Asset Management today Set Goals and Objectives Collect Inventory and Condition Data Rates of Deterioration Performance Standards & Measures Life-Cycle Cost Analysis Investment Strategies Programs, Projects, and Practices Monitoring Feedback and Adjustments
Design and Implementation of Road Maintenance Reform. Republic of Moldova
For any kind of planning (programme, Project)!
We need Data/Information:
Road Network
Work standards
Traffic data (Vehicle Fleet)
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Before 1 December 2010 We need
- More than 1? If so:- SPECIFY
- Visualizing section’s conditions- Map (GIS)
-Verify -Cost estimates-Maintenance activities
-Routine-Periodic
- Rehabilitation- Terminology
- VF available- Previous studies?
- Purchase of new traffic counter will be recommended
Design and Implementation of Road Maintenance Reform. Republic of Moldova
GISData collection
Evaluation
0-500 500-1500 1500-40004000-7000 7000-0
20
40
60
80
100
120
Systems
Asset EvaluationCost-BenefitsMinistry, RA, RU
Condition Data and analysis
Visual inspections
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Condition Data and analysis
Need for Inspection Manual- Course will be recommended
IRIPurchase of newequipment will be recommended-For this study:- 900 km of:-National and Secondary roads
- HDM 4- Purchase will be recommended
- Overview next week:- Programme- Project
− Modelling RN− Review results− Writing report
Next week
Script for selection of Homogenous sectionsis available
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Information, Data What kind of information do we need?
It is always dependent on: What decisions do we need to make? What information/data are required to make these
decisions? Can we afford to collect the data? If it needs updating, can we afford to keep data current over
time?
Guiding Principle Collect only the data you need! Collect it only when you need to! The level of detail should be appropriate for the decisions
being made: Network level data for network level analyses project level for project level analyses
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Calibration of Condition DataFor Program Analysis
STEP BY STEP
Design and Implementation of Road Maintenance Reform. Republic of Moldova
What to be Calibrated?
Distress Mode
All Structural Cracking
(%)
Wide Structural Cracking
(%)
Transverse Thermal Cracking
(%)
Ravelling (%)
No. potholes per km
Edge break (m² per km)
Mean rut depth (mm)
New 0 0 0 1 0 0 2
Good 5 0 0 10 0 10 5
Fair 15 9.5 0 20 5 100 15
Poor 20 15 0 25 20 200 20
Bad 25 19 0 30 50 300 25
Design and Implementation of Road Maintenance Reform. Republic of Moldova
How to calibrate?
1. Select Sections in different condition– Good to Bad using data in existing PMS– Use Agreed criteria for IRI:
Road Class
Paved Roads Unpaved Roads
Good Fair Poor Bad Good Poor Bad National Roads 4 6 8 >8 - - -Secondary 5 7 9 >9 6 8 10
Design and Implementation of Road Maintenance Reform. Republic of Moldova
2- Inspect selected section in different condition as follows:a) Randomly choose 3 sections of
100 mI. Each section has to be marked
GPS, or other means
b) Use inspection manual, describe distresses
c) Fill the protocol for each section of 100I. Severity II. Propagation of distresses
d) Estimate distresses severity and propagation and calibrate HDM4 configuration
Design and Implementation of Road Maintenance Reform. Republic of Moldova
2. Inspection Manual Shall contain the following
1. Definition of different distresses– Cracking along wheel patch– Alligator cracking– thermal Cracking, etc…
2. Severity– Rutting:
– S1 < 10 mm– S2 >10 and < 20 mm– S3 > 20 mm
3. Propagation/distribution/Spreading – Local < 10% of the total
section’s length– Moderate > 10% <50% of the
total section’s length– General > 50% of the total
section’s length
4. Method of measurement5. Protocol for inspection
(papers or digital)
Exam
ple
Exam
ple
Exam
ple
Exam
ple
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Inspection Manual
Recommendation
1- Study Existing Manual,
2- Identify described distresses in the existing manual and compare with default distresses in HDM4
3- Prioritize which distresses can be measured today
4- Method of measurements for each distresses
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Data collection for Project analysis
For Project analysis we need detailed data
Working only on the section o be repaired
Identifying distresses following the Inspection manual Exa
mple
Project 2 km
Section A
-B