8/12/2019 Parking_Garage_Feasibility_Report.pdf
1/40
RD DR FTPARKINGGARAGEFEASIBILITYSTUDYPreparedFor:
PARKINGADVISORYSUBCOMMITTEE
April2011
PreparedBy:
49 West 37th
Street 5th
FloorNew York, New York 10018
8/12/2019 Parking_Garage_Feasibility_Report.pdf
2/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
TABLE OF CONTENTS
Section 1.0 Introduction Page 1Section 2.0 Parking Demand Analysis Page 3Section 3.0 Site Alternatives & Preliminary Design Concepts Page 8Section 4.0 Financial Analysis (to be completed) Page 18
LIST OF TABLES
Table #1 Parking Occupancy Surveys Page 4Table #2 Parking Demand Ratios Page 6Table #3 Projected Staffing & Enrollment Growth (Fall 2013) Page 7Table #4 Projected Parking Demand Increases Page 7
Table #5 Lot #1 Conceptual Construction Budget Page 13Table #6 Lot #2 Conceptual Construction Budget Page 14Table #7 Lot #5 Conceptual Construction Budget Page 15Table #8 Parking Garage Site Alternates Matrix Page 17Table #9 Capital Cost & Debt Service Page 22Table #10 Operating & Maintenance Budget Page 23
LIST OF FIGURES/PLANS
Site Identification Aerial Page 9Site Footprint Studies After Page 10Lot #1 Concept Plans After Page 12Lot #2 Concept Plans After Page 13Lot #5 Concept Plans After Page 14
8/12/2019 Parking_Garage_Feasibility_Report.pdf
3/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 1 of 24
SECTION 1.0 - INTRODUCTION
DESMANAssociateswasretainedtoprovideconsultingservicesforWilliamPatersonUniversity(WPU)forthepurpose
ofperformingaFeasibilityStudy foraddingaparkinggarageon thecampus.Toaccomplish thiswecompleted the
followingtasks,workinginconjunctionwiththeUniversitysParkingAdvisorySubCommittee,whichwascomprisedof
thefollowing:
AdministrationandFinanceVicePresident,SteveBolyai AdministrationandFinanceAssociateVicePresident,RosemarieGenco AdministrationAssociateVicePresident,RichardStomber CapitalProjects,DesignandConstructionDirector,JohnUrinyi CommuterServicesDirector,AllenWilliams PublicSafetyandUniversityPoliceInterimDirector,BobFulleman FacultyRepresentativeRajenderKaur,DepartmentofEnglish
PARKINGDEMANDANALYSIS Our initial task consisted of updating the supply and demand analysis performed byDESMAN in2004.Thistaskidentifiedcurrentparkingoccupanciesandthenumberofparkingspacesrequiredtomeetthe
parkingneedsbothtodayandforecasted3yearsforward.
Basedontheverificationofparkingspaceinventory,fromdatathatwasprovidedbytheUniversity,DESMANtabulatedthe
parkingsupplyanddemandonthecampus. Byusingthedemandbasedratioscalculatedinthe2004Study,anestimate
offutureparkingdemandatWPUwasforecasted.
SITEALTERNATIVESANALYSIS&PRELIMINARYDESIGNCONCEPTS ConsideringtheinfluenceoftheUniversitysgoalsforthisprojectaswellas forecastedparkingdemand,anumberofsiteswere identified forpossibleconsideration for future
parkingalternatives.Criteriaweredevelopedtoevaluateandprioritizealternativesitesforfuturestructuredparking. Using
thesecriteria,parkingsiteswerecomparativelyevaluated. Asaresultofthisprocess,asiteevaluationmatrixwasdeveloped
includingadvantagesanddisadvantagesasmeasuredby identifiedcriteriaandsummarized inthematrix. Asimplerating
systemof1 to3was incorporated toprioritizeparkingsites,withthegoalofselectingmultipleparkingsites thatwillbe
subjecttoamoreindepthdesignstudyandeconomicanalysis.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
4/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 2 of 24
OptionswerepresentedanddiscussedwiththeParkingAdvisorySubCommittee tosolicitcommentsanddiscussvarious
advantagesanddisadvantagesofeachpotentialsitesolution.Afteranumberofpreferredsiteswereselected,functional
design concepts and preliminary building plans were developed to further investigate and analyze each sites
feasibility. Concept Design Documents including Grade, Typical and Roof Plans, were prepared to visualize the
followingprojectcomponents:
VehicularIngressandEgressLocations. RampingMethods,slopesandlocations. InternalTrafficFlow. ParkingGeometry,includingbaywidths/heights,parkingangleandstallwidths. Perfloorspacecounts. PossibleStair/elevatorlocations. Efficiencyonsq.ft.perspacebasis.
