Payitem Tracking System (PTS)

September 19, 2014

Page 2: Payitem Tracking System (PTS) September 19, 2014.

• Hours of Availability• Type of Contracts• Authority• Location of PTS• Navigation• Stockpiles

- Creation of a Stockpile Component on Pay Item- Factors- Edit, Delete and Close Stockpiles- Add Inventory to a Component of a Stockpile- Add Additional Components to Pay Item that has been Stockpiled- Stockpile on Partial Pay Item (Operational Installation of Component)- Stockpile Report

Payitem Tracking System (PTS) Topics Covered

Page 3: Payitem Tracking System (PTS) September 19, 2014.

• Payments on Partial Pay Items and Regular Items- Partial Pay Items: Percentage Breakdown- Worksheet Summary- Divider, Links and Item types (Regular, Partial, Stockpile and Both)- Worksheet Details Page

- Recording the Installation of Stockpiled Item (An Item not identified as a Partial Pay Item with Operational Percentage)

- Record Installation of material component ‘Off the Truck’ when Item has current material components stockpiled.

- Record Installation of Partial Pay Item- Record Installation of Partial Pay Item with stockpiled material

components for separate operations- Record Installation of a Regular Pay Item

Payitem Tracking System (PTS) Topics Covered

Page 4: Payitem Tracking System (PTS) September 19, 2014.

• Transfer of Pay Quantity Data into SiteManager- Transfer Function- Estimate Detail Report - Transfer Pitfalls

• PTS after Estimate is Generated in SiteManager

Payitem Tracking System (PTS)Topics Covered

Page 5: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS) application

Hours of Availability6am – 9pm Monday – Friday 6am – 7pm SaturdayNo Guaranteed Availability on Sunday

Page 6: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS) application

Types of Contracts

All Construction contracts in SiteManager that were executed after 07/15/2014.

Note: there are some Construction contracts that were using PTS prior to this date. Use of PTS is still required on those contracts.

Page 7: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS) application

Who Has Access? Users who belong to the SiteManager Resident-Project Engineers users group will have full access to all PTS tabs.

Users who belong to the SiteManager Lead Inspector users group will have access to the Worksheet Summary tab.

The User requires SiteManager Contract Authority to their contract under the above users group.

Page 8: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS) application

How to get there?

Page 9: Payitem Tracking System (PTS) September 19, 2014.

TECHNICAL TOPICS

Select ‘CARS’

Construction

Automated

Reporting

System

Page 10: Payitem Tracking System (PTS) September 19, 2014.
Page 11: Payitem Tracking System (PTS) September 19, 2014.

Should you have questions or concerns you may contract the

State Construction Office (via E-mail by clicking this link) or call them.

Your District SiteManager Coordinator is available for you to.

Page 12: Payitem Tracking System (PTS) September 19, 2014.

NavigationBy Tabs

Page 13: Payitem Tracking System (PTS) September 19, 2014.

Help Tab

Links on the Help tab will open the Partial Payment User Guide

Page 14: Payitem Tracking System (PTS) September 19, 2014.

Partial Payment User Guide

By clicking on a Table of Contents Subject… the document will jump to that page.

Page 15: Payitem Tracking System (PTS) September 19, 2014.

Reports

This report shows All Items Eligible for Partial Payment with the partial

percentages for each item.

This is the same report found in the CPAM Section 5.11.3.2.

Page 16: Payitem Tracking System (PTS) September 19, 2014.

This report shows the percentages for each item for the selected contract.

Please print the report and provide a copy to the contractor during the pre-con.

Reports

Example on next slide

Page 17: Payitem Tracking System (PTS) September 19, 2014.

Example of Percentage Break Down

report

Payment on Contract Items identified as Partial Pay Items must be conducted through the Payitem Tracking System (PTS) Worksheet Tab

Page 18: Payitem Tracking System (PTS) September 19, 2014.

