P6000 VEHICLE OPERATIONS ADDITION CONSTRUCTION CONTRACT NUMBER: N40080-15-D0154 JOINT BASE ANDREWS, MD SAMAHA ASSOCIATES, P.C. Architects 10521 Rosehaven Street Suite 200 Fairfax, VA 22030 PROFESSIONAL SERVICE INDUSTRIES, INC Geotechnical 2930 Eskridge Road Fairfax, VA 22031 NCPC SUBMITTAL APRIL 13,2017 BRINJAC Engineers MEP Engineers 8618 Westwood Center Drive Suite 305 Vienna, VA 22182 GHD Fire Protection/ ATFP -Security 14585 Avion Pkwy Suite 150 Chantilly, VA 20151 ADTEK Engineers Civil/ Structural Engineers 9990 Fairfax Blvd. Suite 300 Fairfax, VA 22030 LOCATION MAP N P6000 VEHICLE OPERATIONS VICINITY MAP N JOINT BASE ANDREWS 1 2 3 4 5 1 2 3 4 5 A B C D A B C D DES DRW REVIEWED BY BRENDA BARGER, PM N A V A L F A C I L I T I E S E N G I N E E R I N G C O M M A N D D E P A R T M E N T O F T H E N A V Y N A V A L F A C I L I T I E S E N G I N E E R I N G C O M M A N D - J O I N T B A S E A N D R E W S CODE ID. NO. 0 SIZE D SCALE: MAXIMO NO. STA. PROJ. NO. WORK ORDER NO. CONSTR. CONTR. NO. NAVFAC DRAWING NO. SHEET OF DRAWFORM REVISION REVDATE: SYM DESCRIPTION DATE APPR P 3 0 0 1 R L O C A T E J A D O C ( S A T E L L I T E S I T E ) C A M P S P R I N G S , M D 0 14 N40080-15-D-0154 NCPC SUBMITTAL PRELIMINARY NOT FOR CONSTRUCTION P6000 VEHICLE OPERATIONS ADDITION COVER SHEET GE001 0 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
THE CONTRACTOR MUST COORDINATE AND SCHEDULE WORK ON THISPROJECT WITH THE CONTRACTING OFFICER.
NOTIFY THE CONTRACTING OFFICER IMMEDIATELY OF DISCREPANCIES INTHE PLANS AND FIELD CONDITIONS.
SHEET METAL WORK MUST COMPLY WITH SHEET METAL AND AIRCONDITIONING CONTRACTOR'S NATIONAL ASSOCIATION'S (SMACNA)ARCHITECTURAL SHEET METAL MANUAL LATEST EDITION, AND WITH THEPROJECT SPECIFICATIONS.
ALL ROOFING WORK MUST COMPLY WITH THE NATIONAL ROOFINGCONTRACTOR'S MANUAL AND THE PROJECT SPECIFICATIONS.
PORTABLE FIRE EXTINGUISHERS WILL BE PROVIDED BY THECONTRACTOR, COORDINATE QUANTITY AND TYPE WITH THE 11TH CESFIRE DEPARTMENT.
ALL CONSTRUCTION MUST COMPLY WITH REQUIREMENTS OFAPPLICABLE UFC GUIDELINES; STATE AND COUNTY CODES; ANDARCHITECTURAL BARRIERS ACT (ABA), ACCESSIBILITY GUIDELINES ANDDEPSECDEF MEMORANDUM ACCESS FOR PEOPLE WITH DISABILITIES,DATED OCT 31, 2008.
THE CONTRACTOR MUST CONFORM TO THE STRICTER INTERPRETATIONOF CODES WHEN THERE ARE CONFLICTS BETWEEN CODES.