FINANCIAL ANALYSIS Utilizing Concept Design Drawings and the construction budget thatwas developed, a financialanalysiswasperformedfortheLot1alternatetoassisttheUniversityininvestigatingfundinganddevelopmentrequirements
andoptions.Projectcosts, including softcostsandassociated feeswere investigated for two financingoptions.The first
scenariowasdevelopedassumingtheUniversityfundstheprojectthroughtheNewJerseyEducationalFacilitiesAuthority,or
anotherlikebondingagency,asatraditionalcapitalimprovementproject.Thesecondscenarioforecastedtheprojectcosts
andfundingrequirementsiftheUniversityenteredintoaPublicPrivatePartnership(P3),wherebyprivateinvestmentfunds
wouldbeusedtofinancethedevelopmentandconstructioncosts.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
5/40
8/12/2019 Parking_Garage_Feasibility_Report.pdf
6/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 4 of 24
TABLE#1
ParkingOccupancySurveys
Location/Facility Lot Capacity Nov. 2003 Parking Survey Oct. 2010 Parking SurveyLot1 124 124 124
Lot 2 284 313 237
Lot 3 299 261 286
Lot 4 375 364 375
Lot 5 1030 1055 1030
Lot 6 874 862 857
Lot 8 60 47 53
Admissions Lot 16 12 4
Visitors Lot 37 15 34Veritans Lot 200 25 37
415 Hamburg Tpk. 40
TotalReported Population 3 299 3 078 3 087
Faculty 370 380
Staff 720 746
On-Campus Resident
Students 2300 2630
Commuter Students 8625 8730
8/12/2019 Parking_Garage_Feasibility_Report.pdf
7/40
8/12/2019 Parking_Garage_Feasibility_Report.pdf
8/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 6 of 24
Giventheapparentaccuracyofthismodelandpresumingitsaccuracywithrespecttoindividualusergroups(faculty,
staff, students,etc.), the population topeak parking demand factors could be utilizedwhen assessing the parking
demandontheWPUcampusasstaffingandenrollmentlevels increaseovertime. Thefollowingtableillustratesthe
factorsthatweredevelopedspecificallyforWPU.
TABLE#2
PopulationtoPeakParkingDemandRatios
(drove&
parked
own
car/persons
per
auto
present
during
peak
period)
Category Demand RatioFaculty 0.54
Staff 0.82
On-Campus Resident Students 0.50
All Other Students 0.24
Visitor/Other 0.46
Giventhedevelopmentofaccuratepopulationbasedparkingratiosforeachcampususergroup,projectionsforfuture
staffingandenrollmentcouldbeusedtoestimateanticipatedpeakweekdayparkingdemand fortheWPUcampus.
Theuniversityhasprovidedprojectedgrowthnumbersforthenextthreeyearsonthecampuswhichcanbeusedto
forecastparkingneeds.Theforecastedgrowthforthefallsemesterin2013isasfollows:
8/12/2019 Parking_Garage_Feasibility_Report.pdf
9/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 7 of 24
TABLE#3
ProjectedStaffing&EnrollmentGrowth
Fall2013
Category Growth ProjectionFaculty 20
Staff 40On-Campus Resident Students 370
All Other Students 1400
Visitor/Other 50
Utilizingtheabovegrowthfactorsandpopulationbasedparkingratiosfortheseusercategorieswillresultinaforecastfor
addedunconstrainedparkingdemandexpectedonthecampus.Thefollowingtableillustratedtheseforecasts.
