Top Banner

of 65

One Word Ans

Apr 06, 2018

Download

Documents

ss_chinni
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/3/2019 One Word Ans

    1/65

    ONE WARDE ANSWERS

    Normal size of Control room building is 40 *30mts

    Normal area required for the S/S is 800 * 600mts

    D G set Capacity for substation is 250 KVA

    Substation Land level must be 300 mm above the Ground level (HFL)Space required for one bay 75 *27mts

    Substation bearing capacity is more than 10 ton / m^2

    Width of single and double line road is 3.75mts and 7.0mts

    Height of boundary wall is 2.5 mts-3.5mts

    Width of bay is 27mts

    Gantry height of 400 kV is 15mts + 8.5mtspeak

    Gantry height of 220kv is 10mts +5.5 mts peak

    Gantry to gantry 21mts

    Distance between bays 21mts

    400kv ph: -ph clearance 7mts22 0kv ph-ph clearance 4mts

    Clearance in S/S 400kv 220kv

    Ph to earth 3.5m

    Ph to ph 7m 4.5m

    Bus to Bus 10m

    Bus Bar height 8m

    Bus Bar ph to ph 7m

    Bus Bar size 4 inch IPS

    Creep age distance of 400kv AC bushing is 10500mmDia of earth mat rod is 40mm (400, 220kv)

    Dia of earth mat rod is 32mm (132kv)

    Earth flat size is 75 *12mm

    Earth mat should buried 600mm below the ground level

    Station Earth resistance max 0.5 ohms

    Height of the lightning mask is 47mts spike length is 3mts

    Switching impulse is 250 microsecond / 250 m sec.

    Leakage of (GIS) SF6 of each compartment should be less than 1%.

    Mineral insulating oil-type-paraffinic

    Transformer oil must have minimum Flash point 140Conservator air cell is made forNitral rubber

    In ICT internal fault is make due to over heating and sudden switching surge

    NGR is Petersonl oil

    MVAR flow should not from one voltage level to the other voltage level

    TSE - thyristor switching capacitors

    TCR thyrestor controlled reactors

    VTS Voltage Transformer Supervision

    RLDC is doing only central sector scheduling ,

  • 8/3/2019 One Word Ans

    2/65

    A B T : Availability Based Tariff

    : S R Introduced 01.01.03

    A B T :- A B T has been so so effective in improving the Grid Discipline and operation.

    It is heartening to note that Commercial and Economic forces even in India shows that

    results can be obtained from Sensible and relatively simple measures .

    RELIABILITY

    1. Two 220v Battery set

    2. Two 48v Battery set

    3. Main 1 , Main 2 protection

    4. One and Half Breaker System

    5. Bus 1 ,and Bus 2

    6. Shunt Reactor

    7. 400/220 kv Auto Transformer

    8. Fault Locator

    Objectives of grid managements system frequency, voltage, loading, security system

    reliability, Grid discipline merit order of breakdown.

    EVENT LOGGER To record the event in the system

    FAULT LOCATER To measured the fault distance in the line

    DISTURBANCE RECORDER To record the disturbance in the system

    To identify voltage current of pre or post conditionHaving 8 Analog channel and 16 Digital channel

    BUS BAR protection In time of un balancing current or voltage the bus bar

    protection is Operated

    LBB or BFR Any fault condition Breaker trip command via 186 (trip

    relay) . Breaker failure relay simultaneously command

    LBB relay.186 . will not operate the breaker. after 200 ml

    sec LBB operate. At . the time BUSBAR section dead

    TAN DELTA Indication of quality and healthiness of the insulation in

    the

    (Test purpose) bushing or Equipments (0.007 at 20c

    CIRCUITE BREAKER It is ON load device. Contact resistance end to end 150 .

    . micro ohms Switching automatic interruption

    P I R ( 400 ohms ) Are reduce the switching surge over voltage

  • 8/3/2019 One Word Ans

    3/65

    to close 8 to 10 mille seconds before the main contact

    GRADING CAPACITOR Uniform voltage distribution on service

    S F- 6 Very ideal for Arc quenching 6kg/cm^2

    It is electro negative and 5 times heavier than air

    ISOLATOR Disconnect under no load condition for safety insulation and

    Maintenance work, center brake type, con.resistance max 300 ohms

    EARTH SWITCH -To discharge the voltage on dead line. To earth contact resistance

    300 micro ohms

    C V T * Stepping down the voltage ,monitoring for metering, protection and

    control

    *They consist of coupling capacitor Made from di-electric impregnatedpaper

    * Coupling capacitors are used for the PLCC

    C V T use To measured the voltage Inputs to Relays / protection For of PLCC

    C T Step down the current for measurement, controls, and protection.

    Having 5 cores

    L A High voltage surge to ground without affect to substation equipments1 Gapped L A, 2 Gapless L A Rated voltage 360kv,CGL 390KV

    . Made for Zinc Oxide conductor

    SURGE ARRESTER Diverting the high voltage surges to earth and protect the

    insulation

    Surge Monitor unit In between the LA and Earth

    WAVE TRAP Trapping Carrier frequency

    Wave trap are providing between the line and power station

    Is a inductive device, to avoid carrier frequency entering thsubstation

    Only allowed power frequency

    LCR 20 to 2000kz Carrier Frequency

    SHUNT REACTOR : -Will control the dynamic over voltage

    To compensate shunt capacitance of T/L either switched or un

    . switched

    Control over voltage under abnormal conditions of system

  • 8/3/2019 One Word Ans

    4/65

    Take care of switching transients

    SHUNT REACTOR Rated power 50 MVAR (Mega Volt Reactive VAR)

    Gapped core construction, gapped core between air gaps are

    . . molded in

    Epoxy resin to prevent movement between individual

    lamination

    Core segments are radial laminated configuration, to prevent

    . fringing flux

    Five limbed core construction has been adopted

    Tan delta 0.00158, Capacitance 44680,

    IR value 1000 M ohms

    N G R To limit the earth fault current it is connected neutral point of

    S.R

    Established Current to trap at the Neutral Point of the N G R

    I R value primary to earth is 900m ohm

    Tan delta value 0.00310,capacitance 310 pf (Pico farode)

    S I L Surge impedance load to limit theTL at reactive VAR absorbed

    . by Line equals the capacitive VAR supplied by the line

    LIGHTNING MASK Lightning mask protect the substation area covered in 30

    Height 45 mts Spike 3 mts

    BLOCKING OF

    AUTO RECLOSE LBB, Reactor protection, over voltage, Bus bar protection, .

    . Z2 to, Z3 of distance protection circuit breaker problem, carrier

    fail, . receipt of direct trip

    R T U Remote terminal unit-Analog (parameter) &Digital(equipment) . . . .

    . Datas From RTU is transmitted to the nearest sub LDC Trough

    PLCC

    HVDC Two different Generating station or to link with Asynchronous

    link

    System Hydro + Thermal

  • 8/3/2019 One Word Ans

    5/65

    Types of filter in HVDC: -

    . 1. Single frequency tuned filter,

    . 2nd order broad bond damped filter

    3rd order broad bond damped filter, C type broad bond damped

    filter

    Corona ring To make electrical field around the live part uniform resulting

    in electrical stress on insulators and hardware

    Arcing horn Divert the arc under flash over away from insulator string

    Frantic effect In TL receiving end voltage is higher than sending end voltage,

    due

    .. to the capacitive effect of line at lightly loaded on no load case

    Objectives of Grid

    Management : System frequency, System voltage, Line loading

    System security, System reliability, Grid discipline, Merit order

    of b

    Advantages of

    Fiber Optic Cable : -Small size, flexibility, easy of handling, Immunity to

    Electromagnet . Interference,High bandwidth as the frequency, cross talks between Cables is .

    . . . impossible ,

    Unaffected lightning and electric shock, .

    . Immunity To nuclear radiation,

    No frequency clearance is required, not easy to Tap, Direct

    digital . transmission is possible

    Touch potential The potential difference between two points. one on the ground

    other

    Which can simultaneously touch by either end.Step potential

    The potential difference between two points on ground surface. .

    . Which Can be simultaneously touched by feet

    Metal spread reason provide highly resistively for working person

    Minimize hazards of Reptiles

    To avoid surface area for muddy, and water storage

  • 8/3/2019 One Word Ans

    6/65

    Communication advantage :- Highly reliable, Continuously availability,

    Less capital cost, less maintenance

    POWER FACTOR Power factor is the ratio of resistive current to that of total

    current

    COS Q =Ir / It

    COUBLING CAPACITOR For carrier communication

    SHUNT CAPACITOR Power factor improvement during low voltage and low

    power . fact

    STATIC - V A R Step less variation of shunt compensation

    DISSIPATION FACTOR Dissipation Factor is the ratio of resistive current to that

    of . capacitive Current following in insulation materials.Tan Q = Ir / Ic

    SURGE ARRESTER Diverting the high voltage surges to earth and protect the

    insulation

    RANZA Ranza is firstGeneration of Numerical relay, it is

    accuracy memory

    In the last event

    ( Z ) Impedance V / I P 10

    FA1 B1

    L +2

    F- fault , L Line length , P monitor digital reading

    Synchronous motor Power factor improved by the Synchronous motor

    Synchronous admissible for 400kv +or 10%

    Metering Accuracy + or 0.5

    Energy Meter Calibration Error Limit + or - 0.25

    Line loss 2%

    Meter error 1%

    PPM Parts Per Millennium 1/1000000 =0.000001

    P S I Power Grid Safety instruction

    P S I 02 Demarcation of work and testing Areas in substation

    SEM-Special Energy Meter Electronic Energy Meter with 10 days backup 15

    minutes reading

  • 8/3/2019 One Word Ans

    7/65

    ABT-Availability Based Tariff Grid Discipline start at Jan-2003

    Modem Computer messages through the another computer to the way of modem

    Minimum Ground earth mat resistance should be less then 0.5 ohms

    Earth mat has been layed at a depth of600 mm from ground

    Wave Trap Induction is 0.5 M H

    Coupling capacitor capacity 4400pf or 8800pfImpedance matching of line and HF filter is close by coupling device

    MVAR generated by 400kv line is 0.55 MVAR/km

    Capacity of tertiary winding is 105MVA ( 3rd Harmonic )

    Impedance of shunt Reactor approx 3200 ohms

    SF6 Due point should be less then -15

    SF 6 Arc quenching medium at a low and Auto pneumatically controlled

    pressure

    In 400kv switching surge without PIR is 4.6pu and with PIR is 2.3 Pu

    Breaker main contact material is silver coated copper

    Duty cycle of 400kv Breaker is O-0.3 CO (sec) 3 minute CNow a day up to 210 km P40, PIR is required

    Pole Discrepancy not more than 3.33 ms

    Between Two pole breaks should be less than 2.5ms

    Breaker impulse withstand 1425 + 245 kvp

    Rated breaking current 40KA

    Rated making current peak 100KA

    Voltage distribution 4%

    Operating rod of CB is made ofpolytetra fluro ethylene (PTFE)

    Operating rod of ABB CB is 200 mm, CGL-270MMCircuit Breaker (400kv) closing time maximum 150ms

    Circuit Breaker (220kv) closing time maximum 200ms

    Circuit Breaker (400kv) Tripping time maximum 25ms

    Circuit Breaker (220kv) Tripping time maximum 35ms

    250 km PIR not necessary

    Bus Isolator All the Inter locks linked dont bypass

    The maximum fault level in 400kv System 40 kA / 1 sec

    The Dead Time of 400kv system is 0.3sec (300ms)

