OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING ELEMENT 6 - JANUARY, 2012
30

OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

Dec 15, 2015

Download

Documents

Megan Regis
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE

GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING ELEMENT 6 - JANUARY, 2012

Page 2: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

PROJECT MANAGEMENT & REGULATORY STREAMLINING – TEAM MEMBERS • Board Liaisons: Steven Makredes, Target & Kevin Hart, Kaiser

Permanente• Streamlining Project Steering Committee: - Ron Loback, Avolve – Chair & Element 6 Roadmap Champion Lead - Thomas Phillips – Target – Vice Chair - Jonathan Widney – Solibri - Marla Schuchman – ARX – Lead Digital Seals Project • FIATECH Project Manager - Robert Wible

Page 3: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

GENERIC OVERVIEW OF REGULATORY STREAMLINING

• The Nation’s Current Regulatory System & Need for Regulatory Streamlining

• Helping Both the Public & Private Sectors Be More Effective & Efficient• Areas in Need of Streamlining• Examples - Current FIATECH Regulatory Streamlining Projects: - Guideline for Replicable Buildings - ePlan/BIM - Digital Seals - Proof of Concept AutoCodesMAY WE BE OF ASSISANCE?

Page 4: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

NATION’S CURRENT REGULATORY SYSTEM

• Federal Government• 50 State and 4 Territorial Governments•Native American Tribal Governments• 40,000 local jurisdictions – Counties, Cities, Towns

& Townships• Regional & Special District Regulatory Authorities

for – Fire, Water, Sewer, Conservation, Historic Preservation, Economic Development, etc.

Page 5: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

CURRENT REGULATORY SYSTEM – NATURE OF FEDERALISM

• Limited Federal Authority• Police (regulatory powers) generally reserved to

States except for those powers specifically related to Interstate Commerce - Transportation – Air, Water and Federal highways & the Environment • All other powers by 10th Amendment are reserved

to the States and their local units of government.

Page 6: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

CURRENT REGULATORY SYSTEM

Grew from Colonial Times – Simple regulation construction & commerce • 13 Colonies to 50 States & 4 Territories• Nation of 2.5 million to 310 million Complexities of technology& modern life: health, welfare & life safety including the environment

Page 7: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

NEED FOR REGULATORY STREAMLINING

FROM EARLY 1900’S TO PRESENT TREMENDOUS GROWTH IN COMPLEXITY - From Simple regulations over construction, interstate commerce, fire safety, and public health to:• Highway construction, operation & maintenance• Energy production and use• Water, sewer, storm water runoff & pollution• Content of products & their production & use• Recycling & disposal of waste• Health and safety of workers• Transportation of hazardous & oversized materials

Page 8: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

REGULATORY OVERLAP AND DUPLICATION BY AGENCIES AT ALL LEVELS OF GOVERNMENT • EXAMPLES IN ROAD TRANSPORTATION: - What is being transported? - Over what kind of road – Federal, state, county, local road? - What are width and load limits for each type of road and for bridges encountered along the transportation route? - Are any of the components of what is being transported classified as a hazardous material by Federal, state or local government? - Where are vehicles doing the transportation licensed? Who inspects them? - Are “Escort Vehicles” required to accompany what’s being transported? Do different states, local jurisdictions transited along the route have different requirements for escort vehicles?

Page 9: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

REGULATORY STREAMLINING – THE NEED

GIVEN SEVERE RECESSION & NEED FOR MORE RAPID RECOVERY FROM BOTH MAN-MADE AND NATURAL DISASTERS NATION CAN NO LONGER AFFORD A REGULATORY SYSTEM THAT WAS BUILT IN MID-1900’S & IS: • Cumbersome, overlapping, poorly administered• Does not delineate clear lines of authority & jurisdiction• Leaves compliance to guesswork and repeated re-applications, reviews

and inspections• Long waiting periods between each regulatory step• Presents barriers to innovative products, processes & materialsNOT ABOUT REGULATORY ABANDONMENT BUT ABOUT EFFICIENCY!!!

Page 10: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

FOR EXAMPLE – THE BUILDING REGULATORY PROCESS

Page 11: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

FIATECH REGULATORY STREAMLINING PROJECT - MISSION

• Enhance our nation’s public safety, disaster resilience and economic competitiveness…• By streamlining and applying information

technology to the nation’s regulatory process…•Making it more effective and efficient – clarifying

compliance and reducing time in regulatory process by up to 80%

Page 12: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

THE USA IS AWASH IN REGULATIONS & PAPER

“Streamline permitting. Cut red tape so job-creating construction and

infrastructure projects can move forward.”

