PERHITUNGAN BEBAN ATAP BAHAN KAYU, BAJA TRUSS/GABLE GEOMETRI STRUKTUR JARAK GORDING ,BG 1M JARAK KUDA-KUDA ,LK 4M BENTANG KUDA-KUDA L 10 M KEMIRINGAN KUDA-KUDA a 25 DEGRE BEBAN 1 BEBAN AIR HUJAN ,Rai 5 KG/M2 2 BERAT GORDING 0 KG/M (User Option) C.125.50.20.2,0 3.95 KG/M (Optional) ,G 3.95 KG/M (Optional) 3 BERAT PENUTUP ATAP DAN RANGKA 0 KG/M2 (User Option) Penutup atap seng gelombang (BWG 24) tanpa gordeng 10 KG/M2 (Optional) ,GT 10 KG/M2 (Optional) 4 EXPOSED ,PL 0 5 BEBAN TEKANAN ANGIN < 40KM DARI LAUT ,W 40 KG/M2 6 Roof, No Access ,Lrf 100 KG/M2 7 BERAT SENDIRI KUDA-KUDA ,SW AUTOMATION PROGRAM SOLVER BEBAN MATI B. GORDING ,[G x BG] 3.95 KG Penutup atap seng gelombang (BWG 24) tanpa ,[GT x BG x LK] 40 KG EXPOSED ,[PL x BG x LK] 0 BM 43.95 KG B. LAIN-LAIN 5% BEBAN MATI , 5% BM 2.1975 KG P 46.1475 KG QDL 23.07375 KG/M BEBAN ANGIN KOEFISIEN ANGIN TEKAN, CT = (0.4-0.02(a)) -0.1 KOEFISIEN ANGIN HISAP, CH = [-0,4] -0.4 BEBAN TITIK ANGIN ANGIN TEKAN ,CT x BG x LK x -16 KG ANGIN HISAP ,CH x BG x LK x -64 KG BEBAN MERATA ANGIN QWL ANGIN TEKAN -16 KG/M ANGIN HISAP -16 KG/M BEBAN HIDUP SERVICE ,Lrf 100 KG/M BEBAN AIR HUJAN ,Rai 5 KG/M
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PERHITUNGAN BEBAN ATAP
BAHANKAYU, BAJA TRUSS/GABLE
GEOMETRI STRUKTURJARAK GORDING ,BG 1 MJARAK KUDA-KUDA ,LK 4 MBENTANG KUDA-KUDA L 10 MKEMIRINGAN KUDA-KUDA a 25 DEGRE
BEBAN1 BEBAN AIR HUJAN ,Rai 5 KG/M22 BERAT GORDING 0 KG/M (User Option)
BEBAN TITIK ANGINANGIN TEKAN ,CT x BG x LK x W -16 KGANGIN HISAP ,CH x BG x LK x W -64 KG
BEBAN MERATA ANGIN QWLANGIN TEKAN -16 KG/MANGIN HISAP -16 KG/M
BEBAN HIDUPSERVICE ,Lrf 100 KG/MBEBAN AIR HUJAN ,Rai 5 KG/M
QLL 105 KG/M
PERHITUNGAN BEBAN LANTAI
Lx Tul. Atas
Hslb dslab
Tul. Bawah
GEOMETRI STRUKTURTINGGI PLAT RENCANA ,Hslb = 0.12 MTINGGI FINISHING PLAT RENCANA ,Hslf = 0.06 MTINGGI DINDING BATA RENCANA , Hbata = 3.5 MTINGGI PARTISI RENCANA ,Hprt = 0 M
BERAT JENISBETON (1) 2200MORTAR 2000DINDING PAS. BATA MERAH SETENGAH BATU 250AIR 1000PLAFOND GYPSUM + RANGKA 17ME 7BEBAN HIDUP 300
BEBAN PLAT LANTAI BEBAN MATIBeban Mati Tambahan (Air) 0BERAT SENDIRI PLAT LANTAI , Hslb X BJ BETON (1) 0.12 X 2200 = 264Beban Finishing , Hslf x BJ MORTAR 0.06 X 2000 = 120Beban PLAFOND GYPSUM + RANGKA ME = 24TOTAL BEBAN MATI = 408
BEBAN HIDUP = 300
BEBAN PLAT LANTAI DAN PARTISI 0%BEBAN MATIBERAT SENDIRI PLAT LANTAI , Hslb X BJ beton 0.12 X 2200 = 264BERAT FINISHING LANTAI , Hslf X BJ finish 0.06 X 2000 = 120BERAT PROSENTASE PARTISI, % PARTISI XBJprt X Hprt = 0PLAFOND DAN INSTALASI ME = 24
KG/M³KG/M³KG/M³KG/M²KG/M²KG/M²KG/M²
TOTAL BEBAN MATI = 408
BEBAN HIDUP = 300
BEBAN PLAT LANTAI DAN PAS. BATA 35%BEBAN MATIBERAT SENDIRI PLAT LANTAI , Hslb X BJ beton 0.12 X 2200 = 264BERAT FINISHING LANTAI , Hslf X BJ finish 0.06 X 2000 = 120BERAT PROSENTASE PAS. BATA, % BATA XBJbata X Hbata = 306PLAFOND DAN INSTALASI ME = 24TOTAL BEBAN MATI = 714
