BSC6900 GU Installation & Commissioning
Page3Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Foreword
The commissioning is performed after the hardware installation and before the services are provided
The OMU operating system is installed before the OMU is delivered
The commissioning ensures the RNC works properly as designed
Page4Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
References
“BSC6900 GU OMU Administration Guide”
“BSC6900 GU Commissioning Guide”
Page5Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Objectives
Upon completion of this course, you will be able to:
Describe BSC6900 commissioning procedure
Outline OMU software functions
Complete BSC6900 commissioning
Complete BSC6900 application software installation
Page6Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Page7Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
BSC6900 O&M Subsystem
Component
LMT
OMUa boards
SCUa boards
OM modules
on other boards
Page8Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
BSC6900 O&M Subsystem
BSC6900 O&M system adopts server and client
mode
OMU as a server
LMT as a client
EMS (Element Management System) system
iManager M2000 works for integrated O&M
Page9Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU IP Address Planning
IP Address Planning Principle
Internal fixed
IP address
The preset IP addresses of the internal Ethernet adapters
are:
Active BAM: 80.168.3.50 (255.0.0.0)
Standby BAM: 80.168.3.60 (255.0.0.0)
External fixed
IP address
The preset IP addresses of the external Ethernet adapters
are:
Active BAM: 172.121.139.201 (255.255.255.0)
Standby BAM: 172.121.139.202 (255.255.255.0)
The settings can be reconfigured on site based on the
actual networking topology
Page10Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU IP Address Planning
IP Address Planning Principle
Internal/External virtual IP
address
The virtual IP address is set in the same subnet with the internal/ external fixed IP addresses of the active and standby BAMs
Backup
channel IP
addresses
The preset backup channel IP addresses of the active and standby BAMs are: Active BAM: 192.168.3.50 (255.255.255.0) Standby BAM: 192.168.3.60 (255.255.255.0)The IP address should not be changed
Commissioning
IP address
The preset commissioning IP addresses are:Active BAM: 192.168.6.50 (255.255.255.0)Standby BAM: 192.168.6.60 (255.255.255.0)
The IP address should not be changed.
Page11Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU Internal Network IP Address Planning
Active OMUa
Internalnetworksegment
Standby OMUa
80.168.3.50/880.168.3.50/8 80.168.3.60/880.168.3.60/8
SCUa SCUa
Backboard
Intel Ethernet adapters
Intel Ethernet adapters
192.168.3.50/24192.168.3.50/24 192.168.3.60/24192.168.3.60/24
Dedicated backup channel
BSC6900 FAM
Virtual IP
80.168.3.40/8
Virtual IP
80.168.3.40/8
ETH4-SCU7
ETH5-SCU6
ETH4-SCU7
ETH5-SCU6
ETH3-UPDATE
ETH3-UPDATE
Page12Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU External Network IP Address Planning
Active OMUa
LMT/M2000
Standby OMUa
ExternalnetworkSegment GE adapter
172.121.139.201/24172.121.139.201/24 172.121.139.202/24172.121.139.202/24
Virtual IP 172.121.139.200/24Virtual IP 172.121.139.200/24
ETH0
ETH1
ETH2
ETH0
ETH1
ETH2
192.168.6.60/24192.168.6.60/24
192.168.6.50/24192.168.6.50/24
Hub
Commissioning Ethernet adapter
Page13Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Page14Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
BSC6900 Software
Dopra Linux Mysql Database
OMU Application
OMU Server
MPS/EPS
Host Software
Program File
Patch File(optional)
Data File
LMT
Windows XPSP2
Java Environment
LMT Software
Page15Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU Software
The OMU
software consist
of multi-level
service
monitoring
entities and
service processes
Page17Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
OMU Software Installation Procedure Obtain the Installation Information on the OMU Remotely Logging In to the OMU Uploading the OMU Application Installation Package to t
he OMU Installing the OMU Application in the Active Workspace Checking the Installation Directory of the OMU Applicatio
ns Checking the Status of omud Process
Page18Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Obtain the Installation Information on the OMU Before the installation, obtain the following
information from Data Sheet of BAM Software
Installation
Password of the operating system administrator
Fixed IP addresses of the internal and external
networks
Page19Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Remotely Logging In to the OMU On the computer run the
SSH terminal, PuTTY Enter the IP address of th
e OMU Log in to the OMU as user
root
Page20Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Uploading the OMU Application Installation Package to the OMU Decompress the BSC6900 version software package to the loca
l drive D Log in to the OMU through the psftp software
Run the lcd D:\ to set the local directory Run the mkdir /mbsc/upgrade to create the target directory Run the cd /mbsc/upgrade to go to the target directory Run the put -r V900R011C00 to upload the OMU application instal
lation packet to the OMU After the loading is complete, enter the exit command to exist the
psftp software
Page21Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Installing the OMU Application in the Active Workarea On the PuTTY terminal, run the following commands
