• CDS-7• State Dept – Mr. Weinz• PACOM• USARPAC• USNS MERCY• AUS HQ JOC• HQ JFNZ• JSDF• FLC-Yokosuka
• C7F• C3F• CTF 76• 351st Civil Affairs Command• DLA Troop Support - Pacific• 30th NCR• HSC-23• MCAST
3
UNCLASSIFIED
UNCLASSIFIED
PP 12 Weekly Planning Rhythm
Thurs Fri SatSun
1300-1500W OPT VTC
1000W read ahead slides
posted to APAN
0900W CA WG
1300W LOG WG
1200W MED WG
1300W FP WG Every other week
Mon Tues Wed
1000W COMMS WG
1000W Comm Integration WGCPF N33 Update
CPF N3
Semi-Monthly Update
1200W ENG WG
4
UNCLASSIFIED
UNCLASSIFIED
SEP
OCT
NOV
DEC
JAN
FEB MAR
APR
MAY
JUN
JUL AUG
Mission Planning/CONOPS (CPF)
Meetings/Conferences (CPF/CDS)
Force Sourcing (CPFN3)
Interagency Coord (CPF N5)
NGO Coordination (CPF N5)
Partner Nations (CPF/C7F)
Transit Plan (CPF/CDS)
Funding/Authorizations (CPF)
Communications (CPF N6)
Assessment (CPF MAG)
Detailed CONOPS (CDS)
PDSS/Advanced Echelon (CDS)
Deployment (CDS)
Planning Timeline
PDSS Advanced Echelon
Deployment
MOU Letters Signed
PN Invitation letters
Assessment plan
PLANORD EXORD
Requirements Systems
Final
FSLO Letter
CPF RFF
Mid Planning Conference
Initial Planning Conference
Initial
5
UNCLASSIFIED
UNCLASSIFIED
ADF Planning Status
General Planning• CJOPS Decision Brief for PP12 signed
Command
Engineering
Medical • ADF Health manning to PP12 planning under way
No Change
6
UNCLASSIFIED
UNCLASSIFIED
ADF Participation
Australia
• Command Element
• Engineering Section
• Medical Personnel contribution of 15 – 20 pers in each contingent
Contingent 1 embark USNS MERCY in Guam and change out in Subic Bay Philippines
Contingent 2: embark USNS MERCY in Subic Bay Philippines and disembark at the
conclusion of mission in Cambodia
Health manning TBC in late November
HQJOC Health PP12 POC:CMDR Kenneth Walters (SO1 Reg / Dom & Joint Ex Hlth Plans)
MAJ Dominic Wade (SO2 Joint Ex Hlth Plans) [email protected] (until 2
Dec 11)
No Change
7
UNCLASSIFIED
UNCLASSIFIED
PP12 RFI Tracker
Number Status Date Req Responsible
Question Other
ADF-001
No Change
8
UNCLASSIFIED
UNCLASSIFIED
JSDF Planning Status
• CONOPS of Japan - Developing the CONOPS of Japan Country selection - Philippine - Vietnam Activities - Medical supports - Community service projects Introduction of culture etc. - Studying other activities - Decision after completion of
PDSS Vehicles - JMSDF Ship (TBD× 1 ) - JASDF Aircraft ( C-130 or KC-767× 1)
Medical team - Approximately 20~30
No Change
9
UNCLASSIFIED
UNCLASSIFIED
JSDF Planning Status
• PDSS - 5 persons / each country Philippine and Vietnam Planners - MED, Ship visit, and others
• Humanitarian community in Japan - Not yet access
• POC LCDR Haga [email protected] DSN:224-7714 or
7723
No Change
10
UNCLASSIFIED
UNCLASSIFIED
JSDF Planning Status
Number Status date WG Requests/Questions Comments
JPN -001 19 OCT PDSSDraft plan of PDSS in Philippine and Vietnam
No Change
11
UNCLASSIFIED
UNCLASSIFIED
NZDF Planning Status
- Decision brief has been prepared for COMD Joint Forces New Zealand based on FST deployment to Vietnam 10 – 24 Jul 12.
