Page 1
5vk4
005E
. v5.
0, 20
18-0
3-01
KRAFTNÄTSWEDISH NATIONAL GR1D
SVENSKA
UNIT, BUSINESS AREANTL Overhead Transmission Lines, Grid Technology
DATE9 March 2020
CONSULTATIONSNAL, NLB, NLP
>1 Jff jtfREVISION
4
OUR REFERENCETR05-IOE
TECHNICAL GUIDELINE
APPROVEDTd
Overhead transmission linesInsulator set and overhead earth wire set
IntroductionThese guidelines describe the requirements on insulator sets and in applicable parts of earth wire sets and cover design, test and installation. The guidelines intend to guarantee satisfaetoiy performance of insulator sets and overhead earth wire set during the lifetime of the overhead line and shall be used at purchasing of insulator sets.
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Page 2
2 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Revision Notes Change notes Date
1 (A) Revision of standards and new template 09 / 07 2010
2 Template changed.Clause. 10.5.1.4 support clamp inserted. Clause 10.5.4.2 creepage text revised. Clause 10.6.7 ”Dry” inserted in headline. Clause 10.6.8 ”Dry” inserted in headline. Clause 10.9.1 locking of bolt and nut inserted. Clause 10.9.2 installation conditions inserted. Clause 10.9.3.2 placement of transposition installation sets revised. 10.8,2.5 revised. 10.8.3 added.
02 / 04 / 2012
3 New template and change of clause numbers. Rev. clause 5.4.2, 6.1, 8.2.5, 9.2 installation requirements. Clause 9 inserted:” nuts in long direction be installed on the side towards lower tower number”. Inserted in clause 9.3 “in vertical direction shall bolt head be installed on the upper side and nuts underneath. Inserted: Transposition sets shall not be installed at crossings with roads.
27 / 06 / 2014
4 Totally reworked 09 / 03 / 2020
Page 3
3 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Content
1 References ........................................................................................................... 6
2 Scope .................................................................................................................... 6
3 Definition ............................................................................................................ 6
4 Requirements ...................................................................................................... 7
4.1 General 7
4.2 Material 7
4.2.1 Insulators 7
4.2.2 Insulator fittings 7
4.2.3 Power arc protection devices 7
4.2.4 Suspension and support clamps 7
4.2.5 Tension clamps 7
4.3 Design 8
4.3.1 General 8
4.3.2 Insulation 8
4.3.3 Arching distance 10
4.3.4 Yokes 10
4.3.5 Arcing ring (Power arc protection device) 10
4.3.6 Counterweights 10
4.4 Mechanical requirements 11
4.5 Electrical requirements 11
4.5.1 General 11
4.5.2 Power frequency withstand voltage 11
4.5.3 Corona 11
4.5.4 Radio interference 11
4.5.5 Lightning overvoltage 11
4.5.6 Switching overvoltage 12
4.5.7 Short circuit current 12
5 Type test ............................................................................................................ 12
5.1 General 12
5.2 Dimensions 12
Page 4
4 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
5.3 Wet power frequency withstand voltage 12
5.4 Corona 13
5.5 Radio interference 13
5.6 Dry lightning impulse withstand voltage 14
5.7 Wet switching impulse withstand test 14
5.8 AC power arc test 14
6 Delivery ............................................................................................................. 14
6.1 Documentation 14
6.1.1 General 14
6.1.2 Assembly drawing 15
6.1.3 Reports 15
6.1.4 Transport and storage 15
7 Installation ........................................................................................................ 15
7.1 General 15
7.2 Installation of straight line, angle line and V-string insulator sets 15
7.2.1 General 15
7.2.2 Straight line suspension insulator sets 15
7.2.3 Angle line suspension insulator sets 16
7.2.4 V-string insulator sets 16
7.3 Installation of tension and transposition insulator sets 17
7.3.1 Tension insulator set 17
7.3.2 Transposition insulator sets 17
8 Tables................................................................................................................. 19
Tabell 1 Withstand voltage 19
9 Figures .............................................................................................................. 20
Figure 1 Straight line suspension insulator set 20
Figure 2 Angle suspension insulator set 22
Figure 3 V-string suspension insulator set 23
Figure 4 Tension insulator set 24
Figure 5 Transposition tension insulator set 26
Figure 6 Earth wire sets 27
Figure 7 Attachment of counterweight 28