    Normal Rating current of400kv Equipment 2000 / 3150 AThe charging reactive power for100km is about 120 MVAR

    Contact resistance of interrupter is 50 75 micro ohm

    Value of breaker grading capacitor is 500 PF

    LA non linear (zin.o) resistor is using when voltage increase resistance is decrease

    Silicon grease is applied on the busing to avoid flash over due to deposit old dust,

    other . Particles

    Value of PIR is 400 ohms (8 to 10 mille sec- before close the main contact)

    Maximum value of contact rsistance of breaker is 150 micro ohms (75 +75)

  • 8/3/2019 One Word Ans

    8/65

    In 400kv BIL (lightning impulse) is 1425 kvp, Switching impulse 1050kvp

    Surge impedance loading for 420 kv system is 550 MW

    Power Frequency with stand voltage 630kv rms

    Switching impulse level for 400kv equipment 1050kv peak

    Insulation level of Transformer1300kv

    Insulation level of Breaker and other Equipment 1425kvpLighting with standing capacity 1550kvp

    Condition monitoring of transformers DGA, C+TAN DELTA, FRA, Exciting

    magnetization, Current test, IR value, Ratio test, winding resistance

    Basic impedance level in 400kv is 1425kvp

    Switching impedance in 400kv is1050kvp

    Lightning impulse with stand voltage 1550 kv peak

    Transformer Bushing insulation level 1050kv peak

    Power frequency 630kv rms

    Rating of surge arrestor in 400kv is 390 kV for 10 sec

    NGR is petersonl oilPower line impedance is 0.3-0.4 ohm /km

    Normal flux density transformer is less than< 1.2 web

    Accuracy of fault locator is 3%

    Operating time of bus bar protection is 1 cycle

    Conservator air cell is made forneutral rubber

    Transformer oil has minimum flash point 140 dig.

    Transformer oil is mainly used for1-insulation , 2-coolent.

    Transformer oil - Paraffinic and Nephthenic.

    Transformer oil is undergoes Electrical and Thermal Stresses insideTransformer oil In case of problem in the transformer, Insulating Oil gets de-

    composed . and various gases like Hydrogen , Hydro carbon are

    Generated and Solid . Insulation Generate Co,& Co2

    Transformer Bushing for 400kv 245kv

    Rated current 1250 A

    Insulation level 1050 kvp

    Power frequency 460

    Value of the damping resistance in CVTis 13 ohms and 23 ohms

    EHV grade transformer oil having minimum BDV 60kv with 2.5mm electrode gape

    Line matching unit is part of the PLCC equipmentPIR are reduce the switching surge over voltage

    Breaker puffer pressure is 17 kg /cm

    Normal life of on transformer is 25years

    Condition monitoring of C B: --DCRM, Breaker timings, Capacitance&Tan delta of

    grading

    Capacitors,Due point of SF6 gas

    PIR closing is 8 to 10 mille sec

    In ICT-OLTC tap changer is change in voltage; 1.25 % of voltage 17 steps

  • 8/3/2019 One Word Ans

    9/65

    Auto Transformer Tapping - +10% tapping HV

    Transformer Territory winding for suppressing the Third Harmonic

    PRD pressure 10 psi alarm (Pound per square inch)

    Normal insulating oil drum capacity 209 lit

    Before filling oil in transformer underthe vacuum pressure

  • 8/3/2019 One Word Ans

    10/65

    NGR rated power 3.0 MVAR

    NGR System voltage 145kv class

    NGR Rated Impedance 561 ohms

    NGR HV bushing 145kv

    NGR Neutral bushing 36kv

    NGR To Limit the Earth Fault currentCapacitance 310 PF,Tan delta 0.00310,I.R value Primary to Earth 900M.ohms

    Nuclear power station will trip at a frequency of51.5 Hz

    N G RTan delta 0.00310, Capacitance 310 PF

    Conservator Bladder Material Mitrile Rubber

    C V T-Each stag 132 kV

    C V T-Rated secondary voltage 110 V 3

    Brea down voltage (KV) 60 KV for 2.5mm gap

    Water content PPM = 30 PPM

    Short time thermal current 40 KA/ 1Sec

    Dynamic peak current 100 KAC T un used secondary core (terminals) should be short

    C T secondary winding resistance minimum (500v megger) 50 M ohms

    Dew point limit of SF6 IN -35 at normal -26 during O&M.

    Dissipation Factor = Reactive current (To detect weakness in HV insulation)

    Capacitive current

    Dissipation Factor - Ratio of resistive current to that of Capacitive current

    Tan Delta = Ir / Ic (Ir-resistive current) (Ic-capacitive current)Power factor = COS 0 = Ir / It

    Power factor - The Ratio of Resistive current that of Total current

    Tan Delta should not be more than 0.007 at 20c

    OPGW- Maintenance-SRLDC, NRLDC, ULDC, CC-Engineering , CC-OS

    Size of Copper Earth

    95 sq mm copper main Earth

    35 sq mm copper Additional Earth

    Safety Clearance Ladder & Stick

    400kv 3.1 meters

    230kv 2.4 meters

    MVAR = Active power

    Reactive power

  • 8/3/2019 One Word Ans

    11/65

    VRM Voltage Recording Meter

    FRM Frequency Recording Meter

    P P M Parts per millennium 1 / 1000000 =0.000001

    Availability calculation

    Total NO of Lines in operation 40

    Total NO of Days in month (January) 31days

    Total NO of Hours in a Day 24 hours

    Total Actual Time = No of line X No of days X No of Hours

    Total Outage Attributable to Power Grid Include AMP + Fault tripping + Mal

    operation + Breakdown (71.63hrs)

    Percentage of Availability -% of ABT = Total Actual Time Outages X 100Total Actual Time

    UST Ungrounded Specimen Test

    GST Grounded Specimen Test

    Generally measured using sharing bridge (or) Ratio Arm Bridge

    Thalcher Kolar Line length is 1400 Commissioning on 14.12.03

    A C PLANT Chennai, Selam centralized compressor capacity 50 tone each

    Trichy 3.75 tone x 2 9 (Freon gas-R 22 ,R 12 )

    O&M Expenses 1% on capital cost

    SOS As and When Required

    Voltage Control

    400 kv system 360---400---420

    220kv system 200---220---245

    Frequency Control 49.0 Hz---50.5 Hz

    Gateway of Telecom 3 places ,Mumbai ,Channai ,Kochi

    R L D C has 5 centers. E-W-Mumbai, N-Delhi ,S-Bangalur, NE-Shillong

    Grid code: -Standard List of Element Outage Categories

    PUNCOM :-Every 10 second DATA updated

    Microwave Tower :- Receive and Repeated station

    SCADA :- Supervisory Control And Data Acquisition

    OPGC :- Optic fiber Geopical Cabling

  • 8/3/2019 One Word Ans

    12/65

    Kudankulam Atomic Power station:- Aim AT 2000mw by Russian collaboration

    Each Reactor consist of 1000 MW

    :-Thrunelveli,Udumelpet,Kochi,Edaman,Thruvandr

    um

    If the Neutral is not Grounded1. The Capacitance current in the healthy phase increases to V3 Times the normal

    value

    2. The Capacitance current in the faulty phase become 3 times the normal value

    3. Healthy feeders are taken to Line to Line

    Need for Grounding the Neutral is

    1. Protective scheme can be used to disconnect the fault

    2. Arching Ground is eliminated

    FIRE FIGHTING PUMP HOUSE

    Jacky pump ,Compressor Auto start and Auto stop

    Hydrant pump , Emulsifier pump Auto start and Manual stop

    FFP house water storage tankcapacity 300M^3

    Storage tank capacity 450 M^3Hydropnematic tank capacity 18 M^3

    Hydrant points must be at a distance of 60Mts

    Diesel Engine - Kirlosker Cummins

    Rated - BHP 155 / 2100rpm

    Pump Capacity - 410 m^3 / hour (Becon)

    Emulsifier pump B&C/L make

    - Delta Star connection ,132 kw / 180 HP, 213 A ,2960rpm

    Becon make - BHP 410 m^3 / hourHydrant pump B&C / L make

    - Delta connection ,37 kw / 50 HP, 63 A ,2920rpm

    Becon make - BHP 80 m^3 / hour

    Jockey pump - B&C / L make

    - Delta connection ,11 kw / 15 HP, 20 A ,2900rpm

    Becon make - BHP 32 m^3 / hour

    Compressor - Star connection 1.5kw / 2 HP , 3.4 A 1405rpm

  • 8/3/2019 One Word Ans

    13/65

    Non-Return Valve KOLES 250mm inlet

    Hydrant point - 16 points having

    Co2 - 15 nos

    Dry Chemical Powder (DCP) 40 nos

    Heat detector (Quartozoid bulb) burst at above 79c

    A C PLANT

    Freon gas F22 Grade

    Compressor oil grade Freezol 68

    USV Un loading Solenoid Valve

    A C Plant Compressor 3.5 ton

    LIGHTNINIG ARRESTER

    To safe yard Equipment for Lightning Surges

    Incase of High Voltage Resistance will decrease

    Gapped L AGapless LA Silver Carbide

    Mare ELPRO

    Ratting Current 10 KA

    Ratting Voltage 360 KV

    Maximum Spark Voltage 870 kv / 1.25 micro sec

    Maximum Spark Voltage 1125 kv / 1.25 micro sec

  • 8/3/2019 One Word Ans

    14/65

    CIRCUIT BREAKER Automatic Switching during normal or abnormal condition

    1 Breaker System Three Breaker used in Two Feeder

    Advantage 1 Fault one Breaker or Bus or Line will not Interruption to the System

    2 Addition of Circuits to the System is possible.

    Grading Capacitors : Uniform voltage Distribution on service

    P I R : 400 ohms before closing 8 to 10 mille second from Main contacts

    Hydraulic operated : N2 Gas Accumulator is used for

    Arc Interruption : 1 High Resistance

    2 Current Zero Resistance

    CB Annual maintenance

    Timing test pole to pole difference 3.5 msGrading Capacitor Tan delta (UST)

    I R value 5kv megger

    Insulation Resistance 500v megger

    Operating Times

    Static Contact Resistance

    Dynamic Contact Resistance Measurement (DCRM)

    Tan delta & Capacitance of Grading Capacitance

    Due point of SF6

  • 8/3/2019 One Word Ans

    15/65

    DCRM Dynamic Contact Resistance Measurementtest

    - Current , Resistance ,Traveling speed

    - Open , Close , Close open time

    - Set Amplitude 36 for opening

    - In this test identify Main Contact if any damage- Current inject 100 A

    - 400KV breaker 2000 micro ohms set

    - sampling speed set 10kilo cycle

    - check for stroke length of CB

    - check for over travel or over shut

    - check for default travel

    - check for Travel measurement

    - check for Velocity measurement

    - velocity = Distance

    - Time

    Operating rod ABB 200mm

    Operating rod CGL 270mm

    Pole Discrepancy Test difference 2.5 ms

    Trip coil 1 , Trip coil 2 15 to 20 ohm

    Difference between Main contact and PIR contactDucter value (contact Resistance)

    Dew point test (-35) press two time for purging and test last value

    ABB SF 6 Circuit Breaker

    Breaker has supporting insulators,PIR , main contact, Grading Capacitors.

