Beton K-250 untuk Plat Terras tebal 10 cm uk. 1.25 x 16 0.08% 0.08%0.08% 0.08%
27 2.92% 1.46% 1.46%28 Pek Beton K-250 untuk Lisplang beton 10/80 atap ruang tunggu 0.05% 0.05%
C.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKALC.3.1. PEKERJAAN ELEKTRIKAL 0.60% 0.32% 0.06% 0.22%C.3.3. PEKERJAAN INSTALASI AIR
A INSTALASI TALANG VERTICAL 0.08% 0.08%B. INSTALASI AIR KOTOR + KOTORAN CLOSET 0.11% 0.05% 0.06%C. INSTALASI AIR BERSIH 0.25% 0.25%
D. LANTAI - II - (DI ATAS + 4.50) 75.00%D.1. PEKERJAAN SIPIL 9.69% 0.43% 0.54% 3.27% 5.45%
1 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. A type K1 0.17% 0.17%2 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. B type K1 0.28% 0.28%3 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. C type K1 0.28% 0.28%4 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. D type K1 0.28% 0.28%5 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. E type K1 0.28% 0.28%7 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 1 type B1 0.25% 0.25%8 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 2 type B1 0.25% 0.25%9 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3 type B1 0.25% 0.25%
Keterangan
Beton K-250 un Balok 20/40 type B3 di Cl. E (2-3-4) plat teras +300( / 4 m)Pek Beton K-250 untuk Plat lt II tebal 12 cm ( + 4.50 )+Plat Rg. Tunggu
Page 322 of 334
10 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 4 type B1 0.20% 0.20%11 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 5 type B1 0.18% 0.18%12 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. B type B1 0.34% 0.34%13 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. C type B1 0.34% 0.34%14 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. D type B1 0.34% 0.34%15 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. E type B1 0.34% 0.34%16 Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 1.65% 1.65%17 PEKERJAAN TANGGA UTAMA
Pekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.02% 0.02%Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3A type B1 0.06% 0.06%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.04% 0.04%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.16% 0.16%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.01% 0.01%Pek.Plesteran halus 1 : 4 0.00% 0.00%Pek. Acian 0.00% 0.00%Pek. Pengecatan 0.00% 0.00%Pek. Railling stailess steel Ø 2" tebal 2 mm 0.07% 0.07%
18 PEKERJAAN LIFT UTAMAPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.16% 0.16%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.07% 0.07%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.05% 0.05%Pek. Pas. 1/2 bata 1 : 4 setinggi + 4.00 0.07% 0.07%Pek.Plesteran halus 1 : 4 0.04% 0.04%Pek. Acian 0.03% 0.03%
19 PEKERJAAN TANGGA DARURATPekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.03% 0.03%Pekerjaan Beton K-175 un. Ring Balustrade 15/15 0.00% 0.00%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.14% 0.14%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.02% 0.02%Pek.Plesteran halus 1 : 4 0.01% 0.01%Pek. Acian 0.01% 0.01%Pek. Pengecatan 0.01% 0.01%
20 Pek. Beton Praktis K-175 un. Kolom 15/15 0.00% 0.00%21 Pek. Beton Praktis K-175 un. Balok Ring 15/15 di atas Pas. Dinding 0.02% 0.02%22 Pek. Beton Praktis K-175 un. Balok Latei 15/15 di atas Kosen pas.Ddn. 0.01% 0.01%23 Beton Praktis K-175 un.Canopy Jend (50x120x10) CL.B(4-5)-CL.5 0.01% 0.01%24 Beton Praktis K-175 un.Balok 15/20 Canopy Jend CL.B(4-5)-CL.5 0.01% 0.01%20 3.17% 3.17%25 Pek Beton K-250 untuk Lisplang beton 10/80 atap ruang tunggu 0.05% 0.05%
D.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKALD.3.1. PEKERJAAN ELEKTRIKAL 0.45% 0.45%D.3.3. PEKERJAAN INSTALASI AIR
A INSTALASI TALANG VERTICAL 0.08% 0.08%B. INSTALASI AIR KOTOR + KOTORAN CLOSET 0.11% 0.11%C. INSTALASI AIR BERSIH 0.26% 0.26%
E. LANTAI - III - (DI ATAS + 8.50)E.1. PEKERJAAN SIPIL 8.65% 4.30% 1.06% 3.11% 0.08% 0.10%