Reports

These Reports will be detailed later in this guide

- Stockpile- Estimate Details by Estimate- Estimate Details by Contract- WorkSheet Summary

Page 19: Payitem Tracking System (PTS) September 19, 2014.

Navigation Features Drop downs

- Can be changed anytime their present.- Will default to lead project first time a contract is selected- System will remember last contract and project selected

Page 20: Payitem Tracking System (PTS) September 19, 2014.

Navigation Features

Search boxes- Wild cards are not required. - Will search the Pay Item and Description for a match

Page 21: Payitem Tracking System (PTS) September 19, 2014.

Example of search box useNavigation Features

Enter a partial description

into Search Box

Returns list to match

Page 22: Payitem Tracking System (PTS) September 19, 2014.

Example of search box useNavigation Features

Enter a partial pay item number into Search Box

Returns list to match

Page 23: Payitem Tracking System (PTS) September 19, 2014.

StockPiles

Payitem Tracking System (PTS)

- Creation of a Stockpile Component on Pay Item- Factors- Edit, Delete and Close Stockpiles- Add Inventory to a Component of a Stockpile- Add Additional Components to Pay Item that has been Stockpiled- Stockpile on Partial Pay Item (Operational Installation of Component)- Stockpile Report

Page 24: Payitem Tracking System (PTS) September 19, 2014.

To Add New Line Item Stockpile Click ‘Add Line Item’ link.

Note: When first entering the Stockpile Tab,No Stockpile data exist. The No records found

warning will appear.

Stockpile

Page 25: Payitem Tracking System (PTS) September 19, 2014.

All items (that may be Stockpiled) under the Financial Project Number

will be shown to select from.

Project selected... may select other projects under contract.

Stockpile

Note: Once a non-Partial Pay Item is Stockpiled, All payments will be conducted

through the PTS Worksheet Detail.

Page 26: Payitem Tracking System (PTS) September 19, 2014.

Search for Pull Boxes

Select Item to Stockpile

Stockpile

Page 27: Payitem Tracking System (PTS) September 19, 2014.

SiteManager Item Data

Stockpile data to be entered

Item Selected

Stockpile

Page 28: Payitem Tracking System (PTS) September 19, 2014.

Stockpile

The Description is the description on the invoice of the materials being supplied to the contractor. You have 60 characters to work with.

The Invoice Qty is the quantity reported on the invoice of the material being shipped.

The Invoice Number is the number assigned by the Supplier to the Contractor for this shipment of materials.

The invoice Amt is the dollar amount of the invoice that pertains to the materials being stockpiled. This dollar amount could include taxes and shipping cost.

The Unit Price will be automatically populated for you when you enter inthe Factor.

Page 29: Payitem Tracking System (PTS) September 19, 2014.

Stockpile

The Location is a description of the physical location of the materials being stockpiled. You have 60 characters to work with.

The Factor is the conversion factor of the invoiced material vs. the material in place.

Page 30: Payitem Tracking System (PTS) September 19, 2014.

StockpileFactor

Pull Boxes

How you determine the factor

Simply put, the Factor is the ratio of Stock Units to Constructed Units.

Factor = Stock Units / Constructed Units

Stock Unit = Pull Box

Stock Unit = Pull Box Lid

FDOT Pays for Unit Price for 1 Pull Box Installed

Q: How much stock does it take to construct one FDOT unit in the ground ? Pull Box Stock (Material Invoiced) at EA

Pull Box (Material in Place) paid at EA= Factor of 1 for Pull Box Stockpile

1 Stock - Pull Box Lid

1 FDOT pays unit in ground –Pull Box= Factor of 1 for Pull Box Lid Stockpile

Page 31: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Guardrail Panels Stock Unit = LF

FDOT Pays for Guardrail by the LF

Q: How much stock does it take to construct one FDOT unit in the ground ?