    Operating pressure - Fully Pneumatic system

    Pressure maintain 31.5 kg /cm 2

    Closing time 100 to 120ms

    Tripping time 18 to 22ms

    SF-6 General Lock out 5.6 barSF-6 Alarm 5.8 bar

    SF-6 Operating Pressure 7.5 / bar 20 c

    PIR Pre Insertion Resistance 400 ohms ,it is contact 8 to 10 ms before the main contact

    Grading Capacitors 500 Uniformly distributed the voltage operation

    Due point (SF-6) -27

    Duty cycle O 0.3sec CO

    ABB Closing & Tripping coil Resistance 15 to 20 ohms

    Trip & Closing coil - 15 to 20 ohms

  • 8/3/2019 One Word Ans

    16/65

    Breaker Contact Resistance 150 micro ohms end to end

    Operating Rod - 200mm

    63A 27.6 - Annunciation

    63T - Trip

    63C - Close63S - Start and Stop

    P D - Pole Discrepancy

    Pressure setting AIR Pressure SF 6 Pressure

    Dynamic Contact Resistance Three Years Once

    Tan delta & Capacitance Three Years Once

    In ABB Breaker occur problem in Trichy

    Magnetic ventle fail, Drive mechanism Oring fail , actuated ring damage

    220 KV BREAKER

    TCO - 50 ms

    TOC - 200 ms

    ABB -35

    BHEL -36

    CGL -35 NGEL -36

    BHEL BREAKER

    Accumulator oil Aero shell fluid 4 / 21 lit

    Operating Electro magnetic, Hydraulic pressure

    Hydraulic pressure 32.5 normal

    ON 31.3

    OFF 32.5

    Air Lock out 30.5

    Closing lock out 27.3General Lock out 25.3

    SF6 6.0Kg / cm2

    Opening time

  • 8/3/2019 One Word Ans

    17/65

    Opening coil 80 ohms

    Opening Pneumatic

    Closing Spring system

    CGL BREAKER

    Opening pneumatic pressureClosing spring system

    Operating pressure 15.5 kg / cm2

    SF-6 Pressure 6.0 kg / cm2

    Operating time < 20 milli sec.

    Closing time

  • 8/3/2019 One Word Ans

    18/65

    WT

    = =

    LMU

    BT

    PLCC

  • 8/3/2019 One Word Ans

    19/65

    BATTERY

    Momenting current withstands the long period. Used for protection, PLCC, Auxiliary

    supplies, triping & closing coil supplies Emergency lighting

    Safety Materials Apron , Gaggle , Fresh water arrangement

    Soda Solution Purpose for Neutralization of Acid

    Acid proof Black paint coated

    Acid proof Floor Tails

    Acid and De Mineralized water marked and keep it separate .

    . room

    CELLS

    Station Batteries are Led Acid Cells

    No of positive plates ( Anode ) = X

    No of Negative plates( Cathode) = X+1

    Charged plates Positive ( Anode ) Brown

    Negative plates Negative( Cathode) Gray

  • 8/3/2019 One Word Ans

    20/65

    Charging is Electrolysis.

    Discharging is Galanism

    Electrolysis Electrolysis is the conversion of Electric energy in to

    chemical . Energy in Electrolysis Where by reaction areCompelled

    Charging DC potential is applied the positive electrode attracts the . .

    . negative sulphate Iron

    Station Batteries are LED ACID CELL

    +Ve plate Led peroxide

    --Ve plate Spongy Led

    Separators Micro process P V C / SinteredElectrolyte Sulphuric Acid H2SO4

    35%Acid 65% D. M. Water

    Specific Gravity (Normal) 1200

    Fully charged condition 1210

    IN 220 V Battery

    Capacity 300 AH

    Boost voltage 283.0v 2.65 v each

    Fully charged 2.16 v each

    Float voltage 235.5v 2.16v each

    Discharge cell 1.8 v each

    Curative discharge ones in year

    Discharge current 30A X 10 hours

    Boost +ve terminal 88

    th

    cell

    IN 48 V Battery

    Capacity 300 AH

    Float voltage 51.8 v 2.16 v each

    Boost voltage 63.5 v 2.65 v each

    Boost +ve terminal 20th cell

    % Of Battery Capacity

  • 8/3/2019 One Word Ans

    21/65

    Discharge current X Hour X 100

    Ampere Hour (300 AH)

    E.g. 29 A X 9 Hours X 100 = 87 % = 300 AH

    Half Yearly - Earth Fault Relay checkYearly - All Battery check

    Charger Transformer winding 50 M.ohm

    Curative Discharge Maintanance Three years once

    To discharge at 1.8v

    CELLS

    1. Series current I : n E amps

    R + nr

    2. Parallel current I : E amps

    R + r / n3. Series & Parallel I : n E amps

    R+ nr / m

    LINES

    Cost of variation Tower 30 35 %

    Cost of variation conductor 35 40 %

    Cost of variation Installation, Earthing 25 30 %

    Cost of variation Insulator 4 5 %

    Cost of variation Hardware 2 3 %

    Moose conductor 61---54 / 3.53 + 7 / 3.53

    Moose sectional area 31.77mmMoose mass per 1Mts length 2.004kg

    DC resistance 0.05552 ohms / km

    Moose minimum tensile strength 161.2Kn

    All aluminum alloy conductor (AAAC) 61 / 3.53mm

    ACSR Aluminum Conductor Steel Reinforced 75

    . 54 Al-3.53mm / 7 Steel-3.53mm

    AAAC Diameter of conductor 31.95mm

    AAAC approx. Wt 1.666kg per mts

  • 8/3/2019 One Word Ans

    22/65

    Earth wire 7 / 3.66mm steel Dia 10.98mm

    Copper bond suspension 1, tension - 2

    IEC Industrial electro technical commission

    IN 400 KV

    No of insulator in V string 2 x 23 (120kn) HVDC 38 No of insulator in Pilot string 23

    Double Single suspension 1 x 23 (120kn)(3.85mts-length)

    Suspension 2 x 24

    Single tension 1 x 24

    Double tension 2 x 23 (160 kn)(4.11mts-length)

    ACSR Moos conductor impudence 0.345 ohms / km

    DC resistance 2.5 ohms / km

    Double tension insulator 2*23 no 160kn

    Long rod insulator are made of electro porcelain

    Railway crossing, river crossing 24 insulators

    IN 220 KV

    Single suspension 13 or 14 / 70kn

    Pilot 13 or 14 / 70kn

    Double suspension 2 x 14 / 70kn

    Single tension 14 or 15 /120kn

    Double tension 2 x 15 / 120kn

    Insulator creepage distance 292mm

    Distance between subs conductor (spacer) 450mm (45cm)

    Maximum load on the conductor is 70 % of UTS

    ACSR PANTHER 110 / 132kv 30stans / 3mm+ 7 / 3mm

    ACSR ZEEBRA 220 / 220kv 54 /3.18mm+ 7 / 3.18mm

    ACSR MOOSE 400kv-54 / 3.53mm + 7 / 3.53mm

    ACSR BUSIMIS 800 KV-AC, 500 KV-HVDC

    EARTH wire 7 / 3.66mm

    INSULATOR Disc 255 mm dia 120 KN mechanical strength

    Typical corona extinction level in 400kv is 320kv

    Shielding angle 132kv / 30

    Shielding angle 220kv / 30

    Shielding angle 400kv / 20

    Shielding angle 500kv HVDC 10

    Shielding angle 800KV 20

    Shielding angle for river crossing tower 10

    Pollution level minimum creepage light 16mm / kV

  • 8/3/2019 One Word Ans

    23/65

    Pollution level minimum creepage medium 20mm / kV

    Pollution level minimum creepage heavy 25mm / kV

    Pollution level minimum creepage very heavy 31mm /kV

    AC line insulator standard disc

    DC line insulator antifog disc type

    Tower earthing

    Pipe earthing G S pipe 25mm dia and 3060 mm length

    Pipe earthing (in soft soil) G S pipe 25mm dia and 2.50mts length

    Counter pies earthing 15-meter earth wire buried 1meter depth

    for radial direction

    Earth value (max) 8 to 10 ohms

    Railway crossing, river crossing double earthing

    Self supporting tower D type towerTransposition tower C type tower

    Height of tower single circuit 30mts

    Height of tower double circuit 45mts

    Max sag allowed 12.47mts

    Railway clearance 19.3mts, 18mts(220kv)

    Telecom clearance 4.5mts

    Mid span joint 30 meter away from the tower

    TOWER

    A - Self supporting towers

    B Conventional guyed towers

    C Chaintle guyed towers

    Type of Tower

    S/C D/C

    A DA Type Tower 0 to 2 degree

    B DB Type Tower 2 to 15 degreeC DC Type Tower 15 to 30 degree (Transposition Tower)

    D DD Type Tower 30 to 60 degree

    Transposition tower

    Single circuit C type

    Double circuit DC type

    Tension tower

  • 8/3/2019 One Word Ans

    24/65

    0 degree - Sectional tower

    2 to 15 degree

    15 to 30 degree

    30 to 60 degree - Dead end tower

    Dead end , River end - Anchor Tower - DD type45 Single Pilot

    Above 45 Double Pilot

    Foundation

    Foundation Depth 3.01 meter

    1. Normal dry

    2. Wet

    3. Partially submerged

    4. Fully submerged

    5. Dry fissured rock6. Wet fissured rock

    7. Hard rock foundation

    8. Block cotton soil

    Required Squire Area

    A type 36 Sq m

    B type 56 Sq m

    C type 84 Sq m

    D type 126 Sq m

    Special Tower Is used at location such as those involving long spans for River crossing

    ,Valley crossing, Creek crossing , Power line crossing falling on the line route.

    No of insulators

    400kv Dia 255mm

    Single suspension 1 x 23nos 120 KN (255 x 145 mm)

    Pilot 1 x 23 nos 120 kn

    V string 2 x 23 nos 90 KN

    Double suspension 2 x 24 nos 160 KN (280 x 145 mm)

    Disc

    220 kv 120kn - 255 X 145 mm

    400 kv - 120kn 255 x 145 mm (1 x 23)

    160kn 280 x 145 mm (2 x 24)

    800 kv - 210kn 280 x 170 mm (2 x 40) , (2 x 35)

    UPSEB - 300kn - 320 x 195 mm (2 x 29) , (2 x 31)both for suspension & tension

  • 8/3/2019 One Word Ans

    25/65

    220kv Dia 255mm

    Single suspension, Pilot 13 or 14 / 70 KN

    Double suspension 2 x 14 / 70kn

    Single tension 14 or 15 / 120kn

    Double tension 2 x 15 / 160kn

    Shielding Angle

    110kv-30 ,220kv-30 ,400kv-20 ,800kv-20 ,+ - 500kv 10

    Span Normal

    800kv 400mts, 450mts

    400kv 400mts

    220kv 335, 350, 375mts

    Spacer 45 centimeters

    Clearance

    In EHV lines the clearance above ground shall not be less than 5.2 m + 0.3 m for every

    33 KV

    Single circuit Ph to ph 11mts

    Double circuit ph to ph 8mts

    Mid span clearance ph to earth wire 9mts

    Clearance for 400kv with any other line 6.1mtsTele communication clearance 6.1mts

