1 Opermgt 345 Shannon January, 2001 Project Management Basic Concepts Opermgt 345 January, 2001
44

Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

Dec 16, 2015

Download

Documents

Sheila Venner
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

1Opermgt 345 Shannon January, 2001

Project ManagementBasic Concepts

Opermgt 345

January, 2001

Page 2: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

2Opermgt 345 Shannon January, 2001

What is a Project?

A Project is a series of activities and tasks that:

Have a specific objective to be completed with certain objectives

Have a defined start and end dates

Have funding limits (if applicable)

Consume Resources

Page 3: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

3Opermgt 345 Shannon January, 2001

Typical Project Structure

ProjectDefinition

ProjectDefinition

ProjectPlanning

ProjectPlanning

ProjectImplementation

ProjectImplementation

ProjectMonitoring

ProjectMonitoring

ProjectAdjustment

ProjectAdjustment

ProjectEvaluation

ProjectEvaluation

Page 4: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

4Opermgt 345 Shannon January, 2001

Project Life CycleR

esou

rces

and

Eff

ort

Phase 1

•Goals•Scope•Baseline•Requirements•Feasibility•Desirability

ConceptualDesign

Phase 2

AdvancedDevelopment

•Plan•Budget•Schedule•Management Commitment

Phase 3

DetailedDesign

•Define Responsibility•Team•Organization Structure•Detailed Plan•Kickoff

Phase 4

ProjectImplementation

•Manage•Measure•Control•Update and Modify Plan•Problem Solve

ProjectTermination

Phase 5

•Closeout•Document•Suggest Improvements•Reassign•Dissolve Project Team

Page 5: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

5Opermgt 345 Shannon January, 2001

Successful Projects

A successful project is one which achieves the following objectives:

– Completed On Time– Completed Within Cost– Meets Performance Criteria– Minimum Disruption of the Main Work of the

Organization– Effective Utilization of Resources

Page 6: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

6Opermgt 345 Shannon January, 2001

The Triple Play ofProject Management

Constraints

Time Cost

Performance

Page 7: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

7Opermgt 345 Shannon January, 2001

Triple Constraint Trade-offs

Budget

ScheduleEarly Late TIME

$

Performance Specifications

Better

Worse

Page 8: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

8Opermgt 345 Shannon January, 2001

Major causes of failure

Selection of a unsound projectSelecting the wrong person as a project

managerLack of support from upper managementMisused management techniquesProject termination not planned

Page 9: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

9Opermgt 345 Shannon January, 2001

Project Definition

Build Canoe Rental Building onCoeur d A’lene Lake

Page 10: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

10Opermgt 345 Shannon January, 2001

Form Project Team

•Select Project Leader

•Identify Key People

•Gain Management Commitment

•Define Project Team Operating Rules

Page 11: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

11Opermgt 345 Shannon January, 2001

The Top Level Project Tasks

Brainstormthe

Major Tasks

Brainstormthe

Major Tasks

EstablishWork Flow

EstablishWork Flow

AB

C

D E F

G

Page 12: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

12Opermgt 345 Shannon January, 2001

Define Top Level TasksCanoe Example

Site Preparation

Build Dock

Build Building

Finish and Ready for Business

Page 13: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

13Opermgt 345 Shannon January, 2001

Sequence Top Level Tasks

Site Preparation

Build Dock

Build Building

Finish

Page 14: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

14Opermgt 345 Shannon January, 2001

Sub-Tasks

A

B

C

D E F

G

Detailed Tasks

Detailed Tasks

Develop Work Sequence

Page 15: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

15Opermgt 345 Shannon January, 2001

Brainstorm Sub-Tasks

Site Preparation Build Dock Build Building Finish

Dock Site

Building Site

Install Pilings

Build Dock

Foundation

Frame

Roof

Power

Siding

Paint

Order Canoes

Landscape

AssembleCanoes

Open forBusiness

Page 16: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

16Opermgt 345 Shannon January, 2001

Work Breakdown Structure

Top Level Task

2nd LevelTask

2nd LevelTask

2nd LevelTask

2nd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

Lower Level Tasks

Page 17: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

17Opermgt 345 Shannon January, 2001

Sequence Sub-TasksTask Description Immediate Predecessor

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canoes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Page 18: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

18Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

(Activities on Arrows)

1

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 19: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

19Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 20: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

20Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

J

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 21: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

21Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 22: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

22Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 23: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

23Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 24: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

24Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut

LAssemble Canoes

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 25: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

25Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut

LAssemble Canoes

7F

Frame Hut

Roof

I

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 26: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

26Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 27: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

27Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

10M

FinishLandscape

11N

Open forBusiness

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 28: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

28Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart) Canoe ExampleAdd Times

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d

Task Description Time

Page 29: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

29Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

10M

FinishLandscape

11N

Open forBusiness

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 30: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

30Opermgt 345 Shannon January, 2001

Build Network Diagram(PERT Chart) Canoe ExampleAdd Times

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d

Task Description Time

Page 31: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

31Opermgt 345 Shannon January, 2001

Determining Project Length

Option 1: Sum all the task durations: A Prepare Dock Site - 3 d B Prepare Hut Site - 4 d C Install Dock Pilings A 6 d D Foundation for Hut B 3 d E Build Dock C 4 d F Frame Hut D 3 d G Power to Hut D 2 d H Side the Hut F 2 d I Roof the Hut F 3 d J Order Canoes and Receive Canoes - 2 d K Paint Hut H 4 d L Assemble Canoes J 10 d M Finish Landscaping L,I,K,E,G 4 d N Open for Business M 2 d

Sum = 52 daysAnything wrong with this approach?

Page 32: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

32Opermgt 345 Shannon January, 2001

Determining Project Length

Option 2: Determine duration of each network path

Page 33: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

33Opermgt 345 Shannon January, 2001

Network DiagramProject Paths

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 days

Page 34: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

34Opermgt 345 Shannon January, 2001

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 days

Network DiagramProject Paths

Page 35: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

35Opermgt 345 Shannon January, 2001

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-I-M-N = 18 days

Network DiagramProject Paths

Page 36: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

36Opermgt 345 Shannon January, 2001

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 days

Network DiagramProject Paths

Page 37: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

37Opermgt 345 Shannon January, 2001

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

J (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days

Network DiagramProject Paths

Page 38: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

38Opermgt 345 Shannon January, 2001

Critical Path

The Critical Path is the Longest PathThrough the Network.

Page 39: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

39Opermgt 345 Shannon January, 2001

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Network Diagram Canoe ExampleCritical Path

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days

Page 40: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

40Opermgt 345 Shannon January, 2001

Completed Task Timetable

Task Description Immediate Predecessor Time ES LS EF LF

A Prepare Dock Site - 3 d 0 3 3 6 B Prepare Hut Site - 4 d 0 0 4 4 C Install Dock Pilings A 6 d 3 6 9 12 D Foundation for Hut B 3 d 4 4 7 7 E Build Dock C 4 d 9 12 13 16 F Frame Hut D 3 d 7 7 10 10 G Power to Hut D 2 d 7 14 9 16 H Side the Hut F 2 d 10 10 12 12 I Roof the Hut F 3 d 10 13 13 16 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 K Paint Hut H 4 d 12 12 16 16 L Assemble Canoes J 10 d 2 6 12 16 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 N Open for Business M 2 d 20 20 22 22

Page 41: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

41Opermgt 345 Shannon January, 2001

Slack Time

Total Slack = The length of time an activity can bedelayed without affecting the projectcompletion time.

Total Slack = Late Start - Early Start

Total Slack = Late Finish - Early FinishFor Critical Activities

Free Slack = The time a task can be delayed without delaying another task.

Page 42: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

42Opermgt 345 Shannon January, 2001

Slack Time

Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 N Open for Business M 2 d 20 20 22 22 0

Page 43: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

43Opermgt 345 Shannon January, 2001

Critical Path Tasks

Critical Path = All tasks with slack = zero

Page 44: Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts Opermgt 345 January, 2001.

44Opermgt 345 Shannon January, 2001

Critical Path Tasks

Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 *** C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 *** E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 *** G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 *** I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 *** L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 *** N Open for Business M 2 d 20 20 22 22 0 ***

Critical Path = B - D - F - H - K - M - N