Top Banner
Operation, Maintenance, & Operation, Maintenance, & Replacement of AMD Passive Replacement of AMD Passive Treatment Systems Treatment Systems Where we’ve been Where we are now Where we’re heading Past, Present and Future Presented by Pam Milavec DEP Bureau of Abandoned Mine Reclamation August 12, 2008
30

Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Mar 31, 2015

Download

Documents

Jasmin Sears
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Operation, Maintenance, & Operation, Maintenance, & Replacement of AMD Passive Replacement of AMD Passive Treatment SystemsTreatment Systems

Operation, Maintenance, & Operation, Maintenance, & Replacement of AMD Passive Replacement of AMD Passive Treatment SystemsTreatment Systems

•Where we’ve been

•Where we are now

•Where we’re heading

Past, Present and Future

Presented by Pam Milavec DEP Bureau of Abandoned Mine Reclamation

August 12, 2008

Page 2: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Where have we been?Where have we been?

Page 3: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Why Operation and Maintenance?Why Operation and Maintenance?

Currently more than 259 systems in operation with a public investment of over $77 million

Experience has shown that passive systems have routine operational needs, have expected and often unexpected major maintenance requirements and will eventually need to be replaced

Failure to provide for OMR will result in the loss of restored water resources and public investment

Page 4: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

TermsTerms Construction: Cost to build the treatment system. O & M: Operation and maintenance activities including

inspections, sampling, sample analysis, flushing, scheduled maintenance, and non-catastrophic unscheduled maintenance.

R: Single replacement of the system. Projected costs may approach original construction costs.

O, M & R: Combined operation, maintenance and replacement costs.

Page 5: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

O, M & R Plan Should IncludeO, M & R Plan Should Include

Narrative describing O, M & R Maintenance agreement with all parties,

including property owners O, M & R Site Map

Flushing points, sample points, BMPs Site specific instructions “As-built” plans

Page 6: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Long-term Cost AnalysisLong-term Cost Analysis

Page 7: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Information Sources: AMDInformation Sources: AMD DEP/BAMR -actual construction and O & M costs for

existing systems plus estimated replacement costs NRCS - project bid cost plus estimated

O, M & R Stream Restoration Inc. – estimated

O, M & R for existing projects Hedin Environmental - estimated construction and

long-term O, M & R for Babb Creek system

Page 8: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Average Annual Factors for AMD Treatment Systems *Average Annual Factors for AMD Treatment Systems *

Vertical Flow Systems.....…………..... 5% Anoxic Limestone Drain Systems....... 4% Compost Anaerobic wetlands............. 4% Pyrolusite© Systems........................... 3% Open limestone channels.................... 1% Lime sand addition programs..….….... 33-50% Automated lime doser......................... 13%

OMR Workgroup Average………….….4%

* Annual percentage of construction costs

Page 9: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Breakdown of O, M & R forVertical Flow SystemsBreakdown of O, M & R forVertical Flow Systems

Routine operations (sampling,........... 20%inspections, flushing)

Water sample lab analyses ............... 10% Maintenance – repairs & supplies ..... 30% System reconstruction...................... 40%

Total O, M & R............................... 100%

(65% DEP provided, 35% local)

Page 10: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Guiding Principles for Projects in PennsylvaniaGuiding Principles for Projects in Pennsylvania

True Sustainable Operation, Maintenance & Replacement is based on LOCAL COMMUNITY

Ownership & InvolvementThe goal is a system of healthy

INTERDEPENDENCE & PARTNERSHIP between

government and local sponsors

Page 11: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

OMR Support StrategyOMR Support Strategy

Local Sponsors provide routine operation and maintenance

Maintenance needs assisted by local industry, local government and/or BAMR construction staff

DEP provides funding for more significant maintenance and eventual system replacement

Page 12: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Where are we now?Where are we now?

Page 13: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Present Status:Present Status: GG projects now require OMR plans as a deliverable GG project applications that adequately address OMR receive a

higher score, particularly when non-government sources are utilized Local sponsors are expected to provide routine operations GG has an OMR project-type category and provides funding for

maintenance and replacement on a competitive scoring, annual grant, basis

WPCAMR has received a grant to fund lab analyses WPCAMR has received 2 Quick Response grants and has applied

for a third in the 2008 grant round BAMR has put together OMR task force to evaluate existing BAMR

passive treatment systems

Page 14: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Growing Greener O, M & R Category:Existing Facilities

Growing Greener O, M & R Category:Existing Facilities

Annual grant cycle Competitively Evaluated and Scored Evaluation and scoring criteria

O, M & R plan conceptually soundPublic-private support with local government, residents, industry, etc.Maintenance/replacement essential for continued environmental benefit

Page 15: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

WPCAMR Lab Analysis GrantWPCAMR Lab Analysis Grant $166,000 grant provides funding for lab analysis by

local labs: Mahaffey Lab (Grampian) & G&C Lab in Summerville

Currently covering 7 counties: Allegheny, Armstrong, Butler, Clarion, Clearfield, Indiana and Jefferson