    Earth wire to conductor 9.0 mts

    Railway clearance minimum (400kv) 19.3mts

    Railway clearance minimum (220kv) 15.4mts

    Railway clearance minimum (132kv) 14.6mts

    Railway clearance minimum (66kv) 14.1mts

    Road Crossing (High Way) 12.7mts

    Railway crossing must be at an angle of 65*to 90*

    National High way, State High way 12.70mts

    500kv HVDC earth clearance 12.5mtsCircuit-To-Circuit 16mts

    800kv 15.0 mts

    800kv conductor to conductor 15.0 mts

    Live part to nearest part Minimum ground clearance P & T clearance

    400kv 3.1mts 8.84 mts 4.88 mts

    220kv 2.8mts 7.01mts 3.05 mts

    110kv 1.4mts 6.10mts (132kv) 2.74mts

  • 8/3/2019 One Word Ans

    26/65

    63kv 1.0mts 5.49mts

    33kv 0.8mts 3.70mts

    Line to Line

    400kv 6.2mts

    220kv 4.58mts132kv 3.05mts

    vertical clearance for 400kv / 220kv 5.2 mts

    Right of way ROW Ph to earth

    800kv 85mts 12.0mts

    500kv HVD 51mts 12.5mts

    400kv 52mts 8.842mts

    400kv single circuit 48mts

    220kv 35mts 7.015mts132k 27mts 6.1mts

    110k 22mts

    66k 18mts 5.5mts

    wind span :- In between two center point of the span either sides of the tower

    A B C

    c d

    Wind span of the tower B = a / 2 + b / 2 a b

    Weight span of the tower B = c + d

    Transposition tower :-

    Changing position of the phase conductor at every 1/3 of the line length

    To equalize Impedance per phase Normally C type DC type tower with 0 degree

    Wind zone 1=33, 2=39, 3 =44(normal), 4 =47, 5 =50, 6 =55

    Wind zone standardization = 35, 45, 50 mt / sec

    Composite insulators (very light):-Fiber glass rod as core+ silicone ashed material

    Vibration damper (4R) is damping 4 resonant frequencies

    Basic wind speed is 44 m / sec

    Life of tower normal 50 years, HVDC tower 150 years, River crossing 500 years

    Types of survey

    Walk our survey, preliminary survey, Detail survey, Check survey

    Topographical map is 1: 50,000

  • 8/3/2019 One Word Ans

    27/65

    Line survey 1 cm = 5km

    Height of the single circuit Tower is 30 mts

    Height of the double circuit Tower is 45mts

    Shielding angle of the tower is 20

    Maximum height of the tower is 135 meter (N.Sagar-Gooty)

    Standard tower extension 3, 6, 9, 12, 18, 25 mtsTower extension will be fixing at bottom

    Lug extension 1.5mts, 2.5mts, 3.5mts

    In normal soil-soil investigation is doing up to 7 mts depth

    In river crossing soil investigation is doing up to 40 mts depth

    Tack welding below wrist level in S/ circuit

    Tack welding below Bottom crass arm level in D/ circuit

    Maintain sub conductor spacing 6 per 400 mtsRepair sleeve more then two stands broken in outer layer

    Copper bond length 500 mm in length

    Spacer rod ( retaining rod ) 4 rods for each side

    Vibration Damper 1) stock bridge Vibration Damper, 2) spacer damper

    In ERS polymer insulator are used

    Absorption index megger value of15sec to 60sec

    Hot line stick is Fibre Epoxy

    Insulator materials Alumina, feldspar, SilicaMaximum height of tree bellow line 5.5mts

    Depth of foundation 3.1mts

    Chimney 1: 1.5 :3

    Maximum sag allowed 12.87 mts

    Power line crossing clearance 6.10mts

    500 kv HVDC earth clearance is 12.5mts

    First HVDC project at AP to MP

    HVDC 500MW conversion 300 MVAR will consume at both ends

    H V D C Power Loss = 4 % onlyD.C Line :Regulate have much of power sent to use

    TSC-Thyrestor Switching Capacitor, TCR-Thyrestor Controlled Reactor

    Synchronizing is 90% of system voltage in both sides

    Current carrying ofBersimis conductor is 950A

    Thalcher to Kolar line length 1400 km

    Break even distance in HVDC is 650 700km (Repeated station)

    HVDC 500MW conversion 300 MVARwill consume at both ends

  • 8/3/2019 One Word Ans

    28/65

    Dead time of HVDC is 200 msec

    Right of way (ROW) ofHVDC is 46mts

    500 kv HVDC Earth clearance 12.5mts

    Chandrapur HVDC 500 MW Back to Back

    HVDC Transmission AdvantagesRequired only two conductors

    Less transmission voltage drop , Better voltage regulation

    Less Corona loss

    Less Interference with communication lines and no insatiability of power transmission

    In HVDC Frequency meter not required

    Regulate have much of power sent use

    HVDC use as Assynchronizing

    G R Ground Return

    M R Metallic Return

    Basic wind speed is 44km / sec

    In ERS polymer insulators or used

    ERS erection, power grid adopt GINPOLF method

    ERS supplied by LINPSEY manufacturing company Canada

    F type towers where angle is >60 in 800kv

    Maximum height of ERS tower is 78 mts

    If the joined of fiber OPGW at 600c

    OPGW Inter portion consist of Aluminum tube which houses the optical fiber and

    outer . . portion is Ordinary G I wire and act as Earth wire

    With out shutdown PID , OPGW , Put non Auto mode

    Hot line maintenance is hot stick method and bare hand method

    Hot stick method - Line man work with an insulated stick on the live conductorBare hand method Line man who does the maintenance job is at the same potential of

    the . conductor And is totally insulated from the ground by using insulated

    ladder

    Bare hand method

    Clearance for 400kv 7 feet ,

    Clearance for 220kv 5 feet ,

    Tools Glass based Epoxy Resin

  • 8/3/2019 One Word Ans

    29/65

    Hot line maintenance Change of insulators,

    Hot line maintenance shunting is doing after 3rd insulator

    Hot man should not wear any ring, chain, watch, which make cause circulating current

    Hot line stick EPOXY GLASS 100kv / ft / 5minutes

    Hot line Insulation Resistance 100kv / ft / 5 minutesHot line leakage current 14 micro amp / ft

    Hot line suit Faraday Cage FIBRE 25%,NOMEX 75% (Metaly cotton cloths)

    Hot line Ladder EPOXY GLASS RESIN

    Hot stick tester :- Leakage current not less than 30 micro ampere

    Hot line work should taken Auto recloser shell be in OFF for the line at both end

    First Hotline bare hand method First Hotline bare hand technique in power Grid and in

    . . . India was Carried out on Salem Bangalure 400kv in

    1990

    Dress - Mentally Cotton Cloths

    P P Rope-Poly Propylene Rope

    Midspan joint should be 30mts away from tower

    Polymer insulators are using in ERS

    ERS supplied by LINPSEY manufacturing company in Canada

    ERS errection, power grid adopt GINPOLE method

    LILO:- For existing Line divert to connect another substation

    Thrunelveli: -Multicircuit substationKanpur :-Unique Sub station

    Kayankulam :-Unique power substation

    GAS Insulated substation

    Thermal power :- Coal ,Fuel , Gas

    Wind power :-Air

    Hydro power :-Water

    Nuclear power :-Uranium

    Solar Power :-Sun Light

    Ramagundam , Singarolli :-500 MWLightning :- 2 x 10*8 volts and : 4 x 10*4 current , 10 5 second

    Trichy Neyveli II 164.17km

    Trichy Ney-TS-I Ex 172.26km

    Trichy Madurai I 130.37km

    Trichy Madurai II 130.37km

    Selam Neyveli I 174.9km

  • 8/3/2019 One Word Ans

    30/65

    Selam Neyveli II 178.7km

    Selam Bangalore 181.357km

    Selam Hosur 127.7km

    Selam Udumelpet I 150.5KM

    Selam Udumelpet II 147.6KM

    M R T

    FSK Frequency Shift Key

    VDU Visual Display Unit

    VTS Voltage Transformer Supervision

    PSB Power Swing BlockSOTF Sw bus bar protection scheme itch On Fault

    REF Restricted Earth Fault

    P40 YTG 33 phase selector

    PUR Permissive Under Reach

    POR Permissive Over reach

    J1 , J2, K D C Supply

    E C V T Volt

  • 8/3/2019 One Word Ans

    31/65

    H A C Supply

    A C T Terminals

    L Event Logger , Annunciation

    B Bus bar

    C protection circuit

    D meteringU potential free contact

    Meter Calibration

    Error Limit - 0.25 + or -

    Line loss - 2%

    Meter Error - 1%

    Considerable Allowed Error - 3%

    Monitor Equipment

    DR , EL , Recording Instruments , Fault Locator

    Ranza Fault Locator Ranza is a Numerical Relay (Digital)

    Sorel Disturbance Recorder -

    Analog channel 8 ,Digital channel 12 -16

    Analog channel C T-1R,2Y,3B,4N CVT 5R,6Y,7B,8N

    Horizontal line 100ms apart printed

    Voltage 2 cm - 480v peak to peak

    Current 2 cm - 10,000 Amp peak to peak

    20 db Transmission lossBPL exchange 24 subscriber , 16 Trunk

    The capital investment of the protective relaying may be order of 3 5 % of the total

    Cost of substation equipment.

    Modern static relay capable of sensing fault with in 20ms

    The dead time of 400kv system is 0.3sec

    The recline time depends on operation of breaker which is 2.5 sec

    Station protection Bus Bar, Stub, TEEDType of relay 1)Disc type 2) Magnetic type 3)Digital type -Electromagnetic Digital

    Electromagnetic static

    Current operated relay-Normal current flow 180 (over line)

    Burden of the ct metering core is 40va accuracy 0.5

    LBB operating current is 200mA after 200m sec

    Fault current 130kv is 31kA

  • 8/3/2019 One Word Ans

    32/65

    Coupling device does impedance matching of line and HF filter

    Wave trap Available 0.5 Mh , 1.0 Mh , 2 Mh (0.5 Mh)

    Power swing blocking time for 40m.sec

    Current setting of stub protection is 2500

    MVAR generated by 400kv line is 0.55MVAR / km

    The transformer differential relay production operate in harmonics exceeds 20%

    Over fluxing relay (k=V/F) < 2.35 alarm. >2.35 trip 1.25 setting time 50 sec

    Impedances of shunt reactor is opprox 3200 ohms

    Shunt reactor backup protection relay set for 70% impedance, time delay 1.5sec

    P 40 stability angle varies from 30 to 90, depends up on the line length

    SF 6 due point should be less than - 15 degree C

    Power equation V1 V2 x sin Q Sin Q is the load angle depends up on X

    X

    Bushing C T used for R E F relay

    CT super vision relay dial setting 1.4 volts

    Operating time of Bus bar protection is 1 cycle

    Accuracy of Fault locater is 3%

    P S B Power Swing Block relay

    Carrier aided signal through NSD 40

    RAZFEE relay tripping time 3ms

    Auto re close 80% to 90% of the fault in power system or transient in nature

    Auto re close are employed to successfully restore the system stability

    Dead time 1 phase auto re close 0.6 sec

    3 phase auto re close 0.5 sec

    Reclaim time = 25 sec

    Delayed time = 51 secRasfee relay tripping time - 3 ms

    SOTF relay is in service only for 200 m sec at the time of charging

    Loss in coupling capacitor should be with in 0.5db

    LMU is for maximum power transfer from carrier equipment to line

    Zero sequence Impedance of the line = Z Q = 1.064 ohms / km

    Positive sequence impedance of the line = Z1= 0.0275+0.331 ohms / km

  • 8/3/2019 One Word Ans

    33/65

    Breaker failure protection 20%of the full load current expected by the CB is

    not cleared by set time relay operate

    50 Hz 1 Harmonic

    100 Hz II Harmonic150 Hz III Harmonic

    Fault locator

    % of fault location = Fault impedance X 100

    Line impedance

    Zone I 80% of the line length and instaneous Trip (

  • 8/3/2019 One Word Ans

    34/65

    Analog data transmission is every 10 sec

    Digital data by exemption every 4 sec

    RTU is synchronized with GPS (Global positioning system) time and every 15 minutes

    it . will check and correct

    RTU Terminal units :-Analog (parameters)&Digital (equipment) Datas from RTU is

    transmitted to the Nearest sub LDC through PLCC

    Class I data (digital data) status indication of CB, Isolator

    Class II data (analog data) V, I, P, Q, F

    Normally scads scan class II data. If any events occur in class I data will over come

    and transmit every 4 sec

    System operation means system monitoring and managementDuring auto reclose NGR reduces secondary arcing current

