Developing Africa’s energy potential and integrating power supply systems for sustainable development in African countries (case of Niger). Outline Introduction………………………………………………………………………………………..….…3 Development of the AGADEM oil and gas fields……………………….……..…..…..3 - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Outline Introduction………………………………………………………………………………………..….…3

Developing Africa’s energy potential and integrating power supply systems for sustainable development in African

countries (case of Niger)

Page 2: Outline Introduction………………………………………………………………………………………..….…3

Outline  Introduction………………………………………………………………………………………..….…3 

Development of the AGADEM oil and gas fields……………………….……..…..…..3 

Construction of a 330 KV high-voltage interconnection line linking Agadem-Zinder-Tahoua-Filingué-Niamey…………………………………...…..………………...4

 

 Project feasibility ……………………………………………..……………………………………4 

 Advantages………………………………………………..………………….……………..………..5

 Prospects……….……………………………………………….…………………………..………… 5

Page 3: Outline Introduction………………………………………………………………………………………..….…3

IntroductionThe  electricity  crisis  Niger  is  going  through  is structural by nature. It is linked, on the one hand, to the  inadequacy  and  instability  of  the  electrical power  generation  in  Nigeria,  which  is  providing Niger almost  full  supply, and  to  the deficiency and obsolescence of the equipment for electrical power transmission between Nigeria and Niger.

Page 4: Outline Introduction………………………………………………………………………………………..….…3

The  local  production  of  electricity  accounts  for approximately one third of the overall consumption. It  is generated through the combustion of  imported hydrocarbons,  with  very  low  generation  capacities for a very high cost per kWh. And this is a hindrance to  industrial development.  Joint  reflections must be initiated  to  seek  the  appropriate  solution  that  will enable  Niger  to  generate  cheap  electrical  power required  for  its  long-term  economic  and  social development.This contribution is made from this angle.

Page 5: Outline Introduction………………………………………………………………………………………..….…3

Development of the AGADEM Oil and Gas FieldsThe  development  of  the  Agadem  oil  fields  gave evidence of the existence of 10 billion cubic meters of natural gas  in Agadem. This development  is  still underway  and  several  oil  companies  are  seeking exploration  permits  for  the  Agadem  block.  This proven  quantity  of  gas  will  enable  electricity generation on Agadem in large supply and over the long term. 

As of May 2010, the national electrical power demand recorded  is  about  150  MW.  The  strong  scenario-based prospective studies anticipate the demand of electricity to be of 1260 MW by 2030 in Niger.

Page 6: Outline Introduction………………………………………………………………………………………..….…3

Given the large quantity of gas available in Agadem, a thermal gas combined cycle power station of 500 MW may be built to start with.The power generated at the Agadem power station

will be conveyed to points of use by a 330 KV transmission line 

Also,  Niger,  Algeria  and  Nigeria  have  entered  into  a cooperation  agreement  to  build  a  trans-Saharan pipeline  connecting  them  to  Europe.  Under  this agreement,  Niger  may  access  a  large  of  quantity  of gas  to  cover  its  needs.  This  additional  resource  will supply fuel to new power plants.

Page 7: Outline Introduction………………………………………………………………………………………..….…3

Construction of a 330-KV high-voltage line linking Agadem-Zinder-Tahoua-Filingué-Niamey

  The transmission line for the power generated in Agadem will be about 1516-km long, breaking down as follows: Agadem-Zinder,  616  km;  Zinder-Tahoua,  460  km; Tahoua-Filingué, 240 km; Filingué-Niamey, 200 km. 

 The layout of the 330-KV electricity transmission line will be exactly the same as the layout of the pipeline linking Agadem to Zinder over 460 km. In Zinder, this line will be  combined  to  the  existing  132-KV  Zinder-Gazaoua-Maradi  line  to  supply  the  Zinder, Maradi  and  Tahoua regions and possibly part of Northern Nigeria.

Page 8: Outline Introduction………………………………………………………………………………………..….…3

Oil  refining  in  Zinder  will  generate  60  000  tons  of liquefied gas (LPG) per year, which may be used to supply fuel  for  another  combined  cycle power plant generating 60-MW that will be connected to the 330-KV grid.  In  Tahoua,  the  330-KV  line  will  be  combined  to  the existing  network  to  supply  the  Tahoua  region  and, possibly,  the  Agadez  region  with  the  construction  of  a 132-kV connecting line for Zinder-Tchirozérine.

The  future  Salkadamna  power  plant,  which  will eventually generate 200-MW power, will be connected to the 330-KV line. The  330-KV  line  will  reach  Niamey  via  Filingué  where significant coal indices have been identified.

Page 9: Outline Introduction………………………………………………………………………………………..….…3

In Niamey, the 330-KV line will supply the Niamey and Tillabéry  regions  as  well  as  Niger’s  neighbouring countries  through  the  connection  to  the  Northern WAPP  electricity  backbone,  which  will  consist  in building a 330-KV line between Birni Kebbi (Nigeria) - Zabori  (Niger)  -  Niamey  (Niger)  -Ouagadougou (Burkina Faso) and feeder  line from Zabori  (Niger)  to Bembéréké (Bénin).

The  future  Kandadji  hydropower  plant,  which  will eventually  generate  130-MW  power,  will  be connected to the 330-KV line. 

Page 10: Outline Introduction………………………………………………………………………………………..….…3

Feasibility of the project The project for construction of a natural gas-fired power plant in Agadem, with an outgoing 330-KV power line on the Agadem-Zinder-Tahoua-Filingué-Niamey axis is technically feasible and economically justifiable.

AdvantagesThis project will help meet definitely and over the long term the power requirements necessary for Niger’s economic and social development.It  will  serve  as  an  integration  factor  by  enabling  Niger  to integrate  the West African Power Pool  system, get  involved  in the future ECOWAS electricity market and turn Niger into power pole which will eventually be  in a position to export electricity to  neighbouring  countries  such  as  Nigeria,  Burkina-Faso  and Benin,  thanks  to  its  considerable  energy  potential,  especially the Agadem natural gas.

Page 11: Outline Introduction………………………………………………………………………………………..….…3

Currently,  there  are  several  financing  opportunities due  to  the  fact  the  resolution  of  electrical  power issues  in  Africa  stands  high  on  the  agenda  of international  financial  institutions  such  as  UEMOA, AfDB, the World Bank, etc. 

The recent final declaration of the 25th France-Africa Summit is a case in point.

In the context of a mutually fruitful cooperation, this project  is  of  interest  to  the  Russian  company GAZPROM,  which  made  a  declaration  of  intent  of collaborative effort involving GAZPROM and the State of Niger.

Page 12: Outline Introduction………………………………………………………………………………………..….…3

Prospects

  This  contribution  provides  an  avenue  which,  we hope, will  be widened  through  your  reflections  so as  to  bring  the  authorities  in  charge  of  solving energy  issues  to  support  technical,  bold  and ambitious solutions.

 