Top Banner
Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez- Mateos TE-MPE Technical Meeting CERN, April 16 2015
25

Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Jan 05, 2016

Download

Documents

Gerald Walton
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Overview of the CLIQ UnitsProject

Knud Dahlerup-Petersen, Félix Rodríguez-Mateos

TE-MPE Technical Meeting

CERN, April 16 2015

Page 2: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Outline

• Introduction and general aspects• Choice of main components• Safety aspects• The mini-Review and principal outcome• A glance to the future of CLIQ• The Team

2

Page 3: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Introduction and general aspects

Page 4: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

• Several units of CLIQ power supplies have been manufactured by the MSC Group over the last years and used at CERN for testing of different magnets in SM18• We do not present here the “ad-hoc”

design of those units• This previous design has given the

needed flexibility to optimize parameters as capacity, voltage/current, frequency and dumping time constant

• There is now a request from MSC to the MPE Group to produce 3 units, 2 of which will be sent to FNAL by the end of May’15. The third one will serve as spare

• If successful, this project will continue with more prototypes and ultimately a production of series for Hi-Lumi upgrade magnets

4

A new hybrid protection system for high-field superconducting

magnetsE Ravaioli, V I Datskov, G Kirby, H H J ten Kate, and A P Verweij

Page 5: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

• The EE Section got the mandate in early February 2015• Delivery for end of May 2015• Choice of components was determined by the very short delivery time• Resource organization was affected by the short lead time, with

involvement of an important fraction of the section members• Experience from the DQHDS is an important feature, although being of a

different nature (only discharge)

5

Some facts and boundary conditions

Page 6: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Choice of main components

Page 7: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

• The CLIQ power unit is not only a supply, it is an energy exchanger• This will lead to the characteristic ringing, which is being increasingly damped by the

resistances in the circuit, mainly the rapidly increasing resistance of the quenching coil, but also by the series-equivalent resistance of the capacitor bank and cable leads

• The ringing leads to both positive and negative voltages on the storage capacitors within one current direction

7

Capacitors (1)

Typical CLIQ discharge (Emmanuele)

Page 8: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

The storage capacitor bank for CLIQ must, according to above considerations, be of bipolar type

Further requirements• Low internal series-equivalent resistance• High capacitance density • Minimum bus bar work for connection• Switch between 1 or 2 capacitors

Selected type• Self-healing, dry type, metallized polypropylene• Data: 500 V, 2 x 40 mF, 2 x 44 kg (from LHC QF/QD snubber capacitor

spares)• With over-charge protection and over-pressure indication • Stored energy: 10 kJ

8

Capacitors (2): selection

Page 9: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Charging circuitThe LHC 3-step type of charger is replaced by a 100 mA constant-current charger of commercial origin - tailored to our application. Full charging time around 400 s.

Charging voltage shall be adjustable in steps of 50 V (manual commutation, up/down).

Charging from 110 V, 60 Hz as from 240 V, 50 Hz.

Capacitor voltage and charging current shall be displayed as well as the end of charging state.

16/04/2015 MPE Technical Meeting 9

Page 10: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

• Discharge characteristics of bi-directional nature (discharge / recharge currents) => semiconductor switches in a bi-directional arrangement have been chosen

• Good experience from the LHC quench discharge heater units with the use of thyristor switches => decision to keep the thyristors option for the CLIQ units

Thyristors will be used in both directions in order to assure a ‘certain separation’ of the main magnet powering circuit from the heater circuit outside the provoked coupling period

The two opposite thyristors shall be fired simultaneously for 0.5 s. No trigger redundancy in each unit is considered necessary

10

Thyristors (1)

Page 11: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Two candidate thyristors have been considered:

1. Single Thyristor used for fast opening pulse to LHC main circuit energy extraction switches (BCM). To be doubled

2. Bi-directional Thyristor for energy management. Approved by ABB for the CLIQ application. Two thyristors in one wafer

The thyristor firing shall be provoked through application of a train of pulses, from a 12 kHz generator through pulse transformers.

Discharge current shall be measured by adequate AC current transformer (6kA peak, 10 -3 accuracy).

11

Thyristors (2): selection

1. 2.

Page 12: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Safety aspects

Page 13: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

• A main breaker (or a switch + fuse), accessible on the outside panels of the CLIQ unit, shall assure not only interruption of the input power but equally switch-in a bank of discharge resistors which will assure an automatic ‘internal’ discharge of the complete capacitor bank. The total discharge time shall be 1 minute maximum.

• In addition to a clear indication of the actual charging voltage/current (analog voltmeter or galvanometer per capacitor), a visible indicator shall show safe conditions (<40V).

