Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Mar 18, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and
Page 2: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Overview of the Installation Flow of Builders’ lift

Planning/Coordination :

Design, Application, Efficiency and Logistic

Safety

Moving Forward

Contents

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 3: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Overview of the Installation Flow

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 4: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Design and Application

Planning/Coordination

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

The use of Builders’ Lifts, if properly planned, designed and

used, can provide a convenient and safe means of vertical

transportation for site personnel and materials

Page 5: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Your Project Design & Application

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Sole application/

In combination

with passenger hoist

Capacity & Size

Site Progress

vs

Time of availability

Stops arrangement

(considering 11m

interval requirement)

Appropriate assignment

of lift (location

designation)

1. Package assignment (Exclusive or Hybrid)

2. Capacity and Size

3. Phasing deployment (i.e. stops arrangement per phase)

4. Builders’ Lifts allocation and designation

5. Time of availability

Page 6: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Efficiency and Logistic

Planning/Coordination

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 7: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Your Project Efficiency & Logistic

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Transit storage arrangement

(i.e. initial set-up and stage

installation phase)

Clear & safe access

for delivery and

dismantling

Well organized

service timing

Sound structural provision

for hoisting, cathead

installation and crash

deck erection

Clear and tidy working area in

front of respective lift lobby

during installation phase

1. Site Storage and house keeping

2. Structural design interface

3. Clear and Safe Access

4. Sufficient and tidy working space

5. Well coordinated downtime arrangement

Page 8: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Risk Assessment Competency and Supervision Work briefing prior to work commencement Permit-to-work LALG checking and examination Shaft opening protection

Recommended Tools/Device

Safety

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 9: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Safety NO GO LIST (Zero Tolerance)

We do not tolerate any violation concerning the use of …

Fall Protection

Safe Hoistway Access Process

LOTO (Log-Out/Tag-Out)

Jumper

Appropriate hoisting/rigging equipment and methods

Safety certified sub-contractor companies, and individually trained and

qualified sub-contractor employees

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 10: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Builder’s Lift

“The NEXT”

Safer and Efficient

Moving Forward

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 11: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

The NEXT Step by Step to the Top

The next generation of Builders’ Lifts.

Self-climbing vertical transportation

during the construction phase

Independent from construction work

The extension process only takes a

maximum of 24 hours, excl. 3rd party

acceptance tests

Water-proofed

crash-deck

Lifting platform

Machine platform

Lift car

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 12: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

The NEXT The Machine Platform

The machine platform contains all the

machine room equipment allowing to run

the elevator:

Builders’ Lift machine with control &

converter

Guided within the permanent guide rails

Equipped with separate safety gears

Fitted with retractable supporting beams

to secure towards the shaft structure

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 13: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

The NEXT The Lifting Platform

The optional lifting platform extends the

Builders’ Lift to a self-climbing system:

Independent hoisting crane to hoist the

machine platform

Climbs itself up using a dedicated

suspension point provided at the crash-

deck or slip form

Fitted with retractable supporting

beams to secure towards the shaft

structure

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 14: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Moving Forward

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017

Page 15: Overview of the Installation Flow of Builders’ lift...with passenger hoist Capacity & Size Site Progress vs Time of availability Stops arrangement 4. ... deck erection Clear and

Thank you for your attention

LECA | CIC Vol 4 Seminar | Safety : Planning & Coordination | 2017