Oil & Gas Plant Construction Project Execution Plan Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly. http:// www.slideshare.net/DavidHMoloney/oil-gas-plant-construction-project-execution-plan https://www.youtube.com/watch?v=PiRY0ERoXfI 6avid H Moloney 4th August 2016 Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Gas & Oil Plant . This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Video Presentation is innovative and has many beneficial uses.
180
Embed
Oil & Gas Plant Construction, Project Execution Plan
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Oil & Gas Plant Construction
Project Execution Plan
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Gas & Oil Plant .
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
Earthworks includes Excavation, Trenches, Haulage, Grading Backfilling, Filling & Compaction
Earthworks
Excavate & Load Tipper Trucks
Trench Excavation with Stepped Faces
Trench Excavation with Battered Faces
Tipper Trucks Unloading
Spreading & Compaction Clay fillE
art
hw
ork
s
Spreading & Compaction Clay fillE
art
hw
ork
s
Backfill TrenchE
art
hw
ork
s
Dozer Pushing ClayE
art
hw
ork
s
Dozer Ripping GroundE
art
hw
ork
s
Excavator with Hydraulic RockbreakerE
art
hw
ork
s
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes
Eart
hw
ork
s
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
CABC ( Crushed aggregate base course )E
art
hw
ork
s
Mixing Plant
Testing Compaction
Site Trial
Mixing CABCE
art
hw
ork
s
Spreading & Compaction CABC ( Crushed aggregate base course )E
art
hw
ork
s
Spreading & Compaction CABC ( Crushed aggregate base course ) E
art
hw
ork
s
Spreading & Compaction CABC ( Crushed aggregate base course )E
art
hw
ork
s
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.
Construction of Azerbaijan Oil Pipeline 42” by 450km. Overview Construction Sequence
A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and reinstating the land to its original condition..
Crossing Railway, Roads, Rivers, etc.Pump Station
Oil Pipeline 42”Contents
Overview Surveying & Setting OutClearing & GradingDouble Jointing i.e. welding 2 pipes togetherStringing out PipesBend Pipes for changes in direction sideways and up & downWelding Pipes into a string, Test Weld by X Ray.Anti-corrosion Coat to JointsTrenching i.e. excavate trenchLowering pipe string into trenchBackfilling TrenchReinstatement of Pipeline ROW (Right-of-Way)Reinstatement of River BanksCrossing - Horizontal Directional DrillingCrossing - Thrust BoringCrossing - River Hydrotest & PiggingTie-in i.e. connect to existing pipelineMiscellaneous
Pause Slides to Read
Overview Pipeline Construction Animation
To see animations, view YouTube film.
Cable laying 132KVa Electric
Cable LayingP
ipew
ork
Brief Description
132 kVa Cable laying .
Cable Laying P
ipew
ork
Cable Laying P
ipew
ork
Cable Laying P
ipew
ork
Contents
Horizontal Directional DrillingP
ipew
ork
Brief Description
Horizontal Directional Drilling under a taxiway.
Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
Horizontal Directional DrillingP
ipew
ork
Crossings – River, Motorway & RailP
ipew
ork
Overview Pipeline Crossings Construction Animation
Micro TunnellingT
unnels
Micro Tunnelling Sequence David H Moloney
ⓒ David H Moloney
Tunnels
Contents
Includes Sequence, Methods & Equipment
Road Construction
Road Construction Sequence Animation
Asphalt Pavement
Includes Sequence, Methods & Equipment
Fencing & Gates
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
FencingM
iscella
ne
ous
FencingM
iscella
ne
ous
FencingM
iscella
ne
ous
FencingM
iscella
ne
ous
Contents
Setting out & Surveying
Setting out & Surveying
Contents
Emergency Phone Numbers & Response H
ealth,
Safe
ty &
Environm
ent
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Health,
Safe
ty &
Environm
ent
Safety PrecautionsH
ealth,
Safe
ty &
Environm
ent
Safety DocumentsH
ealth,
Safe
ty &
Environm
ent
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
Safety DocumentsH
ealth,
Safe
ty &
Environm
ent
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
Safety Training on Site M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Safety Training Matrix M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Emergency Response Drill H
SE
Drills and exercises are used to rehearse anticipated emergency scenarios
Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection
Environmentally Friendly Site Air, Noise, Water & Soil PollutionH
ealth,
Safe
ty &
Environm
ent
Water Pollution PreventionH
ealth,
Safe
ty &
Environm
ent
Segregation of Waste H
ealth,
Safe
ty &
Environm
ent
Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Putting Waste Concrete to use
ⓒ David H Moloney
Health,
Safe
ty &
Environm
ent
Precast bases for signs and hoarding, Precast blocks for walls.
Contents
Staff Directory
Brief Description
List of staff and their
contact details
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Filing System
Quotations Comparison Sheet
Staff Responsibility Matrix
Contents
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Site LaboratoryG
enera
l item
s
Contents
Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
Programme for Construction
Gantt Charts to plan and schedule projects
Primary Substation-
Chiller Plant
Pump House
IRRIGATION WATER TANKS
Irrigation Pump House-
POTABLE/FIRE WATER TANK
Programme using Timeline & 3D Images
Airport Central Utility Yard
Pump House
Piling
Primary Substation-711
Chiller Plant-714Pump House-715
Irrigation Pump House-716
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
POTABLE/FIRE WATER TANK
Time Chainage Diagram The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Sample Only
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Contents
Temporary Contractors Site Facilities
ⓒ David H Moloney
Brief Description
Site Offices, Camp Accommodation for 1,250 workers, Canteen, Recreation, Fabrication shops, Stores, Plant Yard. In five locations along the route.
Welfare Facilities
ⓒ David H Moloney
Genera
l Item
s
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Site Hoarding examples
ⓒ David H Moloney
Genera
l Item
s
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
Genera
l Item
s
Wheel Wash Drive-through
ⓒ David H Moloney
Genera
l Item
s
Used to wash the wheels of trucks prior to leaving site.
Wheel Wash Drive-throughG
enera
l Item
s
Weighbridge & Sheeting Access
ⓒ David H Moloney
Genera
l Item
s
Access tower for covering tipper truck bodies to prevent air pollution.
Dust Suppression
ⓒ David H Moloney
Genera
l Item
s
Wetting the ground to prevent dust blowing in the wind
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant. ⓒ David H Moloney
Rock is blasted free from a quarry face and fragmented. The blasted rock is crushed and screened to produce different size ranges of aggregates
Quarry & Aggregate ProductionG
enera
l Item
s
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production
Concrete Batching Plant
ⓒ David H Moloney
Concre
te
Concrete Batching Yard 3 Nr MixersG
enera
l Item
s
Concrete MixG
enera
l Item
s
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concre
te
Contents
Notes
Production by David H Moloney