ALL CONSTRUCTION AND MATERIALS MUST BE NEW, UNLESSSPECIFICALLY INDICATED AS "EXISTING"
THE CONTRACTOR MUST FIELD INSPECT ALL EXISTING CONDITIONSPRIOR TO THE START OF CONSTRUCTION AND NOTIFY THECONTRACTING OFFICER OF DISCREPANCIES BETWEEN THECONSTRUCTION DOCUMENTS AND THE INTENT OF NEW WORKREQUIRED.
PARTITION DIMENSIONS SHOWN ARE NOMINAL FACE OF STUD TO FACEOF FINISH SURFACE OR FACE OF STUD TO FACE OF MASONRY ONCONCRETE UNLESS NOTED OTHERWISE. DIMENSIONS FOLLOWED BY+/- MUST BE FIELD VERIFIED.
THE CONTRACTOR MUST LAY OUT PARTITIONS PRIOR TOCONSTRUCTION OF PARTITIONS. THE CONTRACTOR MUST IMMEDIATELYNOTIFY THE OWNER'S REPRESENTATIVE OF DISCREPANCIES IN SPACELAYOUTS AND DIMENSIONS.
DO NOT SCALE DRAWINGS RELATED TO ARCHITECTURAL ORSTRUCTURAL ELEMENTS.
MASONRY DIMENSIONS ARE NOMINAL.
DO NOT USE COMBUSTIBLE MATERIALS OR KRAFT FACED INSULATIONIN PLENUM CEILINGS.
MAINTAIN REQUIRED MEANS OF EGRESS FOR AREAS OCCUPIED DURINGCONSTRUCTION. THE CONTRACTOR MUST PROVIDE TEMPORARYILLUMINATED EXIT SIGNS AS REQUIRED BY APPLICABLE CODES AT THECONTRACTOR'S COST DURING CONSTRUCTION.
THE CONTRACTOR MUST PROPERLY DISPOSE OF CONSTRUCTIONDEBRIS PER SPECIFICATIONS. DO NOT STOCKPILE DEBRIS ON SITE.
CONTRACTOR'S ACCESS TO WORK AREAS MUST BE LIMITED TOROUTES AND TIMES COORDINATED WITH GOVERNMENT.
OWNER MUST HAVE RIGHT OF REFUSAL ON SALVAGEABLE EQUIPMENTREMOVED AS A RESULT OF DEMOLITION ACTIVITIES.
COORDINATE WITH MECHANICAL AND ELECTRICAL DRAWINGS FORCEILING MOUNTED ITEMS NOT SHOWN ON THESE DRAWINGS.
ALL DOOR FRAMES MUST BE INSTALLED 4" FROM PERPENDICULARADJACENT WALL UNLESS NOTED OTHERWISE.
LOCATION OF CONSTRUCTION TRAILERS, STORAGE CONTAINERS,STAGINGAREAS, ETC. MUST BE COORDINATED WITH THE CONTRACTING OFFICERPRIOR TO THE START OF CONSTRUCTION.
PROVIDE SLEEVES, LINTELS, AND SEALANTS FOR WALL PENETRATIONS.
SCHEDULE - ACCESSORIESNO. ITEM TITLE MODEL MANUF. MTG HT
1 GRAB BAR B-5806 X 42 BOBRICK SEE ELEV.2 GRAB BAR B-5806 X 18 BOBRICK SEE ELEV.3 GRAB BAR B-5806 X 36 BOBRICK SEE ELEV.4 TOILET PAPER DISEPNSER B-2888 BOBRICK SEE ELEV.5 SOAP DISPENSER B-2111 BOBRICK SEE ELEV.7 MIRROR B-290 18X36 BOBRICK SEE ELEV.8 SANITARY NAPKIN DISPOSE B-254 BOBRICK SEE ELEV.9 RECESSED PAPER TOWEL
DISPENSE/WASTEB-369 BOBRICK SEE ELEV.
