1 Overcoming Construction Challenges: The Dixboro Road Bridge Project • “Old” bridges originally constructed 1921; widened 1969. • Road Commission received notification from the MDOT of the Critical Bridge award in 1992. • Preliminary corridor study initiated 1995; Environmental Assessment initiated 1997, completed 1999. • Final design commenced 2000. • Project bid January 2004. Low bid $9.6M, 2.2% over Engineers Estimate. April 1947 December 1956
24
Embed
Overcoming Construction Challenges: The Dixboro Road ... · 1 Overcoming Construction Challenges: The Dixboro Road Bridge Project • “Old” bridges originally constructed 1921;
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
Overcoming Construction Challenges:
The Dixboro Road Bridge Project
• “Old” bridges originally constructed 1921; widened 1969.
• Road Commission received notification from the MDOT of the Critical Bridge award in 1992.