Page 1
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Integrated Concurrent Engineering
John Kunz
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
The big ideas: Integrated Concurrent Engineering (ICE) is a social
method, helped by technology, to create and evaluate multi-
discipline, multi-stakeholder VDC models extremely rapidly.
Multiple factors together enable its success.
Page 2
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Learning goals for Week-2
• Learn basic theory and practice of ICE, Metrics, TEI
• Review submissions from W-1 and clarify +/∆ practices
• Plan class project
Chalmers Integrated Product, Organization and Process (c) 2015
2
Page 3
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Reflections
• Interesting that there is so much software to use for
management.
• Lots of things are automated and automation works well.
Project management seems underserved and has
potential, so it is interesting
• I like that there is still a need for the human and
judgement.
• Surprising tat this is not used so much, but it seems easy
and fast to use and easy to learn
• It is interesting to reflect on how much time to plan vs.
start early. Is there a golden rule to follow?
Chalmers Integrated Product, Organization and Process (c) 2015
3
Page 4
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Details for Week-2
• Dinner at my home this Tuesday
• Due date for homework: Sundays
Chalmers Integrated Product, Organization and Process (c) 2015
4
Page 5
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
5
Integrated Concurrent Engineering (ICE) Background
Given
• Objective = Rapid, effective design
“extreme collaboration” (~1 week)
• Excellent POP software
• Collocated team
• iRoom
• Good generic POP model
• SD (DD) phase focus
Performance change
XC
Good
traditio
nal
Latency
(secs)0
20000
40000
60000
Latency (secs)
Duration (days)
XC
Good traditional
0
50
100
150
200
250
300
Duration
Page 6
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
6
The big ideas of ICE
• Exceptional performance, e.g., Team-X at NASA-JPL
• It works because it achieves exceptionally short
information latency and short task durations, reliably
• Multiple factors enable ICE to work
Page 7
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
7
Integrated Concurrent Engineering at JPL (ICE)
Properties
• Collocated Organization (Closed Knowledge Network)
• Excellent Technical Infrastructure
• Formal Objective Metrics
• Informal Process and Culture
Photo thanks to JPL
Page 8
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
8
Integrated Concurrent Engineering at CIFE
Integrated Collaborative Engineering (ICE) at CIFE
• Collocated Organization (Closed Knowledge Network)
• Excellent Technical Infrastructure
• Formal Objective Metrics
• Informal Process and Culture
Page 9
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
10
Tasks of a typical ICE session
1. Plan: Specify project intent, or functional goals and objectives –
wants:
– Broad goals for content of models at specified LOD
– Specific measured performance objectives
– Specific deliverables and commitments by specific teams and
individuals
2. Do: Model project design, or “forms”:
– in response to goals and objectives
3. Check: Verify model content re specification
4. Act:
• Predict project performance, or behaviors – attribute values
– Predictions based on models, judgement
• Evaluate project performance:
– Acceptability of predicted behaviors vs. specific objectives
Page 10
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
1. Plans: Specifications of project intent, or functional goals and objectives:
– Broad goals for project and content of models at specified LOD
– Specific team and individual deliverables and commitments
– Specific measurable performance objectives
2. Models of project designs, or “forms” -- dos
– Product: 3D BIM
– Organization: team members, budgets, charters
– Process: tasks, methods, resources
3. Checks:
• Verification of model content re specification – conformance checks
• Predictions of project performance – attributes– Predictions based on models and stakeholder judgment
– Assumptions used in predictions
4. Next steps:
• Evaluation of project performance:
• Risk assessment and mitigation strategy
• Actions using current design and models)Chalmers Integrated Product, Organization and Process (c) 2015
11
Deliverables of a typical ICE session
Page 11
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Potential value of VDC
• Better project or corporate
performance (measurably)
– Suggests need for ~weekly
performance data: specify >3
metrics
• Better clarity of decision processes,
for
– Decision-makers
– Execution team
– Executive team
• Better plans and clear commitments
for working team
• Increased profitability: ↓rework; ↓work
effort; ↑business
VDC methods:
• Models: Product (3/4D),
organization (commitments),
process (plan, schedule)
• Collaboration methods: ICE
• Analyses (model-based): Clash,
Structure, QTO, cost, energy, …
• Metrics: Outcome, process,
controllable factors
Chalmers Integrated Product, Organization and Process (c) 2015
12
Page 12
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
13
Observations
ICE at NASA-JPL characteristics
• Organization: Multiple stations (~18)
• Process: careful design
• Technology:
– Multiple shared display screens
– Shared database (Icemaker)
Page 13
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
14
Coordination Latency is the fundamental performance metric for knowledge work
• Response latency = Time from a designer posing a
question to receipt of a useful answer
• Decision latency = Time from receiving useful
information to making a decision with it
• Good engineering practice for both: 2 days
– weeks typical
• Measurable ICE Objective for latency: minutes,
reliably
– For and as assessed by all intended stakeholders
Page 14
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
15
Simple analysis of Latency
Traditional
• Project requires
100 “queries” per engineer @ Latency = 2 days (good!)