1 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. B type K1 0.29% 0.29%2 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. C type K1 0.29% 0.29%3 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. D type K1 0.29% 0.29%4 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. E type K1 0.29% 0.29%7 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 1 type B1 0.19% 0.19%8 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 2 type B1 0.19% 0.19%9 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3 type B1 0.20% 0.20%
10 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 4 type B1 0.20% 0.20%11 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 5 type B1 0.19% 0.19%12 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. B type B1 0.35% 0.35%13 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. C type B1 0.35% 0.35%14 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. D type B1 0.35% 0.35%15 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. E type B1 0.35% 0.35%16 Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 1.25% 0.63% 0.63%12 PEKERJAAN TANGGA UTAMA
Pekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.02% 0.02%Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3A type B1 0.06% 0.06%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.04% 0.04%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.16% 0.16%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.01% 0.01%Pek.Plesteran halus 1 : 4 0.00% 0.00%Pek. Acian 0.00% 0.00%Pek. Pengecatan 0.00% 0.00%Pek. Railling stailess steel Ø 2" tebal 2 mm 0.07% 0.07%
13 PEKERJAAN LIFT UTAMAPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.15% 0.15%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.08% 0.08%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.05% 0.05%Pek. Pas. 1/2 bata 1 : 4 setinggi + 4.00 0.07% 0.07%Pek.Plesteran halus 1 : 4 0.05% 0.05%Pek. Acian 0.03% 0.03%Pek. Pasangan pelapis Muka Lift bahan Marmer 0.08% 0.08%Pek. Pasangan pelapis Muka Lift bahan Granit Import 0.02% 0.02%
14 PEKERJAAN TANGGA DARURATPekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.03% 0.03%Pekerjaan Beton K-175 un. Ring Balustrade 15/15 0.00% 0.00%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.15% 0.15%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.01% 0.01%Pek.Plesteran halus 1 : 4 0.01% 0.01%Pek. Acian 0.01% 0.01%Pek. Pengecatan 0.00% 0.00%
15 Pek. Beton Praktis K-175 un. Kolom 15/15 0.00% 0.00%16 Pek. Beton Praktis K-175 un. Balok Ring 15/15 di atas Pas. Dinding 0.01% 0.01%17 Pek. Beton Praktis K-175 un. Balok Latei 15/15 di atas Kosen pas.Ddn. 0.00% 0.00%18 Beton Praktis K-175 un.Canopy Jend (50x120x10) CL.B(4-5)-CL.5 0.01% 0.01%19 Beton Praktis K-175 un.Balok 15/20 Canopy Jend CL.B(4-5)-CL.5 0.01% 0.01%20 2.68% 2.68%21 Pek Beton K-250 untuk Lisplang beton 10/80 atap ruang tunggu 0.05% 0.05%
E.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKALE.3.1. PEKERJAAN ELEKTRIKAL 1.70% 0.08% 0.60% 0.86% 0.12% 0.04%E.3.3. PEKERJAAN INSTALASI AIR
Pek Beton K-250 untuk Plat lt 3 tebal 12 cm ( + 8.50 )+Plat R.Tunggu
Pekerjaan Beton K-250 untuk Plat lantai 4 tebal 12 cm ( + 12.50 )+Plat
Page 323 of 334
A INSTALASI TALANG VERTICAL 0.18% 0.18% 50.00%B. INSTALASI AIR KOTOR + KOTORAN CLOSET 0.11% 0.11%C. INSTALASI AIR BERSIH 0.25% 0.25%
F. LANTAI - IV - (DI ATAS + 12.50)F.1. PEKERJAAN SIPIL 6.71% 0.33% 0.47% 0.47% 2.35% 3.02% 0.05%
1 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. B type K1 0.30% 0.10% 0.10% 0.10%2 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. C type K1 0.30% 0.10% 0.10% 0.10%3 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. D type K1 0.12% 0.04% 0.04% 0.04%4 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. E type K1 0.30% 0.10% 0.10% 0.10%5 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 1 type B1 0.19% 0.06% 0.06% 0.06%6 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 2 type B1 0.08% 0.03% 0.03% 0.03%7 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3 type B1 0.15% 0.05% 0.05% 0.05%9 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 5 type B1 0.19% 0.19%
