-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 7Information Document Revision 1 24 June 2011
3. PAVEMENT DESIGN
3.1 INTRODUCTION
Volume 2 Exhibit D Special Specifications Part DI Employers
Requirementsdetails the following salient consideration for the
airfield pavements:
1. The pavement design for the various airfield elements shall
comply with theFederal Aviation Administration FAA standards and
proposed practices.
2. For flexible pavement type - layered flexible pavement shall
be consideredincluding the following exclusive succession of layers
from top to bottom:bituminous concrete surface course, tack coat,
bituminous base course,prime coat, unbound crushed aggregate base
and/or aggregate sub-basecourses, compacted subgrade, and natural
subgrade etc.
3. For rigid pavement - jointed plain concrete pavement (JPCP)
shall beconsidered with adequately spaced contraction joints, while
using dowelbars for load transfer across joints (it is assumed that
dowelling is only inone direction). Jointed reinforced concrete
pavement (JRCP) shall be usedonly when odd shaped slabs are
encountered. For the rigid Jointed PlainConcrete Pavement, layered
rigid pavement shall be considered includingthe following exclusive
succession of layers from top to bottom: PortlandCement Concrete
Slab, cement or asphalt treated base course, unboundcrushed
aggregate base and/or aggregate subbase courses,
compactedsub-grade, and natural sub-grade.
4. The properties of the subgrade soil shall be studied in order
to determinethe corresponding subgrade soil design parameters (CBR,
Modulus ofElasticity, Modulus of subgrade reaction, etc.).
5. The airfield fleet mix using KAIA shall be analyzed and
generated for thedesign life, taking into account the annual growth
in air traffic.
6. The distribution of the aircraft loading around the various
zones of theairport and consequently the anticipated load on each
airfield element shallbe determined separately.
7. The airfield pavement design shall be carried out using the
latest state-of-the-art computer programs (software) that cater for
the large body aircraftwheel configuration such as the A380, A340,
B777, B747, AN225, etc. andthat can account for the wander effect
in order to optimize the resultingpavement thicknesses. Fatigue
equations shall conform to therequirements of the US Corps of
Engineers for asphalt concrete andgranular materials and subgrade
and to those of the Portland CementAssociation for cement
concrete.
8. The pavement design of shoulder shall be checked to
accommodateoccasional passages of critical aircrafts considered in
pavement design andthe critical axle load of emergency or
maintenance vehicles which maypass over the area, according to the
International standards.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 8Information Document Revision 1 24 June 2011
3.2 BASIS OF DESIGN
3.2.1 Overview
The pavement design for the aircraft pavements associated with
the developmentof the Saudi Aerospace Engineering Industries
Aircraft Maintenance Hangars,Jeddah - individual hangar pavements,
external apron, Taxiway MA and TaxilaneLB, has considered a range
of factors including:
The existing site conditions
Existing subsoil conditions
Proposed operating conditions
Current and proposed aircraft types
Aircraft wheel and body jacks
Aircraft tugs
Emergency service vehicles
Concrete strength
This report presents a summary of the key assumptions and input
data used todevelop the designs for the individual hangar
pavements, external apron,Taxiway MA and Taxilane LB in terms
of:
Aircraft loads
Aircraft tug loads and operating frequency
Aircraft jacking operations
Frequency of operations
Subsoil strength
Concrete strength (for rigid) pavements
Emergency service vehicle loads and operating frequency
A number of design scenarios have been considered in developing
the pavementthicknesses. These design scenarios were undertaken to
test the sensitivity ofthe pavement thickness for both rigid and
flexible pavements to variations in thedesign assumptions in terms
of:
Frequency of aircraft operations
Frequency of jacking operations
Subsoil strength
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 9Information Document Revision 1 24 June 2011
The results of the individual analyses are summarized in this
report, whilecomplete details are included in Appendices C and
D.
3.2.2 Pavement Types
Flexible Pavements
Flexible pavements generally consist of a dense, hot mix asphalt
surfacingplaced on an unbound crushed aggregate base and/or
aggregate sub-basecourses), and the pavement is then supported by
the subgrade. The design forSaudi Aerospace Engineering Industries
Aircraft Maintenance Hangars is beingcarried out using the U.S.