Page 5
5 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 8 Straight line suspension insulator set bolt orientation 29
Figure 9 Tension insulator set bolt orientation 30
Page 6
6 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
1 References EN ISO 9001 Quality management systems - Requirements C.I.S.P.R 16-2-1 Specification for radio disturbance and immunity
measuring apparatus and methods - Part 2: Methods of measurement of disturbances and immunity
C.I.S.P.R 18 – 2 Radio interference characteristics of overhead power
lines and high-voltage equipment - Part 2: Methods of measurement and procedure for determining limits
IEC 61284 Overhead lines - Requirements and tests for fittings IEC 61467 Insulators for overhead lines with a nominal voltage
above 1 000 V- A.C. Power Arc Tests on insulator sets EN 50341-1 Overhead electrical lines exceeding AC 1 kV General
requirements – Common specifications SS-EN 50341-2-18 Overhead electrical lines exceeding AC 1 kV National
Normative Aspects (NNA) for Sweden IEC 60383-2 Insulators for overhead lines with a nominal voltage
above 1 000 V- Part 2: Insulator strings and insulator sets for a.c. systems - Definitions, test methods and acceptance criteria
TR05-01 Svenska kraftnät Teknisk riktlinje - Luftledningar
Anläggningsdokumentation TR05-04E Svenska kraftnät Technical guidelines - Conductors TR05-05E Svenska kraftnät Technical guidelines – Suspension
clamp and support clamp TR05-06E Svenska kraftnät Technical guidelines – Tension clamp TR05-11E Svenska kraftnät Technical guidelines – Insulators
TR05-12E Svenska kraftnät Technical guideline – Fittings for
insulator and overhead earth wire sets
2 Scope
These guidelines are applicable to suspension, tension and transposition insulator
sets and overhead earth wire set which are to be used on AC overhead lines with
alternating current and comprise design, testing and installation.
3 Definition
Technical terms and definitions used in these guidelines:
Insulator set
Page 7
7 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Device for insulating conductors either in suspension or tension.
Insulator string
The insulating part of the insulator set consisting of one or more insulators joined
together.
Highest voltage for equipment
The highest value of phase-to-phase voltage for which the equipment is designed.
The highest voltage for equipment is designated Um in this document.
Corona extinction voltage
The voltage where no corona is visible when the voltage is reduced from a level with
visible corona.
Fault current
The greatest short duration current which is caused by either a short-circuit (Ik) or
an earth fault (3Io).
USCD
Creepage distance of an insulator divided by the r.m.s. value of the highest
operating voltage across the insulator.
4 Requirements
4.1 General The manufacturer shall have a quality system in accordance with at least EN ISO 9001.
4.2 Material
4.2.1 Insulators
Insulators shall conform to the requirements of Svk TR05-11E.
4.2.2 Insulator fittings
Insulator fittings shall conform to the requirements of Svk TR05-12E.
4.2.3 Power arc protection devices
Power arc protection devices shall conform to the requirements of Svk TR05-12E.
4.2.4 Suspension and support clamps
Suspension and support clamps shall conform to the requirements of Svk TR05-
05E.
4.2.5 Tension clamps
Tension clamps shall conform to the requirements of Svk TR05-06E.
Page 8
8 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
4.3 Design
4.3.1 General
Insulator set design shall conform to TR05-10E figure 1-5 with respect to fittings,
fitting orientation, and ability to pivot. In addition the overall length of the
insulator set shall be designed to be as short as possible.
Earth wire set design shall conform to TR05-10E figure 6 with respect to fittings,
fitting orientation, and ability to pivot.
Maximum length for individual extension links in tension set is 2 m. Joint between
extension links shall have the ability to pivot horizontally as well as vertically. See
example below.
4.3.2 Insulation
Creepage
Pollution classes for areas in Sweden shall be in accordance with the table below.
Area Pollution classes USCD (mm/kV)
Distance from the coast
West coast
E-Very heavy 53,7 0-0,5 km
D-heavy 43,3 0,5-15 km
C-Medium 34,7 15-30 km
East coast in Götaland C-Medium 34,7 0-10 km
Skåne C-Medium 34,7 -
Öland and Gotland C-Medium 34,7 -
Remaining areas AB-Light 25 -
It is recommended to increase the creepage distance one pollution class for
insulation placed within 50 m from roads with motorized traffic which is
salted in wintertime.
