Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection Workshop April 11, 2013
28

Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Jan 18, 2016

Download

Documents

Erin Bell
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Operation & Maintenanceof Permanent Stormwater

ControlsOverview of Inspection Requirements

Laura Prickett, AICP, CPESC EOA, Inc.

Construction Inspection WorkshopApril 11, 2013

Page 2: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Outline of Presentation

Permanent Stormwater Controls that Require O&M Verification Inspections

O&M Requirements in the Municipal Regional Stormwater Permit

The O&M Verification Inspection Plan

Tools for Conducting, Tracking and Reporting O&M Inspections

For more information…

Page 3: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Permanent Facilities that Require O&M Inspections

Provision C.3.h of the MRP requires agencies to conduct inspections to verify operation & maintenance (O&M) of: • Stormwater treatment measures, and • Hydromodification management measures

Page 4: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Stormwater Treatment Measures

Engineered systems that remove pollutants from stormwater runoff

Bioretention Area (biotreatment)Bioretention Area (biotreatment)

Page 5: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Stormwater Treatment Measures

Engineered systems that remove pollutants from stormwater runoff

Media Filter (limited use for Special Projects)

Media Filter (limited use for Special Projects)

Page 6: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Hydromodification Management (HM) Facilities

Reduce development-induced erosion Detain stormwater so that post-project

peak flows and durations match pre-project conditions for a range of flows.

Page 7: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Hydromodification Management (HM) Facilities

Basins, tanks or vaults with specialized outlet that slowly releases water.

Detention basin with specialized outletDetention basin with specialized outlet

Page 8: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

O&M Requirements (Provision C.3.h)

Agencies subject to the MRP must: • Require facility owners to conduct ongoing

maintenance (e.g. , maintenance agreement).• Prepare and implement plan for annual O&M

verification inspections, including new installations.

• Conduct O&M verification inspections; provide enforcement as needed.

• Track and report on inspections.

Page 9: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

What about Municipality-owned Facilities?

O&M inspection requirements do not distiguish between municipal and non-municipal facilities.

Inspect, track and report on facilities that your municipality is responsible for maintaining.

Page 10: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

O&M Verification Inspection Plan

Begin implementing by 12/1/10. Each fiscal year, inspect:• All newly installed stormwater treatment and

HM controls within 45 days of installation• 20% of the total number of installed stormwater

treatment and HM controls (when rounding, round up!)

• 20% of all installed vault-based systems (round up)

All installed treatment and HM facilities must be inspected at least once every 5 years.

Page 11: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Lessons Learned from NOVs

Round up when calculating 20 percent of facilities per year. • If your agency has fewer than 5 facilities, be

sure to inspect one per year.

Page 12: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Tools for Inspecting, Tracking & Reporting

O&M Verification Inspection Checklist Annual Report Table Each agency should have an internal

tracking table, which is NOT submitted with Annual Report.

Page 13: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

O&M Verification Checklist

Page 14: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Example Tracking TableMRP Attachment G-1

Page 15: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

DRAFT Annual Report FormC.3.h Reporting Table

Page 16: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

For More Information…

Countywide Program Password Protected ND page www.flowstobay.org (click on “Municipalities,” then “ND”)• O&M Verification Inspection Plan Template• O&M Verification Inspection Checklist• Model maintenance agreement

Municipal Regional Stormwater Permit www.flowstobay.org (click on “Municipalities,” then scroll to “Municipal Stormwater Permit”)

May conduct as part of overall final inspection of constructed project UNLESS:• Stormwater treatment and/or HM facilities become operational

earlier, IN WHICH CASE—Inspect and approve stormwater facilities before they become operational

Page 17: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Common Issues in Inspections of Newly-Installed Treatment

Measures

Laura Prickett, AICP, CPESCEOA, Inc.

Construction Inspection WorkshopApril 11, 2013

Page 18: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Outline

Purpose of inspection What to look for during inspection Common issues Checklist for 45-day inspection

Page 19: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Purpose of Inspection

Verify treatment measures and/or hydromodification management controls are installed per approved plans.

At a minimum, inspect those components that are visible in the finished condition.

If possible, also inspect below grade components during construction.

Page 20: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Prepare for the Inspection Review project plans to identify:• The number of treatment measures and/or

HM systems to be installed on the site.• The locations of treatment measures

and/or HM systems.• The dimensions of treatment measures

and/or HM systems.

Page 21: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Prepare for the Inspection

Review project plans to identify:• How high flows will be managed/diverted.• Type and extent of plant cover.• Type of approved irrigation system.

In this system, high flows will enter raised inlet.

Page 22: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

During the Inspection

Confirm that installation matches approved plans regarding:• Total number and type(s) of facilities.• Location of facilities on the site.• Dimensions of facilities.• Request confirmation from site

superintendent that biotreatment soil is per MRP specifications.

Page 23: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

During the Inspection

Confirm that installation matches approved plans regarding:• Type and extent of plant cover.• Functional irrigation system.• High-flow bypass or overflow path.

Overflow drain designed to keep out trash and debris.

Page 24: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Common Issues Is there exposed soil?• Exposed soil should be covered with 2” of

mulch, except for area immediately surrounding tree trunks (roots need air).

Will vegetation block inlets to the treatment measure when mature?

Turf is blocking inlet; insufficient drop between pavement and top of grade in planting area.

Page 25: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Common Issues Is there positive drainage to the

treatment measures? Is there permanent erosion control at

points of concentrated flow?

Cobbles reduce erosion at entrance to bioretention area.

Page 26: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Common Issues Are plants healthy? Accumulation of sediment from

construction activity? • Accumulated sediment must be removed.

Page 27: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

O&M Verification ChecklistMay be used for 45-Day inspections; will have to

use “Comments” section

Page 28: Operation & Maintenance of Permanent Stormwater Controls Overview of Inspection Requirements Laura Prickett, AICP, CPESC EOA, Inc. Construction Inspection.

Thank you!