Department of Transportation Federal AviationAdministration (FAA)
design program FAARFIELD, used in conjunction with theFAA Advisory
Circular (AC) 150/5320-6E. This AC includes guidelinerequirements
for the various materials for the pavement layers. Where the
ACrequires engineering judgement regarding the material to be used
this is detailedand justification for the choices made is
given.
For flexible pavement design, FAARFIELD uses the maximum
vertical strain atthe top of the subgrade and the maximum
horizontal strain at the bottom of theasphalt surface layer as the
predictors of pavement structural life. FAARFIELDprovides the
required thickness for all individual layers of flexible pavement
(inthis case surface, base and sub-base) needed to support a given
aircraft trafficmix over a particular subgrade for the given design
period.
Rigid Pavements
The basic composition of an airfield rigid pavement is a
Portland cement concrete,PCC (which is often referred to as
Pavement Quality Concrete PQC), on agranular or stabilised sub-base
supported on the in-situ subgrade after suitablecompaction. The
purpose of a base course under a rigid pavement is to
provideuniform stable support for the pavement slabs, and support
across the joints. Aminimum thickness of 100mm of base is required
under all rigid pavements.According to FAA, stabilized materials
are required for a base course under rigidpavements serving
airplanes weighing 45,359kg or more to improve load transferacross
joint lines and reduce pumping type erosion effects due to flexure
of theslabs at the joint lines.
For rigid pavement design, FAARFIELD uses the maximum horizontal
stress atthe bottom edge of the PQC slab as the predictor of
pavement structural life. Themaximum horizontal stress for design
is determined using an edge loadingcondition with approximately 30%
load transfer to the adjacent slab.
Once load transfer exceeds 40% across a joint line the interior
thickness of theslab then becomes the critical element. Localised
thickened edges are requiredat transitions from concrete to
asphaltic surfacing or at box outs for manholes,service pit, grated
drains, etc. FAARFIELD provides the required thickness of therigid
pavement slab needed to support a given aircraft traffic mix over a
particularsubgrade/base course for the given design period. The
life of the concretesurfacing is very sensitive to changes in slab
thickness, and the stiffness of theimmediate supporting layer.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 10Information Document Revision 1 24 June 2011
The required thickness of concrete pavement is related to the
strength of theconcrete used for construction of the pavement. For
airfield pavement design, thestrength of the concrete is
characterized by the flexural strength (since theprimary action and
failure mode of a concrete pavement is in flexure), rather thanthe
more commonly used unconfined crushing strength tests (UCS)
associatedwith building works.
The construction of rigid pavements will be done in slabs which
are as square aspossible, and with joints spaced to minimize the
warping stresses that occur dueto variations in temperature and
moisture. These joints also act to minimizerandom cracking. Slab
thickness relates to joint spacing with slabs typically
beingjointed at between 4.5 and 5.0m (slab size is a ratio of
typically 12-15 times theslab thickness).
In the direction of paving, joints will be saw-cut across the
paving lane when theconcrete has reached sufficient strength
(contraction joints). This will act toinduce cracking of the
pavement at these locations. In the transverse direction,joints
will be dowelled to ensure effective load transfer across the
joints (dowelledconstruction joints).
Pavement Joints
Pavement joints and transitions are of particular importance in
a successfulpavement design, especially for airports where
maintenance access is oftendifficult. Areas adjacent to structures
(e.g. drainage channels, pits, manholes, etc.)can be subject to
differential settlement issues and these need to be designedout
where possible. Transitions from rigid to flexible pavement are
also acommon area of concern. Our design addresses such issues by
presenting ourdetailed jointing and transition details.
3.2.3 Aircraft Types and Masses
The range of aircraft assumed to be accessing the aircraft
maintenance facilityand individual hangars are summarised in Table
3.1. The aircraft mix assumed inthe initial pavement designs was
based on the information contained in theTender Documents.
Specifically, Drawings PD-APR-TR-005, PD-APR-TR-006,PD-GD-A-003 and
PD-G-AD-100 to 103 indicated a range of aircraft types in theeach
hangar.
Following a tender query, Notice to Tenderers No 11 provided the
followingclarification in relation to aircraft types:
The intent is to service the combination of aircraft shown in
each hangar. Thedesign is driven by limitations in adjustability of
work docks between aircraft types.