BAHAN BANGUNANAIR 1000BAJA 7850BESI TUANG 7250BATU ALAM 2600BATU BELAH, BATU BULAT, BATU GUNUNG (BERAT TUMPUK) 1500BATU KARANG (BERAT TUMPUK) 700BATU PECAH 1450BOULDER STONE 1800KERIKIL, KORAL (KERING UDARA SAMPAI LEMBAP, TANPA DIAYA 1650PASIR (KERING UDARA SAMPAI LEMBAP) 1600PASIR (JENUH AIR) 1800PASIR KERIKIL, KORAL (KERING UDARA SAMPAI LEMBAP) 1850BETON (1) 2200BETON BERTULANG (2) 2400BETON BERTULANG MUTU TINGGI 2500RABAT BETON 2100BETON RINGAN 600GRANITE TILE 2600
HOTMIX 2200MORTAR 2000PASANGAN BATA MERAH 1700PASANGAN BATU BELAH, BATU BELAT, BATU GUNUNG 2200PASANGAN BATU CETAK 2200PASANGAN BATU KARANG 1450KAYU (KELAS I) (3) 1000TANAH, LEMPUNG DAN LANAU (KERING UDARA SAMPAI LEMBA 1700TANAH, LEMPUNG DAN LANAU (BASAH) 2000TANAH HITAM 1400
KG/M²KG/M²KG/M²KG/M²KG/M²
KG/M²
KG/M²KG/M²KG/M²KG/M²
DINDING PAS. BATA MERAH SATU BATU 450DINDING PAS. BATA MERAH SETENGAH BATU 250DINDING PASANGAN BATAKO BERLUBANG TEBAL DINDING 20 CM 200DINDING PASANGAN BATAKO BERLUBANG TEBAL DINDING 10 CM 120DINDING PASANGAN BATAKO TANPA LUBANG TEBAL DINDING 300DINDING PASANGAN BATAKO TANPA LUBANG TEBAL DINDING 200DINDING PARTISI 50
ASPAL, BAHAN-BAHAN MINERAL TAMBAHAN 14LANTAI KAYU SEDERHANA DENGAN BALOK KAYU, BENTANG MA 40PENUTUP LANTAI DARI UBIN SEMEN PORTLAND, TERASO DAN 24Ceramic tile + purlin 50ADUKAN, PER CM DARI SEMEN 21ADUKAN, PER CM DARI KAPUR, SEMEN MERAH ATAU TRAS 17GRANITE TILE 2600HOTMIX 2200MORTAR 2000EXPOSED 0
Momen ultimate rencana girder Mu = 135270.00Gaya geser ultimate rencana girder Vu = 135270.00
10. PEMBESIAN GIRDER10.1. TULANGAN LENTURMomen rencana ultimit Girder, Mu = 135270.00Mutu beton : K - 300 fc' = 24.9Mutu baja tulangan : U - 24 fy = 240Tebal slab beton, ts = 120Lebar badan Girder, b = 250Tinggi Girder, h = 400Lebar sayap T-Girder diambil nilai yang terkecil dari : L/4 = 6250
s = 250012 * ts = 1440
Diambil lebar efektif sayap T-Girder, beff = 2000 mm beff = 1440Jarak pusat tulangan terhadap sisi luar beton, d' = 150 mm d' = 30Modulus elastis baja, Es = 2.00E+05 MPa Es = 2.0.E+05Faktor bentuk distribusi tegangan beton, 0.85
Rasio tulangan minimum, rmin = 1.4 / fy = 0.0058333333Luas tulangan yang diperlukan, As = r * beff * d = 1006.96Diameter tulangan yang digunakan, D 16
201.06Jumlah tulangan yang diperlukan, n = As / As1 = 5.01
Digunakan tulangan, 6 D 16
As = As1 * n = 1206.371579Tebal selimut beton, td = 30Diameter sengkang yang digunakan, ds = 10Jumlah tulangan tiap baris, nt = 5Jarak bersih antara tulangan,
X = ( b - nt * D - 2 * td - 2 * ds) / (nt - 1) = 22.5> 35 mm CEK
b1 =
f =
Mn = Mu/f =
Rn = Mn * 106 / (beff * d2) =
As1 = p/4 * D2 =
Untuk menjamin agar Girder bersifat daktail, maka tulangan tekan diambil 30% tulangantarik, sehingga : As' = 30% * As = 422.23005264
Digunakan tulangan, 3 D 16
10.2. KONTROL KAPASITAS MOMEN ULTIMATE
Tebal slab beton, ts = 120Lebar efektif sayap, beff = 1440Lebar badan Girder, b = 250Tinggi Girder, h = 400Jarak pusat tulangan terhadap sisi luar beton, d' = 30Tinggi efektif T-Girder, d = h - d' = 370Luas tulangan, As = 1206.37Kuat tekan beton, fc' = 24.9Kuat leleh baja, fy = 240Untuk garis netral berada di dalam sayap T-Girder, maka : Cc > TsGaya internal tekan beton pada sayap,