cd /mbsc/upgrade/V900R011C00/install/setup chmod +x ./install_bam.sh ./install_bam.sh Enter the run mode Setting the office name Setting the language Setting the admin/FTP password Setting the external virtual IP address Setting the OMU system type
Page22Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Checking the Installation Directory of the OMU Applications Log in to the OMU by PuTTY Run the cd /mbsc/bam Check whether the OMU installatio
n directory
Page23Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Checking the Status of omud Process Log in to the OMU by PuTTY Run the /etc/rc.d/omud status
The returned information is running, it means the omud is working normally
The returned information is unused, run the /etc/rc.d/omud start command to start the omud
The returned information is neither running nor unused, reinstall the OMU application in the active workspace
Page24Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Page25Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Contents
3. BSC6900 Commissioning3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure
Page26Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Introduction to BSC6900 Commissioning Definition of BSC6900 Commissioning
The commissioning of equipment, BSC6900
board software and data file loading , interfaces
verification , and services verification after
hardware installation
To ensures that the BSC6900 works properly as
designed
Page27Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Preparation For BSC6900 Commissioning Preparation For BSC6900 Commissioning
Verify hardware status
BSC6900 hardware is installed and passed the hardware
installation check and powering-on check
OMU is configured before delivery
LMT PC meets the configuration requirements
Software preparation
BAM and LMT application software are ready
License file is ready
MML command script for initial configuration is ready
Page28Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Preparation For BSC6900 Commissioning (Cont.)
Verify commissioning network status At least one BTS and one NodeB are connected to the local BSC
6900. The BTS and the NodeB should have passed commissioning and can provide basic functions
At least one set of Core Network (CN) equipment is connected to the local BSC6900. The CN equipment should have passed the commissioning and can provide basic functions
If the BSC6900 is connected to the RNC, then that RNC must have passed the commissioning
Three single-mode UEs, three single-mode MSs and one dual-mode UE are ready for test and are registered in the HLR
Page29Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Contents
3. BSC6900 Commissioning
3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure
Page30Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
BSC6900 Commissioning Procedure BSC6900 Commissioning Procedure
Verifying the Equipment
Activating and Verifying the License
Loading the BSC6900 Board Software and Data Files
Verifying the Interfaces
Handling the Alarms Generated During the
Commissioning
Verifying the Services
Connecting the BSC6900 to the M2000
Creating Scheduled Tasks
Page31Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Equipment
Verifying the Equipment Verifying the OMU
Log in to the OMU through PuTTY Check that the OMU application is normally installed If OMU application is not installed or abnormal, please reinstall
software
Verifying the LMT Log in to the BSC6900 through the LMT Run the MML command LST VER to check the version of OMU
Page32Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Activating and Verifying the License Activating and Verifying the License
Downloading license to OMU active workspace
directory /ftp/license (DLD LICENSE)
Querying the detail information of the license file (LST
LICENSE)
Activating the license file (ACT LICENSE)
Checking the license consistency between host and
OMU (CMP LICENSE)
Page33Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Loading the BSC6900 Board Software and Data Files Loading the BSC6900 Board Software and Data Files
Generating the Data File
Clear the data in the BAM database (RST DATA)
Generate the data file in ineffective state
– SET CFGDATAINEFFECTIVE
– Batch Commands
– FMT DATA
Setting the Loading Mode (SET LODCTRL)
Loading the MPS/EPS/TCS (RST SUBRACK)
Checking the consistency of the data and the version (ACT
CRC & CMP BRDVER)
Page34Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Abis Interface Verifying the Abis Interfaces (over TDM)
Verifying Physical links at the BSC (DSP E1T1 & DSP OPT) Verifying Control Plane on the Abis interface (DSP LAPDLN
K) Verifying User Plane on the Abis interface (DSP ABISTS) Verifying Cell status and Channels (DSP BTSSTAT)
Page35Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Abis Interface Verifying the Abis Interfaces (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT & DSP PPPLNK & DSP MPGRP)
Verifying Control Plane on the Abis interface (DSP LAPDLNK & DSP ADJNODE)
Verifying User Plane on the Abis interface (DSP IPPATH) Verifying Cell status and channels (DSP BTSSTAT)
Page36Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Abis Interface Verifying the Abis Interfaces (over HDLC)
Verifying Physical Links at the BSC (DSP E1T1) Verifying Control Plane on the Abis interface (DSP LAPDLN