It could be a need to increase the creepage distance for insulation placed
nearby polluting industries.
Creepage distance on transmission lines and its substations should be
coordinated.
Page 9
9 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
In new built 400 kV transmission lines with conductor 3x910 Al59/phase shall the
number of insulators and type be as below:
Pollution class Suspension set Tension set
AB 16xU210B 14xU300B
2x14xU300B
C 16xU210BP (fog) 14xU300BP (fog)
2x14xU300BP (fog)
D-E Class C with RTV coating Class C with RTV coating
In new built 220 kV transmission lines shall the number and type of insulators be
as below:
When rebuilding existing transmission lines, insulators shall be selected so that
original creep distance is preserved.
Pollution class Suspension set Tension set
AB 14xU70BL
14xU120B
12xU210B
11xU300B
Strings shall have the same
quantity of insulators as for
suspension string. Insulator
type, single or double string are
depending on design load.
C 14xU70BL (fog)
14xU120B (fog)
12xU210B (fog)
11xU300B (fog)
D 14xU70BL (fog) 1)
14xU120BP (fog) 1)
12xU210BP (fog)
11xU300BP (fog)
1) With RTV coating
E Class D with RTV coating
Page 10
10 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
4.3.3 Arching distance
For new lines shall the distance between power arcing horns be as below:
Highest voltage for equipment
kV
Arching distance
mm
245 1760 −20+35
420 2300 −20+50
In rare cases at line connection to station it can be necessary to increase arcing
horn distance for the adjacent line towers. This shall be decided together with
Svenska kraftnät.
When rebuilding existing transmission lines, original arching distance shall be
preserved.
4.3.4 Yokes
Yokes for twin and triple bundle conductors for new lines shall be so designed that
the distance between sub-conductors will be 450 mm up to and including a
conductor diameter of 32 mm and 600 mm for conductor diameter greater than 32
mm.
Yokes for twin and triple bundle conductors for exiting lines shall be so designed
that the distance between sub-conductors will be unchanged.
4.3.5 Arcing ring (Power arc protection device)
Power arc protection devices shall conform to the requirements of Svk TR05-12E.
Radiated heat from power arcs shall not damage insulator sets.
4.3.6 Counterweights
Straight line and angle suspension insulator sets for the suspension of single, twin
or triple conductors shall be so designed as to allow for the addition of
counterweights when necessary.
Counterweights shall conform to the requirements of Svk TR05-12E.
Attachment of counterweight shall conform to TR05-10E figure 7.
The transverse swing of suspension insulator sets, with counterweights fitted to
suspension clamps, shall be limited to 45°. See Svk TR05-05E.
Page 11
11 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
4.4 Mechanical requirements Insulator sets shall conform to the mechanical requirements of SS-EN 50341-2-18
Overhead electrical lines exceeding AC 1 kV National Normative Aspects (NNA) for
Sweden.
4.5 Electrical requirements
4.5.1 General
Electrical designing/dimensioning shall, in addition to what is stated in these
technical guidelines, be performed in accordance with SS-EN 50341-18-2 Overhead
electrical lines exceeding AC 1 kV National Normative Aspects (NNA) for Sweden .
The length of the insulator string for insulator sets intended for insulation between
phase and earth shall be such that the required arcing distance to achieve the
withstand voltages given in TR05-10E table 1 are obtained.
The length of the insulator string in insulator sets intended for insulation between
phases shall be such that minimum arcing distances of 130% and 137% of that for
phase to earth insulation are obtained for the highest voltages for equipment of 245
kV and 420 kV respectively
4.5.2 Power frequency withstand voltage
The power frequency withstand voltage of insulator sets, which are intended for
phase to earth insulation, shall be the minimum voltage stated in TR05-10E table 1
when tested in accordance with IEC 60383-2.
The power frequency withstand voltage of insulator sets, which are intended for
phase to phase insulation, shall be a minimum of 3 times the voltage stated in
TR05-10E table 1 when tested in accordance with IEC 60383-2.
4.5.3 Corona The insulator set shall have no visible corona at the test voltage defined by:
1,1*3
UgeTest volta m
Where Um is the highest voltage for equipment stated in TR05-10E table 1.
