Organics Waste Processing Facility Construction Progress Update December 15, 2010
Feb 23, 2016
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Masonry and structural steel work in administration building area(November 15, 2010)
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Tunnel 7 spigot piping and Granular A backfilling(November 16, 2010)
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Backfilling and compaction in biofilter cells(November 22, 2010)
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Concrete pour for tunnel wall along Gridline 4(November 24, 2010
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Precast hollow core slab installation in administration building(November 25, 2010)
Organics Waste Processing Facility Construction Progress Update
December 15, 2010
Precast hollow core slab installed over tunnel 7(November 26, 2010)