Requires an OMR plan Has been underutilized Grant expired 6/30/08; an extension has been

requested but no decision has been made yet

Page 16: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

WPCAMR Quick Response GrantWPCAMR Quick Response Grant Started in 2006 A mechanism to quickly provide GG funds to local sponsors when

failure to act quickly will likely result in serious environmental consequences or will contribute to further damage of a project

Current grant has a remaining balance of $189,000 and has been extended to 6/30/09

2007 grant adds $100,000, with an end date of 2010 WPCAMR has applied for a new grant for the 2008 round of GG Applications are available on the GG web site – search under

“quick response” key words The application process is relatively streamlined and

straightforward

Page 17: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Quick Response (continued)Quick Response (continued) Completed applications, with a contractor’s cost estimate

attached, are submitted to the DMO Watershed Manager Watershed Manager and District Mining Manager must approve

project and forward to WPCAMR WPCAMR sends letter to applicant stating whether funding is

approved or not If approved, applicant has contractor complete repairs,

Watershed Manager reviews and approves repairs, WPCAMR then disperses funds to applicant and applies to DEP for reimbursement

Must have signed landowner access and permits, if needed

Page 18: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Types of Projects funded:Types of Projects funded: Damage caused by storm events – damage to ditches, berms,

intake structures and spillways (most frequent cause of funds needed has been damage due to storm events)

Non-storm related berm and pipe damage Sludge removal from compost Replacement of valves Repairs to a stream bank stabilization project after a storm event

(non-AMD project) 11 projects funded so far; costs have ranged from $2,800 to

$55,000

Page 19: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

BAMR’s OMR TaskforceBAMR’s OMR Taskforce Established to address OMR needs of BAMR-constructed

passive treatment systems In Cambria office, 2 teams have been established that include

engineers and geologists Have completed 2 evaluations and are currently working on 2

more Most problematic sites are given top priority, but the goal is to

develop an OMR workplan for all 24 systems designed and constructed by the Cambria Office

Harrisburg staff is focusing on BF projects designed there, while Wilkes-Barre staff will be working on projects built by BAMR in their District

Reports will eventually be posted on BAMR’s web site

Page 20: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

BAMR AMD Project OMR Report Format 5/14/08

BAMR AMD Project OMR Report Format 5/14/08

Project BackgroundProject number, name, twp., county, receiving streamIdentify what the goal of the project was and general background of the project Project info Project design info – design methodology, design flow and qualityProject description - describe the treatment system including each individual treatment cell Status of routine operations, past maintenance and retrofitsStatus of restoration efforts in the watershed and partner viabilityProperty owner info and status of BAMR access rightsAttachments: (if on-line, links may be used to locate this info)

System water quality data spreadsheet in a standardized formatStream survey report or data, if available (post-construction)As-builts (to be completed by Inspectors/Designers/Surveyors)Monitoring map indicating sample point ID and location O & M/monitoring planTopographic map depicting treatment system locationDirections to site

Page 21: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Performance Evaluation and Recommendations:Evaluation:Water quality data trends (may want to depict with graphs or other visuals)Results of field review (include a discussion of any analysis or field tests completed by BAMR as part of this evaluation)Summary of current status of systemDiscuss whether project goals were accomplishedRecommended Options:Retrofit/major repair to be designed in-house and bid outRetrofit/major repair to be designed through the passive design consultant contract and bid outRetrofit/major repair to be undertaken by the BD crewContinue current operationModify current operation, including operational or monitoring modificationsAbandon system, remove treatment system and restore areaScope of Work for Recommended Option (if applicable)Narrative or list of work neededEstimated cost (identify funding source, if known)Materials list (type and quantity), for BD projectsAttach needed drawings or schematicsPost-construction follow up ReportOnce recommended work is completed, a follow-up report is to be completed and attached that includes costs and success of recommendation Each time a performance evaluation is initiated, the above sections should be repeated under the new date

Page 22: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.
Page 23: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.
Page 24: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.
Page 25: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.
Page 26: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.
Page 27: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Where are we going?Where are we going?

Page 28: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

Draft Set-Aside Position Paper:Plan to Address OMR

Draft Set-Aside Position Paper:Plan to Address OMR

Successful Growing Greener Applicants to handle routine operations

DEP to provide mechanism to fund emergencies and non-routine maintenance; current Quick-Response program provides a template

DEP to develop appropriate application to seek grants for complete or partial system replacement

Funds also will be provided to BAMR for Commonwealth-constructed systems and “orphaned” systems

Page 29: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.

FundingFunding

DEP has committed $2 million this year to support OMR Set-Aside funding increases under re-authorized SMCRA will

likely be a source of funding for DEP support of OMR The DEP will make funding decisions based on OMR costs for

current systems and what the projected costs will be for future systems; current estimates are that the OMR need is $2 million/year, thereby requiring approx. $46 million to be deposited into an interest-bearing fund, based on current financial scenarios – just for the passive systems currently operating

Set Aside funds used in this manner will not be available to construct treatment facilities, thereby reducing the overall funding available for AMD abatement and treatment projects

Page 30: Operation, Maintenance, & Replacement of AMD Passive Treatment Systems Where weve been Where we are now Where were heading Past, Present and Future Presented.