FPSOs – THE “GO TO” DEVELOPMENT TECHNOLOGY FOR DEEPWATER DISCOVERIES
Jubilee Field Development: Project & Production Performance
Dr Gilbert Yevi – Jubilee Asset Manager, Tullow Ghana Limited – June 2013
Jubilee Field Development: Project & Production Performance – June 2013
ContentContent
S iSection Page
Oil Industry History in Ghana 3
Th J bil Fi ld 4The Jubilee Field 4
Development Project 5
J bil T d 8Jubilee Today 8
Local Content & Infrastructure 16
S & C l i 22Summary & Conclusions 22
Jubilee Field Development: Project & Production Performance – June 2013 Slide 2
Ghana – a short oil & gas industry historyGhana – a short oil & gas industry history
1900+• early land wells find oil & gas shows only
1957 Ghana gains independence• 1970 ‐ Signal Oil discovered Saltpond Field offshore Ghana, still producing c.500 bopd via MOPU
1983 GNPC established as statutory body with E&P responsibilities• legal and fiscal framework for E&P activities
• following shallow water discoveries sub‐commercial
21st Century shift to deepwater • since 2000 ‐ Significant number of deepwater exploration wells have been drilled in Ghana by international oil companies
• June ‐ July 2007 ‐Mahogany‐1/Hyedua‐1 wells discovery g y / ythe Jubilee field
• 2008 to 2011 – discoveries at Odum, Teak, Tweneboa, Enyenra, Akassa + also Paradise (Hess), Sankofa + GyeNyame (Eni), Dzata (Lukoil)
Jubilee Field Development: Project & Production Performance – June 2013
y ( ), ( )
Slide 3
The Jubilee FieldThe Jubilee Field
Fi t j il di i Gh• First major oil discovery in Ghana
• 130km west southwest of Takoradi port
• Discovered in 2007
• 370+ million bbl oil (P50)
• 60km offshore
• Water depth 1,000 ‐ 1,700mp
• Unitised between two blocks
Jubilee Field Development: Project & Production Performance – June 2013 Slide 4
Jubilee Reservoir Development (5 ll d ill d & 3 l t d i 8 ll Ph 1A b fi ld d l t j t i th t t )(5 more wells drilled & 3 completed in an 8 wells Phase 1A brown field development project since the start‐up)
Field Phase‐1 Cum. Oil (MMstb) 370 22 MMstb/Well 41 MMstb/Well
Phase 1 Producers 9
Jubilee Field Development: Project & Production Performance – June 2013
Phase‐1 Producers 9
Phase‐1 Injectors 8
Slide 5
Jubilee Field Layout – FPSO and Subsea EquipmentJubilee Field Layout – FPSO and Subsea Equipment
FPSO
Flexible Flowlines
Manifolds
Subsea Trees
Jubilee Field Development: Project & Production Performance – June 2013 Slide 6
Jubilee Project Delivery: the record 40 monthJubilee Project Delivery: the record 40 month
FPSO arrived
Licences awarded
Firstdiscovery
IPT andOperatorformed
Phase 1 DevelopmentPlan approved
in Ghana
First Oil
2004/2006 2007 2008 2009 2010
Discovery to First Oil – 31/2 years
• Shared objectives with Government and close working with GNPC• Involvement of all partners in the team, and regular interactionU f h l f i l d i d• Use of proven technology, functional spec, and experienced contractors
• Early start of development work• Rapid decision making
Jubilee Field Development: Project & Production Performance – June 2013
p g
Slide 7
Jubilee Field – Phase 1 schedule benchmarkingJubilee Field – Phase 1 schedule benchmarking
Jubilee Phase 1 scheme
La Ceiba
Zafiro
Kuito
Triton Energy
Exxon Mobil
Chevron
Early Production Systems/Phased Development
Baobab
Chinguetti
Laminaria
CNR
Woodside
Woodside
l
Full Field Development/Conventional Approaches
Girassol
Okume
Xikomba
Bonga
Total
Hess
Exxon Mobil
Shell Di t A dBonga
Anasuria
Jasmim
Kizomba A
Shell
Total
Exxon Mobil
Discovery to Award Appraisal & Develop
Execute (Award to 1st Oil)
Kizomba B
BBLT‐Blk 14
Auger TLP
Chevron
Exxon Mobil
Shell
Jubilee Field Development: Project & Production Performance – June 2013
0 1 2 3 4 5 6 7 8 9 10 11Discovery to First Oil (years)
Slide 8
Jubilee Project: Organization Set‐up for Record DeliveryJubilee Project: Organization Set‐up for Record Delivery
