ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public Buildings Originally Given By John Shonder TC 7.6 Meeting January 25, 2015 Chicago, IL Rüdiger Lohse Dan Howett IEA Annex 61 Meeting April 13, 2015 Reading, UK
20

ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

Dec 28, 2015

Download

Documents

Jeffery Robbins
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

ORNL is managed by UT-Battelle for the US Department of Energy

IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public Buildings

Originally Given ByJohn ShonderTC 7.6 MeetingJanuary 25, 2015Chicago, IL

Rüdiger LohseDan HowettIEA Annex 61 MeetingApril 13, 2015Reading, UK

Page 2: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

2 Presentation_name

The Problem

• Governments worldwide are targeting more stringent energy reductions in their buildings

– In the US, EISA 2007 requires 30% reduction by 2015 compared to a 2003 baseline

– EU targets 2050 carbon neutral building stock

• Lack of funding and know- how: Funding for projects required to meet these targets is limited

• Lack of high effective business models to implement energy conservation in buildings

• Private investment – obtained through performance-based contracts – can fill the gap, but these projects have typically yielded savings in the range of 10% to 30% (ESCO business)

• IEA-EBC Annex 61 is developing technical and business solutions to allow deeper savings to be achieved using a combination of public and private funding

Page 3: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

3 Presentation_name

Objective of Subtask B

• Develop business models for deep energy retrofit/refurbishment of government buildings and building groups using combined government/public and private funding to overcome existing barriers and to support the necessary increase in pace and quality of refurbishment activities

Page 4: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

4 Presentation_name

Subtask B Strategya) Lessons learnt from accomplished DER: Gather case study information on business models used in existing deep retrofit projects planning tools, impacts and investment costs of DER measure bundles, quality assurance mechanisms.

b) Depict life- cycle cash- flows accounting monetized benefits resulting from DER projects

Reliable planning

tools

Impacts of DER measure bundles

Investment costs for DER

bundles

Quality assurance

mechanisms

Annex 61 Subtask A

Energy related benefits:• E- consumption • E- source modification

Non energy related savings:• Maintenance costs• Improved indoor climate• Extended floor area• Asset value

Page 5: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

5 Presentation_name

Case study benefits/cash flows: Modeling Results for Office Building 224 kWh/m²yr H / 62 kWh/m²yr. E Scenario 1:”base case” 2: new building

adopted3: - 50% 4: Passive

House

Primary energy savings

34% 60% 54% 70%

a)Heating energy savings

33% 68% 60% 

83%

b)incremental primary investment energy (€/m²)

200- 230 300- 330 

280- 310 380- 430

bb) delta primary investment costs in comparison to scenario 1

 -

100- 110 80- 100 180- 200

c)delta cost savings)in comparison to €/m²yr

- 10 7- 10 10- 14

bb/c - 10 10-11 14-18

Page 6: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

6 Presentation_name

Subtask B Strategy• Develop of advanced business model allocating investments and

services between building owner and ESCos, development of financing mechanism by accounting and securing life- cycle costs and benefits (table shows new advanced business model for SMESCos in Germany)

ESCO

Design

Investment DER bundles

Performance guarantee

O&M

Funding

Private Equity Building Owner

Loan Guarantee PPP

Payment of Performance i.e. energy savings

Quality Assurance

Facilitator

Page 7: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

7 Presentation_name

Subtask B Strategy

• Development of advanced financing mechanisms:

• a) securing monetary streams between building owner and ESCO (performance guarantee with/without loan guarantee)

• b) securing third party investments by a quality assurance process such as ICP

Building ownerESCO

performance guarantee

Private equity

ESCO Quality assurance i.e. ICP

Planning process

Performance projection

O&M process

Monitoring &verification

Page 8: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

8 Presentation_name

Subtask B Strategy

• Development of advanced financing mechanisms:

c) Setting up an inventory of accomplished and evaluated DER and other EE measures in buildings on EU and USA:

– Comparison of ex ante / ex prediction/ ex post refurbishment energy consumption

– Investment costs

– Performance indexes (EUIs etc.)

• Business Model Market application:

• a) Analyze regulatory framework in the participating countries to determine barriers project implementation

• b) Engage with stakeholders (building owners and managers, financial community, and energy services companies) to develop improved business models corresponding to the environment in each country

Page 9: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

9 Presentation_name

Challenges: Do we really use theappropriate business models?

The “owner- directed”/”inhouse”- approach lacks EE incentive mechanisms:

• In EU 95% of building refurbishments are carried out in “owner- directed or in- house” business models:

– Architects/planners are responsible for planning, procurement, quality assurance in the construction phase

– Building owner- provides (mostly non- experts) funding, engages bank loans for funding and is in charge for the building operations after the accomplishment of the construction phase

– Crafts- /Trades Men: construction, maintenance services

• Experienced malfunctions of “owner- directed/in- house- business models”:

– Open feed back model with no feed- back and response (PERFORMANCE) integrated

– Decision making is typically not referring to life- cycle based criteria

– lacking stimulation to meet calculated efficiency targets and fixed investment budgets

Page 10: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

10 Presentation_name

Challenges: do we really use theappropriate business models?