    SIL (surge impedance load) it is the theoretical loading limit of TL at reactive VAR

    absorbed by the line Equals the capacitive VAR supplied by the line

    100 MW generators can generate 60 MVAR and it can absorb 50 MVAR

    For REFbushing C T is using

    In steady static stability safe load angle is 30To down load SEM data 486 computers is sufficient (Dos based)

    Burden of SEM is 0.5 VA / phase

    Current setting of stub protection is 2500A

    0ver fluxing is creating- voltage increasing = voltage k>1.11

    Frequency decreasing frequency

    Over fluxing relay working at HV , LV, Frequency

    Auto re close is set at 600ms to 1sec

    Reactor Backup timing 1 sec from 0.5 sec

    Restraint bias 50% and 30%

  • 8/3/2019 One Word Ans

    35/65

    Instantaneous Tripping relay time is less then 100ms

    Differential (87R) DTH-31 setting bias 15

    Circulating current 400kv main CT+ 400 Tie CT+ 400kv Neutral CT+ 230kv CT

    . . 87 (all are 1000/1A)

    REF Is circulated relay

    VTS Voltage Transformer Supervision

    Synchronizing - 90% of system voltage &Frequency in both side

    Carrier Aided signal though NSD 40 PLCC

    STUB Line protection - 51 ST Over Current Protection

    STUB LINE PROTECTION- 51 ST (current relay)Normal dial setting current in 1 amp.

    Timer set 0.3sec.

    Stub line protection used during the bus shutdown.

    Fuse Failure Relay 97

    RANZA (Fault Locator)- % of the faulty line length will be displayed

    Fault Locator (Madurai feeder) Type- XTF Ph fault-57P, Earth fault 57N

    Transformer

    Differential DTH 31

    Circulating current CAG 34

    Differential over current CDD 41 voltage /frequency =k>1.11

    Over load CAG 39

    Over fluxing GTTM 22Differential (Bus bar) SBNH 163

    Shunt reactor

    Differential CAG 34

    Restricted Earth fault CAG 14

    Back up YTG 33

    Reactor Backup Protection 87 RC ,RB

  • 8/3/2019 One Word Ans

    36/65

    Transformer & Reactor Test

    Transformer , Reactor , Bushing , & Breaker also tested UST mode

    Transformer , Reactor Winding , ABB - CVT , also tested GST mode

    Measurement of winding resistance All three phase Jumper removedMagnetic Balance test

    Magnetizing current test

    Measurement of polarity and phase relationship

    Floating Neutral voltage measurement

    Short circuit test

    Bucholze relay test

    IR value Insulation test

    Tan delta & Capacitance measurement

    Dissipation Factor COS Q / SIN Q = Tan delta

    Capacitance and Dissipation Factor Tan delta test.UST modeTan delta Dissipation Factor 0.007

    The rate of change of Dissipation Factor (Tan delta ) 0.001 / year

    The rate of change of Capacitance value max + or 1%

    WTI and OTI calibration

    Auto Reclose 186A,152X,186B 186L / O RYB

    Auto Reclose

    Reclaim time 25 sec

    Dead time 1 secDead timer 0.5 sec

    Timer for Delayed Auto reclose 2.5sec

    L B B protection 50 zx , 50 zy (2 / 50z Timer)50 Z

    L B B protection

    Timer 2/50z time (plug) setting 0.2 sec

    Circuit Breaker - Trip Circuit supervision (TC-1) 195RYB

    Circuit Breaker - Trip Circuit supervision (TC-2) 295RYB

    Phase Selector 21 RYB

    VT Fuse Failure Relay 97

    STUB Line Blind Zone protection 51-ST

    STUB Line Blind Zone protection 0.3 sec

    Carrier Lock Out 85 LO

  • 8/3/2019 One Word Ans

    37/65

    Reactor Differential protection 87R

    Reactor Differential protection Setting Bias 30%

    Reactor Restricted Earth Fault protection 64R

    Reactor Back up protection 21R (YTG 33)98R (Timer)Reactor Back up protection - 60% of the Reactor Impedance

    - Zone 3 = 1.25 sec

    Differential Over Current Protection (67 AX,BX,CX,NX)

    Differential Over Current Setting 0.2 Amps

    Over Fluxing Protection 99

    Circulating Current Differential Protection (87)

    Circulating Current Differential Protection

    Current setting 0.1 Amps

    Over Load Protection

    Current Setting 1Amps

    Dial Setting - 10 Amps

    Disturbance recorder

    Having 8 Analog channels 4 in current & 4 in voltage

    Having 16 Digital channels-logic-Protection

    Digital signal cannot transmit for a long distance therefore repeaters are provided

    Digital signal is faster then Analog signalMinimum 20-25 second time will take to reach a data from RTU station to RLDC

    Router is using to communicate to the other station

    TCP / IP-Transmission control protocol ,Internal protocol

    PROTECTIVE RELAYING

    Protective relaying is one of the several features of system design with minimizing

    damage

    to the equipments. And interruptions to services when electrical features occur

    It is sensitively, selectively speed and reliability .

    Protective relaying is design as minimizing damage to equipment interruptions when

    electrical features occurs .

    1.Over current relay - increase 10 %. Current and time relay 10 sec

    2.Over voltage relay - 110 % for 5 sec (Trichy 4 sec) , 140 % Instantaneous first line of the defense

    2.back up relaying =>functions only when primary relay fail

    Primary relaying may fail because of failure in any of the following

    1. Current or voltage supply to the relays

    2. DC tripping voltage supply3. Protective relaying

    3. Tripping circuit

    4. Circuit beaker

    Protective layers operate

    1. Magnetitude voltage, current or both

    2. Frequency

    3. Phase angle

    4. Duration5. Rate of change of

    6. Direction of order of change

    7. Harmonies or wave shape

    Zone of protection the section that is protected by a set of relays is called the zone

    of protection

    Inputs current, voltage, frequency, power input supply carrier input PLCC

    System voltages are usually transformed from 400kv to 110 volt by CVTFeeder protections

    1. Lightning strokes

    2. Phase / earth fault

    3. Over voltage

    Representative value of a lightning stroke

    Voltage =2*10^8 volts

    Current =4*10^4 amps

  • 8/3/2019 One Word Ans

    39/65

    Duration 10^-5 sec

    LAS are provided on the both side of transformer.

    The mainly used scheme 400kv systems are

    1. Distance scheme2. Phase comparison scheme

    Distance relay scheme

    The relay system is made to operate only when the distance of fault point from

    the

    Relaying point is with in the relay setting.

    The relay compares the ratio of voltage and current in the protected feeder.

    Distance protection (impedance protection)\basically of three types of distance relay

    1.Impedence relay, 2. Reactance relay, 3. Admittance mho relay

    Micro mho typ distance relays have been employed generally on medium

    And long lines. The relays capable of looking in one direction only towards the fault

    On the protected feeder section.

    Micro mho Protection (Main I) distance protection (impedance protection)

    Fault locator circuit Micro mho protection

    Line V T Supply ^

    To operation depends upon voltage to current ratio.

    It is compares the fault current seen by the relay and the voltage at the relaying pointto drive the distance of the fault . It is designed to operate only for fault

    Occurring between the fault location and selected reach point .

    Micro mho (21)-Main-1 protection 186 RYB 186 T (3 Phase)

    Main I micro mho

    Main II phase comparison P40 + ZTCM

    Micro mho relay tripping time - 8ms

    ZONE OF PROTECTION

    zone 1 80% of protected length . time delay instantaneous

    zone 2 100%protected line length + 50% of the shortest time delay 500m.zone 3 200% of protected line =>1500ms

    zone 4 20% of protected line =>1500ms

    V.T. SUPERVISION.

    The voltage transformer Supervision uses drive the NPS components of the line Voltage

    and line current.

    An unbalanced fault in the voltage transformer circuit causes NPS voltage above setting

    without detectable NPS current and cause VTS to operate.

  • 8/3/2019 One Word Ans

    40/65

    SYNCHRONIZING SCHEME

    The differences in phase voltage and frequency are with in selected limit before closing

    - Up two section of a power system.

    Distance relay by remote end this means slow and un selective tripping and wide

    spread block out

    PERMISSIVE UNDER REACH SCHEME

    For protection of 21 the relay is permissive command to other end

    On receiving permissive trip command + operation of zone 2 will lead to immediate

    tripping called aided trip

    PERMISSIVE OVER REACH

    In fault on zone 2 at the remote end zone comparator operation along with carrier

    receive signal give instant tripping with aided trip indication.

    Code 1 direct trip signal Hand trip, over voltage, Shunt reactor, LBB.Code - 2 Permissive Inter trip signal zone 2 relay operation causes Breaker tripping

    CARRIER lock Out relay for tripping of an receipt of inter trip signal and at the same

    time

    It Lock out carrier

    SWITCH ON TO FAULT

    For SOTF action at least one of zone comparator operation is needed additionally

    SOTF:- Need 3 phases Trip

    SOTF system detection is activated by using on External breaker closing signal.Time 220 m / s Instantaneous

    This features is available only when all three pole dead signal is present for a period of

    200ms or 110ms

    under this condition when any of the low set current detector pickup with out voltage

    detector operation .

    Three phase tripping with SOTF indication will be initiated.

    (P- 40) Phase comparison relays schemes (principle relay)

    Main II ProtectionCurrent Operated Relay (current in put relay)

    Minimum Operating time 10 ms

    Average Operating time 20 ms

    Main CT (2000A) + Tie CT (2000A) 78 21 ABC (phase selector relay)This method provides high speed and selective unit type protection.

  • 8/3/2019 One Word Ans

    41/65

    Comparison of phase angle between two sides communicated to any time phase angle

    30

    If phase3 angle to change to high so trip command will come

    The phase comparison relay schemes are generally recommended below 300 KM long

    line Because the effective of line charging current and alteration of carrier signals.

    This relay schemes the phase radiation ship between current entering and leaving

    the protected feeds sections employing the power line carrier communication

    1. Comparison of phase angles between two sides communicated to any time phase

    angle 30

    2 .If phase angle to change to high so trip command will be come.