10 ADA BENCH FLOOR MTD. American SEE ELEV.11 GRAB BAR B-68616 BOBRICK SEE ELEV.12 SHOWER SEAT B-5181 BOBRICK SEE ELEV.13 SHOWER CURTAINW/ ROD B-207 AND B-204-2 BOBRICK SEE ELEV.14 Robe Hook 693530-PC Brizo
A
5/8" ABUSERESIST. GYPBOARD EACH FACE
3 5/8" 20 GAMTL STUDS @16" OC MAX
B
3" SOUNDATTENUATION
CONT RUNNER,ANCHOR TOCONC. SLAB
BASE AS SCHED.
FIN. FLOOR ASSCHED.
CEILING ASSCHEDULED
5/8" ABUSERESIST. GYPBOARD EACH FACE
3 5/8" 20 GAMTL STUDS @16" OC MAX
3" SOUNDATTENUATION
CONT RUNNER,ANCHOR TOCONC. SLAB
BASE AS SCHED.
FIN. FLOOR ASSCHED.
CEILING ASSCHEDULED
7/8" HATCHANNELS@ 16"O.C.
C
5/8" ABUSE RESIST.GYP. BOARD
CEILING ASSCHEDULED
FIN. FLOOR ASSCHED.
BASE AS SCHED.
D
(2) LAYERS 5/8"ABUSE RESIST. GYPBOARD
6" 20 GA MTL STUDS@ 16" OC MAX
6" SOUNDATTENUATION
CONT RUNNER,ANCHOR TOCONC. SLAB
BASE AS SCHED.
FIN. FLOOR ASSCHED.
CEILING ASSCHEDULED
5/8" ABUSERESIST. GYPBOARD
TYPE A TYPE B TYPE C
TYPE E (OVERHEAD COILING DOOR)
3'-0"
7'-0"
3'-0"
6'-0"
7'-0"
6'-0"
7'-0"
VARIES
VARIES
3'-0"
3'-0"
3'-0"
VARIES
TYPE D
VARIES
4"7'-0"
2" 3'-0" 2" 2" 3'-0" 2"
2"7'-0"
2" 6'-0" 2"
4"7'-0"
7'-4"
8"2'-0"
2"
4'-2"
4"
4'-10"
2" 1'-4"
2"
3'-0" 2"
TYPE D
TYPE A TYPE B TYPE C
2"EQ 2"
EQ2"
2" 2'-8" 2"
2"EQ 2"
EQ2"
2" EQ
2"
EQ
2"
EQ 2"
4'-4"
4'-4"
3'-0" 6'-0"
W1 W2
3'-0"
3'-0"
1 2 3 4 5
1 2 3 4 5
A
B
C
D
A
B
C
D
DES DRW
REVIEWED BY
BRENDA BARGER, PM
NAVAL FACILITIES ENGINEERI NG COMMAND
DEPARTMENT OF THE NAVY
NAV
A L F
ACIL
ITI E
S EN
GIN
E ER
ING
CO
MM
A ND
-JO
INT
BASE
AN
DR
E WS
CODE ID. NO. 0 SIZE D
SCALE:
MAXIMO NO.
STA. PROJ. NO.
WORK ORDER NO.
CONSTR. CONTR. NO.
NAVFAC DRAWING NO.
