OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011
10

OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

Apr 01, 2015

Download

Documents

Darwin Fowers
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

OVERVIEW OF THE PROCUREMENT PROCESS

UNDER

IPA COMPONENT- III RCOP

SMC Meeting, 18 May 2011

Page 2: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

2

Procurement Plan

3 months 6 months 9 months

ServiceService Procedure ideally takes at least 9-10 months

SupplySupply and WorksWorks Procedure ideally takes at least 6-7 months

Receiving Initial T

ender Docum

ents

Procurement Notice 30 days

Tender Launch 50 days

Tender Evaluation

Shortlist Evaluation

Contract Award

Procurement Notice 60 days

Forecast Notice 30 days

Tender Evaluation

Contract Award

Procurement Notice 90 days

Tender Evaluation

Contract Award

Forecast Notice 30 days

Forecast Notice 30 days

Page 3: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

3

RCOP Progress in tendering process:

* Tender processes for Works, Supervision (Service) and Supply components of 3 projects are combined respectively.

Priority 1 Works Service Supply

Establishment of Business Incubators & Development of a Network among Incubators in Turkey (Kastamonu, Malatya, Tokat)

FN Spv TA: Shortlist TA: n.a

n.a

Development of the Research & Technological Infrastructure of Gaziantep *

FN (Cancel)

Spv TA: under Evaluation

TA: FN

FNKayseri-Erciyes Technopark Regional Innovation Centre (Kayseri, Yozgat) *

TA: FN

FIRASET (Fırat Rainbow Surrounding Enterprise Taskforce) (Elazığ) *

TA: FN

Winter Tourism Corridor in Erzurum, Erzincan and Kars

n.a n.a n.a

n.a

Page 4: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

4

RCOP Progress in tendering process:

Priority 1 (cont’d) Direct Grant

Greater Anatolia Guarantee Facility

Budget: 32 MEUR

Implementing

G43 Anatolian Venture Capital Fund

Budget: 16 MEUR

Contracting

Page 5: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

5

RCOP Progress in tendering process:

Priority 2 Service Supply

Enlargement of the European Turkish Business Centres Network, Phase I (Sivas, Antakya, Batman, Van)

Contracting Implementing n.a

Empowering SMEs for Networking and Regional Cooperation (Samsun, Trabzon, Gaziantep, Kahramanmaraş, Çorum)

Implementing Implementing n.a n.a

Page 6: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

6

RCOP Progress in tendering process:

Priority 3 Service Supply

Technical Assistance for the Implementation of RCOP

Contracting FN n.a (FWC) Completed-2010

(FWC) Implementing.

FN

Page 7: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

7

RCOP Progress in tendering process:

2nd Project Package:

7 Projects > 26 Components (7 Works; 7 Spv TA; 6 Supply; 6 TA)

FN published for 7 Components Estimated date for signature of contracts >

Second half of 2012-2013

Page 8: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

8

COMMITMENT / DISBURSEMENT RCOP FORECAST 2007-2011

YearOP Allocation

(EURO)

Potential Decommitment (N+3) (EURO)

Forecasted Disbursement

(EURO)

2007 41,900,000.00 N/A  

2008 43,500,000.00 N/A  

2009 54,800,000.00 N/A 64,275,000.00

2010 71,430,000.00 41,900,000.00 27,259,577.18

2011 88,020,000.00 43,500,000.00 12,543,293.96

2012   54,800,000.00 32,243,977.88

2013   71,430,000.00 44,855,828.21

2014   88,020,000.00 13,312,442.34

Notes: 1- Cut off date is 09.05.2011 in terms of Procurement Plan. 2007-2011 Programming years has been taken into consideration.

2- In general, the ratio of EU and TR contribution 85%-15% while in 6 projects the EU contribution is between 82-83%.

3- For each year, total disbursement from CFCU till the end of December is considered as verifiable by the Commission.

Page 9: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

9

COMMITMENT / DISBURSEMENT RCOP FORECAST 2011

Notes: 1- Cut off date is 09.05.2011 in terms of Procurement Plan. 2007-2011 Programming years has been taken into consideration.

2- In general, the ratio of EU and TR contribution 85%-15% while in 6 projects the EU contribution is between 82-83%.

3- For each year, total disbursement from CFCU till the end of December is considered as verifiable by the Commission.

YearPotential

Decommitment (N+3)

Forecasted Disbursement

Cumulative Forecasted

Disbursement Decommitment Risk

2007  N/A        

2008  N/A        

2009  N/A 64,275,000.00      

2010 41,900,000.00 27,259,577.18 91,534,577.18 -49,634,577.18 No Risk

2011 43,500,000.00 12,543,293.96 62,177,871.14 -18,677,871.14 No Risk

2012 54,800,000.00 32,243,977.88 50,921,849.02 3,878,150.98 3,8 Mil.

2013 71,430,000.00 44,855,828.21 44,855,828.21 26,574,171.79 26,5 Mil.

2014 88,020,000.00 13,312,442.34 13,312,442.34 74,707,557.66 74,7 Mil.

Page 10: OVERVIEW OF THE PROCUREMENT PROCESS UNDER IPA COMPONENT- III RCOP SMC Meeting, 18 May 2011.

10

THANK YOU FOR YOUR ATTENTION