• After re-powering from the mains input, there shall be no automatic re-charging of the capacitor bank (system is latched). Charging shall be initiated manually.

• After a discharge the system is automatically latched. Recharging only by manual activation.

• Activation of the equipment stop button shall initiate an internal discharge of the capacitors

• For changing the capacitance value (switch between 1 or 2 capacitors), possibilities should be studied that do not imply opening of the rack (lockable switch that can only be activated after discharge of the capacitors)

13

Page 14: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

The mini-Review and principal outcome

Page 15: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Objectives• Validation of the implementation of the

concept• Coherence of the choices with respect to the

established functionalities• Correctness with integration and

implementation according to the electrical standards applicable

• Safety aspects

15

Page 16: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Panel• Jean-Paul Burnet, TE/EPC• Alexandr Erokhin, TE/MPE• José Carlos Gascón, DGS-SEE-XP• Christian Giloux, TE/MSC• Andrzej Siemko, TE/MPE (ex-officio) • Yves Thurel, TE/EPC

16

The mini-Review took place on April 8, 2015

Page 17: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Agenda1. Scope and objectives of the review Félix Rodríguez Mateos 10’

2. Introduction to the CLIQ protection method

Emmanuele Ravaioli 15’

3. General aspects of the design, choice of components and safety issues

Knud Dahlerup-Petersen 15’

4. Details of the design Joaquim Mourao 30’

5. Integration and implementation Mathieu Favre 15’

6. Discussion and questions from the panel

All 30’

17

Page 18: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Recommendations (1)

• Components• use the higher rated ABB thyristors which give larger margin in all

parameters• set 0.5s for the duration of the train of pulses• discharge resistors should not to be mounted on a PCB, 20 resistors

in series should not be used• thyristor firing circuit to be completed (paying attention to

magnetization of the pulse transformers)• use an AC current transformer instead of a LEM for discharge current

measurement• qualify the AC/DC converter in terms of EMC or use qualified material

16/04/2015 MPE Technical Meeting 18

Page 19: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Recommendations (2)• Safety

• maximum discharge time should be 1 min• use a switch that a) triggers internal discharge, b) short-circuits

capacitors and c) allows opening the cubicles (if required)• use a properly rated circuit breaker for ON/OFF and not a

“sectionneur”, or add a fuse• earthing issue: for such mobile units as the ones under discussion the

earth connection given through the powering mains is enough• no need for special screws, idem for internal plastic covers• install galvanometers to show the charge/discharge of each capacitor

• Project Management• prepare test programme well in advance• prepare documentation for the future users• structure the project (mandate, functional specifications, technical

specifications, planning, responsibilities, etc)

16/04/2015 MPE Technical Meeting 19

Page 20: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

A glance to the future of CLIQ

Page 21: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Near future plan for protecting magnets with CLIQ

LHC-high luminosity upgrade

QXF is the inner triplet large quadrupole strings of magnets either side of the ATLAS and CMS.

Model testing in Fermi-lab (two units plus spare)

Model testing in CERN (Two units plus spare)

First long magnet prototype test in BNL (Two units plus spare)

Production of 32 + spares units for LHC-HL, assuming two units per magnet.

Courtesy Glyn Kirby

Page 22: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Longer term possibilities for use in LHC-HL upgrade• CERN

• Orbit correctors for LHC-HL: Twin aperture independently powered dipole• MQY for LHC-HL with pushed performance for the upgrade. Currently being

tested in SM 18 at CERN. • Each magnet would need 4 units

• LHC: Main dipole will be tested at CERN in SM18 in the following months in view for rapid repair of LHC systems

• Outside CERN• KEK Japan: D1, LHC-HL Single aperture standalone dipoles requiring 4 units

+ spares • CEA France: Q4 Twin aperture quadrupoles ~ 16 units + spares• GSI: they are investigating for use with their magnet systems

• Further future• 16 Tesla hybrid FCC models

• block design & cos-theta design could benefit from CLIQ• CCT design (canted cosine theta) may rely on CLIQ; LBNL have requested two

units for future testing of their 16 Tesla CCT magnet.

Page 23: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

The team

Page 24: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.

Members of the team in MPE• Knud Dahlerup-Petersen• Arnie Dinius• Mathieu Favre• Joaquim Mourao• Bozhidar Panev• Emmanuele Ravaioli• Felix Rodriguez Mateos• Other contributors: Gert Jan Coelingh

Alexandr Erokhin

Yan Bastian

24

Page 25: Overview of the CLIQ Units Project Knud Dahlerup-Petersen, Félix Rodríguez-Mateos TE-MPE Technical Meeting CERN, April 16 2015.