No Change
13
Medical Update
• Medical WG Telcon re-scheduled for Wed, 2 Nov 11, 1200 hrs
• NSTR
14
UNCLASSIFIED
UNCLASSIFIED
Engineering Update
Engineering Working Group conducted telecon 31 Oct
PDSS teams- tracking, no issues
CONOPS being developed to determine FIE/SIE feasibility.
Possible engagement in Exercise Pacific Angel, VNM phase.
Australian Defence Force approval is approximately 90% complete.- PDSS person has already been identified once approved
- SQNLDR Owen Gardner has joined the team as the PP12 JOC representative
Completed On-track Off-Track/Recoverable Off-Track not recoverable
15
UNCLASSIFIED
UNCLASSIFIED
Logistics Update
• PDSS:– PDSS Logistic team set for departure
• Husbanding Requirements – ongoing discussions with SUPPO
MERCY, FLC Yokosuka and FLC Singapore – Potential long-lead time requirements– Ports under Contracted support vs non-contracted
No Change
16
UNCLASSIFIED
UNCLASSIFIED
Civil Affairs Working Group
No Change
COMPACFLT VTC CONFIRMATION SHEET VTC HELP DESK PHONE NUMBER (808) 474-8506 / 4941
EMAIL [email protected] Set-up time for this VTC: ONE HOUR
VTC CLASSIFICATION
UNCLASSED CONFERENCE
VTC Date and Time:
17 OCT 1930Z – 2100Z / 0930-1100 HST
HOST and Participants, Area Code VTC DIAL-UP NUMBER SPEED
1. (HOST) COMPACFLT 808 474-1760 1282. Participant: Commander Destoyer
Squardon 7808 474-1761 128
3. Participant: USNS MERCY 808 474-1762 1284. Participant: US ARMY 351st 808 474-1763 1285. Participant: MCAST 808 484-4910 1286. Participant: Naval Post Grad School 808 484-4911 1287. Participant: COE 808 484-4912 1289. Participant: AUDIO ONLY FOR UP TO
9 PARTICIPANTS808-471-2663
Host Code 8506
WG time changed to 0900 Hawaii standard time.Location changed to Main VTC room
17 17 Completed On-track Off-Track/Recoverable Off-Track not recoverable
Item / Task Status Action Date Req Notes
IT & Radio Operator Manning
CPF N3/ CDS /
01DEC11 - CPF N3 Global Force Manager FORAC: Each MEDCAP = 2-IT (CHIME), 1-JCSE IEP (TBD).4 MEDCAPS maximum (8 ITs, 4 IEP).
Annex K / COMM Plan
CPF N6/C7F/ C3F/CDS
PRE-MPC
- IAW NTTP 3-57 Navy HCA OPS-Based on PN/HN COMM interoperability assessments and simultaneous missions.-OPTASK COMMS required.
BGAN SATCOM
CPF N6/CDS PRE-MPC
- Not required for PDSS. (17OCT11 CDS-7 N6 email).- OPTEST CPF BGANs (JAN12).- Develop CONOPS for BGAN use.
Host Nation Spectrum Mgt
C7F N6 /CDS PRE-MPC
-Determine frequency restrictions for each host nation.
PP12 CIS Information Systems Status(01NOV11)
18 18 Completed On-track Off-Track/Recoverable Off-Track not recoverable
Item / Task Status Action Date Req
Notes
PAO Network CPF PAO/N6/ CDS/MERCY
PRE-MPC -Defense Video & Imagery Distribution System (DVIDS) : PAO determine if available. Ashore use only.- Verified Fast File Transfer (FFT) SW (version 2.43) Installed in MERCY. Verifying current IATO cert.
PN-NGO Business Center(SSC LANT CHARLESTON)
CPF N6 / CDS/MERCY
APR12 -SPAWAR PN-NGO Business Center (Wireless and terminals) is the afloat solution. -MERCY to coordinate refresh/OPTEST/training in San Diego by SPAWAR. Determine coat/SOW.- CDS procure printer consumables for entire mission.-IA/business rules.
