Top Banner

of 12

Otc 15336

Jun 03, 2018

Download

Documents

mehdi6409
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/12/2019 Otc 15336

    1/12

    OTC 15336

    Installation of Deepwater Pipelines With Sled Assemblies Using The New J-LaySystem of the DCV BalderDick Wolbers and Rob Hovinga - Heerema Marine Contractors B.V.

    Copyright 2003, Offshore Technology Conference

    This paper was prepared for presentation at the 2003 Offshore Technology Conference held inHouston, Texas, U.S.A., 58 May 2003.

    This paper was selected for presentation by an OTC Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, as

    presented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect anyposition of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the writtenconsent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. The

    abstract must contain conspicuous acknowledgment of where and by whom the paper waspresented.

    ABSTRACTThis paper describes the most important features required for

    installing deepwater pipelines, pipelines with in-line sled

    assemblies, PLETs, and SCRs. This includes methodologiesspecifically developed to suit the capabilities of DCV Balder.

    During the last quarter of 2002, Heerema Marine Contractors

    (HMC) performed an extensive Trials program proving all

    pipelay methodologies and associated installation procedures

    of the DCV Balder. This included the installation of 10 km

    28-inch and 24-inch pipe with a Pipeline End Termination

    (PLET) and an in-line sled assembly.

    Subsequent to successful completion of these trials, the DCVBalder started with installation projects which included the

    installation of in-line sled assemblies with weights up to 136

    mT.

    INTRODUCTIONIn the past ten years, major oil companies extended theirexploration activities more and more into deeper water

    offshore areas, driven by portfolio considerations and the

    depletion of their easily accessible reservoirs.

    Heerema Marine Contractors (HMC) decided to respond to

    these market trends by setting up and executing a deepwaterinvestment program to convert the Semi-Submersible Crane

    Vessel (SSCV) Balder into the Deepwater Construction Vessel

    (DCV) Balder.

    Features of the DCV Balder specification include the 1050 mT

    capacity J-lay system and a 650 mT A&R winch, which incombination with the worlds largest Mooring Line

    Deployment winch provides the unique capability to lower

    pipelines with loads up 1200 T. The combination of the J-lay

    tower with the two main cranes of the DCV Balder allows for

    handling of large structures such as PLETs and in-line sleds

    complete with mudmats.

    Maintaining its existing heavy lifting capacity results in the

    following main benefits:

    The ability to use one vessel to execute all marine

    installation works for a complete Deepwater Field

    Architecture including the export system, thereby

    eliminating intermediate mobilizations, mode changes

    interface risks, and multiple mobilization charges.

    The ability to install deepwater flowlines and exporpipelines (up to 32-inch OD) with PLETs and in-line sled

    assemblies of up to 150 mT in water depths exceeding

    2000 meters.

    The ability to install Steel Catenary Risers (SCRs) andalternative risers concepts with special care for fatigue life

    considerations.

    DCV Balder is presently working for the BP Southern Green

    Canyon/Mississippi Canyon Deepwater development in the

    Gulf of Mexico. The Scope of Work comprises of theinstallation of the complete infrastructure for four major

    deepwater fields and associated deepwater export pipelines

    This would not only include 330 km of export pipelines and100 km of flowlines, but also 20 in-line sled assemblies and

    fifteen Steel Catenary Risers (SCRs). A typical deepwater

    field layout is presented in Figure 1.

    Recently completed projects include the installation of a 6.5

    mile pipeline with an in-line sled assembly weighing 136 mT

    This paper presents the specification and use of the DCV

    Balders enhanced capabilities, and the development of therevised working practices adopted by HMC. In addition

    HMCs Quality, Environment, Safety, and Health (QESH)

    Management System applied on all deepwater installation

    projects will be addressed.

    DCV BALDER CAPABILITIES

    The DCV Balder [Figure 2] was built as Semi-Submersible

    Crane Vessel (SSCV) in 1978. An extensive lifetime

    extension and conversion program was executed in 2001 [Ref

    1, 2, and 3]. Each of the seven new thrusters in the DP system

    is powered by the unique feature of having independent and

    separated engine rooms for each individual thruster. Thi

    means that losing one complete engine room due to fire or

    flooding in a DP Class 3, only results in the loss of one

    thruster. Hereby, the capability is maintained to hold positionin more than 40-knot winds in a DP Class 3 condition. The

  • 8/12/2019 Otc 15336

    2/12

  • 8/12/2019 Otc 15336

    3/12

    OTC 15336 3

    specific meetings and toolbox talks. In total, 33 JSAs were

    implemented, safety induction meetings for all crew members

    were held, and 1,994 toolbox talks took place, thus trainingapproximately 800 crew members to the procedures associated

    with deepwater pipelay.

    The offshore superintendents were assigned to the project as

    early as the HAZID and HAZOP sessions, thus activelyparticipating in the engineering. The clients were also

    participating in the sessions such as to develop a mutual

    understanding.