TABLE#4
ProjectedParkingDemandIncreases
Fall2013
Category Growth Projection Demand Ratio Parking SpaceDemandFaculty 20 0.54 11Staff 40 0.82 33
On-Campus Resident Students 370 0.50 185
All Other Students 1400 0.24 336
Visitor/Other 50 0.46 23
TOTAL PARKING DEMAND 588
8/12/2019 Parking_Garage_Feasibility_Report.pdf
10/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 8 of 24
Aspreviouslyillustratedwiththerecorded2003and2010surveys,parkingdemandshaveremainedrelativelyconstantover
that period while student populations have grown by almost 4%. This could be attributed to many factors such as
modifications to the class schedules and/or programs thereby shifting the distribution of student population during
traditionalmidday peak period, increased dependence on public transportation and/or a capacity constrained parking
system.Ifweassumethatitwasanythingbutacapacityconstrainedparkingsystem,thenthestudentdemandfactorwould
needtobemodifiedslightlytoaccountfortheaddedpopulationgeneratingasimilarparkingdemand.
Accounting
for
an
added
student
population
of
approximately
500
students
would
reduce
the
demand
factor
to
roughly
0.22
spacesperstudentduringthemiddaypeakperiod.Thiswouldinturnreducethedemandforthiscategorytoapproximately
308spaceswith1400addedstudentsintheFallof2013.Thereforeforplanningandfeasibilitypurposes,theaddedparking
demandsthatcouldbeexpectedwiththeforecastedgrowthinyear2013willapproach530spaces.This,whenaddedtothe
existingdeficitof250spaceswiththeeliminationoftheVeritansLotandwhentheprincipalofpracticalcapacityisapplied,
wouldsuggestaminimumparkingexpansionof750800spacesshouldbeplanned.
SECTION 3.0 - SITE ALTERNATIVES ANALYSIS & PRELIMINARY DESIGN CONCEPTS
The Parking Advisory SubCommittees goals were to select and evaluate potential sites that would meet the
immediateand forecastedparkingdemands for thecampus.Theunderlyingpremisewas thatanyexpansionwould
result intheUniversitysfirststructuredparkingfacility. Theinitialstepwastoidentifyviableoptions,orsites,onthe
campusthatcouldsupportastructuredparkingfacility. Someofthecriteriausedtoidentifyviablesiteswerethefollowing:
Siteavailabilityownership. Siteconditions(subsurfaceconditions,topography,etc.). Sitesize(dimensions). GatewayImpacts. ProximitytoCampusdestinations. Vehicularaccess. Pedestrianaccess. Sharedparkingopportunities. Alternativeplansfordisplacedcarsduringconstruction. Constructionstagingandstorageissues.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
11/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 9 of 24
Thisdeliberation resulted in theParkingAdvisoryCommittee selecting sixareasof thecampus for furtherconsideration.
Theseareas,orsites,wereidentifiedasSite#1(Lot1),Site#2(Lot2),Site#3(St.JosephsWayneHospitaljointuse),Site
#4(HobartHall),Site#5(Lot5)andSite#6(MorrisonHall). Thefollowing imagegraphically illustratesthesegeneral
locationsonthecampus.
SITEIDENTIFICATIONAERIAL
8/12/2019 Parking_Garage_Feasibility_Report.pdf
12/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 10 of 24
Thenextstep inouranalysiswastotakeacloser lookattheopportunitiesateachoneofthe identifiedsitesonthe
campus. This was done by incorporating industry practices with regard to parking geometry, functional design
requirementsand thephysicalcharacteristicsofeach site. Footprintsweredeveloped foreachof the six locations
takingintoconsiderationsuchitemsassiteconditions,sitesizeandstandardparkinggeometricalrequirements,vehicular
accessandminimizingthedisplacementofexistingparkingspaces.Thisresultedintheplacementofgaragefootprintsthat
wouldrespondtothesegeneralrequirements.Theplacementofthefootprintscouldthenbeconvertedtoparkingcapacities
toallowtheCommitteetoassessthevalidityofeachsite.
Thefollowingdiagramsillustrateingreaterdetaileachsiteslocationonthecampusandtheresultantparkingfootprintsthat
would be feasible. These footprintswere then tested against the ability for each site to support the suggested parking
requirements/needs,orwhatwouldbethenumberoflevelsneededtoachieveagoalofaddingapproximately900additional
spacesonthecampus.Thebuildingmassingwasthencomparedtothesurroundingbuildingsonthecampustoqualitatively
measureitsimpact.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
13/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
14/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
15/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
16/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
17/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
18/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
19/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
20/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 11 of 24
The Parking Advisory Committee reviewed the opportunities for each of the sites and reached the following
conclusions. In general, floor to floor heights are programmed at 11 feet, and bay widths are 60 feet, which is
comprisedofan18footdeepparkingspace,24footwidedrive/circulationaisleandan18footdeepparking. Parking
spaceswereassumedtobe9feetwideforthisexercise.A900spaceparkinggaragewouldequateto280,000290,000
squarefeetofbuildingarea.