Stock 1 LF (Material Invoiced per LF)

Guardrail (Material in Place) paid at 1 LF= Factor of 1 for Stockpile Guardrail Panels

StockpileFactorGuardrail

Page 32: Payitem Tracking System (PTS) September 19, 2014.

Stock Unit = Guardrail Posts (each)

Q: How much stock does it take to construct one FDOT unit in the ground ?

* From Design Standards *1 post is to be constructed per

every 6.25 feet of guardrail

= 0.16 Factor for Guardrail Posts

StockpileFactor

Guardrail Posts

FDOT pays for Guardrail by the LF

Stock (1 post)

6.25 LF (Constructed Guardrail)

Page 33: Payitem Tracking System (PTS) September 19, 2014.

StockpilePull Boxes Example

Page 34: Payitem Tracking System (PTS) September 19, 2014.

Starting at Invoice Number

use tab key to tab between data fields

StockpilePull Boxes Example

Page 35: Payitem Tracking System (PTS) September 19, 2014.

The PTS application will populated and calculate these Data Fields

StockpilePull Boxes Example

Page 36: Payitem Tracking System (PTS) September 19, 2014.

Article 9-5.5.2 (2)

- Partial payments for structural steel and precast prestressed items will not exceed 85% of the bid price for the item.

- Partial payments for all other items will not exceed 75% of the bid price of the item in which the material is to be used.

StockpilePull Boxes Example

If the Invoice Amount exceeded the limits specified in Standard Specifications Article 9-5.5.2 (2) then PTS would decrease dollar amount

of the Invoice Amount Paid to the specification percentage allowed.

Page 37: Payitem Tracking System (PTS) September 19, 2014.

Selecting the Create button saves the Stockpile

StockpilePull Boxes Example

Page 38: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Created

Click “+” to expand

Click “-” to collapse

StockpileDetail

Page 39: Payitem Tracking System (PTS) September 19, 2014.

If you click on the Invoice Number link, you will be able to view but not edit the information you entered for the material.

Stockpile Pull Boxes Example

Page 40: Payitem Tracking System (PTS) September 19, 2014.

To edit the Stockpile Record

To delete the Stockpile Record

You can “Close” out a stock pile. You would do this when you have paid on the Initial stockpile and you no longer need any of the stockpile materials.

The application will deduct the quantity previously paid on an estimate from the original stockpile quantity. The application will create a negative DWR quantity that will generate the dollar amount that will need to be deducted from the Contractor’s payment.

You are encouraged to provide some explanation as to why the stockpile is to be closed out. If you don’t supply an explanation, the system will default to “Close Out” as the reason. Once you enter your explanation, click on “OK”.

Stockpile Pull Boxes Example

Page 41: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Adding Inventory

Adding inventory to a stockpile that was previously added through the PTS application.

New stock material is like the original stock material.

Page 42: Payitem Tracking System (PTS) September 19, 2014.

To replenish a stockpile that you previously added through the application, click on the “Add Inventory” link.

- Only do this if the new material is like the original material.

Adding Inventory will create a Replenish Sequence Id.

Stockpile Add Inventory Example Pull Boxes

Page 43: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Add Components

Adding a new component to item that was previously stockpiled.

For new stock material that is different than the original stock material that was previously added through the PTS application..

Page 44: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Add Component Example Guardrail

Components: Sometimes invoices received will contain various components of a pay item.

Example: Guardrail posts and rail panels. Same item with 2 components.

Page 45: Payitem Tracking System (PTS) September 19, 2014.

Stockpile Partial Pay Items - Operations

Stockpiles can be required on Partial Pay Items. Items with Operationally-Sequenced Installation of Components.

Page 46: Payitem Tracking System (PTS) September 19, 2014.

Items identified as Partial Pay Items may have components that can be stockpiled.

Stockpile data entered

Operation of component to be installed

StockpilePartial Pay Items

Operations

Page 47: Payitem Tracking System (PTS) September 19, 2014.