10 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. B type B1 0.35% 0.35%11 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. C type B1 0.12% 0.12%13 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. E type B1 0.35% 0.35%14 Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.29% 0.29%15 PEKERJAAN LISPLANG ATAP + PENUTUP CLADDING WALL
Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 Konsol Lisplang 0.13% 0.13%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 Lisplang 0.46% 0.46%
16 PEKERJAAN TANGGA UTAMAPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.03% 0.03%Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 3A type B1 0.06% 0.06%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.04% 0.04%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.41% 0.41%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.01% 0.01%Pek.Plesteran halus 1 : 4 0.01% 0.01%Pek. Acian 0.00% 0.00%Pek. Pengecatan 0.00% 0.00%
17 PEKERJAAN LIFT UTAMAPekerjaan Beton K-250 untuk Kolom 30/30 type K-2 0.15% 0.15%Pekerjaan Beton K-250 untuk Balok Anak 30/60 type B2 0.03% 0.03%Pekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.05% 0.05%Pek. Pas. 1/2 bata 1 : 4 setinggi + 4.00 0.07% 0.07%Pek.Plesteran halus 1 : 4 0.05% 0.05%Pek. Acian 0.03% 0.03%Pek. Pasangan pelapis Muka Lift bahan Marmer 0.08% 0.08%Pek. Pasangan pelapis Muka Lift bahan Granit Import 0.02% 0.02%
18 PEKERJAAN TANGGA DARURATPekerjaan Beton K-250 untuk Balok Anak 20/40 type B3 0.04% 0.04%Pekerjaan Beton K-175 un. Ring Balustrade 15/15 0.00% 0.00%Pekerjaan Beton K-250 untuk Plat lantai tangga T=12 cm 0.15% 0.15%Pek. Pas. 1/2 bata 1 : 4 setinggi 80 cm di lantai Tangga sisi tengah 0.02% 0.02%Pek.Plesteran halus 1 : 4 0.01% 0.01%Pek. Acian 0.01% 0.01%Pek. Pengecatan 0.01% 0.01%
F4. PEKERJAAN MEBELAIR DAN INTERIORG. LANTAI RUANG MESIN LIFT (+ 16.50)
G.1. PEKERJAAN SIPIL 1.18% 0.08% 0.08% 0.68% 0.35%1 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. B type K1 0.12% 0.04% 0.04% 0.04%2 Pekerjaan beton K-250 untuk Kolom Utama 50/50 posisi Cl. C type K1 0.12% 0.04% 0.04% 0.04%3 Pekerjaan beton K-250 untuk Kolom Utama30/30 posisi Cl. 3 type K2 0.05% 0.05%4 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. B type B1 0.09% 0.09%5 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl.C type B1 0.09% 0.09%6 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl. 2 type B1 0.08% 0.08%7 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl.3 type B1 0.08% 0.08%8 Pekerjaan Beton K-250 untuk Balok Utama 35/70 posisi Cl.3.A type B1 0.04% 0.04%9 Pekerjaan Beton K-250 untuk Balok Utama 20/40 posisi Cl.2.A type B3 0.01% 0.01%
10 Pekerjaan Beton K-250 untuk Balok Utama 20/40 posisi Cl.2C type B3 0.01% 0.01%11 Pekerjaan Beton K-250 untuk Balok Utama 30/60 posisi Cl.B1 type B2 0.08% 0.08%12 Pekerjaan Beton K-250 untuk Balok Utama 20/40 posisi Cl.B3 type B3 0.04% 0.04%13 Pek. Beton Praktis K-175 un. Kolom 15/15 0.02% 0.02%14 Pek. Beton Praktis K-175 un. Balok Latei 15/15 di atas Kosen pas.Ddn. 0.00% 0.00%15 Beton Praktis K-175 un.Canopy Jend (50x120x10) CL.B(4-5)-CL.5 0.01% 0.01%16 Beton Praktis K-175 un.Balok 15/20 Canopy Jend CL.B(4-5)-CL.5 0.00% 0.00%17 0.30% 0.30%16 Pek Beton K-250 untuk talang kantong t=10 cm lebar 90 dan balok 15/20 0.04% 0.04%
G.2 PEKERJAAN ARSITEKTURALG.2.1. PEKERJAAN PASANGAN DAN PLESTERAN 0.30% 0.30%G.2.2. PEKERJAAN LANTAI DAN PELAPIS DINDING 1.01% 1.01%G.2.3. PEKERJAAN KOSEN PINTU,JENDELA,ASSESORIES DAN KACA 1.67% 1.67%G.2.4. PEKERJAAN PENGECATAN 0.24% 0.24%
Pekerjaan Beton K-250 untuk plat lisplang/talang t=10 cm - U=1.50 m +.16.50Pekerjaan Beton K-250 untuk plat penutup Clidding Wall t=10 cm - +.17.30
Pek Beton K-250 untuk Plat lt atap tebal 12 cm ( + 16.50 )
Pek Beton K-250 untuk Plat lt tebal 12 cm ( + 20.52 )