4.5.4 Radio interference
The radio interference level for insulator sets shall be less than 60 dB at the highest
voltage for equipment with 50 Hz alternating voltage (r.m.s. value) over 1V
interference voltage and 500 kHz measuring frequency
4.5.5 Lightning overvoltage
The lightning impulse withstand voltage for insulator sets intended for phase to
earth insulation shall be that stated in TR05-10E table 1 when tested in accordance
with IEC 60383-2.
Page 12
12 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
4.5.6 Switching overvoltage
The switching impulse withstand voltage for insulator sets intended for phase to
earth insulation shall be that stated in TR05-10E table 1 when tested in accordance
with IEC 60383-2.
The switching impulse withstand voltage for insulator sets intended for insulation
between phases shall be a minimum of 140% for 245 kV and 150% for 420 kV
highest voltages for equipment of that stated in TR05-10E table 1 when tested in
accordance with IEC 60383-2.
4.5.7 Short circuit current
Insulator sets shall be thermally designed to resist the stated fault current and fault
time so that the mechanical strength of fittings, which are subject to fault current,
is not weakened due to the heating caused by the fault current. In addition the zinc
layer of hot-dip galvanized steel fittings is not to be damaged. Welding due to
power arcs between fittings included in insulator sets shall be as far as possible
avoided.
5 Type test
5.1 General Unless otherwise agreed the type test is to be performed in accordance with TR05-
10E clause 5.2, on one test insulator set for each type and included all components.
On request of the client type test is to be performed in accordance with TR05-10E
clauses 5.32 - 5.8 with an agreed quantity of insulator sets.
The insulator set shall be installed in accordance with the relevant drawings and
simulate insulator set in service.
The tests shall be performed in such a way that neither the method nor the
equipment affects the result.
5.2 Dimensions The intention of this test is to check that the insulator set being in accordance with
the manufacturers drawings regarding measurements.
The test is performed by assemble all the components.
5.3 Wet power frequency withstand voltage The intention of this test is to establish the wet power frequency withstand voltage
of a complete insulator set.
Page 13
13 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
The insulator set is to be installed such that the clearance from live to earth given in
TR05-10E table 1 is obtained. The insulator set is then to be subjected to 50 Hz
alternating current. This test is to be performed as a wet test in accordance with
IEC 60383-2.
The wet power frequency withstand voltage of insulator sets, which are intended
for phase to earth insulation, shall be the minimum voltage stated in TR05-10E
table 1.
The wet power frequency withstand voltage of insulator sets, which are intended
for phase to phase insulation, shall be a minimum of 3 times the voltage stated in
TR05-10E table 1.
5.4 Corona The intention of this test is to establish the corona extinction voltage for a complete
insulator set and is to be performed in a fully-darkened room. During the corona
test the use of either field glasses with a minimum optical performance 7x50, or an
image intensifier with light amplification greater than 40 000 in accordance with
IEC 61284, is recommended.
The distance from the live phase to earth shall be as stated in TR05-10E table 1 and
the insulator set is to be subjected to 50 Hz alternating current.
The corona extinction voltage shall exceed the calculated test voltage in accordance
with TR05-10E clause 4.5.3.
The positive and negative corona extinction voltage is to be recorded. It shall be
documented by colour photographs, one with visible corona and another at the
corona extinction voltage level, with the voltage levels being indicated on the
photographs.
The test shall be performed in accordance with the applicable sections of IEC
61284.
5.5 Radio interference The intention of this test is to establish the level of radio interference for a complete
insulator set.
The test shall be performed with the highest voltage for equipment, 50 Hz
alternating voltage (r.m.s. value) over 1 V interference voltage and 500 kHz
measuring frequency. Testing is to be in accordance with C.I.S.P.R publication 16-
SER and the results evaluated in accordance with C.I.S.P.R publication 18-2.
The distance from the live phase to earth shall be as stated in TR05-10E table 1.
Page 14
14 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
The level of interference at the highest voltage for equipment shall fulfil the
requirements of TR05-10E clause 4.5.4.
5.6 Dry lightning impulse withstand voltage The intention of this test is to establish the lightning impulse withstand voltage for
a complete insulator set.
The distance from the live phase to earth shall be as stated in TR05-10E table 1 and
the insulator set is to be subjected to a lightning impulse withstand voltage test in
accordance with IEC 60383-2.