1. Line maintenance hangars shall receive all types of
aircrafts.
2. Wide body heavy maintenance hangars shall be designed to
receive allwide body aircrafts except the A380.
3. Narrow body heavy maintenance hangars shall be designed to
receive allnarrow body aircrafts.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 11Information Document Revision 1 24 June 2011
4. A380 heavy maintenance hangars shall be designed to received
A380aircrafts.
5. Wide body paint and wash hangars shall be designed to receive
all wideand narrow body aircrafts except the A380.
6. A380 paint and wash hangars shall be designed to receive all
types ofaircrafts.
The pavement thickness designs as presented in subsequent
sections are basedon the aircraft indicated in Table 3.1.
The design criteria for the pavements associated with the
aircraft maintenancefacility is based on the aircraft at operating
empty weight (OEW) with provision forvarying amounts of fuel.
The internal pavements of the paint hangars, wash hangars and
heavymaintenance hangars are based on operating empty weight (OEW)
+ 10%fuel.
The internal pavements of the line maintenance hangars are based
onoperating empty weight (OEW) + 50% fuel.
The aircraft parking apron is based on the aircraft arriving at
themaintenance facility at operating empty weight + 50% fuel, prior
to beingde-fuelled and moved into the hangars.
Departing aircraft are assumed to be at operating empty weight +
50% fuelfollowing refuelling.
Table 3.2 provides a summary of a range of masses for individual
aircraft.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 17Information Document Revision 1 24 June 2011
3.2.4 Aircraft Jacking Operations and Movements
The initial pavement designs were based on a range of
assumptions regardingthe frequency of aircraft jacking in each of
the hangars.
Following a tender query, Notice to Tenderers No 11 provided the
followingclarification in relation to aircraft jacking
frequency:
Line maintenance is unscheduled. The hangar is likely to be in
use 24 hours aday and for minor overnight repairs and for RON
positions in poor weather. It is tosupport typical line maintenance
activity.
Heavy maintenance hangars are expected to be fully occupies with
aircraft in Cand D checks. As such, aircraft are likely to be in
the narrow hangars for 20-40days and in the widebody hangars for
30-45 days. Assume a regular cycle ofaircraft in and out of each
hangar bay on that schedule.
Aircraft will be in the paint hangar for approximately 6 days,
and assume aregular cycle of aircraft in and out of that hangar on
the schedule. The washhangar is less regularly scheduled, but
assume it is used daily. The designers areassumed to know the
normal operations of MRO facilities for the line and
heavymaintenance.
Aircraft Wash Hangars
The previous pavement designs assumed two (2) aircraft per day
througheach of the wash hangars Wash Hangar 1 (A380-800 only),
WashHangar 2 (B747-400 only).
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been designed for all aircraft types indicated in
Table 3.1 at afrequency of two (2) aircraft per day through each of
the wash hangars.
The number of annual movements are summarised in Table 3.3.
No body jacking is assumed in the wash hangars.
No wheel jacking is assumed in the wash hangars.
Aircraft Paint Hangars
The previous pavement designs assumed one (1) aircraft per
monththrough each of the paint hangars Paint Hangar 1 (B747-400
only), PaintHangar 2 (A380-800 only).
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been designed for all aircraft types indicated in
Table 3.1 at afrequency of one (1) aircraft every six (6) days
through each of the painthangars.
The number of annual movements are summarised in Table 3.3.
No body jacking is assumed in the paint hangars.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 18Information Document Revision 1 24 June 2011
No wheel jacking is assumed in the paint hangars.
Heavy Maintenance Hangar No 1 (A380)
The previous pavement designs assumed two (2) aircraft per week
werebeing jacked in the hangar.
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been redesigned for all aircraft types indicated in
Table 3.1 at thefollowing a frequencies:
- Body jacking operations are based on one (1) aircraft being
jackedper month or 12 annual jacking operations.
- Wheel jacking operations are based on one (1) jacking
operation perlanding gear assembly per month or 12 annual wheel
jackingoperations.
Heavy Maintenance Hangar No 2 & 3 (Narrow Body including
B757)
The previous pavement designs assumed two (2) aircraft per week
werebeing jacked in the hangar.