Partner Nation Interoperability
CPF N6 / CDS
POST-MPC
-Verify Partner Nation (PN) CIS POCs.-Verify APAN accounts for all PN CIS WG team members.-PN CIS capability review.-Develop CIS Interoperability Matrix in Annex K.
HumanitarianElectronic Record System (HERS)
CIS WG/CDS N6
TBD -Mission funded by MARFORPAC Experimental Center (MEC)-PDSS Automated Data Collection training complete 21OCT11 at CPF. ADC capability deploying w/ PDSS.
PP12 CIS Information Systems Status(01NOV11)
19 19 Completed On-track Off-Track/Recoverable Off-Track not recoverable
Item / Task Status Action Date Req
Notes
Remote MED-DENCAP /CC Comms Arch
CDS / CPF/ JCSE
TBD -UHF data and voice SATCOM/LOS Comms for CAP to air/ship.-JCSE IEP dynamic solution approval in progress.
Host Nation MIL C4
PDSS OIC
PDSS -PDSS OICs for assessment action.-Training provided to Blue Team 21OCT11.
Host NationCIVIL Comms
PDSS OIC
PDSS -PDSS OICs for assessment action.-Training provided to Blue Team 21OCT11.
Remote Site US Mission CISAssessment
PDSS OIC/AOIC
PDSS -JCSE Planner not included in PDSS. PDSS AOIC to conduct assessments with provided checklists and guidance.-Command Center (CC) Comms assessment.-Training provided to Blue Team 21OCT11.
PDSS CISComms
CPF/ CDS PDSS OICs
PRE-PDSS
-Iridium Phones: CPF N6 issued phone to Blue OIC.-In country cell phones: MERCY to provide from PP10 mission phones.-Automated Data Collection (8 cell phones app) issued to Blue OIC.
PP12 CIS Information Systems Status(01NOV11)
20 20 Completed On-track Off-Track/Recoverable Off-Track not recoverable
Item / Task Status Action Date Req
Notes
Knowledge Management /Data Protection
CDS/MERCY
TBD -MEDCAP/CDS/Mission Data storage and protection
Command Center Ashore CIS
CDS PDSS -Identify configuration and location in each country.
IT SMEERequests
CDS PDSS -PDSS determine scope (SYSADMIN, repair, training, etc.).
SATCOM Requests
C3F/C7F/CDS
FEB12 -Standard USN process.
MERCY COMMs Suite Groom
CDS /MERCY
APR12 -Determine groom requirements
PP12 CIS Information Systems Status(01NOV11)
21 21 Completed On-track Off-Track/Recoverable Off-Track not recoverable
Item / Task Status Action Date Req
Notes
FSET on MERCY
CPF /MSC
TBD - Field Service Engineering Team (FSET) rqmt determination by CDS-7 pending-Funding transfer to SPAWAR TBD
End of Mission CIS Exit Plan
CPF/CDS
TBD -Transfer custody of loaned CIS items back to CPF
Knowledge Management /Data Protection
CDS/MERCY
TBD -MEDCAP/CDS/Mission Data storage and protection
PP12 CIS Information Systems Status(01NOV11)
22
UNCLASSIFIED
UNCLASSIFIED
Force Protection Update
• Next FPWG, 8 Nov
• PDSS Pre-Travel Requirements– Updated ISOPREPs– APACS– iATP– AOR location specific brief– Level I ATFP– SERE 100 B
• NCIS/Security Requirements: Informal N2 RFI
23
UNCLASSIFIED
UNCLASSIFIED
Public Affairs Update
- Request PAO workspace in Bldg 55
- ADSW on track for 1 DEC start• Integrate with CPF staff 7-23 NOV
- Media Coordination• Discovery Channel embark- waiting on paperwork from
Discovery’s end• Thai Channel 5 embark• Social media embeds
- Coordinate DVIDS training for PA team• Equipment request
- CPF Band• Embark/Disembark HI• About 17 personnel
24
UNCLASSIFIED
UNCLASSIFIED
PP12 Communication Integration
Initial Stakeholder analysis complete
Working draft communication “plan” to include assessment
Communication Framework:• Pacific Partnership (2012) brings enhanced capability, opportunity for subject
matter expert exchange and a venue for broadened regional relationship building at HN invitation
The story of Pacific Partnership (2012):• Will have shared ownership (providers, recipients, enablers) and be told from
these individual perspectives• Will be told by the HN, PNs and NGOs• Will be focused on key, distinctive audiences vice single audience saturation
and will leverage emerging media• Will be synchronized across time and space to ensure consistency (or
approach and message) and stakeholder engagement to achieve desired goals• Will be echoed by other activities, operations and engagements (PVST, SMEE)• Will be captured, assessed and archived
No Change
25
Mission Commander Priorities
• CMOC
– Mission Statement– Structure/Deliverable/Cell Manning?