Site#1Lot1BetweenFacilitiesandScienceHallEasto Aestheticallyoneofthebetterlocationsrequiringtheleastamountoffaadearticulation.o Doesnotimpactanyexistingparkingspaces.o Elevatorsandpedestrianbridgeswillbe required tospan fromtopdeck togradeadjacentto the
ScienceHall.
o TruckaccesstoStudentCenterloadingdockneedstobemaintained.o Thewarehouseandswitchgearwouldneedtoberelocated.o Providesgoodaccesstoandfromthreecampusentrypoints.
Site#2Aand#2BLot2o OptionBwasdeemedtobefunctionallysuperior.o OptionBwouldbemoreeconomicalthanOptionAintermsofcostperspace.o Providesgoodaccesstoandfromthreeentrypoints.o Resultsinthelossofspaceduringconstruction.o Notasclosetocampusdestinationsassomeoftheothersites.
Site#3St.JosephsWayneHospitalWestofLot5o Thetopographyofthissiteischallenging.o Requirestheinvolvementofanotherpropertyowner.o Theheightofnewgaragemayblockexistingsolarpanels.
Site#4EastofHobartHallo Buildableareadoesnotappearlargeenoughtomeetprojectedparkingrequirements.o PedestrianbridgecrossingPomptonRoadwouldberequired.o Trafficsafetyisaconcern.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
21/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 12 of 24
Site#5Lot5o Fivelevelstructurewouldberequiredfor800addedspaces.o Resultsinthelossofspaceduringconstruction.o Highlydesirablelocationforcommuters,residents,andStudentCentervisitors.o GoodvehicularaccessfromPomptonRoadandCollegeRoad,o AddedtraffictoEntry4mayneedtobemitigated.o LoadingDockaccessforWayneHallneedstobemaintained.
Site#6EastofMorrisonHallo Proximitytocampusdestinationsisquestionable.o Existingtopographycreatesfunctionalandeconomicchallenges.o Buildableareadoesnotappearlargeenoughtomeetprojectedparkingrequirements.
The ParkingAdvisory Committee completed their review of theopportunities foreach of the sites and concluded,
basedontheabovefactors,thatSite#1Lot1,Site#2BLot2andSite#5Lot5shouldbeadvancedforfurtherplanning
andstudy.Withtheselectionofthesesites,functionaldesignconceptsandpreliminarybuildingplansweredeveloped
tofurther
investigate
and
analyze
each
sites
feasibility.
Concept
Design
Documents
including
Grade,
Typical
and
Roof
Plans,werepreparedtovisualizethefollowingprojectcomponents:
PossibleVehicularIngressandEgresslocations. RampingMethods,slopesandlocations. InternalTrafficFlow. ParkingGeometry,includingbaywidths/heights,parkingangleandstallwidths. BuildingSections. Perfloorandtotalparkingspacecounts. PossibleStair/elevatorlocationsandconnectionstothecampus.
Constructionbudgetswerealsopreparedforeachoptiontoassistthecommitteetoevaluatethealternatives.Budgets
werepreparedonasquarefootbasisforthemajordivisionsofwork(i.e.earthwork,foundations,structure,elevators,
architecturaltreatment,plumbing,electrical,etc.),usingourinhousedatabaseofcostsforrecentsimilarareaprojects
anddiscussionswithcontractorsandmaterialsuppliers.TheconceptplansandbudgetsforLot#1,Lot#2andLot#5
areasfollows:
8/12/2019 Parking_Garage_Feasibility_Report.pdf
22/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
23/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
24/40
8/12/2019 Parking_Garage_Feasibility_Report.pdf
25/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 13 of 24
TABLE#5
LOT#1CONCEPTUALCONSTRUCTIONBUDGET
8/12/2019 Parking_Garage_Feasibility_Report.pdf
26/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
27/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
28/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 14 of 24
TABLE#6
LOT#2CONCEPTUALCONSTRUCTIONBUDGET
8/12/2019 Parking_Garage_Feasibility_Report.pdf
29/40
DESMA
8/12/2019 Parking_Garage_Feasibility_Report.pdf
30/40
8/12/2019 Parking_Garage_Feasibility_Report.pdf
31/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 15 of 24
TABLE#7LOT#5CONCEPTUALCONSTRUCTIONBUDGET
8/12/2019 Parking_Garage_Feasibility_Report.pdf
32/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 16 of 24
Theconcept
designs
were
presented
to
the
Parking
Advisory
Committee
to
discuss
the
pros
and
cons
of
the
alternatives.
