Top Banner
Development and Construction o f On-Shore Windfarms Andrew Aveyard Green Cat Renewables Jim Wilkinson CA Blackwells
36
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: onshore-windfarm-part-2

Development  and Construction of On-Shore Windfarms

Andrew Aveyard Green Cat RenewablesJim WilkinsonCA Blackwells

Page 2: onshore-windfarm-part-2

Green Cat Renewables

• + 40 Environmental Consultants, Engineers, and Legal Support

• 4 offices in Scotland and England• Construction projects have ranged from single

turbines (0.33MW) too a 11.5MW project• Planning projects range upto 85MW project (25

turbines)• +50 turbines and 60MW operational (+2% Scottish on

shore turbines, +50% small scale [sub 10mw])

Page 3: onshore-windfarm-part-2

Services

• Owners Engineer• Banks Engineer• Project / Portfolio Due Diligence

Page 4: onshore-windfarm-part-2

Andrew Aveyard

• Engineering Team Leader 2010 – to date• Grown from 2 staff up to 12 technical staff• Grown from 4 turbines a year up to 55 turbines due

in 2012• Grown annual turnover from £120k up to £890k

Page 5: onshore-windfarm-part-2

Planning Process

• Feasibility• Scoping• Planning Application• Planning Consent

Page 6: onshore-windfarm-part-2

Development Process

• Project Review, Financial options & Risk Assessment• Geotechnical Site Investigation• Civil / Electrical Design• Tender Process• Purification of pre-construction planning conditions• Financial and Technical Due Diligence• Site Preparation (access roads, crane hardstandings)• Turbine Construction• Operations

Page 7: onshore-windfarm-part-2

Development Model

• Secured finance• Non recourse finance

Page 8: onshore-windfarm-part-2

Contract Structure

• Balance of Plant• Multi Contract Choice based on risk assessment and

agreement on who will carry what risk

Page 9: onshore-windfarm-part-2

Project Review

• Project• Planning Conditions• Grid Connection• Wind Resource• Finance options• Turbine options• Contractor options• Programme• Risk Assessment

Page 10: onshore-windfarm-part-2

Site Visit

Page 11: onshore-windfarm-part-2

Site Visit

Page 12: onshore-windfarm-part-2

Site Visit

Page 13: onshore-windfarm-part-2

Geotechnical Investigation

Page 14: onshore-windfarm-part-2

Geotechnical Investigation

• Feasibility• Scoping• Planning Application• Planning Consent

Page 15: onshore-windfarm-part-2

Design

• Civils (access road, crane hardstanding and drainage)• Foundations• Electrical (cable layout)• Off site works (road widening, junction

improvements, ect)

Page 16: onshore-windfarm-part-2

Design

Page 17: onshore-windfarm-part-2

Design

Page 18: onshore-windfarm-part-2

Tender Process

• Form of Contract– Design and Build– Construct– Lump sum– Rates and Measurable

Page 19: onshore-windfarm-part-2

Purification of Pre-construction Planning Conditions

• Construction Method Statement• Route Access Report• Archaeology • Ecology• Radar / MOD• Operational Conditions

Page 20: onshore-windfarm-part-2

Financial & Legal Due Diligence• Funding Documents• Security Documents• Bank Guarantees and Bonds • Direct Agreements• Power Purchase• Turbine Supply and Maintenance Documents• Property Documents• Consents• Construction Documents• Corporate Documents • Insurance Documents • Financial Model • Bank Accounts

Page 21: onshore-windfarm-part-2

Technical Due Diligence• Planning Overview• Wind Resource• Turbine Supplier• Contractor• Ground Conditions• Transportation and Road issues• Work Schedules• Civils and Construction Works• Grid Connection• Metering• Communications• Construction Works

Page 22: onshore-windfarm-part-2

Financial Close

• 10% equity from Client• Funds made available• Grid Connection Deposit and Turbine Deposit • Principal Contractor formally appointed• Construction able to commence

Page 23: onshore-windfarm-part-2

Construction

Page 24: onshore-windfarm-part-2

Turbine Construction

• Turbine manufacturer– Foundations loads, design or completion– Turbine delivery– Turbine erection– Internal electrics– Commissioning

Page 25: onshore-windfarm-part-2

Turbine Construction

Page 26: onshore-windfarm-part-2

Turbine Construction

Page 27: onshore-windfarm-part-2

Turbine Construction

Page 28: onshore-windfarm-part-2

Turbine Construction

Page 29: onshore-windfarm-part-2

Turbine Construction

Page 30: onshore-windfarm-part-2

Turbine Construction

Page 31: onshore-windfarm-part-2

Turbine Construction

Page 32: onshore-windfarm-part-2

Turbine Construction

Page 33: onshore-windfarm-part-2

Turbine Construction

Page 34: onshore-windfarm-part-2

Post Construction

• Commissioning• Take over• Snagging• OFGEM • PPA

Page 35: onshore-windfarm-part-2

Operations

• OFGEM: monthly returns and queries• Council: monitor operational conditions• Operations monitoring: generation & hardware

Page 36: onshore-windfarm-part-2

Development & Construction of on On-Shore Windfarms

Questions