SHEET OF
DRAWFORM REVISION
REVDATE:
SYM
DESCRIPTION
DATE
APPR
P3001 RLOCATE JADOC (SAT ELLITE SITE)
CAMP SPRINGS, MD
0
14
N40080-15-D-0154
NCPC
SUBMITTAL
PREL
IMIN
ARY
NOT F
OR CO
NSTR
UCTIO
N
As indicated
P600
0 VE
HICL
E O
PERA
TIO
NS A
DDIT
ION
DOO
R SC
HEDU
LE
AE60111
1" = 1'-0"AE6011 WALL TYPES
SCHEDULE - DOORDOOR FRAME HARDWARE
NOTESUNIT MARKDOORTYPE
SIZE DOORMAT
FIRERATING TYPE SIZE
FRAMEMAT
DETAIL HARDWARESET
KEYSIDE RMNOWIDTH HEIGHT HEAD JAMB THRESHOLD
000 01 B 6'-0" 7'-0" HM C 6" HM001 02 D 5'-11" 7'-10 3/4" HM014 03 A 3'-0" 7'-0" HM B 5 3/4" HM015 04 A 3'-0" 7'-0" HM B 5 3/4" HM016 05 A 3'-0" 7'-0" HM B 5 3/4" HM026 08 A 3'-0" 7'-0" HM D 6 3/4" HM026 09 A 3'-0" 7'-0" HM B 5 3/4" HM008 10 A 3'-0" 7'-0" HM B 5 3/4" HM017 11 A 3'-0" 7'-0" HM B 5 3/4" HM020 12 A 3'-0" 7'-0" HM B 5 3/4" HM021 13 A 3'-0" 7'-0" HM B 9 3/4" HM028 14 A 3'-0" 7'-0" HM B 5 3/4" HM028 15 A 3'-0" 7'-0" HM D 6 3/4" HM023 18 A 3'-0" 7'-0" HM B 5 3/4" HM012 19 A 3'-0" 7'-0" HM B 5 3/4" HM013 20 A 3'-0" 7'-0" HM D 6 3/4" HM027 21 A 3'-0" 7'-0" HM B 6" HM025 22 B 6'-0" 7'-0" HM 6"029 23 B 6'-0" 7'-0" HM C 6" HM029 24 A 3'-0" 7'-0" HM A 6" HM022 25 A 3'-0" 7'-0" HM A 6" HM024 26 A 3'-0" 7'-0" HM A 6" HM029 27 A 3'-0" 7'-0" HM A 4 3/4" HM010 28 A 3'-0" 7'-0" HM B 5 3/4" HM009 30 A 3'-0" 7'-0" HM B 5 3/4" HM
1/4" = 1'-0"DOOR AND FRAME TYPES2
AE601
REF.
0' 2' 8'
GRAPHIC SCALE
NOTE: IF THIS DRAWING IS A REDUCTION USE GRAPHICSCALES.
3/16"
4'
MAIN DISPATCH003
LOBBY002
AIR CREWDISPATCH
006 MALE LOCKER010
FEMALE LOCKER009
READY ROOM013
PANTRY011
CORRIDOR026
STORAGE029
DISPATCH SUPPORTSUPER005
OPERATORRECORDS &LICENSING
014TRAINING OFFICE
015
TRAININGCLASSROOM
016
OFFICER INCHARGE017
EQUIPMENTSUPPORT020
VEST.001
VEHICLE OPSSUPER019
SECURE ROOM021
EDS DISPATCH007
CORRIDOR027
CORRIDOR028
VEHICLE OPS MGR018
MECHANICAL ROOM023
COMM. ROOM022
WATER HEATER012
STORAGE025
EDS SUPER004
ENTRY000
VENDINGMACHINES(NIC)
JC008
FINISH LEGEND
ACOUSTICAL CEILING TILE
CONCRETE BLOCK
CONCRETE BLOCK [PAINTED WITH HIGH-REFLECTIVE NONSLIP EPOXY PAINT]
CONCRETE [SEALED]
CARPET [TILE]
CERAMIC TILE
CERAMIC TILE BASE
CERAMIC WALL TILE
EXPOSED STRUCTURE
PAINT
PLASTIC LAMINATE
RESILIENT TILE
STATIC DISSIPATIVE TILE
VINYL BASE
VINYL COMPOSITION TILE
ACT
CB
CONC-P
CONC-S
CPT
CT
CTB
CTW
EXP
P
PL
RT
SDT
VB
VCT
THESE NOTES ARE GENERAL IN NATURE AND SHALLAPPLY TO THE ENTIRE PROJECT
FINISH NOTES
WHERE CASEWORK OR OTHER EQUIPMENT IS SCHEDULEDFOR A ROOM, THE FLOOR MATERIAL WILL EXTEND UNDERTHIS EQUIPMENT TO ALL WALLS.