Page 13: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

ENABLING NEW WAYS TO WORK

ePlan Review

DIG-SIGs

AutoCodes

ReplicableBuildingsGuideline

ReplicableBuildingsGuideline

Page 14: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

REPLICABLE BUILDINGS GUIDELINE

• Participants: Target Corporation, DuPont, Intel, Avolve Software, Solibri, ICC, Salem, OR; Clark Co., NV; Salt Lake City, UT

• RBG Status:– Key to large-scale regulatory reform– Defines “replicable” structure qualifications– Adoption parameters (high-level)– Guideline Drafted by FIATECH in 2009 and Released by ICC for adoption/use

Sept., 2010• Supporting adoption by jurisdictions in 2010 -11• Target Corporation field-testing and reports

Page 15: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

REPLICABLE BUILDINGS GUIDELINE

• Keys elements – Single review for all but site specific issues– Repeatable process, check lists– Provides authoritative review for validation – Top-down and bottom-up adoption– Case studies (and more case studies)– Being adopted now by NY, NJ, & localities across U.S.SAMPLE SAVINGS - TARGET STORES $100,000PER STORE IN DEMONSTRATION PROJECT

Page 16: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

DIGITAL SEALS PROJECT

• PROBLEM BEING ADDRESSED: Only ½ of 50 States and most countries do net yet recognize digital seals on building plans slowing the use of ePlan review technologies

• PROJECT APPROACH: Identify barriers to gaining jurisdiction approval of digital seals and produce a Guide to Using Digital Seals that FIATECH members and stakeholders can use to work with administrative and legislative bodies to gain approval e-seal approval

• PROJECT TEAM & LEAD: ARX – LEAD, Participating members: Hatch, Avolve, Solibri, Target, Kaiser Permanent – Partner - AIA

• PROJECT DELIVERABLES: Research, Produce, Disseminate Guide , Identify several jurisdictions to target to gain acceptance of digital seals. - Produce and Release in 2012

Page 17: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – EXPEDITED PERMITTING VIA DIGITAL REVIEW

PHASES I AND II - UPDATE AND STATUS REPORT

60 DAYS TO 60 SECONDS!

Page 18: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES PROJECT OBJECTIVE

•Mission:–Make plan review, storage, retrieval more

efficient reduce plan review time by 80%–Facilitate use of BIM data in both the regulatory

& construction processes–Create greater uniformity across the nation in

code adoption, interpretation and application

Page 19: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – UPDATE – PHASE IA

• Phase I – Background– Scope– Objectives– Methodology

• POC Implementation and status

• 2D Plan Review Collection Results– Number of respondents– Number of comments (gross, average)– Spread of the comments– Analysis of responses

Page 20: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

POC PARTICIPANTS – 14 VOLUNTARY PARTNERS

• ICC – Chicago

• States– New Jersey– New York

• Counties– Mecklenburg, NC

• Cities– Bend, OR– San Jose, CA– Livermore, CA– Redwood City, CA– Irvine, CA– Salt Lake City, UT– Amarillo, TX– Carrollton, TX– Houston, TX– Philadelphia, PA

Page 21: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

★★

Mecklenburg County, NC

State of NJ

State of NY

Philadelphia

Amarillo

Carrollton

Houston

Salt Lake City

Bend

Irvine

Livermore Redwood City San Jose

ICC - Chicago

Page 22: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES UPDATE – PHASE IA (CONTINUED)• 2D Plan Review Data Analysis– What we learned• Vs what we expected• What we didn’t expect

– GAP Analysis between respondents• Did not anticipate the need for this, so really a positive development• What to do with this information?

• Approval if issues corrected?– If NO, why not?

Page 23: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

SNAPSHOT OF COMMENTS

Codes Comments Non-Compliant

Not Enough Info

Guideline Statements

IBC 2009 IL, NC, NY, OR, PA, TX, UT

177 46 122 11

ADA OR

CBC CA

NJAC/IBC/ANSI

NJ

High 42 16 26 5

Low 1 0 1 0

Page 24: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – PHASE IB - UNDERWAY

• 3D Model Review– Check against current SMC Rulesets– Modify Templates Accordingly– Identify 2D components in 3D model

• Inform Target Corporation of Model Discrepancies– As compared to 2D– As required for viable checking• Creates a model protocol by-product

Page 25: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – PHASE IB (METHODOLOGY)

• Invite three jurisdictions to participate in 3D Checking

• Provide Technology and Familiarization Sessions to Participants

• Provide Rulesets to Jurisdictions

• Modify Ruleset Templates for Specific Jurisdictions

Page 26: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – PHASE IB – CURRENT STATUS

• Collaborate with participants in running Accessibility and Egress Check

• Record process and approaches for intent v content understanding

• Generate results

• DEVELOP Jurisdiction Report Format

Page 27: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – PHASE IB – LOOKING AHEAD

• Review results from Jurisdiction Model Checks

• Compare results for consistency

• Generate a GAP analysis

• Complete by 15 December 2011

• Use results to influence Ruleset development

• Discussion - The ROI ecosystem

Page 28: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

AUTOCODES – PHASE II – BEYOND THE POC

• Area of next focus– Expanded use of Accessibility and Egress Rulesets – different building types– Fire & Life Safety– Mechanical & Engineering (M&E)

• Engage with Phase I Jurisdictions + Expanded Audience– Design Firms, GC’s and MEP firms– Owners and Code Consultants

Page 29: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

CAN FIATECH HELP YOU WITH YOUR REGULATORY STREAMLINING ISSUES IN?• Building design & construction• Zoning & Land Use• Environment• Transportation• Energy Use• Work place safety• Other areas

Page 30: OVERVIEW OF THE NEED FOR REGULATORY STREAMLINING & FIATECH’S ROLE GENERIC PRESENTATION FROM THE FIATECH REALTIME PROJECT MANAGEMENT AND REGULATORY STREAMLINING.

IF SO CONTACT US TO LEARN MORE ABOUT BENEFITS OF REGULATORY STREAMLINING & FIATECH

Contact FIATECH Regulatory Streamlining Project Manager, Robert Wible at:• 703-568-2323• [email protected]