    When the difference between the phase angle of currents at both end crosses a preset

    value the line trips

    To take maintenance inform CPCC for test and also inform other end

    Put both end to out of service

    C T wire short and check current ZERO

    Protection operated test apply current 5,6 7,8 9,10

    I 1 - Positive phase sequence Low set , High set

    I 2 -Negative phase sequence Low set , High set

    Put dummy Load 75 ohms

    P 40 (78) Main-2 protection 86 RYB 86 T (3 Phase)

    Over voltage protection 59RYB(2 / 59 Timer) 86 OV T

    V / I = Z (Z Distance )

    DIFFERENTIAL PROTECTION RELAY

    Transformer Differential relay is Unit protection

    Primary 1000 / 1 for 400kv

    Secondary 800 / 1 for 220kv

    The Differential protection provides complete protection for winding and terminal faults

    The system operate on circulating current principle in CT at each side balance each

    other

    An internal fault creates an un balance and operation of relays

  • 8/3/2019 One Word Ans

    42/65

    DTH 31 used for Two winding transformer used as 0.33 VA phase at rated current 1A

    DTH 32 used for 3 phase 3 winding transformer used as 0.39 VA per phase at rated

    currant 1A

    The relay operates when differential current exceeds 15% relay rated current (fixed )

    The bias setting is (adjusting) 30%High set current 10 times of the normal current (normal 1A)

    Second harmonic content of the differential current exceeds 20%

    Interposing C Ts are used for ratio correction when ever necessary should be adopted

    on the -Inter posting CT by connecting them in star / delta.

    Type of differential relay is used in our substation DTH 31

    Harmonic Restraint of Differential relay is turned for 2 nd Harmonic

    In Transformer Differential relay 400kv main CT and Tie CT 5 th core as used

    For Through fault Differential relay has to restrain

    Transformer Differential relay in our substation is Group A protection

    Differential relay is one that operates when the Vector difference of two or more similarElectrical quantities exceeds a pre determine values

    PHASE SELECTOR RELAY ( 21 )

    Phase Selector Relay is also provided with P-40 for identification faulty phase and also

    for

    Auto re close

    OVER VOLTAGE ( 86 ov ) , (86 ovx)

    86 OV Main & Tie Breaker TC-1& TC-2 also LBB of Main & Tie Breaker

    86 OVX Remote end trip CH-1,CH-2 ,Auto re close Lock Out of Main & Tie

    Breaker

    Time delay 110% for 5 sec Vn 69.85 = 440v (Trichy-4 sec)

    Instantaneous 140 % < 100 ms instantaneous Vn 88.90v = 560v

    POWER SWING BLOCK

    Power swing black will be detected out side of operating zone.

    More than 40 m/s Power swing block. Less than 40 m / s as fault.

    Time to enter operating zone from outer zone.

    BUS BAR PROTECTION

    Incoming current and out going current are balanced maintain in Bus Bar Protection

    If any Bus fault the current will be high that time

    That time Bus Bar Protection operated zone A & zone B

  • 8/3/2019 One Word Ans

    43/65

    VS = IF (RCT+ 2RL ^2) 86.6V setting = 100v

    RCT Resistance across CT , RL Load Resistance of conductor

    All Bus Bar protection are Differential protection,

    Fast acting Differential relay,

    Bus Bar protection scheme for 400 kv system is high impedance Circulating Current

    relay scheme .

    Bus bar protection relay scheme is the vector sum of the currents Entering

    and leaving the bus zone is compared.

    This relay discriminate internal and external faults.

    Current flowing through Secondaries will be balanced

    Current will become unbalanced and will cause voltage rise at relay point Then Bus Bar

    protection operated

    Fault level in Bus Bar is higher then lines or Transformer

    High set current which distinguishes between CT open condition or Bus fault condition

    2000/1 setting 75v

    Bus bar protection is stable and free from thro faults.

    High Impedance un biased differential protection is used for the protection of bus bar.

    Bus bar main lone and Bus bar check Zone is connected to separate current transformer

    (C.T)-

    - Cores on all connected breakers accept the bus bar breaker.

    CT wire supervision VT X 31 CTR 2000 /1 setting 10v

    Plug setting 75 volts

    BUS WIRE SUPERVISION

    Bus wire supervision is provided for alarm and tripping in case of CT wire open

    Setting 14 v and delay 3 seconds

    Zone A - All CTs connected Bus I

    Zone B - All CTs connected Bus IIZone C - All CTs connected Bus I or Bus II

    Bus wire supervision 14 and delay of 3 seconds

    LOCAL BREAKER BACK UB PROTECTION (L B B)

    Line Main CT core 4 (1000 / 1A) 50z

    Line Tie CT core 4 (1000 / 1A) 2/50z Fault Locator

    Reactor Bushing CT core 2 (1000 / 1A)

  • 8/3/2019 One Word Ans

    44/65

    This relay is provided for protection ,in case of Breaker failed 0 Trip during a fault

    condition the operation of LBB will initiate tripping of other feeder. And Bus feeding

    to the faulty Breaker

    There by isolating the faulty Breaker

    Current (plug) setting 20% of 1Amps

    Relay with stand twice the rated current continuously

    100 times rated current for 1 sec

    Accuracy + or 10% of the current setting for any fault condition

    For Feeder

    Phase 1.2 amps

    Neutral 0.4 amps

    Time delay 200 ms

    For Transformer

    Phase 0.2 amps

    Neutral 0.2 amps

    Time delay 200 ms

    REACTOR PROTECTION

    DIFFERENTIAL RPOTECTION

    Differential protection is working at circulating current principle .

    The Differential protection relay provide complete protection for winding and terminal

    fault

    RESTRICTED EARTH FAULT 64 R Group - B

    Restricted Earth fault protection is complete winding for Earth fault

    The Differential protection will not provide protection for fault near the Neutral side

    Of the winding. If the Earthing in done through Impedance

    LINE REACTOR BACK UP 21R Group A

    It may pick up due to non-availability of 110-v supply of CVT and it can be

    checked

    operation of this protection

    IEEE NOTATIONS FOR VARIOUS RELAYS

    IEEE DEVICE NUMBER TYPES OF RELAY

  • 8/3/2019 One Word Ans

    45/65

    21 R - Reactor Distance Back Up Relay

    21- Phase selector relay

    24 - Volts / Hertz relay

    25 - Check Synchronize Relay 25 SK

    27 - Under Voltage relay

    30 - Annunciator relayDTH-31 - Directional protection relay

    32 - Directional power relay

    37 - Under current relay

    40 - Field failure relay

    P-40 - Phase comparison relay

    46N - Negative sequence over current relay

    49 machine or transformer thermal relay

    50 - Instantaneous over current relay

    50Z - LBB Local Breaker Back up relay

    51 ST - Stub line protection relay (current test)51 - AC time over current relay

    52A - Circuit Breaker auxiliary switch (normally open)

    52B - Circuit Breaker auxiliary switch (normally close)

    55 - Power factor relay

    59 - Over voltage relay

    60 Voltage or current balance relay

    64 - Restricted earth fault protective relay

    67 - Directional over current relay

    67N - Ground directional over current relay68 - Blocking relay

    74 - Alarm relay

    76 - DC over current relay

    79 - Auto re close relay

    81 - Frequency relay

    85 - Lock out relay

    86 over voltage relay

    87 - Differential relay

    87 - Circulating current relay

    94 - Tripping relay95 Supervision Relay

    95x Zone Bus Wire Shorting Realy

    97 - VT fuses fail relay

    99 - Over fluxing relay

    TRANSFORMER PRODUCTION

  • 8/3/2019 One Word Ans

    46/65

    Transformer : Transforming electrical voltage one stage to another stage for self

    induction

    or mutual induction with do not power change

    Efficiency : 98%

    DIFFERENTIAL PROTECTION RELAY

    Transformer Differential relay is Unit protection

    Connected between Main Bushing CT and 220kv CT

    When differential current exceeds 0.35 amps

    The Differential protection provides complete protection for winding and terminal faults

    The system operate on circulating current principle in CT at each side balance each

    other

    An internal fault creates an un balance and operation of relays

    DTH 31 used for Two winding transformer used as 0.33 VA phase at rated current 1A

    DTH 32 used for 3 phase 3 winding transformer used as 0.39 VA per phase at rated . .

    . . currant 1A

    The relay operates when differential current exceeds 15% relay rated current (fixed )

    The bias setting is (adjusting) 30%

    High set current 10 times of the normal current (normal 1A)

    Second harmonic content of the differential current exceeds 20%

    Interposing CTs used for ratio correction when ever necessary should be adopted on the

    -Inter posting CT by connecting them in star / delta.

    Type of differential relay is used in our substation DTH 31

    Harmonic Restraint of Differential relay is turned for 2 nd Harmonic

    In Transformer Differential relay 400kv main CT and Tie CT 5 th core as usedFor Through fault Differential relay has to restrain

    Transformer Differential relay in our substation is Group A protection

    Differential relay is one that operates when the Vector difference of two or more similar

    Electrical quantities exceeds a pre determine values

    TRANSFORMER 400KV BUSHING CT

    Core 1 500 / 1A - O / C , O / L ,& E / F

  • 8/3/2019 One Word Ans

    47/65

    Core 2 1000 / 1A - Spare

    Core 3 505 / 1.5 - WDG . Temp

    TRANSFORMER 220KV BUSHING CT

    Core 1 Spare

    Core 2 Differential Over Current , Over Load Protection

    CIRCULATING CURRENT- CAG 34

    Circulating current relay is a unit production working on the circulating current

    principle

    Normal condition current flowing through the relay is 0.

    For any fault zero current will flow through the relay causing instantaneous tripping

    This relay will operate for phase to phase and phase to earth.

    Normal setting 0.1amps.

    OVER FLUX RELAY GTT21

    0ver fluxing is creating- voltage increasing = voltage k>1.11

    Frequency decreasing frequency

    Power frequency and voltage causes both an increase in stress on insulation.

    And working Magnetic flux proportionate increase.

    System voltage and frequency maintain under 360 to 420, 49 to 51.5.

    Transformer is applied to the over flux relay which operates if the E / F ratio crosses the

    setting.

    When Voltage increase 10% rated value at 50 Hz

    Setting 2.5v / Hz Alarm 2.25 v / Hx Alarm 3.5 sec

    RESTRICTED EARTH FAULT PROTECTION

    Connected between main CT and Neutral CT

    DIRECTIONAL OVER CURRENT

    OIL TEMPERATURE

    WINDING TEMPERATURE

    O L T C , & P R D

  • 8/3/2019 One Word Ans

    48/65

    DISTURBANCE RECORDER

    Disturbance Recorder is a vital component of EHV feeder protection system.

    Disturbance Recorder is monitor various system parameters like Voltage, line .

    Current, System frequency, Various Relay contacts, states the records the parameters in. case of fault

    Soral has 8 Analog Channels, 16 logic Channels.

    Normal recording 1 sec post fault, and 0.3 sec free fault

    It Connected to a Time synchronizing system of getting accurate timing of fault and

    relay operation

    EVENT LOGGER (PERM200)

    Event Logger helps an analyzing a Disturbance by providing the events like

    Relay operation, Tripping, Healthiness of relay, Auxiliary system etc.

    And also record of various switching operations carried out.