• PDSS Blue
– Philippines site survey; Cambodia survey preparations/site selection.– OIC and AOIC concerned/feedback from Engineers is that current Cambodia Itinerary
is un-executable as written.
• PDSS Gold Preparations
– Confirm / Finalize Participants– Status of: VISAs, FP requirements, medical requirements, passports, travel
arrangements
• PDSS Planning
– Welcome Aboard Package/Pre-deployment Handbook• Putting on APAN website is only a partial solution/select mailings should also
be considered.
– Main Planning Conference (30-31 Jan in San Diego)• What was CPF legal issue with funding Admiral Kidd CC that they had to work
through?
26
Mission Commander Priorities
• Mission Training
– Mission Rehearsal (March 2012)
• Ship to Shore movements (ADVON, Main Body, Teams, etc.)• Communications (Ship, shore and PA releasable products)• MEDCAP• DENCAP• VETCAP• Engineering• COMREL• Partner Nation Interoperability• AT/FP• Key Leader Engagements
– PA/Integrated communications training– Cultural awareness training
• Budget
– Confirm what current funding is available– Concerned a clear path for COMREL funding for mission has not been arranged.– Execution plan?
• Meetings
– CDS 7 (others?) with ETGLANT (07-10 NOV)
– CDS 7 with Project Handclasp (09 DEC)
27
Engineering Lead Planner Comments (Ref: Cambodia PDSS)
• We have concerns about the feasibility of the proposed Cambodian PDSS itinerary as proposed by the ODC. The draft itinerary sent out will not work given the 1 week timeframe. The proposed itinerary is not feasible for the following reasons:
• It is virtually impossible to link MEDCAP and ENCAP site surveys together. There is a huge difference in the amount of time required at each site location. The engineers will need 3-4 hours at each proposed site to conduct detailed planning. This has been tried before and inevitably the medical planners and waiting for the engineers. It makes absolutely no sense to have the whole team standing around waiting for the engineers
• For planning purposes each portion of this PDSS needs to conduct site surveys independently i.e. medical, engineer, logistics, ops, etc
• If there are 2 or more sites per province the engineers need 4 hours per site plus 3-4 hours per province to conduct research WRT materials and services required for construction.
• Bottom line we can survey 2 potential sites per day. That is 2 construction projects not 2 provinces. If the project proposal is complicated we could spend as much as 8 hours on one site. The problem is we only get one visit to measure, plan, calculate, etc.
28
Engineering Lead Planner Comments (Ref: Cambodia PDSS)
– We also need time to identify the following in the vicinity of each project site:
– Hotels– Hospitals for MEDEVAC– Vendors: Hardware, fuel, services, food, etc.– **These are all required to determine feasibility
• Recommendation: Look at 6-7 sites (not provinces) and ultimately select 3-4. It’s imperative that in order to have MEDEVAC capability and logistics support the sites need to be within 1 hour of Phnom Penh or Sianoukville. This is also important because 50% of the engineers will be aboard Mercy transiting back and forth. Assumption is that the mission commander would like to do site visits during the mission and attend ribbon cutting ceremonies.
29
UNCLASSIFIED
UNCLASSIFIED
Closing Questions/Comments
• CPF Staff• State Dept – Mr. Weinz• PACOM• USARPAC• USNS MERCY• AUS HQ JOC• HQ JFNZ• JSDF• FLC-Yokosuka
• C7F• C3F• CTF 76• 351st Civil Affairs Command• DLA Troop Support - Pacific• 30th NCR• HSC-23• MCAST• CDS-7