The lightning impulse withstand voltage shall exceed the voltage stated in TR05-
10E table 1.
5.7 Wet switching impulse withstand test The intention of this test is to establish the switching impulse withstand voltage for
a complete insulator set.
The distance from the live phase to earth shall be as stated in TR05-10E table 1 and
the insulator set is to be subjected to a wet switching impulse withstand voltage test
in accordance with IEC 60383-2.
The switching impulse withstand voltage shall exceed the voltage stated in TR05-
10E table 1.
5.8 AC power arc test The intention of this test is to establish the capacity of a complete insulator set to
withstand flash-over with a power arc.
Complete insulator set with clamps and conductors is to be installed and tested in
accordance with IEC 61467 test series X and test circuit A (In = 0,5 Isys and two tn=
0,2 s and one of tn=1 s).
The insulator set shall fulfill the acceptances criteria in accordance with IEC 61467.
6 Delivery
6.1 Documentation
6.1.1 General
All documentation shall be written in English.
Complete documentation according to TR05-10E clauses 6.1.2 - 6.1.3 shall be
available to the client before delivery.
Page 15
15 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
6.1.2 Assembly drawing
Assembly drawing shall have a minimum of two views at an appropriate scale
according to TR05-01. On each drawing shall be given:
Type and/or catalogue number
Principal dimensions
Arcing distance
Creepage distance
Breaking load
Fault current
Weight, with and without insulators
List of materials
6.1.3 Reports
Complete reports, with all measured values reported, from all controls according to
TR05-10E clause 5.
6.1.4 Transport and storage
The insulator sets shall be packed up in such a way that they will not be damaged or
fouled at transport, construction and storing.
7 Installation
7.1 General Installation of insulator sets shall be performed in accordance with the relevant
drawings. The arching ring nuts shall be locked with two punches.
7.2 Installation of straight line, angle line and V-string insulator sets
7.2.1 General
Suspension sets shall be installed vertical to the direction of the line. Maximum
allowed deviation to the vertical plane at the suspension clamp is L/40, where L=
length of the insulator set.
7.2.2 Straight line suspension insulator sets
Arching horn on suspension insulator sets shall be installed in such a way that any
power arc will have a predestined direction transverse to the direction of the line
and outwards away from the insulator set and the support.
Page 16
16 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
With a horizontal phase arrangement arching horn for the middle phase shall be
installed in such a way that the power arc will have a predestined direction to the
right transverse to the direction of the line when looking towards higher support
numbers.
The pivot bolt nut and the eye of the split pin in a socket are to be installed facing
the support. For the middle phase the nut and the eye of the split pin are to be
installed facing left when looking towards higher support numbers. See TR05-10E
figure 8a.
The pivot bolt nuts in fittings between the conductors and the yoke plate are to be
installed facing each other in twin bundle conductor arrangements and similarly
for the upper two conductors in triple bundle conductor arrangements. See TR05-
10E figures 8b and 8c respectively.
In longitudinal direction shall the nuts be installed facing against lower support
number.
7.2.3 Angle line suspension insulator sets
Power arc protection devices on angle suspension insulator sets shall be installed in
such a way that any power arc will have a predestined direction upwards.
In inclined suspension insulator sets the pivot bolt nut and the eyes of split pins in
sockets are to be installed facing downwards.
Nuts on horizontally orientated pivot bolts and the eyes of split pins in sockets are
to be installed facing the support. For the middle phase the nut and the eye of the
split pin are to be installed facing left when looking towards higher support
numbers.
The pivot bolt nuts in fittings between the conductors and the yoke plate are to be
installed facing each other in twin bundle conductor arrangements and similarly
for the upper two conductors in triple bundle conductor arrangements. See TR05-
10E figures 8b and 8c respectively.
In longitudinal direction shall the nuts be installed facing against lower support
number.
7.2.4 V-string insulator sets
Arching horn on V-string suspension insulator sets shall be installed in such a way
that any power arc will have a predestined direction upwards.
For inclined insulator sets the pivot bolts nuts, the eyes of split pins in sockets and
power arc protection device attachment arms, are to be installed facing downwards.
Page 17
17 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Nuts in horizontally orientated pivot bolts and the eyes of split pins in sockets are
to be installed facing the support. For the middle phase the nut and eyes of the
split pins are to be installed facing left when looking towards higher support
numbers.
