Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1. chilled / mixed water to counting houses 2. cooling station transfer lines 3. stations construction Future works 4. VELO concentric lines construction 5. rack cooling and fire extinction network
7
Embed
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
-transfer lines for IT, TT, OT, RICH stations under construction, to be finished in week 43 (before the 28th)
-piping to IT/TT safety chiller to be soon designed and installed according to same schedule
-on LHCb demand: isolation valves on four lines installed on RB84 side, bypass dismantled on same side, brackets near to barracks stairs on RB86 modified
-cavern wall on RB86 to be tidied up for pipes installation