Select the Operation in which the component ‘Inlet Bottom’ will be installed.

StockpilePartial Pay Items

Operations

Page 48: Payitem Tracking System (PTS) September 19, 2014.

StockpilePartial Pay Items

Operations

Select the Operation in which the component ‘Inlet Risers’ will be installed.

Page 49: Payitem Tracking System (PTS) September 19, 2014.

StockpilePartial Pay Items

Operations

Select the Operation in which the component ‘Inlet Tops’ will be installed.

Page 50: Payitem Tracking System (PTS) September 19, 2014.

StockpilePartial Pay Items

Operations

Page 51: Payitem Tracking System (PTS) September 19, 2014.

StockpileReport

Page 52: Payitem Tracking System (PTS) September 19, 2014.

StockpileReport

Page 53: Payitem Tracking System (PTS) September 19, 2014.

WorksheetPayitem Tracking System (PTS)

• Partial Payments- Partial Pay Items: Percentage Breakdown- Worksheet Summary- Divider, Links and Item types (Partial, Stockpile and Both)- Worksheet Details Page

- Recording the Installation of Stockpiled Item (An Item not identified as a Partial Pay Item with Operational Percentage)

- Record Installation of material component ‘Off the Truck’ when Item has current material components stockpiled.

- Record Installation of Partial Pay Item- Record Installation of Partial Pay Item with stockpiled material

components for separate operations

Page 54: Payitem Tracking System (PTS) September 19, 2014.

Worksheet

This report shows the percentages for each item for the selected contract.This is the same report from the Reports Tab (Items Eligible for Partial Payment By Contract)

Percentage Break Down Report

Please print the report and provide a copy to the contractor during the pre-con.

Recording payment on Contract Items identified as Partial Pay Items must be conducted through the Payitem Tracking System (PTS) Worksheet Tab

Page 55: Payitem Tracking System (PTS) September 19, 2014.

WorksheetWork Sheet Summary Report

This report is used to show the quantities that will be transferred to SiteManager. This report needs

to be reviewed before transferring items.

Page 56: Payitem Tracking System (PTS) September 19, 2014.

Worksheet Layout

Project selected... may select other projects under contract.

Page 57: Payitem Tracking System (PTS) September 19, 2014.

Worksheet LayoutDividers

Item data on the Right is from New System PTS app

Item data on the Left is from SiteManager

Page 58: Payitem Tracking System (PTS) September 19, 2014.

Worksheet Layout..

Links

Link on the far right. Takes user to the Work

Sheet Details page.

This link is to the page where users will record the installation of items

Link on the far left provides additional details

for selected pay item

Page 59: Payitem Tracking System (PTS) September 19, 2014.

Items Shown

All Items will be shown except Contingency Items.

The items the system identified as partial and items stockpile record(s) are delineated from the regular pay

items.

Examples: P 0400 Item eligible for partial payment

S 0860 Item where Stockpile has been recorded

B 0405 Item that is both an eligible for partial payment and has Stockpile has been recorded

R 0130 Regular items (Items not identified as a Partial Pay Items)

Worksheet Layout

Page 60: Payitem Tracking System (PTS) September 19, 2014.

Quantities from Stockpiles B 0405 Partial Payment with recorded Stockpile

S 0590 Item where Stockpile has been recorded

S 0860 Item where Stockpile has been recorded

Once an Item is Stockpiled (ie S 0590 ) ALL payments on that Item will then be conducted through the Payitem Tracking System (PTS) Worksheet Tab

Worksheet

Page 61: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecording the Installation of Stockpiled Item

* A Regular Item (Item not identified as a Partial Pay Item with Operational Percentage )*

Page 62: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecording the Installation of Stockpiled Item* Regular Item (Item not identified as a Partial Pay Item with Operational Percentage) *

Searched for ‘PED’ item

Found S 1440 where Stockpile has been recordedDWR Qty of 3.675 represents the value of the Contractor’s

Stockpile request for the ItemClick on this DWR Qty link

( 3.675 ) to go to the Work Sheet Details page.