WHERE CERAMIC TILE IS SCHEDULED FOR FLOORS ORWALLS, TILE SHALL BE PROVIDED OVER WET WALL ONLY
PAINT ALL WALLS PRIOR TO CASEWORK INSTALLATION. THEENTIRE WALL SURFACE SHALL BE PAINTED FROM FLOOR TOCEILING.
OUTSIDE MASONRY CORNERS: ALL OUTSIDE CORNERS OFC.M.U. PARTITIONS AND WINDOW JAMBS & SILLS TO BE 1"BULLNOSE C.M.U. BLOCK.
PROVIDE RESILIENT BASE RB.01 AT ALL CASEWORK UNLESSOTHERWISE NOTED.
ALL MISCELLANEOUS STEEL (INCLUDING BUT NOT LIMITED TOTAILINGS, PLATFORMS AND METAL FABRICATIONS) SHALL BEPAINTED.
CONTRACTOR SHALL ASSUME A MINIMUM OF TWO PAINTCOLORS FOR THE STEEL GUARDRAIL AND HANDRAIL SYSTEMS.
OUTSIDE COUNTERTOP CORNERS: PROVIDE CHAMFEREDCORNER AT ALL EXPOSED OUTSIDE COUNTERTOP CORNERSPER DETAIL X/XX.X
GENERAL NOTES
F-1
F-2
F-3
F-4
F-5
F-6
F-7
F-8
THESE NOTES ARE GENERAL IN NATURE ANDSHALL APPLY TO THE ENTIRE PROJECT
1 2 3 4 5
1 2 3 4 5
A
B
C
D
A
B
C
D
DES DRW
REVIEWED BY
BRENDA BARGER, PM
NAVAL FACILITIES ENGINEERI NG COMMAND
DEPARTMENT OF THE NAVY
NAV
A L F
ACIL
ITI E
S EN
GIN
E ER
ING
CO
MM
A ND
-JO
INT
BASE
AN
DR
E WS
CODE ID. NO. 0 SIZE D
SCALE:
MAXIMO NO.
STA. PROJ. NO.
WORK ORDER NO.
CONSTR. CONTR. NO.
NAVFAC DRAWING NO.
SHEET OF
DRAWFORM REVISION
REVDATE:
SYM
DESCRIPTION
DATE
APPR
P3001 RLOCATE JADOC (SAT ELLITE SITE)
CAMP SPRINGS, MD
0
14
N40080-15-D-0154
NCPC
SUBMITTAL
PREL
IMIN
ARY
NOT F
OR CO
NSTR
UCTIO
N
As indicated
P600
0 VE
HICL
E O
PERA
TIO
NS A
DDIT
ION
FINI
SH P
LAN
AF10112
SCALE:
N
3/16" = 1'-0"AF101FINISH FLOOR PLAN1
FINISHES:CPTVB
FINISHES:CT
CTB
FINISHES:WM
FINISHES:CPTVB
FINISHES:CPTVB
FINISHES:CPTVB
FINISHES:CPTVB
FINISHES:CPTVB
FINISHES:CPTVB
FINISHES:SDTVB
FINISHES:CONC-P
FINISHES:CONC-P
FINISHES:RTVB
FINISHES:RTVB
FINISHES:CPTVB
FINISHES:RTVB
FINISHES:RTVBCG
FINISHES:RTVBCG
FINISHES:RTVBCG
FINISHES:RTVBCG
FINISHES:CT
CTBCWT
FINISHES:CT
CTBCWT
FINISHES:CT
CTBCWT
FINISHES:CT
CTBCWT
SCHEDULE - ROOM FINISHESAREA NAME FLOOR FINISH BASE FINISH WALL FINISH CEILING FINISH CEILING HEIGHT NOTES