100 modeling, analysis, meeting “tasks” @ task durations < 2 days
Project duration ~ 200 calendar days (typical)
Latency paces schedule(typical)
Not direct work
ICE (Team-X)
• Project requires
100 “queries” per engineer @ Latency = 1 minute
100 modeling, analysis, sidebar “tasks” @ task durations ~8 minutes
Project duration ~ 2 calendar days (Team-X)
Direct work (modeling + analysis + documentation)paces schedule (Team-X),
Not coordination latency
Page 15
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
16
ICE requires latency management
• Latency extends schedules
– Interdependent tasks have incessant information requests
– Requests have response delays (latency)
– Latency adds no value, measures collaborative waste
• Integrated Concurrent Engineering dramatically cuts time and latency
– Reduces latency from days to minutes
– Direct work tasks must run in minutes
– Enables radically decreased project duration
– Researchers, practitioners report improved cost, quality
– Requires high reliability (> 99%) latency: one major latency source jeopardizes project success
– New organizational form
Page 16
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
How ICE (Team-X) works
Manages:
1. Duration of direct work tasks
– Model, describe, predict,
explain, evaluate, generate
alternatives, decide
– Requires highly skilled
engineers with excellent tools
that they know well and culture
that provides good enough
answers
2. Coordination Latency
– Time for a designer to obtain
usable information
– Requires many enabling factors
Supports both:
1. Associative (divergent) thinking
– Many options, intuitive,
including unique idea
Fluency (lots of options),
Flexibility (different kinds),
Original (at least one)
2. Analytical (convergent) thinking
data, prediction, analysis,
evaluation and recommendations
that believably support decision-
making
– Actionable
Chalmers Integrated Product, Organization and Process (c) 2015
17
Page 17
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
18
ICE Methods
Normal Stations
• Owner
• Product: model functions, scope, behaviors
• Organization: model functions, scope, behaviors
• Process: model functions, scope, behaviors
• Integrated project: POP model
• Facilitator (session leader)
• Project manager
Process
• All stations simultaneously develop model inputs
• Coordinate continuously
• Assess and evaluate first design option
• Deliver project:
– Definition
– Objective assessment
– Option evaluation
Page 18
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
19
Steps to perform ICE sessions …
• Pre-planning: a few days immediately prior to ICE sessions– Invite a very small set of project principals (2-4)
– Do project definition and identify POP model at Level-B with ~10 each of P, O, P elements
• Determine the design space to explore in ICE session:– Invite participants of actors in POP model to ICE session
– Select modeling and analysis tools and methods
• Assure that facility and intended tools are available
• ICE session: ~3 sessions within one week
• Post-session: a few days immediately following ICE sessions to create formal deliverables
Page 19
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
20
When to hold ICE sessions …
• For each major project phase
– at least early (concept and schematic), detailed (DD,
CD) and to plan construction
• Collaborating with your other stakeholders
• Hold a set of about 3 ICE sessions
• Build and analyze a project model for the next
phase in enough detail to identify objectives,
scope and predicted performance believably
Page 20
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
21
Why to hold an ICE session
• Do project definition rapidly and believably
– Define functional objectives, scope, behaviors of Project, i.e.,
• Product, Organization, Process
• Clearly identify tasks and deliverables for next period (week or month)
– Focus: product element and system(s) served
– Who: responsible group, individuals
– What: tasks to perform
– When: according to broadly reviewed and accepted schedule
– How: methods and resources to be used by responsible team(s) to coordinate, do work and verify work
– Context: specific
• risks and uncertainties to address based on broad project review
• coordination tasks to assure success given risks
Page 21