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been redesigned for all aircraft types indicated in
Table 3.1 at thefollowing a frequencies:
- Body jacking operations are based on one (1) aircraft being
jackedever three (3) weeks or 18 annual jacking operations.
- Wheel jacking operations are based on one (1) jacking
operation perlanding gear assembly every three (3) weeks or 18
annual wheeljacking operations.
Heavy Maintenance Hangar No 4, 5, 6 & 7 (Narrow Body
excluding B757)
The previous pavement designs assumed two (2) aircraft per week
werebeing jacked in the hangar.
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been redesigned for all aircraft types indicated in
Table 3.1 at thefollowing a frequencies:
- Body jacking operations are based on one (1) aircraft being
jackedever three (3) weeks or 18 annual jacking operations.
- Wheel jacking operations are based on one (1) jacking
operation perlanding gear assembly every three (3) weeks or 18
annual wheeljacking operations.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 19Information Document Revision 1 24 June 2011
Heavy Maintenance Hangar No 8, 9, 10,11 & 12 (Wide Body)
The previous pavement designs assumed two (2) aircraft per week
werebeing jacked in the hangar.
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been redesigned for all aircraft types indicated in
Table 3.1 at thefollowing a frequencies:
- Body jacking operations are based on one (1) aircraft being
jackedper month or 12 annual jacking operations.
- Wheel jacking operations are based on one (1) jacking
operation perlanding gear assembly per month or 12 annual wheel
jackingoperations.
Line Maintenance Hangars
The previous pavement designs assumed four (4) aircraft per day
througheach of the line maintenance hangar positions Line
Maintenance hangar1 (A380-800/B747-400), Line Maintenance Hangar 2
(B747-400 only).
Based on the clarifications in Notice to Tenderers No 11, the
pavementshave been redesigned for all aircraft types indicated in
Table 3.1 at afrequency of four (4) aircraft per day through each
of the maintenancehangar positions.
The number of annual movements are summarised in Table 3.3.
No body jacking is assumed in the line maintenance hangars.
Wheel jacking operations are based on one (1) jacking operation
perlanding gear assembly per day or 365 annual wheel jacking
operations.
Table 3.3 Aircraft Jacking Operations
Wash Hangar 1 - - 730
Wash Hangar 2 - - 730
Paint Hangar 1 - - 61
Paint Hangar 2 - - 61
Heavy Maintenance Hangar 1 12 12 12
Heavy Maintenance Hangar 2 18 18 18
Heavy Maintenance Hangar 3 18 18 18
Heavy Maintenance Hangar 4 18 18 18
Heavy Maintenance Hangar 5 18 18 18
Heavy Maintenance Hangar 6 18 18 18
Heavy Maintenance Hangar 7 18 18 18
Heavy Maintenance Hangar 8 12 12 12
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 20Information Document Revision 1 24 June 2011
Table 3.3 Aircraft Jacking Operations (cont.)
Heavy Maintenance Hangar 9 12 12 12
Heavy Maintenance Hangar 10 12 12 12
Heavy Maintenance Hangar 11 12 12 12
Heavy Maintenance Hangar 12 12 12 12
Line Maintenance Hangar 1 - 365 1,460
Line Maintenance Hangar 2 - 365 1,460
Note: One aircraft operating in and out of the hangar is
equivalent to two movementsfor the purposes of pavement design.
3.2.5 Aircraft Jacks
Body Jacks
Two types of body jacks have been adopted, these being inner
main wing jacksand remainder of fuselage and outer wing jacks. All
jacks are assumed to bepneumatic tripod jacks with circular base
plates. The following jack details havebeen assumed in the
development of the pavement design for the hangars:
Main wing jacks assumed base plate diameter = 300mm
Forward fuselage jack - assumed base plate dimension = 300mm
Rear fuselage jack assumed base plate dimension = 300mm
Reminder of jack positions assumed base plate diameter =
300mm
Wheel Jacks
For all wide body aircraft, the wheel jacks have been assumed as
225mm x450mm for the main landing gear and nose landing gear.
For all narrow body aircraft, the wheel jacks have been assumed
as 200mm x450mm for the main landing gear and 125mm x 300mm for the
nose landing gear.