The pivot bolt nuts in fittings between the conductors and the yoke plate are to be
installed facing each other in twin bundle conductor arrangements and similarly
for the two upper conductors in triple bundle conductor arrangements.
In longitudinal direction shall the nuts be installed facing against lower support
number.
7.3 Installation of tension and transposition insulator sets
7.3.1 Tension insulator set
Power arc protection devices on tension insulator sets shall be installed in such a
way that any power arc will have a predestined direction upwards.
Nuts on vertical orientated pivot bolts, the eyes of split pins in sockets and power
arc protection device attachment arms, are to be installed facing downwards.
Nuts on horizontally orientated pivot bolts and the eyes of split pins in sockets are
to be installed facing the support. For the middle phase the nuts and eyes of the
split pins are to be installed facing left when looking towards higher support
numbers. See TR05-10E figure 9a.
The pivot bolt nuts on fittings between the conductors and the yoke plate are to be
installed facing each other in twin bundle conductor arrangements and similarly
for the upper conductors in triple bundle conductor arrangements. See TR05-10E
figures 9b and 9c respectively.
For bolts in vertical direction shall the bolt head be on the upper side and the nut
underneath.
7.3.2 Transposition insulator sets
Transposition tension sets are not allowed in spans that cross traffic routes,
railways and transmission lines, nor in the adjacent spans.
Power arc protection devices on transposition insulator sets shall be installed in
such a way that any power arc will have a predestined direction upwards.
Nuts on vertically orientated pivot bolts, the eyes of pins in sockets and power arc
protection device attachment arms, are to be installed facing downwards.
Page 18
18 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Nuts on horizontally orientated pivot bolts and the eyes of split pins in sockets are
to be installed facing the support. For the middle phase the nuts and the eyes of
split pins are to be installed facing left when looking towards higher support
numbers. See TR05-10E figure 9a.
The pivot bolts nuts on fittings between the conductors and the yoke plate are to be
installed facing each other in twin bundle conductor arrangements and similarly
for the two upper conductors in triple bundle conductor arrangements. See TR05-
10E figures 9b and 9c respectively.
For bolts in vertical direction shall the bolt head be on the upper side and the nut
underneath.
Page 19
19 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
8 Tables
Tabell 1 Withstand voltage
Highest voltage for equipment
kV
Rated withstand voltage
kV
Distance
m
Um, phase – phase Lightning impulse
Switching impulse
Power frequency
Phase to earth
245 850 650 360 3
420 1175 950 - 4
Page 20
20 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
9 Figures
Figure 1 Straight line suspension insulator set
Figure 1a Single string, triplex conductor
Page 21
21 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 1b Single string for dropper attachment, triplex conductor
Page 22
22 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 2 Angle suspension insulator set
Page 23
23 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 3 V-string suspension insulator set
Page 24
24 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 4 Tension insulator set
Figure 4a Single string, simplex conductor
Figure 4b Single string, duplex conductor
Figure 4c Double string, duplex conductor
Page 25
25 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 4d Long, double string, duplex conductor
Figure 4e Double string, triplex conductor
Figure 4f Long, double string, triplex conductor
Page 26
26 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 5 Transposition tension insulator set
Figure 5a Single string, simplex conductor
Figure 5b Single string, duplex conductor
Figure 5c Double string, triplex conductor
Page 27
27 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 6 Earth wire sets
Figure 6a Suspension set
Figure 6b Tension set
Figure 6c Insulated tension set
Page 28
28 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 7 Attachment of counterweight
Figure 7a Counterweight installation, single conductor
Figure 7b Counterweight installation, duplex conductors
Figure 7c Counterweight installation, triplex conductors
Page 29
29 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 8 Straight line suspension insulator set bolt orientation The arrows indicate the direction bolts must face when looking towards higher
support numbers.
Figure 8a Straight line support
Figure 8b Twin bundle conductor Figure 8c Triple bundle conductor
Page 30
30 (30)
TECHNICAL GUIDELINE 9 March 2020 TR05-10E rev 4
Figure 9 Tension insulator set bolt orientation The arrows indicate the direction bolts must face.
Figure 9a Terminal support
Figure 9b Twin bundle conductors
Figure 9c Triple bundle conductors
Towards higher support numbers