K) Verifying User Plane on the Abis interface (DSP HDLCLNK) Verifying Cell status and Channels (DSP BTSSTAT)
Page37Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the A Interface
Verifying the A Interface (over TDM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP
OPT)
Verifying Control Plane on the A interface
– DSP MTP2LNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
Verifying User Plane on the A interface (DSP ACIC)
Page38Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the A Interface
Verifying the A Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT &
DSP PPPLNK & DSP MPGRP)
Verifying Control Plane on the A interface
– DSP SCTPLNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying User Plane on the A interface (DSP IPPATH)
Page39Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Gb Interface Verifying the Gb Interface (over FR)
Verifying Physical Links at the BSC (DSP E1T1 & DSP BC ) Verifying Control Plane on the Gb interface (DSP SIGBVC &
DSP PTPBVC & DSP NSVC) Verifying User Plane on the Gb interface (DSP PTPBVC & DS
P NSVC)
Page40Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Gb Interface Verifying the Gb Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT & DSP PPPLNK & DSP MPGRP)
Verifying Control Plane on the Gb interface (DSP NSVL & DSP SIGBVC & & DSP PTPBVC)
Verifying User Plane on the Gb interface (DSP NSVL & DSP PTPBVC)
Page41Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Ater Interface Verifying the Ater Interface
Verifying Physical Links at the BSC (DSP E1T1 & DSP OPT) Verifying Signaling Links at the BSC (optional) (DSP ATERS
L) Verifying status of timeslots on the Gb interface (DSP ATERT
S)
Page42Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Pb Interface Verifying the Pb Interface
Verifying Physical Links at the BSC (DSP E1T1) Verifying Control Plane on the Pb interface (DSP LAPDLNK) Verifying status of timeslots on the Pb interface (DSP PBCI
C)
Page43Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iub Interface Verifying the Iub Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP
OPT)
Verifying the Control Plane on the Iub Interface (DSP
SAALLNK & DSP UIUBCP & DSP ADJNODE)
Verifying the User Plane on the Iub Interface (DSP
AAL2PATH)
Verify the Management Plane on the Iub Interface (DSP
IPOAPVC)
Verifying the Cell Setup (DSP UCELL)
Page45Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iub Interface Verifying the Iub Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT &
DSP OPT)
Verifying the Control Plane on the Iub Interface (DSP
SCTPLNK & DSP UIUBCP & DSP ADJNODE)
Verifying the User Plane on the Iub Interface (DSP
IPPATH)
Verify the Management Plane on the Iub Interface (DSP
IPOAPVC)
Verifying the Cell Setup (DSP UCELL)
Page46Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iu-CS Interface Verifying the Iu-CS Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP
OPT)
Verifying the Control Plane on the Iu-CS Interface
– DSP SAALLNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-CS Interface (DSP
AAL2PATH)
Page47Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iu-CS Interface Verifying the Iu-CS Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT &
DSP OPT)
Verifying the Control Plane on the Iu-CS Interface
– DSP SCTPLNK
– DSP M3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-CS Interface (DSP
IPPATH)
Page48Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iu-PS Interface Verifying the Iu-PS Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP
OPT)
Verifying the Control Plane on the Iu-PS Interface
– DSP SAALLNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-PS Interface (PING
IP)
Page49Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the Iu-PS Interface Verifying the Iu-PS Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT &
DSP OPT)
Verifying the Control Plane on the Iu-PS Interface
– DSP SCTPLNK
– DSP M3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-PS Interface (DSP
IPPATH)
Page50Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Handling the Alarms Generated During the Commissioning Handling Alarms During RNC Commissioning
Checking alarm on the LMT
Handling the Alarms by LMT online help
Handling alarms by HUAWEI Technical Support
Page51Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the GSM Services
To be sure BSC can provide services defined in
license file
Basic services
Speech service, data service, mobility management,
and OM management
Feature services
Inter-system handover, location service, and AMR
service
Page52Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Verifying the UMTS Services
To be sure BSC can provide services defined in
license file
Basic services
Voice service, CS stream service, PS service,
mobility management, and OM management
Feature services
Inter-system handover, HSDPA service, HSUPA
service, MBMS service, and location service
Page53Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Connecting the BSC6900 to the M2000 Connect the BSC6900 to the OM network
Configure the IP route from the BSC6900 to the
M2000 (ADD OMUIPRT & ADD EMSIP)
Create the BSC6900 on the M2000
iManagerTM M2000
DCN
Page54Copyright © 2009 Huawei Technologies Co., Ltd. All rights reserved.
Creating Scheduled Tasks
Scheduled tasks for backing up system data (ADD
SCHTSK & ADD SUBTSK)
Scheduled tasks for backing up logs (ADD SCHTSK
& ADD SUBTSK)
Thank youwww.huawei.com