Baselinecosts,parkingefficiencies,siting,floorplansandpotentialtrafficandpedestriancirculationwaspresentedand
discussed. Generalobservationsoftheconceptsaresummarizedbelow.
Lot1o VehicularaccesstothisgarageoptionwouldbegainedthroughLots1and2.o AccessroadtoStudentCenterismaintained.o SectionsofPPOoperations:storeroom,saltshed,switchgear,oldboilerplantwouldneedtobedemolishedaspartofthissolution.o Littletonoimpactonexistingparkingcapacity.o Pedestrianbridgeswouldbeneededforcommunicationtothecampus.
Lot2o Thislocationhasbestproximitytoathleticfacilities.o Inordertoachieveprojectedparkingdemandsthissolutionrequiresoneadditionallevel.o VehicularaccesstothisgarageoptionwouldbegaineddirectlyfromthecampuslooproadandLot2.o Pedestrianbridgesaredesirableforcommunicationtothecampus.o Interimlossof130spacesduringconstruction.o Thislocationisfurthestfromtheprimarycampusdestinations.
Lot5o Thisisthelargestalternativewithat358,000grosssquarefeet(GSF)and1,025spaces.o AccesstothisfacilitywillincreasetraffictoandfromEntry4requiringfurtheranalysisandstudyof
potentialimpactsandmitigation.
oVehicular
entry
and
exit
appears
feasible
from
two
locations
which
will
improve
internal
circulation
and
maydefineusergroundaccess.
o ProximitytotheResidenceHallsisaconcernandprivacyissueswillneedtobeaddressed.o TheSpeertHallloadingdockshouldnotbeaffected.o Interimlossof110spacesduringconstruction.o NJTransitBuscirculationmaybeimpactedand/orrerouted.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
33/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 17 of 24
Asite
evaluation
matrix
was
developed
including
advantages
and
disadvantages
as
measured
by
identified
criteria
and
summarizedinthematrix. Asimpleratingsystemof1to3wasincorporatedtoprioritizethethreeadvancedparkingsitesto
assisttheCommitteeinevaluatingtheoptions.Eachcommitteememberindependentlycompletedthematrixandtheresults
weretabulatedbyDESMANforpresentationtotheCommittee.Thefollowingtableillustratesthetabulatedresultsfromthe
Committeescompletionofthematrix.
TABLE#8
ParkingGarageSiteAlternatives Matrix
Lot 1 Lot 2 Lot 5880 Spaces 1060 Spaces 1115 Spaces
Category 880 Net New Spaces 910 Net New Spaces 1005 Net New Spaces Definitions1-
Sizing/Capacity 2.0 1.0 3.03 having the largest capacity and 1 having the lowest
capacity.
2- Net Increase in Parking 2.1 1.0 2.9 3 having the highest net increase and 1 having the lowest.
3-Parking Efficiency 1.9 1.6 2.3
3 representing best efficiency in terms of sf per parking
space and 1 being least efficient.
4- Expansion Capability 1.9 1.9 2.0 3 representing best opportunity for expansion
5-Mixed Use Potential 2.1 1.5 1.9
3 representing best opportunity for alternate uses and 1
offering worst opportunity. .
6-Ability to Accommodate Different Parkers 2.1 1.5 2.0
3 allowing greatest flexibility to accommodate different
parkers and 1 having least flexibility.
7-Access from Roadway Network 1.8 1.5 2.0
3 providing most direct connections to external roadway
and 1 having least direct.
8-Campus Traffic Flow 2.1 2.1 2.5
3 minimizing conflict points and 1 having greatest
potential for conflict.
9- Pedestrian Connections to Buildings 2.1 1.4 2.5
3 providing most direct unencumbered pedestrian route
and 1 the least.