Find Item 653191 Pay for 5 Each

Pedestrian Signals from Stockpile

Page 63: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Work Sheet Details page

Work Sheet Details page for

PayItem 0953191 FinProj 411042-1-52-01 Contract 40032

Note: DWR Qty & DWR Qty This Est represent the value of the Contractor’s Stockpile request for the Item.

Page 64: Payitem Tracking System (PTS) September 19, 2014.

Work Sheet Details page for

PayItem 0953191 FinProj 411042-1-52-01 Contract 40032

Click ‘New Entry’ to open Payments Column

Recorded Installations will be entered Stockpile/Full Payments column

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Work Sheet Details page

Page 65: Payitem Tracking System (PTS) September 19, 2014.

New Line is created on page for Stockpile/Full Payments column

Enter Qty Reported

Enter RemarkSave

Pay for 5 Each Pedestrian Signals

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Work Sheet Details page

Page 66: Payitem Tracking System (PTS) September 19, 2014.

Note: DWR Qty & DWR Qty This Est updated to include the value of the work to install the 5 pedestrian signals.

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Work Sheet Details page

Page 67: Payitem Tracking System (PTS) September 19, 2014.

Informational Pop-up boxes appear when you mouse-over the Rem% and StkPl% fields

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Work Sheet Details page

Page 68: Payitem Tracking System (PTS) September 19, 2014.

Back to WorkSheet Summary

DWR Qty for Est is updated to include the value of the 10 pedestrian signals stockpiled, of which 5 pedestrian signals were install.

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Page 69: Payitem Tracking System (PTS) September 19, 2014.

Find Item 653191 Pay for 5 Each

Pedestrian Signals “off the truck”

Pay on same item but not from a stockpile

Created a New Line on page for Stockpile/Full Payments column

Click ‘New Entry’ to open Payments Column

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Page 70: Payitem Tracking System (PTS) September 19, 2014.

Enter Remark

Enter Qty Reported installed

‘Off the Truck’

Mark as Full PayItem was not taken from a stockpile.

The item came in ‘Off the Truck.’

This will not draw down the Stockpile

Pay for 5 Each Pedestrian Signals “off the truck”

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Page 71: Payitem Tracking System (PTS) September 19, 2014.

The DWR Qty & DWR Qty This Est has been updated to include the value of the 5 pedestrian signals for both furnish and install.

Field saved. Paid for 5 Each Pedestrian Signals “off the truck”

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Page 72: Payitem Tracking System (PTS) September 19, 2014.

DWR Qty for Est is updated to include the value of the 10 pedestrian signals stockpiled, of which 5 pedestrian signals were install plus 5 more pedestrian signals which where not stockpiled but brought in ‘off the truck.’

Back to WorkSheet Summary

WorksheetRecording the Installation

of Stockpiled Item* Regular Item *

Page 73: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of Partial Pay Item

No previous Stockpile

Page 74: Payitem Tracking System (PTS) September 19, 2014.

Searched for ‘TYPE B’ item

Find Item 0425 1511

Pay for 1 bottom installed & Pay for 1 complete Item Installed

Found P 0565 This Item is eligible for partial paymentClick on this DWR Qty link

( 0.000 ) to go to the Work Sheet Details page.

WorksheetRecord Installation of Partial Pay Item

No previous Stockpile

Page 75: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item(No previous Stockpile )

Pay for 1 bottoms installed

Enter Remark. Example: Structure Number

Only enter whole numbers. 1 each in this example.Do not enter percentage of a quantity.

Save

Pay for 1 bottoms installed

Page 76: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item(No previous Stockpile )

Pay for 1 complete Item Installed

Click New Entry

Page 77: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item(No previous Stockpile )

Only enter whole numbers and Remark (ex. location)

Pay for 1 complete Item Installed

When New Entry is clickedNew Entry Line Appears

To pay for completed item select All Operations box

Note: When all of the operation is completed

“RISER, TOP, GRATE, AND APRON INSTALLED ”

The last 35% may be paid.