• ESPC – Energy Saving Performance Contracting: virtues of performance related business model in comparison to “owner- directed” business models: - Strong contract based stimulation for both contract parties to achieve a

high cost effectiveness by providing a better savings/investment ratio- Guaranteed energy and maintenance cost savings between 25 and 40%

in US, EU- Bankable energy- and maintenance cost savings create revenue streams

which are reliable positions of the funding of deep retrofit projects - Cost structure and decision making criteria aligned to life- cycle costs- ESCOs are using design and experience based knowledge on different ECM

(1) bundles (HVAC/biomass/CHP..) and are performing with satisfactory results

- EPC in its current approach is not the chosen vehicle for deep retrofit projects

• One main target of IEA- Annex 61 is the advancement of existing EPC- related business models for deep retrofit projects

(1) ECM Energy Conservation Measures

Page 11: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

11 Presentation_name

Regional energy efficiency strategies in buildings and neighborhoods

Ene

rgy

Sav

ings

(%)

Investment /m² (€/m²)

EPC „first generation“Energy

Supply Contracting

Regional KEA- EPC Model

25%

50

%

75%

25 50 75 100 250 500 750

Deep Energy Retrofit

How to advance EPC into a tool building strategy

Page 12: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

12 Presentation_name

Market Application: WorkshopInvesting into Energy Efficiency Projects: Why and How

• Organized by Annex 61/ Building Performance Institute/ KEA

• Focused on European market

• Held in Brussels, Belgium November 9 at the Buildings Performance Institute Europe

• Brought together public officials, non-governmental organizations, ESCOs, investors, and technical experts

• 12 speakers

• 85 individuals in attendance

Page 13: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

13 Presentation_name

Keynote Address by Paul Hodson, Head of the European Commission's Energy Efficiency Unit

Lack of evaluated data from accomplished projects is a major issue:

• There is insufficient data on the effectiveness of retrofit projects

• Each project is considered to be different and results not comparable

• This makes benchmarking difficult

• If governments are to see energy efficiency as a resource, there is a need for more and better information on the benefits availablewe

Page 14: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

14 Presentation_name

Rudiger Lohse, Co-Operating Agent of IEA-EBC Annex 61

• Many barriers to implementing energy efficiency projects in the EU

– Market, Financing, Information

– Regulatory/Institutional

– Technical

– Wrong business model is mostly in use

• Using public capital alone to implement EE projects brings no measurement of savings, no guarantees, and reduces the viability of future financed projects

• Using public capital alone to implement EE projects brings no measurement of savings, no guarantees, and reduces the viability of future financed projects

• Annex 61 will focus on performance related business model which will guarantee benefits, reduce demand for third party financing and

Page 15: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

15 Presentation_name

Mark LaFrance, IEA: Key Policy and Metrics to Enable Investments in Deep Energy Renovation• Each renovation project that is done without

incorporating deep energy retrofits is a wasted opportunity

• Paradigm shift is needed

– Highest priority should be to document and replicate cost effective DER as part of normal building renovation activity.

– Establish business case for buildings not currently planned for renovation by targeting a challenging goal and looking beyond energy efficiency. Energy and non- energy related benefits have to be quantitatively valued.

– Establish mitigation cost for early renovation – this would likely require carbon trading and be a lower cost option compared to other solutions such as carbon capture and storage.

Page 16: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

16 Presentation_name

John Coolen, Factor 4, Belgium

• Project facilitation is key to guide owners and ESCO through the process

• Combine non-energy-related building upgrades with energy retrofits

• Provides calculation methods to make the non- energy related savings accountable and gives guidance on how to assess and to verify their performance

Page 17: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

17 Presentation_name

Ove Moerck on Annex 61 Subtask A

• Evaluation of accomplished DER projects in EU and USA

• Which major benefits have been achieved

• Cost- /benefit- curves

• Will be presented in this session

Page 18: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

18 Presentation_name

Eric Berman, RenESCO (Latvia) on DER EPC business models• Upgrade of Soviet-era residential

housing stock

• RenESCO upgrades the buildings at no cost to residents

• Residents then pay their utility bills to RenESCO, who pays the utility and uses the remainder (savings) to pay debt service on the project financing

• Business has been in operation for three years

• Difficulties include lack of consistent policies from governments and financial institutions

Page 19: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

19 Presentation_name

Matt Golden of Environmental Defense Fund, USA and Panama Bartholomy, ICP

Page 20: ORNL is managed by UT-Battelle for the US Department of Energy IEA Annex 61 Subtask B: Development of Business Models for Deep Energy Retrofits in Public.

20 Presentation_name

Main takeaways from Investor’s Day

• Large participation in this event shows the great interest in energy retrofit projects in Europe

• The barriers to projects include

– Lack of information about energy efficiency as a resource

– Lack of clear policies at many levels of government, compounded by the autonomy of the European member countries

– Lack of private capital

– Insufficient business models in use for EE implementation

• Investor´s Day is providing a platform to move barriers and to bring together investors, building owners, ESCos and research

• Investor´s Day is to be considered as groundwork follow up of EEFIG (Energy Efficiency Financial Institution Group (EEFIG)

• Next Investor´s Day will take place in autumn 2015 and will be announced in the next few days