10-Aesthetic Integration into Campus 2.8 1.4 1.5
3 allowing easiest integration and 1 having the potential
greatest impact.
11- Compliance with Master Plan 2.5 1.8 1.8 3 adhering to master plan and 1 being least compliant.
12- Impacts During Construction 2.6 1.9 1.4 3 having the slightest impact and 1 having the greatest.
13-Economics/Construction Costs 2.1 1.6 2.0
3 providing the potential for the least cost per space and 1
having the greatest cost per space.
TOTAL 28.1 20.2 27.8
8/12/2019 Parking_Garage_Feasibility_Report.pdf
34/40
8/12/2019 Parking_Garage_Feasibility_Report.pdf
35/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 19 of 24
UNIVERSITYFUNDED
ANALYSIS
1. PROPOSEDPROJECTLOT1IMPROVEMENT: 880spaceParkingDeck. 5levelfacility. Contractandhourlyparking. Nootheruses/occupiedareasareplannedaspartoftheproject. Revenuecontrolsystemwillrequireprepayment.
2. Estimatedparkinggarageconstructionschedule: 20months3. EstimatedProfessionalArchitectural&EngineeringDesignFees: 8.5%ofconstructioncosts4. EstimatedFeesforUniversityProject/ConstructionManager: 1.8%ofconstructioncosts5. Nolandcostsareincludedaspartofthefinancingforthisproject.6. The parking garage will be taxexempt financed through the New Jersey Educational Facilities
Authority,or
another
like
bonding
agency,
with
a25
year
term.
7. UniversitydoesnotplananycapitalcontributiontotheconstructionoftheparkingdecktoreducetherequiredBondproceeds.
8. No other sharing of the construction of the parking garage with other funding/financingopportunitiestoreducetheBondamounthasbeenused.
9. EstimatedTaxExemptInterestRate: 5.25%10. Assumedleveldebtpaymentfortermofbond.11. EstimatedBondCostsofIssuance/InsuranceandUnderwritersDiscount:5.0%ofconstructioncosts12. ProjectBudgetincludesanallowanceof$350,000fortrafficimprovements.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
36/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 20 of 24
Assumptionsfor
the
privately
funding
scenario,
whereby
the
University
would
have
alease
agreement,
or
some
other
arrangement
forpaymenttotheprivatepartnership,arepresentedbelow. TheUniversitywouldeffectivelymakeannualpaymentstotheprivate
investmententityforthetermoftheloan,atwhichtimetheimprovementwouldrevertbacktotheUniversity.Forthepurposeof
thispresentationofcosts, it isassumedthateventhoughprivate investmentwouldbeusedtosecurefinancingfortheproject,
neitherthelocalorcountyjurisdictionswouldimposerealestatetaxesontheimprovement.
PUBLICPRIVATEPARTNERSHIPFUNDEDANALYSIS
1. PROPOSEDPROJECTLOT1IMPROVEMENT: 880spaceParkingDeck. 5levelfacility. Contractandhourlyparking. Nootheruses/occupiedareasareplannedaspartoftheproject. Revenuecontrolsystemwillrequireprepayment.
2. Estimatedparkinggarageconstructionschedule: 16months3. EstimatedProfessionalArchitectural&EngineeringDesignFees: 8.5%ofconstructioncosts4. DevelopmentFees: 5.0%ofconstructioncosts5. ReturnonInvestment(ROI): 10% ofprojectcosts6. TakeouttermonROI: 7years7. Nolandcostsareincludedaspartofthefinancingforthisproject.8. Theparkinggaragewillbefinancedthroughprivateinvestment,withpartoralloftheprojectcosts
fundedorsecuredbyacommercialloan.Loantermwouldbe20years.
9. Universitydoesnotplananycapitalcontributiontotheconstructionoftheparkingdecktoreducepaymentrequirements.
10. No other sharing of the construction of the parking garage with other funding/financingopportunitiestoreducetheprojectcostshasnotbeenused.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
37/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 21 of 24
11. EstimatedTaxableInterestRate: 6.50%12. EstimatedLegal&ClosingCosts: 2.00%ofconstructioncosts13. ProjectBudgetincludesanallowanceof$350,000fortrafficimprovements.
