OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO [email protected] Nestor De Lorenzo INVAP [email protected]
18

OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO [email protected] ... • Precommissioning

Jun 07, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

OPAL Reactor Commissioning and Operations Planning

David VittorioANSTO [email protected]

Nestor De LorenzoINVAP [email protected]

Page 2: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Outline• Introduction• Organisational Structure• Documentation• Staffing• Precommissioning• Commissioning

Page 3: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Introduction• Contract awarded to INVAP – July 2000• Detailed engineering and construction phase

(Construction licence issued)• First Concrete pour – November 2002• Reactor pool installed – December 2003• Precommissioning - Now• Cold Commissioning – planned for late 2005• Hot Commissioning – planned for first half 2006

(subject to Operating Licence)• Full operation – late 2006

Page 4: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Project Structure

INVAP

ANSTO Project Group

Commissioning Operations

Group (COG)

Page 5: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning Reactor Manager

Chief Technical Advisor

ANSTO OPAL COMMISSIONING OPERATIONS GROUP (COG)

Manager Operations Planning

Administration Training Group Commissioning Planning

Operational Planning

Nuclear AnalysisSupport from Nuclear Analysis

for commissioning and operations activities

Leader Commissioning

Maintenance

Leader Commissioning

Utilisation

Leader Commissioning

Operations

Maintenance Engineers

Maintenance

Utiisation Commissioning Group

As at 1 December 2004

Page 6: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Documentation• Drafted by INVAP• Review and comments by ANSTO• Documentation includes

• Operations manuals• Procedures & Instructions• Maintenance manuals• Design manuals• Engineering reports• Safety Analysis Report

Page 7: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Documentation• Additional documentation prepared by ANSTO

to gain Quality certification to ISO 9001:2000Total 20 Procedures including:Safety ManagementCore ManagementModification Management

• All tests performed using approved procedures• Records maintained• Final reports prepared by Commissioning teams

Page 8: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Documentation• Precommissioning and Commissioning

Procedures• All test performed using detailed approved

procedures• Objective• Method• Equipment• Data sheets• Acceptance criteria

Page 9: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Staffing

• Recruitment process for internal and external staff – including HIFAR staff

• COG consists of approx 50 staff• 30 staff have undertaken a OPAL design and

Operations training course• Operations staff to be chosen for further training

Page 10: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Precommissioning

• INVAP responsible for precommissioning• ANSTO project team provides oversight• COG witness and support precommissioning

activities as needed• Other tests include:

• Factory acceptance tests• Installation tests• Functional tests

Page 11: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Precommissioning

• Precommissioning performed to demonstrate:• Systems operate as expected according to design

objective• OH&S requirements• Interface with other systems or services• Appropriateness of operational and maintenance

documentation

Page 12: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning Stages

• Stage A – Pre Fuel Loading Tests• Plant systems properly function in an integrated

manner• Stage B1 – Fuel loading and first approach to

criticality• Fuel progressively loaded into the core• First criticality

Page 13: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning Stages

• Stage B2 – Low power tests• Continue loading Fuel• Low power tests• Demonstrate core compliance with Nuclear &

Thermal-hydraulic design

Page 14: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning Stages

• Stage C – Power ascension and full, power tests• Staged power increase• Test performed at each power level• Full power tests

• Contract performance demonstration tests• Confirm compliance with contract performance

acceptance criteria

Page 15: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning

• IAEA Guidelines• Purpose of Commissioning

• to demonstrate that plant systems and subsystems operate together in an integrated manner in accordance with the design objective and meet the performance criteria regarding operational requirements, occupational safety requirements and nuclear safety requirements.

Page 16: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning Plan• INVAP and ANSTO responsibilities• Objectives of commissioning• Commissioning Organisation

• Management group• Commissioning group & Teams• Operations group• Construction group• Commissioning Safety Review Committee• Commissioning Quality Assurance group

Page 17: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning

Commissioning OrganisationManagement Group

ANSTO/INVAP

Commissioning Group

-INVAP Comm. Mgr.-RRR Prj Eng Mngr-Comm Reactor Mngr

Commissioning TeamsANSTO/INVAP

Quality Assurance Group

QAAudit

ARPANSA

RRR Safety & Licensing Mngr

Witness tests

Controls

Report

Support

Requests Support

Report

Feedback

Requests Tests

Reports

Authorises

Notifies & requests Authorisation

Liaison

Liaison

Communication

Reports and submissions

Operation Group ANSTOGroup

Construction Group

Operates

Report

CommissioningSafety Review

Committee

Page 18: OPAL Reactor Commissioning and Operations Planning · OPAL Reactor Commissioning and Operations Planning David Vittorio ANSTO david.vittorio@ansto.gov.au ... • Precommissioning