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
22
To plan a set of ICE sessions
• Enable effective use of ICE methods– Professional development of potential team members - create
culture, methods, incentives
– Implement enabling tools: P, O, P modeling and analysis applications, display technology, shared database
• Plan each set of ICE sessions: Identify – Objectives and intended deliverables: models, analyses, reports,
recommendations, …
– Number of sessions and calendar schedule: typically 2-4 over ~ 1 week
– Intended participants, tasks for each session
– Effort and time budgets for use of ICE sessions
– Process performance metrics and methods: measured and assessed quality, schedule, cost
Page 22
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
ICE vs. traditional meetings
Issue ICETraditional
meetings
Outcome re issue at
hand
Resolution Tracking of status
Agenda management Focused on clear, shared
agenda
Tangents, pursuit of
personal agendas
Description of
problem and context
Shared and clear Individual
perceptions
Number of options
considered
Multiple; consider what-
ifs
Focused on agenda
of one individual
Supporting
technologies
Interactive visual models
and analyses
Paper and appeal to
understanding of
others
23
Chalmers Integrated Product, Organization and Process (c) 2015
Page 23
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Decisive: How to Make Better Choices in Life and WorkChip and Dan Heath
Risks in decision-making - decision situations to
avoid:
• Narrow framing of a problem: focus on immediate issue
• Confirmation bias: did it this way last time so let’s do it
that way again
• Short-term emotion: don’t hurt feelings of anyone
• Over-confident: failure to identify Plan-B “just in case”
Chalmers Integrated Product, Organization and Process (c) 2015
24
Page 24
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Decisive: How to Make Better Choices in Life and Work
Risks in decision-making - decision situations to avoid:
• Narrow framing of a problem: focus on immediate issue
Wide set of design options
• Confirmation bias: did it this way last time so let’s do it
that way again
Really test assumptions; embrace disagreement
• Short-term emotion: don’t hurt feelings of anyone
Find distance from past and then decide
• Over-confident: failure to identify Plan-B “just in case”
Prepare multiple contingencies “just in case”
Chalmers Integrated Product, Organization and Process (c) 2015
25
Page 25
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Decisive: How to Make Better Choices in Life and Work
Risks in decision-making - decision situations to avoid:
• Narrow framing of a problem: focus on immediate issue;
Wide set of design options
• Confirmation bias: did it this way last time so let’s do it
that way again
Really test assumptions; embrace disagreement
• Short-term emotion: don’t hurt feelings of anyone
Find distance from past and then decide
• Over-confident: failure to identify Plan-B “just in case”
Prepare multiple contingencies “just in case”
ICE can help
Chalmers Integrated Product, Organization and Process (c) 2015
26
Page 26
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Staff survey: Example of how senior management helps
1. I feel that I can challenge people at any level in my organization without fear.
2. I feel I can ask for and receive the resources (time, budget, equipment) I need to solve
problems.
3. My Manager/Supervisor makes it easy to speak up when problems arise.
4. My Manager /Supervisor listens to bad news, yet still asks for unrealistic targets.
5. When we present bad news, our Manager/Supervisor repeatedly asks for more
information focused on showing that the problem is not as bad as it seems.
6. My Manager/Supervisor encourages us to ask for help outside our organization or the
chain of command (e.g., outside our project or work group or next level up) if we need it.
7. I am aware of what to do when a Manager/Supervisor doesn’t respond appropriately to
bad news and it needs to be escalated to a higher level.
8. My team uses metrics and processes effectively (e.g., trend program, standard metrics,
etc.) to analyze, surface & solve problems.
9. In my organization, we live by our corporate values
10. The formal metrics in my organization often do not convey an accurate picture of
performance.