Thefollowingtableillustratespreliminarycapitalprojectcostsandannualdebtservicepaymentsassociatedwiththe
plannedparkingimprovementsonLot1,incorporatingtheabovementionedfinancialassumptions.Thetwoscenarios
wereforecastedbasedontheconstructionbudgetsthatwerepreparedintermsof2011dollars.Ascanbeseen,the
totalcosttotheUniversitywouldbeslightlyhigherunderaP3taxablefinancingarrangement,butthedebtwouldbe
retiredin20yearsasopposedtotheUniversityfundedtaxexemptoptionof25years.
AdditionallytheUniversitywillhaveadditionalcostsintermsofdesignprofessionalsundertheP3delivery.Thesecosts
generallycomefromtheUniversityfinancingthepreliminaryengineeringstudiesandsurveys,environmentalstudies,
geotechnicalsurveys,trafficsurveysandthearchitecturalfeestodevelopanddefinetheprogramtoa2530%design
effort.Traditionallythesecostsarenonrecoverable inaP3financinganddeliveryandarefundedbytheowner.We
haveincludedacostof$400,000fortheseservices.
8/12/2019 Parking_Garage_Feasibility_Report.pdf
38/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 22 of 24
TABLE#9
CAPITALCOST&DEBTSERVICE
8/12/2019 Parking_Garage_Feasibility_Report.pdf
39/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 23 of 24
Inaddition
to
the
annual
debt
service
for
the
capital
cost,
the
introduction
of
anew
parking
facility
on
the
campus
will
increasetheoperationalbudget fortheUniversitytoaccountforaddedstaffingtomanageandoverseethegarage
and costs associated with utility demands, supplies, equipment and maintenance. Operating and maintenance
expensesfortheproposedLot1facilityhavebeenderivedbasedon industryacceptedoperating lineitembudgets,
Universitysuppliedinformationandourexperiencewithsimilarfacilities.
Basedonourresearchandanalyses,weestimate forthefirstfullyearofoperationthattheoperatingbudgetfora
projectconsistentwith theconceptplansdeveloped forLot1willbeapproximately$299,000withamaintenance
budgetof
$110,000,
which
includes
areserve
for
structural
maintenance
of
$44,000.
These
numbers
have
been
derivedfromthefollowingestimatedlineitembudget.
TABLE#10
OPERATING&MAINTENANCEBUDGET
8/12/2019 Parking_Garage_Feasibility_Report.pdf
40/40
Parking Garage Feasibility Study
April 2011
DESMANA S S O C I A T E S
Page 24 of 24
Basedon
our
research
and
analyses,
we
have
presented
estimated
costs
and
operating
expenses
for
the
construction
ofa900spaceparkingfacilityonLot1ofWPUscampus.OnescenariowaspreparedassumingtheUniversityfundsthe
project as a traditional taxexempt capital improvement project. The second scenario forecasted the project costs and
fundingrequirements iftheUniversityentered intoaPublicPrivatePartnership(P3),wherebyprivatetaxable investment
fundswouldbeusedtofinancethedevelopmentandconstructioncosts.
Forthepurposeoftheseanalyses,weassumedthatWPUwouldmaintaintheresponsibilityofoperatingandmaintaining
theparkingfacility,thusresultinginaneutralcostcomparisonforeitherdeliverymethod.WeestimatethattheUniversitys
costto
operate
and
maintain
anew
900
space
parking
facility
similar
to
the
concept
plans
that
have
been
prepared
for
Lot
1,
wouldbeapproximately$410,000duringthefirstfullyearitisopened.Theoperatingcostsandexpensesareexpectedto
escalateonanannualbasis.
Our analyses for a University bonded taxexempt capital improvement suggest an annual debt service payment of
approximately$1.558millionusinga25yearterm.UnderaPublicPrivatePartnership(P3)delivery,wherebyprivatetaxable
investmentfundsareusedtofinancetheprojectandconstructioncosts,theannualleaseorloanpaymentbytheUniversity
wouldbeapproximately$2.204millioninthefirst7years,assumingatakeoutperiodforthereturnoninvestment,reducing
toapproximately
$1.905
million
in
years
8to
20.
Thus,
the
University
should
expect
an
additional
expense
of
approximately
$2,000,000to$2,500,000peryeartodesign,construct,operateandmaintaina900spaceparkingfacilityonthecampuson
Lot1.The$500,000variationisattributedtotheoptionsinfundinganddeliverymethod.