Page 78: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item(No previous Stockpile )

When All Operations box is checked, PTS will populate remaining

operation fields upon saving. Pay for 1 complete Item Installed

Page 79: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item(No previous Stockpile )

Return to WorkSheet Summary show DWR Qty for estimate

Page 80: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of Partial Pay Item

With stockpiled material components

Page 81: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item* with stockpiled material components

Inlets 425 1543 4 bottoms and 2 risers/tops

Find Item 0425 1543

Pay for 4 bottom installed Pay for 2 Riser, Top, Grate and Apron Installed.

Searched for ‘425’

Click on this DWR Qty link ( 4.515 ) to go to the

Work Sheet Details page.Found B 0405 This Item is both an eligible for partial payment and has Stockpile has been recorded

Page 82: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item* with stockpiled material components

Pay for 4 bottoms installed

Enter Remark. Example: Structure Numbers

When New Entry is clickedNew Entry Line Appears

Note: Stockpile Data

is shown.

Operation: BOTTOM INSTALLED

Only enter whole numbers. 4 each in this example. Do not enter percentage of a quantity.

Save

Page 83: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item* with stockpiled material components

Pay for 2 Riser, Top, Grate and Apron Installed.

Operations dictate the Riser, Top, Grate and Apron cannot be installed unless

the Bottom is Installed.

PTS will not allow payments out of

operational sequence.

Enter Remark Example: Structure Numbers

Operation: RISER, TOP, GRATE, AND APRON

INSTALLED

Only enter whole numbers. 2 each in this example. Do not enter percentage of a quantity.

Save

Page 84: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item* with stockpiled material components

Example of payment Out of Sequence

Only 4 bottoms have been installed.

Attempt to pay for 5th “Riser, Top, Grate and Apron”

failed.

Page 85: Payitem Tracking System (PTS) September 19, 2014.

WorksheetRecord Installation of

Partial Pay Item* with stockpiled material components

Return to WorkSheet Summary show DWR Qty for estimate

Page 86: Payitem Tracking System (PTS) September 19, 2014.

WorksheetWork Sheet Summary Report

This report is used to show the quantities that will be transferred to SiteManager. This report needs

to be reviewed before transferring items.

Page 87: Payitem Tracking System (PTS) September 19, 2014.

WorksheetWork Sheet Summary

Report

Page 88: Payitem Tracking System (PTS) September 19, 2014.

TransferPayitem Tracking System (PTS)

Function transfers all pay item pay quantities that deal with Partial Pay Items and Stockpiled Materials from

PTS into a SiteManager Daily Work Report (DWR).

Page 89: Payitem Tracking System (PTS) September 19, 2014.

TransferThe Transfer screen will allow you to select the ending date of the estimate period.

It is recommended to use the Estimate Cut-Off Date for transfers

If the DWR exists in SM under your UserId for the date and it is locked (authorized) the System will not update that DWR and will present an error message.

- The date will be the date of the new DWR created in SiteManager for the transferred PTS quantities.

- The new DWR in will be created under your UserId.

- If a DWR exists in SM under your UserId for the date you have selected and the DWR is not locked (authorized), the System will use that DWR and add the PTS quantities there. This will allow you to add all pay items not tracked through the PTS application on that DWR, then transfer the PTS quantities on to the DWR.

Page 90: Payitem Tracking System (PTS) September 19, 2014.

TransferSelect a date by double clicking in the date field to bring up the calendar – or

type over with your date.

Page 91: Payitem Tracking System (PTS) September 19, 2014.

Transfer

With date selected click Submit to transfer.

Page 92: Payitem Tracking System (PTS) September 19, 2014.