    During previous projects, a lesson learnt program was set up

    by HMC on the principle that the next project has to benefit

    from the lessons learnt of the previous ones. This approachhas always been very successful. For deepwater projects in

    the Gulf of Mexico, HMC had to develop new installation

    methods. To complement HMCs existing experience,

    resources with specific deepwater pipelay and welding skills

    were engaged at an early stage.

    At the heart of HMCs QESH Management System, three

    crucial activities take place namely:

    Risk Assessment

    Process Control

    Workers involvement

    The implementation of HMCs QESH Management System

    resulted in zero (0) Lost Time Incidents for the total Trials

    period and sets the target for future deepwater installationprojects executed by HMC.

    BP TRIALS

    GeneralThe DCV Balder was scheduled for an extensive TrialsProgram prior to start of the installation of deepwater

    pipelines. Based on these requirements and conditional to

    successful testing, other clients have since awarded HMC with

    installation contracts for deepwater projects.

    HMC and BP/HMC Trials

    The HMC and BP/HMC Trials were part of a testing programthat was set up after the Balder Conversion. The key purpose

    of the Trials was to demonstrate that the DCV Balder, together

    with its new J-lay system, could meet the installation

    requirements of the BP Program in a safe manner. In addition,

    the trials served to familiarize the Balder crew with the J-lay

    equipment and procedures.

    The following test phases can be distinguished:

    Inshore Testing & Offshore DP Trials

    Offshore Testing Phase 1, Mooring Line Deployment

    Winch Trials

    Offshore Testing Phase 2, Pipelay Tests, Including HMC

    & BP/HMC Trials.

    The majority of the Offshore Testing Phase 2 Program was

    held in MC Blocks: 373, 374, 375, 419, 420, and 464 in water

    depths ranging between 875 m (2869 ft) and 1250 m (4100 ft)

    The SoW for the BP Trial part was 10 km. A small portion othe HMC trials was executed in MC Block 644; in water

    depths between 5000 and 5300 ft.

    Besides familiarization and training of the offshore crew thepurpose for the HMC trials was:

    Functional testing of all pipelay components and systems

    Load testing all pipelay components

    System integration test of all pipelay systems working

    together

    Testing of main installation procedures

    Lloyds witnessed all tests during the HMC trials for

    independent verification and certification of all pipelay

    equipment including main installation procedures.

    The BP/HMC trial was a mutually agreed pipelay scope and

    consisted of the following [Ref. Table 2]: Installation of 10 km 28-inch and 24-inch pipeline

    Initiation using a first-end PLET

    Abandonment & Recovery procedure

    Installation of an inline structure, Wye Sled Assembly

    (WSA) [Figure 4 and 5]

    Recovery of all pipe including WSA and PLET

    The BP/HMC trials are visualized in attached step-by-step

    sketch [Figure 8]

    During both HMC and BP/HMC Trials, a 28-inch Trial Wye

    Sled Assembly (WSA) was installed into the tower. During

    the BP/HMC Trial, buoyancy modules were attached to instalthe WSA onto the seabed [Figure 4 and 5].

    The side-step procedure, using the portside crane for lifting

    the sled assembly in the tower and lowering the pipe with sled

    assembly welded was successfully tested [Figure 6 and 7]. Anoverview of the activities executed during the BP trials is

    presented in Figure 8.

    Dynamics of Installation of in-line sled assemblies

    Prior to the start of the installing in-line-sled assemblies

    project, HMC has performed static and dynamic analysis to

    evaluate the installation of the largest structures of whichweight and size were unprecedented in the industry. The

    dynamic analyses have been compared with observations

    made during the installation of the WSA during the trials

    Based on the dynamic analysis and associated fatigue

    analyses, a weather criterion was set. The characteristic of the

    critical welds in the sled assemblye and the acceptance criteria

    for these welds have been taken into account when setting the

    weather limits.

  • 8/12/2019 Otc 15336

    4/12

    4 OTC 15336

    CONCLUSIONS

    On both the BP Trials the use of the DCV Balder confirmedthe following significant advantages:

    Installation of sled assemblies of unprecedented size and

    weight were proven to be successful with the J-lay tower

    of DCV Balder. The ability to install in-line sled assemblies and PLETs

    allows operators to develop deepwater fields in the mostflexible way with wells that can be tied in to export lines

    at any given location.

    For infield flowlines the in-line line sled assemblies and

    PLETs can be used to hook-up future wells to the flowlineinfrastructure such as to adopt the most economical field

    development scenario.

    Permit to Work system in combination with toolbox

    meetings and JSAs resulted in no lost time incidents.

    All pipelay equipment was successfully functional and

    load tested.

    Pipelay procedures and used calculation methods proved

    to be adequate.

    Offshore crew is familiarized with pipelay equipment.

    REFERENCES

    1. The Heerema Balder: From SSCV to DCV, A. Ploeg,

    DOT, 2001.