    Event Logger - plant status and Alarm status in every 4.00 hours

    SUBSTATION PROTECTION

    Bus Bar Protection , L B B , Differential Protection, Circulating Current

    Lightning Arrester , Lightning Mask

    Stub Line protection 51 ST (External resistance 3.3 k ohm)

    Voltage Increasing - Frequency Decreasing Over flux is Creating

    Fuse failure relay 97

    P L C C

  • 8/3/2019 One Word Ans

    49/65

    PLCC- Frequency allotted by international authorities from 30kHz to 500kHz

    PLCC

    Used for communication purpose ,and also used tele metering , tele signaling , tele

    control ,

    Tele printer , tele protection Data transferring signals etc.- In modern power system communication between Load Dispatching Centers to

    Generating station

    - And substation

    PLCC -Ph to Ph coupling used in PLCC (0 4 kHz)

    -Channel 1-Speech channels

    -Channel 2-Protection channel 1 instant telephone speech, protection coupler

    NSD-60,NSD-61

    - Channel 3-Protection channel2 used for CPCC, and all substations for instant

    communication

    AF Multi fluxer used for transmitting Voice, Fax, telemetering, Teleprotection signals

    Speech Channels not used for Telemetering

    Speech Channels bandwidth can be increased to 300 to 3400 Hz

    PLCC level adjustment for speech O3EE 12 & 13

    Level adjust with Level Oscillator and Level Generator Receive level O3EH-

    10&11 measured and Adjust pot O3EH6

    Protection as will as telemetering both can not be used in same channels

    Protection coupler / modem

    Level adjustment NSD 60-R 126 available on mother board of NSD 60

    Level adjustment NSD 61- pot 11 of G3EP

    Telemetering :- For transmission of real time Data from different substation, Generating

    station to LDC,through- Modem Such as NSK 3 & NSK 4 Parameters such as

    MW,MVAR,V,F Transmitted to LDC by using Transducer

    LMU

    Line Matching Unit Used for matching for line impedance and impedance of

    the PLCC equipment 320 ohms per phase

    ETI 21 Single channel

  • 8/3/2019 One Word Ans

    50/65

    ETI 22 Double channel

    PLCC Make ABB-ETI 21,BPL-9505,WS-WSP 100 & PUNCOM

    PLCC E P O B E filter-TF&RF, O-Audio frequency level, B Power

    supply unit

    1st-speech & Data (ETI-21) 2nd speech & protection 3rd

    speech & protection Data available only speech panel

    AGC Automatic Gain Control

    PLCC Power Line Carrier Communication (Band width 4 KHz)

    PTCC Power tele communication

    GDT Gas Discharge Tube

    DTMF Dual Tone Multi Frequency

    FSK Frequency Shift Key

    RF Radio Frequency 0 to 4 KHz

    R T U Remote Terminal Unit

    AGC Automatic Gain Control (AGC volt 5 +1v

    Adopted PLCC carrier frequency range 30 to 500 KHz

    Protection channels in PLCC NSD 4,NSD 41, NSD 60,NSD 61(Trichy), of ABB

    Carrier Aided signal though NSD 40 PLCC

    NSD 40 Code 1 Direct trip

    NSD 60 (4codes) Code 1 Direct tripCode 2 & 3 Permissive trip in conjunction with M1, M2

    Code 4 Check loop test code

    NSD 61 Code 1 & 2 Permissive trip in conjunction with M1, M2

    Code - 3 Direct trip (3codes)

    Modem (Tele metering) NSK3, NSK4, NSK5

    Modem (Tele protection

    Signal protection) NSD-40, NSD-41,NSD-60, NSD-61

    By employing Modem NSD-60, NSD-61

    Telephone EPAX 200.3 MDX50 of BPL

    Balancing Transformer One circuit dead or earth fault, in other circuit signal

    should . affected

  • 8/3/2019 One Word Ans

    51/65

    Protection coupler 4 codes, code1-Direct, code2-Permisive, code3spare,

    code4 - Supervision

    Rx frequency more than TX frequency

    Tx Rx difference 4 Khz

    Prot ch 1 to Prot ch 2 Rx diff 12Khz

    Prot ch 1 to Prot ch 2 Tx diff 8 khz

    Audio frequency 0-4 Khz

    Speech frequency 300 to 2.2 Khz

    IF frequency 16 Khz

    ETI-21 power output 20W ( 3 tier P7EA, P7EB, P7EG )

    ETI 21S power output 40w ( 4 tier P7EA, P7EB, P7EG,P7ES )

    D B- Level Tx +15db, Rx -20db max

    VDU Visual Display Unit

    COUPLING 1,ph to ground, 2. Ph to ph, 3.line to line

    Speech 300 Hz to 2000 Hz

    Tele protection ,tele metering 2000 Hz 3400 Hz

    Protection 2830 Hz, in fault 2580 HzPilot 3631 Hz

    Data 2520 Approximate

    Carrier Aided signal through NSD.40

    POP Point of Presales

    DTMF Dual Tone Multi Frequency

    BPEL BPEL Exchange generally for inter phasing with PLCC

    E3EB RF pre amplifier

    P5EA Power amplifier-20 W

    N5EA Power amplifier- 40 W

    P3EO Will be connect to PLCC outdoor equipment

    AUTO TRANSFORMER (400 / 230 / 33 kv ) TELK / Kerala

  • 8/3/2019 One Word Ans

    52/65

    Transportation filled N2 Gas to a pressure slightly greater then 0.15kg/cm2

    WINDING connection symbol YnaOd 11

    Victor Diagram (HV , LV ) Star , IV Delta

    Territory winding 33 kv

    Capacity 315 KVATransformer Bushing insulation level - 1050kv peak

    Volt / Current 400V / 455A , 230V / 791A

    PRD : - Make M/S Sokrut Udyog Pune (or) QUALITROL make

    Operating Pressure 0.5 to 0.7 kg/cm2

    Operating Time Instantaneous at any temperature

    Operating valve resetting - Automatic

    SPR - Sudden Pressure Relay

    COOLING FAN - Make G E C 36

    - 3 Phase , 740w, 1.5A , Rpm 570OIL PUMP

    - Axial flow 5 HP / 3400 lit / minute

    Volume of Oil - 68800 / lit

    Oil circulation - 3400 x 4 lit/m

    ON LOAD TAPE CHANGER

    Make - BHEL

    - 415V , 1.1KW , 2.75A , 1500rpm

    control voltage - 110vswitching operation 33

    No of steps - 17 taps of 1.25%

    Steps for Tolerance - + or 10%

    OLTC oil minimum BDV 50KV , Moisture content 20ppm

    Due point - 40 c

    Positive pressure - 0.04 to 0.07 bar

    Mercury Filled Vacuum pressure Gage PIRANI type or MELEOD type

    Supply of dry N2 gas is ( -40c)

    BUCHHOLZ RELAY Gas operated relay

    Transformer such as arcing, , partial discharge or local over heating Normally

    Resulting generation of gas .this gas is collected in the relay housing and actuate an

    alarm contact.

  • 8/3/2019 One Word Ans

    53/65

    DRYING OUT PROSES

    When the equipment is opened (T/F or S/R) and the winding insulation is

    exposed

    To atmosphere with draining of oil . it is a must that it should be taken in drying out

    1. Conservator should be isolate from the transformer2. rubber hose should not use in the process

    3. Do all the procedures and drying out start

    4. Raise the oil temperature above 60c

    5. study increase of IR value of the winding

    6. To check BDV of the oil is the value of more than 60kv

    7. Check moisture content of the oil is less than 10ppm

    8. Insert N2 (-40) to the positive pressure of 0.1cc and it is stopped and kept 12

    hours

    9. Then the nitrogen pressure is released and let due point is measured .

    10.The due point is about 20 or below then the dryness of transformer isachived

    11.Oil BDV is 60kv

    12. moisture content < 10 ppm

    13. Due point Nitrogen out let -20

    Testing for Bushing Current Transformer (or) Turret

    Polarity checkApply DC voltage (1.5 v DC) to primary ,the secondary side MA . . .

    . . Meter deflectedRatio Test : - Apply AC current from variyac S1 & S2 , to measured primary volts

    Insulation Resistance Test To remove Neutral Bushing connection

    Check from the neutral to other three phase

    Transformer Bushing Voltage Current Insulation Level

    HV bushing 420 kv 800 A 1425 kvp

    IV bushing 245 kv 1250A 1050 kvp

    LV bushing 52 kv 2000A 250 kvp , 105 kvp / f

    Neutral bushing 36 kv 630A 170 kvpRated Line Earth voltage 21 kv

    Insulation level 1050 kvp

    Main insulation oil impregnated paper

    Short time current rating 3125 kA / sec

    Minimum Greepage 6125mm

    Transformer Air Cell Never exceeded 0.07kg/cm2 at 1.00psi

    Transformer fan start 67c and pump start at 76c

  • 8/3/2019 One Word Ans

    54/65

    Transformer Bushing C T (400 KV )

    Core 1 500/1A over current, Over load, Earth fault

    Core 2 1000/1A Spare

    Core 3 505/1.5 Winding Temperature

    Transformer Bushing C T (230 KV )

    Core 1 1000/1A Spare

    Core 2 1000/1A Differential over current , Over load protection

    Transformer Neutral Bushing C T

    Core 1 Circulating current

    Core 2 Over load protection

    Transformer Protection

    1 Differential Protection 87T 400kv side 500/1A , 220kv side 1000/1A (Group

    B)

    It is connected between 400kv CT and 220kv CT

    Current setting :0.35A restrained ,and 8A for un restrained

    2 R E F -64T 1000/1A , Voltage setting : 40v (Group A)

    It is connect ed between 400kv Bushing CT and 220kv Bushing CT and

    Neutral CT .

    Circulating current 400kv main CT+ 400 Tie CT+ 400kv Neutral CT + 230kv

    CT 87 . (all are 1000/1A)

    3 Differential over current 67RYB-500/1A-PMS-1.5 ,TMS-0.15sec

    4 Differential Earth fault 67N-500/1A,TMS-0.4sec

    5 Over load 500/1A,time-10 sec -110% Alarm (Group A)

    6 Over flux(Group A)

    7 Buchholz(Group A)

    8 Pressure Relief Device Operating pressure-8 PSI (Group A)

    9 Sudden pressure

    10 Oil temperature (Group A)11 OLTC Buchholz (Group B)

    12 Winding temperature (Group B)

    13 Fire protection (Group B)

    14 MOG-Magnetic Oil Gauge

    Basic Insulation Level ( BIL ) 220KV 400KV

    L A 198kv 336kv

    Transformer 900kv 1300kv

  • 8/3/2019 One Word Ans

    55/65

    Other Equipments 1050kv 1425kv

    Supporting insulator - - 1425kv

    SHUNT REACTOR Will control the dynamic over voltage

    To compensate shunt capacitance of T / L either switched or un. . . switched

    Control over voltage under abnormal conditions of system

    Take care of switching transients

    SHUNT REACTOR Rated power 50 MVAR (Mega Volt Reactive VAR)

    Gapped core construction, gapped core between air gaps are

    . . Epoxy resin to prevent movement between individual

    lamination

    Core segments are radial laminated configuration, to prevent

    . fringing flux Five limbed core construction has been adopted

    ES Sending Voltage Z ER

    ER Receiving Voltage ER > ES

    Impedance V^2 ES

    Z (impedance)

    Reactor winding Resistance - 6.6 ohms for each winding

    P X I R60 sec = 1.88

    R600sec

    Capacitance of Leading MVR or Lagging MVR Neutralized ,and control over voltage,

    Neutral current and fault current by inductive coil

    Active power V1 cos 0

    Reactive power V1 sin 0

    Apparent power = Active power/ Reactive power

    Basic Insulation Level SI-1050kvp ,LI-1300 kvpNeutral Bushing 550kvp

    Vibration level 200microns peak to peak (Half yearly maintenance)

    Measure with Transducers or optical detector -10% of the 2nd

    Harmonic

    Noise level 81db

    OIL BDV-60-145kv,15ppm

    Tan delta 0.00158

  • 8/3/2019 One Word Ans

    56/65

    Capacitance 446.80 pf

    IR Value 1000 m.ohms

    Oil 36,000 lit for BHEL ,38,000 lit for CGL

    Shunt ReactorCore I PS Differential protection 87R 200 / 1A

    Core II PS Restricted Earth Fault protection 64R - 200 / 1A

    Core III PS Back up protection 21R - 200 / 1A

    Core IV 1.0 metering - 200 / 1A

    Turret CT cores

    Core I PS Differential protection - 200 / 1A

    Core II PS Main 1 protection ,LBB - 1000 / 1A

    Core III PS Main 2 protection ,DR , FL - 1000 / 1A

    Core VI PS winding Temperature

    Reactor Protection

    400 kv Bushing CT having 4 core

    core 1 = 200/ 1A class PS - Differential Protection circuit

    core 2 = 200/ 1A class PS - Restricted Earth Fault Protection

    core 3 = 200/ 1A class PS - Back Up Protection circuit

    core 4 = 200/ 1A class 1.0 - Metering circuit

    Turret CT having 4 core

    core 1 = 200/1A class PS - Differential Protection circuit

    core 2 = 2000/1000/500/1A class PS Adopted 2000/1A Main-II-Protection

    core 3 = 2000/1000/500/1A class PS Adopted 1000/1A Main-II-Protection,

    LBB . . . core 4 = 69/1 class 5 Winding Temperature Indicator(WTI)

    only B phase

    NGR 3 MVAR

    NGR IR Value test with 5kv megger

    P X I = R15 sec / R60 sec = Giga ohmsUnder fault condition current flow from Neutral to Ground is limited by NGR .