Chalmers Integrated Product, Organization and Process (c) 2015
32
Page 27
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
ICE session
• Plan:
– Form a group to do a class project. Make sure that
team has SimVision
– Take a few minutes and plan for your project:
• “Big Idea”
• Outcome metrics and target values for each x 2-3
• POP framework
• Do: Meet in groups of 2-3 teams in discuss your plans in
an ICE session
• Check and Act: each ICE session summarize
discussions for class
Chalmers Integrated Product, Organization and Process (c) 2015
33
Page 28
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
34
ICE Enabling Factors
(Committed)
Organization(Dynamic) Process
(Visual)
Technology
Stakeholders Present:
(Closed knowledge
network)
Shared reciprocal
expectations
Excellent discipline-
specific modeling,
visualization tools
Focused design staff:
100% committed in
sessions
Processes clear: (low
equivocality)
Rich communications
media
Flat organization
structure
Processes distinct: High
structure independence
Integrated database
Egalitarian culture Resolve problems in small
self-formed groups (Pooled
communications)
High goal congruence
Page 29
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Assessment of status of ICE Enabling Factors
Chalmers Integrated Product, Organization and Process (c) 2015
46
(Committed)
Organization
(Dynamic) Process (Visual)
Technology
Stakeholders Present:Processes clear: (low
equivocality):
Excellent discipline-
specific modeling,
visualization tools:
Focused design staff:
100% committed in
sessions:
Processes distinct:
Rich
communications
media:
Flat organization
structure:
Resolve problems in
small self-formed
groups:
Integrated database:
Egalitarian culture
High goal congruence:
Page 30
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
47
ICE Enabling factors: so what?
• Necessity: excellent ICE performance requires allfactors to work well
• Sufficiency: No one factor suffices
• Early evidence (Stanford classes) of necessity, sufficiency of these factors (from observations or theoretically-founded simulation)
• Process and team experience are crucial, so understanding factors may help understand how to change Team-X to– Make specific improvements
– Replicate Team-X (in less than 10 years it to create it)
Page 31
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
1. Plans: Specifications of project intent, or functional goals and objectives:
– Broad goals for project and content of models at specified LOD
– Specific team and individual deliverables and commitments
– Specific measurable performance objectives
2. Models of project designs, or “forms” -- dos
– Product: 3D BIM
– Organization: team members, budgets, charters
– Process: tasks, methods, resources
3. Checks:
• Verification of model content re specification – conformance checks
• Predictions of project performance – attributes– Predictions based on models and stakeholder judgment
– Assumptions used in predictions
4. Next steps:
• Evaluation of project performance:
• Risk assessment and mitigation strategy
• Actions using current design and models)Chalmers Integrated Product, Organization and Process (c) 2015
48
Deliverables of a typical ICE session
Page 32
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
ICE pre-plan
Chalmers Integrated Product, Organization and Process (c) 2015
49
ICE Plan Example template from templates file
Problems Outcomes Resources
Problems for
session to
focus on
Desired outcomesIntended
Participants
Participant
discipline
Pre-session
assignments
Member of
pre-plan
team
(yes/no)
Role in ICE
session
Member of
post-
session
wrapup
team
(yes/no)
Agenda items
Outcome intent
met?
(Yes/Partial/No)
Meeting
space,
technologies,
models, tools
Specify
architectural
spaces first
floor
Spaces to model are
specified
Mary Architect Owner share project
goals and objectives
Yes Discipline expert Yes Review project goals
and objectives
Smart Boards
Size building
systems
Systems in first floor are
sized and specified
Joe MEP Engineer Define and share
team charter
No Discipline expert No Specify spaces,
systems,
components to
model
Excel
Identify building
construction
components for
first floor
Components (first floor)
that take > 1 hour to install
are listed and added to
spec of components to
model
Hamid PM PM assure
availability of BIM
authoring and review
tools for team
members
Yes Facilitator Yes assign modeling
tasks to individuals
Meeting space
with tables,
chairs for team of
10
Sonya Owner Owner share project
goals and objectives
No Recorder Yes Plan coordination
activities for each
modeling task
ICE pre-plan
Participants Agenda
Page 33
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Production plan Commitments
Chalmers Integrated Product, Organization and Process (c) 2015
50
Commitment Example template from templates file.