    2. HMC Deepwater Field Development experience;

    Working With The Tools Of Today. Frank Lange, DOT,

    2002.

    3. Deepwater moorings installation. J.B. de Jonge. OWA,

    2002.4. Installation Of The Horn Mountain Spar Using The

    Enhanced DCV Balder. Dijkhuizen, Coppens, van der

    Graaf OTC 15367, 2003.

  • 8/12/2019 Otc 15336

    5/12

    OTC 15336 5

    Figure 1 - Typical Deepwater Field Layout

    Export pipelines

    SCR

    PLET

    manifoldsSled assemblies

    Anchor systems Infield flowlines

  • 8/12/2019 Otc 15336

    6/12

    6 OTC 15336

    TABLES

    Table 1 - DCV Balder Characteristics

    Type of Vessel : Deepwater Construction Vessel

    Year Constructed : 1978

    Year Converted : 2001

    Operating Draft : 25 m

    Light Weight : 48,690 mTLength Overall : 154 m

    Breadth : 137 m

    Table 2 BP Trials WSA Data

    WSA Dimensions:

    Overall Length (incl. stems): 69.9m

    Maximum Width (mudmats retracted): 5.9m

    Maximum Width (mudmats extended): 9.1m

    Mudmat Length (incl. ext.): 16.0m

    Top Stem Length (from mudmat edge): 30m

    Bottom Stem Length (from mudmat extension

    edge):16m

    WSA Weights:

    In Air Dry (incl. stems & SSLA): 89 mT

    In Air Dry (excl. stems): 60 mT

    Submerged Empty (excl. stems outside mudmat): 45 mT

    Submerged Flooded (excl. stems outside mudmat): 51 mT

    Pipeline Properties:

    OD x Wt: 28 OD x 30.8mm wt

    Pipeline Weights:

    In Air Dry: 0.517 mT/m

    Submerged Empty: 0.109 mT/m

    Submerged Flooded: 0.449 mT/m

  • 8/12/2019 Otc 15336

    7/12

    OTC 15336 7

    Figure 2 Photo DCV Balder With J-Lay Tower

    Figure 3 - Crates With Double Joints Being Hoisted Onboard DCV

    Balder

  • 8/12/2019 Otc 15336

    8/12

    8 OTC 15336

    Figure 4 - Trials Sled Assembly (WSA) Lifted Into J-Lay

    Tower

    Figure 5 - WSA Lifted Into J-Lay Tower

  • 8/12/2019 Otc 15336

    9/12

    OTC 15336 9

    Figure 6 - Side Step Procedure

    Figure 7 - Hang-Off Table Moving Out

    tabletable

  • 8/12/2019 Otc 15336

    10/12

    10 OTC 15336

    Figure 8 - Schematics of activities executed during BP trials

    Use PS crane jib to install PLET in

    tower.

    Install 20 hex joints, tower angle

    ~80.

    Increase tower angle to 81 degr.

    and install 4 hex-joints.

    BALDER BALDER BALDER

    ROV

    Tower

    angle 90

    PLET

    BALDERBALDER BALDER BALDER

    ROV

    Tower

    angle 90

    PLET

    BALDER

    Recover pipeline and decrease

    tower angle to ideal

    configuration.

    Install 48 hex joints in a 3-day

    production. One day FJC in

    production.

    Install A&R equipment and

    lower pipeline to seabed. A&R

    hook stays connected.

    Increase tower angle to 82.5

    degr. and install 4 hex joints.

    Decrease tower angle back to 80

    degr.

    BALDER BALDERBALDER

    BALDER

    A&R head

    A&R

    hook

    A&R

    BALDER BALDERBALDER

    BALDER

    A&R head

    A&R

    hook

    A&R

  • 8/12/2019 Otc 15336

    11/12

    OTC 15336 11

    Bring WSA into tower using PS

    crane jib.

    Install WSA in tower and

    prepare for buoy installation.Install 21 hex joints (28").

    Install OD transition joint, lower

    pipeline to seabed and adjust

    tower for diameter change.

    BALDER BALDER

    BALDER

    BALDER

    WSA

    Buoy

    Reducer

    piece

    BALDER BALDER

    BALDER

    BALDER

    WSA

    Buoy

    Reducer

    piece

    Use Balder to recover the DMA.Recover complete trial pipeline

    Recover pipeline and install 17

    (1.106" wt) hex joints and 4

    (1.125" wt) hex joints.

    Test gravity hook and chain of

    recovery hold back rigging.

    BALDER

    28" pipe

    BALDEBALDER

    28" pipe

    24" pipe

    Normand

    Ivan

    BALDER

    28" pipe

    BALDEBALDER

    28" pipe

    24" pipe

    Normand

    Ivan

  • 8/12/2019 Otc 15336

    12/12

    12 OTC 15336

    Figure 10 - Photo of sled assembly in fabrication

    Yard

    Figure 11 - Photo Load-out of large in-line sled

    assembly

    Figure 9 - Schematic View Of large in-line sled

    assembly