Making best useof available skills
TullowUnit Operator
KosmosTechnical Operator Anadarko
Liaison with Leading Integrated Providing key staff• Liaison with Government
• Well engineering• Manage production
• Leading Integrated Project Team (IPT)
• Planning and managing d l
• Providing key staff to Operator andIPT during development phase
Jubilee Field Development: Project & Production Performance – June 2013 Slide 9
Measurement of Project SuccessMeasurement of Project Success
“Classic” project execution KPI’sClassic project execution KPI s • EHS – all targets delivered in project & later operations• Cost• Schedule• Quality; reliability, uptime
Key high profile extra items in GhanaKey high profile extra items in Ghana• Organisation build• Environmental assessments & safeguards• Fisheries impact• Regulation establishment• Stakeholder engagement and shared benefitStakeholder engagement and shared benefit• Local employment, content & capacity• Gas industry initiation
Jubilee Field Development: Project & Production Performance – June 2013 Slide 10
Jubilee FPSOJubilee FPSO
• FPSO named the Kwame Nkrumah after the first President of GhanaPresident of Ghana
• Converted from an existing Very Large Crude Carrier (VLCC) tanker by MODEC in the Jurongshipyard, Singapore
• Lease with purchase options (FPSO purchased in December 2012)
• MODEC provide O&M services
• Conversion work commenced in November 2008 and FPSO arrived in Ghanaian waters June 2010. Start‐up November 2010
FPSO design scope:FPSO design scope:‐ 1.65 million barrel liquids storage capacity‐ 120,000 bopd production capacity‐ 230,000 bwpd water injection capacity, p j p y‐ 160 mmscfd gas injection/export capacity‐ 65m wide and 330m long‐ 17 modules weigh more than 12,500 tonnes
Jubilee Field Development: Project & Production Performance – June 2013
‐ 9 anchor legs in c.1,300m of water
Slide 11
Subsea InfrastructureSubsea Infrastructure
FPSO Kwame Nkrumah on the Jubilee FieldSubsea Equipment Quantity
Jubilee Field Development: Project & Production Performance – June 2013 Slide 13
Jubilee Phase 1 Well Construction
• Prior to 2008 Tullow had never drilled a deepwater wellassembled an experienced team and delivered!
Eirik Raude• 12 drill‐wells• 1 DST
Jubilee Phase 1 Well Construction
‐ assembled an experienced team and delivered!
• Drilled 14 new wells and re‐used 3 E&A wells‐ 47 km of new wellbore drilled
• 1 DST• 1 inj test• 1 gauge install
to do all completions+ 1 further drill‐well
• 3 year contract
Blackford Dolphin
• Drilling & completions make up ~50% of grossproject capex‐ drill‐ex ~$700 million‐ completions ~$900 million
• Vertical / deviated wells up to 85 degrees
• Frac pack completions planned for all producers& injectors
Cased Hole Frac Pack
Prod Packer
Tubing
Cased & Perforated with high set screen
Atwood Hunter
& injectors‐ some stacked frac‐packs now needed due to large height of sand
• Eirik Raude drilling operation benchmarked
Fluid LossValve
Prod Packer
Gravel Pack Packer
Laminated
independently to top quartile deepwater drilling performance in West Africa‐ experienced team built‐ excellent Contractor‐Operator working 9 5/8” Casing
Sump Packer
Laminated ZoneSand + Shale
Jubilee Field Development: Project & Production Performance – June 2013
p g‐ a major completions challenge in a new country
1 drill‐well
9 5/8 Casing
12 ¼” Holethrough Reservoir
Slide 14
Long Term Approach: Building Infrastructure Footprint for the Project
Accra HQ officeBuild‐lease
Long Term Approach: Building Infrastructure Footprint for the Project
Accra‐Takoradi air‐bridge~240km
Takoradi Supply + port base + office Dedicated new helo operation
FPSO
Tanker handling
Rig 1 Rig 2
• 240 direct employees; ~85% Ghanaian• Invested $40million+ so far
- in office, shorebase and logistics infrastructure