Our Temple. By Facilities Committee 10 April, 2011 Nani Bhowmik Bal Gopal Shiv Kapoor Pradeep Khanna Srinivas Nookala Kiran Topudurti Deoki Tripathy. Facts Review. Agenda. Reference (20 Feb 2011 BOT meeting minutes) Construction Estimates - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Our Temple

Our Temple

Page 2: Our Temple

Facts ReviewBy Facilities Committee

10 April, 2011

Nani BhowmikBal Gopal

Shiv KapoorPradeep KhannaSrinivas NookalaKiran TopudurtiDeoki Tripathy

Page 3: Our Temple

Agenda

1. Reference (20 Feb 2011 BOT meeting minutes)2. Construction Estimates

1. B&S Main Floor plus Basement (Reduced base bid + Unfinished side wings + Unfinished basement)

2. HTCSCI Main floor plus Basement(Original base bid + Finished side wings + Finished basement)

3. Comparison/Normalization of Bids4. O&M Costs + Capital Payment5. Q&A6. Where do we go from here?

Page 4: Our Temple

20 Feb 2011 BOT Minutes Motion: “Option #4 [reduced base bid] with

unfinished basement and unfinished side wings on the first floor as the final plan with an expected cost of $1.36M”

“if we cannot raise enough money in the next 6 weeks, we should revisit and revise the plan”

“takes full responsibility to raise $188,000 required for the construction of the unfinished basement provided that the basement is included in the construction plan”

Page 5: Our Temple

Construction Estimates - B&S Main Floor Plus Basement (Reduced base bid + Unfinished side wings + Unfinished basement)Reduced base bid: $1,084,580 *

Unfinished side wings: $62,500 **Unfinished basement *** $188,000 Total: $ 1,335,080

* Includes deductions of $143,420 from original base bid of $1,228,000** Option 2 – Option 1 (BOT minutes)

*** Unfinished means….“have restricted access, min heating & A/C”“have stairs entry and blocked for public until it is finished”

Page 6: Our Temple

Requirement for an Unfinished Basement

Page 7: Our Temple

According to the Champaign County Planning and Zoning Administration and the Illinois Capitol Development Board, for a Public Building when the Basement Area is more than 1,000 sq ft, we must install an elevator.

Page 8: Our Temple

Construction Estimates - HTCSCI Main Floor plus Finished Side Wings and Basement Plan(Original base bid + Finished side wings + Finished basement)

Original base bid (no gopurams): $871,460Finished side wings: $200,000Finished basement: $300,000

Total: $1,371,460

Page 9: Our Temple

Comparison/Normalization – Original Bids

Comparison/Normalization of bidsB&S HTCSCI

Original bid

$1,228,000 $871,460

$50,000

Gopurams $35,000

Additional costs $128,000 $128,000

Total $1,406,000 $1,034,460

Side wings Unfinished $62,500Finished $200,000

Basement Unfinished $188,000Finished $300,000Elevator $50,000

Grand Total $1,706,500 $1,534,460

concrete car parking and drive ( not oil and chip)

Water well, power, appliances, security system, speakers, sod. Etc.,

Page 10: Our Temple

Comparison/Normalization – Reduced Options

Comparison/Normalization of bids – With ReductionsB&S HTCSCI

original bid $1,228,000 $871,460

Reduced bid credits -$143,420 -$143,420

Gopurams $35,000

Additional costs $128,000 $128,000

Sub total $1,212,580 $891,040

Side wings Unfinished $62,500Finished $200,000

Basement Unfinished $188,000Finished $300,000Elevator $50,000

Grand Total $1,513,080 $1,391,040

Water well, power, appliances, security system, speakers, sod. Etc.,

Page 11: Our Temple

Summary Comparison

Summary comparisonB&S HTCSCI

Original bid $1,706,500

All finished $1,534,460

Reduced bid $1,513,080

All finished $1,391,040

Unfinshed side wings, Unfinished basement

Unfinshed side wings, Unfinshed basement

Page 12: Our Temple

O&M Costs - Loan

Community loan @2.00% and Bank loan @8.00%

5 years cost Per year Per monthTerm in years 5

Community $300,000.00 $331,224.24$163,564.85 $13,630.40Bank $400,000.00 $486,600.00

Community $300,000.00 $331,224.24

$285,244.85 $23,770.40Bank $900,000.00 $1,095,000.00

Single floor, no side wings (5072 SFT)

Two floors, finished side wings, finished basement

Page 13: Our Temple

O&M Costs – Maintenance

Maintenance

Item 5 year total

Maintenance

Total months 60

$50,000 $255,000

$100,000 $510,000Electricity+gas / month $700 $42,000

$300 $18,000

$1,500 $90,000Telephone + internet /month $60 $3,600cleaning per month $1,500 $90,000security+insurance / month $250 $15,000Garbage collection / month $150 $9,000

Total $522,600Monthly costs $8,710

Total $777,600Monthly costs $12,960

Cost per year or per month

1 priest for 3 deities (basic plan) salary + benefits2 priests for all deities (basic plan + side wings) salaries

lawn, snow mowing etc / monthflowers+puja supplies / month

costs with 1 priest

costs with 2 priests

Page 14: Our Temple

Monthly O&M and Capital Payment Cost Summary

O&M summary

Total$13,630

$8,710 $22,340With 1 priestWith 2 priests $12,960 $26,590

$23,770$32,480With 1 priest $8,710

With 2 priests $12,960 $36,730

Loan payment costs

Maintenance costs

loan of 300k and 400k

loan of 300k and 900k

Page 15: Our Temple

Q&A