Transfer

Transfer Successful

Items and quantities transferred are shown

Page 93: Payitem Tracking System (PTS) September 19, 2014.

Transfer

New DWR created in SiteManager.

Transferred PTS quantities shown

on DWR

Page 94: Payitem Tracking System (PTS) September 19, 2014.

TransferNote: All quantities from

PTS application will be added to SM under the

Prime Contractor

Once quantities have been transferred from the PTS Application to the DWR, that DWR may be used to add all other quantities for the period.

Also the location field was updated by PTS as “See

Estimate Detail Report.” However, to run this PTS

report the estimate must first be generated in SiteManager.

Page 95: Payitem Tracking System (PTS) September 19, 2014.

Transfer

DWR Authorized

Estimate Generated

Page 96: Payitem Tracking System (PTS) September 19, 2014.

Transfer

After the SiteManager estimate is generated…

Run the PTS “Estimate Detail Report.”

Page 97: Payitem Tracking System (PTS) September 19, 2014.

Transfer

Select Contract and Estimate Number

Submit

Page 98: Payitem Tracking System (PTS) September 19, 2014.

The Estimate Detail Report will be attached to the SM/TSO estimate

posted on the Department’s website

Page 99: Payitem Tracking System (PTS) September 19, 2014.

It is recommended to Transfer PTS quantities only ONCE

for the Monthly Estimate period.

Since the Transfer function creates a DWR for the date specified,

multiple transfers on different dates during the estimate period

will create duplicate quantity payments, which if not caught

would result in overpayment to the contractor.

PTS Pitfalls

Page 100: Payitem Tracking System (PTS) September 19, 2014.

PTS Pitfalls

Also, issues arise when quantities on Partial Pay Items or Stockpiled Materials are entered directly on to DWR(s) in SiteManager (the PTS is not used).

Since the PTS System reads SiteManager unequal estimate quantities between the two systems are flagged.

Page 101: Payitem Tracking System (PTS) September 19, 2014.

Example of issue with quantities entered into SiteManager that do not match PTS.

In this case Worksheet Summary Items highlighted in RED are a result of quantities on Partial Pay Items were entered directly on to DWR in SiteManager – PTS was not used.

PTS Pitfalls

Page 102: Payitem Tracking System (PTS) September 19, 2014.

The Exclude Items tab will open a column that will enable you to mark items not to be transferred (before clicking Submit)

This tool is helpful when there is a possible issue with quantities entered into SiteManager that do not match PTS.

Excluding Items when transferring can bring the two systems in balance

Exclude items from transfer (before clicking Submit)

PTS Pitfalls

Page 103: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS)After SM Estimate Generation

What PTS should look like after an estimate in SiteManager has been generated.

Page 104: Payitem Tracking System (PTS) September 19, 2014.

After SM Estimate GenerationAfter the SM estimate is generated…

the PTS Worksheet Summary Shows the SiteManager and PTS

quantity information are in balance.

Page 105: Payitem Tracking System (PTS) September 19, 2014.

After SM Estimate Generation

After the SM estimate is generated…PTS input may begin for the next DWR Qty for the next estimate.

PTS entries may begin as long as the last estimate exists in SM. That estimate may be pending approval in SM to the next level or awaiting payment in EED.

Page 106: Payitem Tracking System (PTS) September 19, 2014.

After SM Estimate Generation

If for some reason Est# 0001 is deleted in SiteManager, the values entered in PTS for the next estimate (Est# 0002) are not lost. They will not be viewable in PTS when Est# 0001 does not exist in SM.

When Est# 0001 is regenerated in SM, the stored PTS DRW Qty for Est# 0002 will reappear… as PTS will now be back on the Current Estimate (Est# 0002).

PTS input conducted for future Est #0002.

Page 107: Payitem Tracking System (PTS) September 19, 2014.

Payitem Tracking System (PTS)Questions - Comments

If you have questions

Contact your SiteManager Coordinator

In you District.