3.2.6 Aircraft Jacking Loads
The basis of the individual aircraft body and wheel jacking
loads is based onadopting relevant information from aircraft
facility manuals and other referencedocumentation where possible
(Appendix A). For body jacking the maximumloads have been adopted.
Body jacking loads are summarised in Table 3.4.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 21Information Document Revision 1 24 June 2011
Table 3.4 Aircraft Body Jacking Loads
A318 6,800 6,000 33,400 n/a n/a
A319 6,800 2,000 33,400 n/a n/a
A320-100 6,800 2,000 33,400 n/a n/a
A320-200 6,800 2,000 33,400 n/a n/a
A321-100 6,800 2,000 33,400 n/a n/a
A321-200 6,800 2,000 33,400 n/a n/a
A330-200 11,135 4,500 73,446 n/a n/a
A330-300 11,135 4,500 73,446 n/a n/a
A340-200 12,300 4,500 80,982 n/a n/a
A340-300 12,300 4,500 81,084 n/a n/a
A340-500 18,000 9,000 96,000 n/a n/a
A340-600 18,000 9,000 96,000 n/a n/a
A350-800 no data no data no data n/a n/a
A350-900 no data no data no data n/a n/a
A350-1000 no data no data no data n/a n/a
A380-800 51,000 12,000 190,000 n/a n/a
B737-600 7,900 9,900 31,700 n/a n/a
B737-700 7,900 9,900 31,700 n/a n/a
B737-800 7,900 9,900 31,700 n/a n/a
B737-900 7,900 9,900 31,700 n/a n/a
B737-900ER 7,900 9,900 31,700 n/a n/a
B747-300 17,900 43,900 90,700 13,600 11,300
B747-400 17,900 43,900 90,700 13,600 11,300
B757-200 12,200 1,800 49,200 n/a n/a
B757-300 12,200 1,800 49,200 n/a n/a
B767-200 12,700 30,400 68,000 9,500 n/a
B767-200ER 12,700 30,400 68,000 9,500 n/a
B767-300 12,700 30,400 68,000 9,500 n/a
B767-300ER 12,700 30,400 68,000 9,500 n/a
B767-400ER 12,700 30,400 68,000 9,500 n/a
B777-200 20,400 44,9900 94,300 10,000 7,800
B777-200ER 20,400 44,9900 94,300 10,000 7,800
B777-300 25,900 57,100 119,000 12,700 9,900
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 22Information Document Revision 1 24 June 2011
Table 3.4 Aircraft Body Jacking Loads (cont.)
B777-300ER 25,900 57,100 119,000 12,700 9,900
B787-9 20,000 37,200 77,600 8,200 5,400
MD-11F 27,800 n/a 109,100 n/a 3,600
The wheel jacking loads have been determined by adopting the
proposed aircraftdesign loads, the percentage of the design
aircraft mass on the landing gearsand the number of wheel jacking
points on the undercarriages of the individualaircraft.
The distribution of the wheel jacking operations has been
assumed as distributedas 80% on the main undercarriage (split 50/50
each side) and 20% on the nosewheel.
For aircraft with a centre main landing gear, the distribution
of the wheel jackingoperations has been assumed as distributed as
30% on the each of the mainlanding gears, 25% on the centre landing
gear and 15% on the nose wheel.
3.2.7 Aircraft Tug
The following tender query has been raised in relation to
aircraft tugs, theclarification of which is pending.
In addition to the data on fire tenders and other emergency
vehicles (RFI Register No28), additionally we require details of
the aircraft tugs likely to be used by SaudiAerospace.
The following data related to the aircraft tug has been assumed
for thedevelopment of the pavement design for the hangars pending
clarification of thetender query:
Wide Body Aircraft
The assumed operating mass of the tug is 50,000kg.
The assumed operating tyre pressure is 520kPa.
Movements are based on four (4) movements (on average) in and
around thehangar per aircraft.
Narrow Body Aircraft
The assumed operating mass of the tug is 30,000kg.
The assumed operating tyre pressure is 520kPa.
