Offshore Wind Astrid Skarheim Onsum, Head of Offshore Wind, Aker Solutions
16

Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

Jun 03, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Offshore Wind

Astrid Skarheim Onsum,

Head of Offshore Wind, Aker Solutions

Page 2: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

175 Years of Change

14 August 2019 Slide 2

Page 3: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Projected Growth in Offshore Wind

14 August 2019 Slide 3

Source: www.IRENA.org

2030: 120 GW

Page 4: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions 14 August 2019 Slide 4

Economy of Scale is Increasing the Turbine Size

Sources: Various; Bloomberg New Energy Finance

Page 5: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Aker Solutions will be a leading provider of

offshore wind energy solutions

Export cable and landfall

Dynamic array cables

Floater

Floating and Subsea Substation

The floating wind system

Page 6: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Floating Wind vs. Large Scale Readiness – 12 myths

14 August 2019 Slide 6

Weight of hulls too high

Simpler installation needed

Maintenance-at-port

missing

Environment - impact not

documented

Lack Floating sub stations

and dynamic cables

Lack of advanced

engineering tools

Lack of Advanced controls

Costly mooring &

anchoring

Advanced tank test

facilities missing

Do not understand wake

effects

Need new industry

standards

Regulatory requirements

and supply chain missing

Weight of hulls too high

Simpler installation needed

Maintenance-at-port

missing

Environment - impact not

documented

Lack Floating sub stations

and dynamic cables

Lack of advanced

engineering tools

Lack of Advanced controls

Costly mooring &

anchoring

Advanced tank test

facilities missing

Do not understand wake

effects

Need new industry

standards

Regulatory requirements

and supply chain missing

Page 7: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions 14 August 2019 Slide 7

Offshore Wind – Falling Cost

Page 8: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Global Potential for Offshore Floating Wind

14 August 2019 Slide 8

Page 9: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Redwood Coast Project, Humboldt Bay, California

■ April 2018: The Redwood Coast Energy

Authority (RCEA) selects consortium of Aker

Solutions, Principle Power and EDPR

Offshore to enter public-private partnership

■ September 2018: Lease application for

offshore wind development off coast of

Humboldt county submitted to the Bureau of

Ocean Energy Management

■ 100-150 MW

■ Located more than 30 kilometers off the

coast of Eureka, CA

■ Planned online in 2024

14 August 2019 Slide 9

Page 10: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Summer 2018 & 2019

14 August 2019 Slide 10

← Kincardine tow-out,

United Kingdom, 2018

WindFloat Atlantic,

3 x 9,5MW

Portugal, 2019 ↓

Page 11: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Norwegian Coast: World’s Best Offshore Wind Conditions

14 August 2019 Slide 11

Page 12: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Ambitious Neighbours

■ UK

Announced 30 GW of offshore wind by

2030

■ Denmark

Announced 12.4 GW of offshore wind

by 2030

■ Norway?

14 August 2019 Slide 12

Page 13: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

Havvind - en ny topp 5 eksportindustri?

August 14, 2019 Slide 13

217

152

92

52 48

32 2920

12 11 6 5

0

50

100

150

200

250

Eksport pr næring 2017 (eksklusiv olje og gass), med eksportandel av total omsetningKilde: Eksportkreditt og Aker Solutions

Page 14: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

217

152

92

52 4840

32 2920

12 11 6

0

50

100

150

200

250

2030

Havvind - en ny topp 5 eksportindustri?

August 14, 2019 Slide 14

Havvind

Page 15: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

New Era of Ocean Economy Opportunities

Floating and Subsea

Power Stations

Floating Wind Power Offshore Aqua

Culture

Subsea Data Centers

Power Hubs

Critical Infrastructure

Landfall and power

storage/balancing

Data and Software

Page 16: Offshore Wind - Norges Rederiforbund...© 2019 Aker Solutions Floating Wind vs. Large Scale Readiness –12 myths 14 August 2019 Slide 6 Weight of hulls too high Simpler installation

© 2019 Aker Solutions

CopyrightCopyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall be altered or removed from any reproduction.

DisclaimerThis Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations, estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations, estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar expressions. Important factors that could cause actual results to differ materially from those expectations include, among others, economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty, expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its directors, officers or employees will have any liability to you or any other persons resulting from your use.

Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions company.

14 August 2019 Slide 16

Copyright and Disclaimer