    To limit the Earth fault current. It is connected Neutral point of Shunt Reactor.

    Disconnect Jumper and Earth connection take winding resistance with 5kv megger

    IR Measurement winding to earth, take 15 seconds and 60 seconds value is ratio called

    Absorption co efficient should be more then 1.3

    IR value primary to Earth 900 m ohms

    Tan Delta 8.00310

  • 8/3/2019 One Word Ans

    57/65

    Capacitance 310 pf

    Key Diagram for Reactor 400kv Feeder

    Reactor Bushing CT (400kv ) Reactor Turret CT NGR Bushing CTNeutral

    CT

    NGR Bushing

    Core 1 = 200/ 1A class PS - spareCore 2 = 200/ 1A class PS - Restricted Earth Fault Protection

    1 High Impedance Differential Protection (87R) 200/1A, Setting Voltage 15v

    This relay offers high impedance to external faults and less impedance to internal

    faults

    It is connected between 400kv bushing CT and Neutral CT87R(Differential)

    2. Restricted Earth Fault (64R) 200/1A (CAG) Group B

    It is connected between SR-400kv bushing CT and Neutral CT for Bus

    Reactor . 64R (REF)It is connected between SR-400kv bushing CT and NGR- CT for Line

    Reactor

    3. Reactor Differential Protection (87RR) DTH-31 1000/1A (Group-A)

    C T Ratio 200/1 Class PS Burden 10VA

    It is connected between 400kv bushing CT and Reactor CT

    Current setting : 0.25A restrained ,and 8A for un restrained

    4. Over load

    5. Reactor Backup impedance Protection (21R) YTG 33- 500/1A

    It is connected between Reactor CT and line CVT or Bus I / Bus II CVT,

    Time delay for Bus reactor ;1 sec

    Time delay for Line reactor ;1.2 sec

    6 Over flux plug setting -1.25, time setting 50 sec

    7 Buchholz

    8 Pressure Relief Device 0.6kg cm^2

    9 Sudden pressure

    10 Oil temperature

  • 8/3/2019 One Word Ans

    58/65

    11 OLTC Buchholz

    12 Winding temperature (Reactor CT core 4 200/1)

    13 Fire protection

    14 MOG-Magnetic Oil Gauge

    CAPASITIVE VOLTAGE TRANSFORMER ( C V T )

    Steping down the Voltage for measuring voltage, Protection, and Control, and also

    PLCC

    400 kv CVT400 / V 3 , 22KV 110 v / V 3

    Consist of 1) Capacitor part, 2) EMU Electro Magnetic Unit

    Core 1 (3PS) Main 1 protection, Fault Locator circuit, Even Logger

    Core 2 (3PS) Main 2 protections, Disturbance Recorder, Reactor Back Up

    . protection, O/ V protection

    Core 3 (0.5) Metering Circuit ,Synchronizing Circuit ,Auto Reclose scheme

    Burden 200 , 200 , 200 VA

    Class 3p 3p 0.5

    Breaking current 600 KA

    Tan delta - 0.007KA

    Dissipation Factor (Capacitance) 4400PF

    Secondary Capacitance 88000pf

    Insulation class A

    220kv C V TCore 1 (3PS) Over current, Metering, Synchronizing ckt

    Core 2 (0.5) Earth fault protection

    Measure Capacitance in GST,UST mode

    UST - Top and Bottom of HF point

    GST Top and Earth

    Primary Winding test - 5kv or 10kv megger

  • 8/3/2019 One Word Ans

    59/65

    Secondary Winding test - 500v megger

    Insulation value

    Primary Winding - 400Mego ohms 5kv megger

    Secondary Winding - 100Mego ohms 500v megger

    In case of line CVT fail - The Distance relay may be pick up

    CURRENT TRANSFORMER

    Stepping Down the current for measurements, protection and control .

    Load current which can be 1000ds of amperes are reduced by the C TS to just a few

    amperes under normal condition

    CT Make W/S accuracy 0.5 %

    Tank oil capacity 840 lit

    N2 Gas 0.2 to 0.5 bar

    Annual maintenance

    IR value

    Secondary to secondary

    Secondary to Earth

    Primary to secondary 5kv megger

    Secondary to Earth 500v

    Secondary Winding

    Core to core resistance check

    Polarity Check Apply 1.5v at Primary in secondary some deflection will come

    Current Injection test use Primary Injection Kit 2000 / 1A

    Un used secondary core should be short

    Tan Delta measurement Top and Common point (Only UST mode)

    Primary Injection (current) testNitrogen pressure (test 0.3 positive pressure)

    I R value Carried out on dry & Sunny day

    Primary to D3 ,Secondary ,Earth (5kv megger)- > 1000 Mega ohms

    Secondary to Secondary ,Earth (500kv megger ) - >100 Mega ohms

    Short the secondary terminals (core) which are not used

    Core 1 2000 / 1000 / 1A ACTR 2000 / 1A Bus Bar protection check zone

  • 8/3/2019 One Word Ans

    60/65

    Core 2 2000 / 1000 / 1A ACTR 2000 / 1A Bus Bar protection main zone

    Core 3 2000 / 1000 / 500 / 1A ACTR 1000 / 1A (class 0.5) Metering

    Core 4 2000 / 1000 / 500 / 1 A ACTR 1000 / 1A Main 1 prot Micro mho, LBB,

    Fault . Locator, Cir. current

    Core 5 2000 / 1000 / 500 / 1 A ACTR 2000 / 1A Main 2 prot (P-40) Disturbance

    Recorder

    Metering

    Main CT+ Tie CT

    Line VT supply ( 63.5/ph )

    Export mainexport check iport main import chek ICT primary

    bushing CTICT secondary

    bushing CT VARH export VARH import main

    Transformer Protection

    Differential Protection 87T 400kv side 500/1A , 220kv side 1000/1A(Group B)

    It is connected between 400kv CT and 220kv CT

    Current setting :0.35A restrained ,and 8A for un restrained

    Circulating current 400kv main CT+ 400 Tie CT+ 400kv Neutral CT + 230kv CT

    . . 87 (all are 1000/1A)

    R E F -64T 1000/1A , Voltage setting : 40v(Group A)

    It is connect ed between 400kv Bushing CT and 220kv Bushing CT and

    Neutral CT .

    Differential over current 67RYB-500/1A-PMS-1.5 ,TMS-0.15sec

    Differential Earth fault 67N-500/1A,TMS-0.4sec

    Over load 500/1A,time-10 sec(Group A)

    Over flux(Group A)

    Meter

  • 8/3/2019 One Word Ans

    61/65

    Buchholz(Group A)

    Pressure Relief Device Operating pressure-8 PSI(Group A)

    Sudden pressure

    Oil temperature(Group A)OLTC Buchholz(Group B)

    Winding temperature(Group B)

    Fire protection(Group B)

    MOG-Magnetic Oil Gauge

    Reactor Protection

    High Impedance Differential Protection (87R) 200/1A, Setting Voltage 15v

    This relay offers high impedance to external faults and less impedance to internal

    faults

    It is connected between 400kv bushing CT and Neutral CTRestricted Earth Fault Protection (64R) 200/1A(Group B)

    It is connected between 400kv bushing CT and Neutral CT for Bus Reactor

    It is connected between 400kv bushing CT and NGR- CT for Line Reactor

    Reactor Differential Protection (87RR) 1000/1A

    It is connected between 400kv bushing CT and Reactor CT

    Current setting : 0.25A restrained ,and 8A for un restrained

    Over load

    Reactor Backup impedance Protection (21R) YTG-33 - 500/1A (Group-A)

    It is connected between Reactor CT and line CVT or Bus I / Bus IICVT, 60% of Reactor impedance

    Reactor Backup Protection Timer 98R (VTT)

    Time delay for Bus reactor ;1 sec

    Time delay for Line reactor ;1.2 sec

    Bushing CT

    Line end 200/1A Differential

    R E F

    Back up

    Metering

    Neutral end ratio 200/1A DifferentialR E F

    W T I /

    Power Swing Block Timer 40ms

    Over flux

    Buchholz trip (Group B)

    Pressure Relief Device(Group B)

    Sudden pressure

  • 8/3/2019 One Word Ans

    62/65

    Oil temperature(Group B)

    OLTC Buchholz

    Winding temperature(Group B)

    Fire protectionMOG-Magnetic Oil Gauge

    NGR(Group B)

    LINE PROTECTION

    Main 1 protection-Micromho 21

    Main 1 protection trip relay-186R,186Y,186B (VAJ)

    Main 2 protection Phase Comparison (P-40) Prot-78

    Main 2 protection trip relay- 86R, 86Y, 86B (VAJ)

    P-40 operating time minimum 10ms, max 20msPhase Selector- 21R,21Y,21B YTG-33 Reactor Back up

    YTG-31 Main 2

    Over Voltage protection 59 R Y B

    140% -Instantaneous,

    -110% for 4 sec

    Over Voltage protection 86OV- Main & Tie - 59R,59Y,59B (VTU)

    86-OVX remote end trip via CH-1,CH2

    Circuit Breaker Trip coil 1- CKT Supervision 195A,195B,195C

    Circuit Breaker Trip coil 2- CKT Supervision 295A,295B,295C

    Auto reclose 186A,152X,186B (VARM)

    Auto reclose Lock out 186x,186y,186z (VAJ)

    V T fuse fail -97

    LBB Protection main 50Z (CTIG) dial setting 1.4 / 0.2 amps

    LBB Protection Tie 50ZT (CTIG)

    LBB Timer 2/50Z

    ZONE 0 1.064 ohms

    ZONE I 80% of protected line impedanceTime delay Instantaneous (< 100ms )

    ZONE II 120% of protected line impedance (or)

    100% of protected line impedance + 60% of the A/ T (or)

    50% of the shortest line impedance

    Time de