– Add a few commitments for follow-up work
Task Priority Short descriptionResponsible
team
Budget (FTE-
hours)
Coordination
dependent
team(s)
Approval
teamDue date
Done on-
timeComments/ model image(s)
1
A (Contract
requirement) Add door in BIM PM 20 Architect PM 4/1/2013 No
2
Page 34
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Coordination commitments
Chalmers Integrated Product, Organization and Process (c) 2015
51
Coordination template from templates file
• Add a few coordination commitments for follow-up
work
Planned
coordination
activity
Responsible
individualsDue date
Due date met
(y/n)?Expected LOD Comments
Coordination Commitments
Page 35
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Deliverable commitment report: Example template
Chalmers Integrated Product, Organization and Process (c) 2015
53
Planned
deliverable
Responsible team,
individualsReceiving team Due date
Due date
met (y/n)?Expected LOD Comments
BIM spec for
current stepCore team BIM architect Mm/dd Top-10 $ elements
BIM review Review team x 50 PM Mm/dd [1:5] each teamNo team priority
yet
Next step plan
developmentCore team PM Mm/dd
Task size 2-5 FTE-
weeks
Sr Mgt approve
next stepSr Management PM Mm/dd Yes/no/ buts Decision required
Deliverables Example
Page 36
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Risks
Chalmers Integrated Product, Organization and Process (c) 2015
54
Risks Example template from templates file
• Add a few based on your review during or at end of
session
Identified risk
Potential
impact of risk
($, time, effort)
Severity:
Low,
Medium,
High
Parties
affected by
risk
Individuals
responsible for
mitigating
design,
approval
Earliest
analysis/ last
responsible
moment dates
Mitigation
activity
Resolution
date met
(Yes/No)?
Comments
BIM ready
partner teams
available
Dramatic
schedule High
Client Early partner
relationship
team
Day-1/ end of
concept phase
BIM training
for partner
staff
Best to set
expectat-ions
early
Sea level rise
Costs/
curtailed
operations
Medium OperationsConcept
design team
Day-1/ end of
ConceptDikes 100-year risk
Goverment
plan OK
Delay open
dayLow Operations Core group
Day-1/ facility
open
Engage
government
review early
Ongoing risk
Paint spec
unclear or
inappropriate
Cost: use
contingency;
schedule delay
Low
Client Core groupDay-1/ facility
open
Vet across
different
examples
Risks - Example
Page 37
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
55
Use ICE for Target value design for cost, schedule, energy, …
• Generate and evaluate many design options w/ICE
• Select target cost
• Rapid design method: PIDO http://network.modefrontier.eu/documentation/pido.html
Value
CostLow High
Assessed project value and
predicted cost of many options
+ ∆
- ∆
Linear value
curve
Page 38
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
56
Use ICE for Target value design for cost, schedule, energy, …
• Generate and evaluate many design options w/ICE
• Select target costValue
CostLow High
Assessed project value and
predicted cost of many options
+ ∆
- ∆
Non-Linear
value curve
Page 39
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility EngineeringChalmers Integrated Product, Organization and Process (c) 2015
57
Use ICE for Target value design for cost, schedule, energy, …
• Generate and evaluate many design options w/ICE
• Select target schedule Value
ScheduleLow High
Assessed project value and predicted
schedule of many options
+ ∆
- ∆
Page 40
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Use ICE for multi-discipline target value design:
• When a change affects two
measures of project success,
–Choose when upside value
exceeds downside risk
–E.g., - ∆ cost risk
< + ∆ upside schedule
compression value
(c) 2015
58
Chalmers Integrated Product, Organization and Process (c) 2015
Page 41
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
To read more
• Section Integrated Concurrent Engineering (ICE)
supports VDC
– Pp 34-38 in VDC recommended reading
– "Virtual Design and Construction: Themes, Case Studies and
Implementation Suggestions," CIFE working Paper #97, 2015.
Chalmers Integrated Product, Organization and Process (c) 2015
59
Page 42
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
ORID: Focused Conversation and Analysis
Objective
What do you recall
seeing?
Reflective
Positive
What do you feel
positive about?
Reflective
Negative
What do you find
negative?
Interpretive
What sense do you
make of it?
Decisional
What agreements
can be made now?
Chalmers Integrated Product, Organization and Process (c) 2015
60
Page 43
Integrated Concurrent Engineering (ICE)
Center for Integrated Facility Engineering
Integrated Concurrent Engineering
John Kunz
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
The big ideas: Integrated Concurrent Engineering (ICE) is a social
method, helped by technology, to create and evaluate multi-
discipline, multi-stakeholder VDC models extremely rapidly.
Multiple factors together enable its success.