Movements are based on four (4) movements (on average) in and
around thehangar per aircraft.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 23Information Document Revision 1 24 June 2011
3.2.8 Emergency Service Vehicles
The following tender query has been raised in relation to
emergency servicesvehicles, the clarification of which is
pending.
Please provide details of the fire tenders and other emergency
service vehicles currentlyoperating at KAIA.
The following data related to the emergency services vehicles
has been assumedfor the development of the pavement design for the
hangars pending clarificationof the tender query:
The emergency services vehicle is assumed to be a 6 wheel
Panther orsimilar.
The assumed operating mass of the emergency service vehicle is
40,000kg.
The assumed operating tyre pressure is 1,000kPa.
3.2.9 Subgrade Strength
As discussed in Section 2, the pavement design is based on a CBR
of 15%. Thesensitivity of pavement thickness to a reduction in the
CBR has been assessedwith CBR 10%.
The rigid pavements are designed for a modulus of subgrade
reaction, equivalentto CBR 15%. The modulus of subgrade reaction,
or k value, can be calculatedapproximately from the CBR value using
the equation:
k = (1500 x CBR/26)0.7788
This gives a value in pci (pounds per cubic inch). For the 15%
CBR, the k value iscalculated as 194 pci, which converts to 52.4
MN/m3. Similarly, the modulus ofsubgrade reaction equivalent to a
CBR of 10% is 38.4 MN/m3.
This report has been prepared on the basis of construction of
the fill embankmentto provide a stable, uniform subgrade with an
equivalent minimum CBR of 15%.Insitu testing will be required to
confirm that such works have been completed asspecified prior to
pavement works commencing.
3.2.10 Concrete Strength
The specification (Section 321313) issued with the Tender
Documents nominatesa design flexural strength of 4.6 MPa at 28
days.
Load transfer will take place through the provision of dowel
bars through thedoweled construction joints and sawn contraction
joints.
3.2.11 Design Period
The design period for the pavements (both rigid and flexible)
has been assumedas 30 years.
-
Saudia Aerospace Engineering Industries Aircraft Maintenance
Hangars, Jeddah 24Information Document Revision 1 24 June 2011
3.3 PAVEMENT DESIGNS
3.3.1 Taxiway MA
Taxiway Pavement
All aircraft entering or leaving the facility will access
Taxiway MA, entering theapron initially. Aircraft are assumed to
enter the taxiway at OEW + 50% fuel andpark on the apron. Aircraft
are assumed to leave the apron (departing themaintenance facility)
at OEW + 50% fuel.
The exception to this is the length of taxiway to the paint
hangars and washhangars. The aircraft using this portion of the
taxiway are assumed to be at OEW+ 10% fuel maximum.
To simplify the analysis at this stage, a uniform pavement
thickness is proposedfor Taxiway MA along its length.
The total number of aircraft entering the facility on an annual
basis is derivedfrom the annual usage of each of the maintenance
hangars annually. Thesesame aircraft are assumed to leave the
facility annually.
The previous pavement design proposed a pavement structure of
60mm PMB on60mm Binder Course on 200mm CABC on 250mm CASBC based on
theassumptions made at the time.
Based on the clarifications in Notice to Tenderers No 11, the
pavements havebeen redesigned. Table 3.5a provides the pavement
thickness requirements forvarying subgrade strengths and
operational scenarios.
Table 3.5a Taxiway MA Pavement Thickness
Base Case Double Aircraft
CBR 15%
60mm PMB on60mm Binder Course
200mm CABC305mm CASBC
60mm PMB on60mm Binder Course
200mm CABC325mm CASBC
CBR 10%
60mm PMB on60mm Binder Course
200mm CABC445mm CASBC
60mm PMB on60mm Binder Course
200mm CABC475mm CASBC
A pavement structure of 60mm PMB on 60mm Binder Course on 200mm
CABCon 350mm CASBC is proposed for Taxiway MA at this time bearing
in mind theassumptions being made. This pavement structure would
seem to cover a rangeof potential operating scenarios. The proposed
pavement extent is indicated onDrawing SK001.
Shoulder Pavement
The shoulder to Taxiway MA is to be designed for occasional
aircraft traffic as perthe Employers Requirements, in addition to
use by emergency service vehicles.Aircraft are assumed to operate
on Taxiway MA at OEW + 50% fuel.